Questions and Answers.xlsx

XLSX spreadsheet 34 KB Posted

Attached to
U.S. Senate Wellbeing Application
Solicitation number
2027-R-007
Issued by

About this file

This file is a Questions and Answers document containing clarifications issued by the U.S. Senate office of the Sergeant at Arms (SAA) for Solicitation 2027-R-007 regarding a secure, fully customizable employee wellbeing application. Amendment 001 extended the proposal due date to December 4, 2026, with pricing valid through April 3, 2027. The anticipated contract performance period runs from March 14, 2027, through March 13, 2028, as the base year, with options available thereafter.

The solicitation requires a commercially available, configurable wellbeing application platform that serves as a centralized digital portal for organization-approved wellbeing programs, resources, events, and engagement activities. The application must support user tiers ranging from 500 to 8,000 users, with each tier priced separately and evaluated individually; the specific tier at award will be determined by the SAA. The contractor must provide hosting, implementation, configuration, maintenance, and support, with the capability to increase or decrease user counts via contract modification. Hosting, implementation, and help-desk support (8 AM–8 PM ET) may be performed remotely from a U.S. location, with on-site presence only as requested. The application must integrate with Senate Okta single sign-on and implement quarterly access codes for ineligible user removal. The contractor must host the application on FedRAMP Moderate or High-authorized cloud infrastructure with U.S.-only data storage and processing, subject to the Senate's risk assessment. Intellectual property rights clarifications establish that pre-existing commercial platform source code and standard content remain the contractor's restricted computer software; the Senate retains ownership of its own branding, content, data, configuration, and Senate-specific integrations. Past performance references must demonstrate relevant experience with comparable software applications, SaaS services, or enterprise IT services within the five years preceding proposal submission, applicable to both the prime contractor and any proposed subcontractors. The solicitation is unrestricted open-market competition with evaluation factors detailed in Section M of the solicitation.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 Solicitation Questions

Question NumberSolicitation Paragraph ReferenceSolicitation Page NumberQuestionSAA ResponseSolicitation Change Required (Y/NLocation of Change
1Is this activity considered a new requirement or a follow-on to an existing contract?A follow on to a current requirement.No
2If there is an incumbent, would you be able to share the vendor’s name, and the contract number, value, contract award date and expiration date?Question not applicable to the requirement.No
3Can you please share incumbent?See above response.No
4C.1.2 & H.11pg 3& pg 20Section C.1.2, page 3, and Section H.11, page 20. C.1.2 asks for "a commercially available, fully customizable wellbeing application," and H.11 transfers "all rights, title, and interest in the software to the U.S. Senate." Will the Senate accept an application the offeror configures and builds for the Senate from commercially available components (an open-source content management platform, hosted on cloud infrastructure authorized at FedRAMP Moderate under Attachment 6, section 14.3.13.2.1.1), delivered with its source code under H.11 and priced per user tier in Attachment 1? Or must the offered application already be sold to other customers as a commercial product?The application should be available commercially and flexible to customize to the Senate's requirements.No
5L.7.1.4pg 43Section L.7.1.4, page 43. May a past performance reference be a project performed by the offeror's proposed key personnel before the offeror was formed, in addition to the offeror's own contracts?Yes.No
6Attachment 1, Pricing Table, note 1. The note says the RFP "CONSISTS OF THIS PRICING TABLE, SOLICITATION 2026-R-044." Please confirm Attachment 1 is the price table for 2027-R-007, with the base year January 2, 2027 to January 31, 2028.2026-R-007 is the correct solicitation number. The anticipated base year dates is changed to March 14, 2026 through March 13, 2026.YesAttachment 1 - Pricing Table
7L.7.1.4Section L.7.1.4 requests three comparable references for both the offeror and subcontractors. Must the prime separately have three comparable projects, or may an offeror rely on the proposed software provider and implementation team’s references? If separate prime references are required, is a prime with no relevant history eligible for a neutral evaluation?If the Offeror is proposing subcontract, past performance references are required for both the prime and subcontractor(s) for work or services similar to the solicitation requirements performed within the last five (5) years.No
8F.3Section F.3 names the Capitol Complex. What on-site implementation, training, or support is required, and may contractor-hosted SaaS delivery and routine support be performed remotely?The contractor may provide delivery and routine support remotelyNo
9The pricing workbook lists license tiers of 500, 1,000, 2,000, 4,000, and 8,000 and sums all tiers. Are these alternatives, cumulative quantities, or marginal tiers? Please confirm the evaluated quantity and pricing basis.These are alternative tiers. Each tier (quantity) will be evaluated individually, the SAA will determine the quantity (tier) at award.YesM.5.4
10The workbook’s base dates are January 2, 2027–January 31, 2028, while B.5 describes a 12-month base. Its February 1, 2027 quote-validity date also appears shorter than L.5’s 90-day period. Please confirm the controlling dates and whether a corrected workbook and PPQ will address their other solicitation-number references.See E9 response above.No
11Attachment 6 & C.2.2.344 &Attachment 6, SOP for Cybersecurity, 14.3.13.2.1.1 (page 44 of 51), sets the impact level for the cloud services (CS) used to deliver the application at FedRAMP Moderate or High. Please confirm this applies to the underlying cloud infrastructure that hosts the offered application (for example, an infrastructure provider whose services carry an authorization at the High level), and that the offered application itself is reviewed under the Senate's own process in C.2.2.3 rather than needing a separate FedRAMP package at award.The Senate will perform a Risk Assessment of the selected offeror's application, if applicable.No
12C.1.148Section C, C.1.1 (page 4 of 48), allows the SAA to award to a contractor without an active SAM record when that is in the Senate's best interest. Will the SAA accept a proposal from an offeror whose SAM renewal has been submitted and is in progress, but not yet active, on the proposal due date?Yes.No
13C.1.24Section C, C.1.2 (page 4 of 48), asks for "a commercially available, fully customizable wellbeing application". Does an application configured for the Senate on the offeror's commercially available application platform (sold commercially today, hosted and supported by the offeror) meet C.1.2, or does the SAA require a packaged wellbeing product already in commercial use?An application configured for the Senate on the offeror's commercially available application platform (sold commercially today, hosted and supported by the offeror) does meet the C.1.2No
14I have a question regarding the scope of the wellbeing application but do not have a section or page number to reference as the information I'm looking for is not included. Attachment 1 does ask for pricing up to 8,000 users. Can you clarify if the 8,000 users are employees who physically work in the Senate in Washington DC, or is the application expected to be fielded nationally to the states and Senate staffers across the country?
The application will be expected to be fielded nationally to staff across the United States.No
15C.1.24Section C.1.2, page 4: would a platform in commercial use, configured for EAP resources, events and challenges, meet the requirement for a commercially available application?A platform in commercial use, configured for EAP resources, events and challenges, will meet the requirement for a commercially available application.No
16H.10.219Section H.10.2, page 19: does this clause apply to contractor staff who run the hosted application but never use the Senate network, buildings or devices?H.10.2 This clause is only applicable to contracts with personnel who meet the following criteria:

a) have been or will be issued a Senate ID badge ordered by the SAA to allow for unescorted access to Senate buildings.

b) will conduct work that requires access to the Senate network; or

c) have been or will be issued a SAA device, including laptop, tablets, or mobile phones.No
17F.313Place of performance (F.3, p. 13). The application is vendor-hosted SaaS. May hosting, implementation and help-desk support be performed remotely from the contractor’s U.S. location, with on-site presence only if the SAA requests it?Hosting, implementation and help-desk support may be performed remotely from the contractor’s U.S. location, with on-site presence only if the SAA requests it.No
18Pricing table (Attachment 1). The TOTAL sums all five license tiers. Is the evaluated price the sum of all tiers, or should one tier be priced as the evaluated quantity? Which tier does the SAA expect at go-live?The Offeror should provide pricing for each tier, the base year and option year for each tier will be evaluated separately.YesPricing Worksheet
Solicitation number and validity (Attachment 1; L.5, p. 42). Attachment 1 cites solicitation 2026-R-044 and quote validity through February 1, 2027, and Attachment 2 cites 2026-R-066. L.5 requires at least 90 calendar days. Please confirm the correct solicitation number and that a 90-day acceptance period from the November 23 closing applies.The correct solicitation is 2027-R-007. Proposals shall be 90 days from the closing date of December 4, 2026 pricing shall be valid until April 3, 2027.Yes
Cloud hosting (Attachment 6, §14.3.13.2.1.1, p. 44). Does the FedRAMP Moderate/High requirement apply to the infrastructure of a vendor-hosted application? Will the SAA accept hosting on a FedRAMP-authorized provider, and what form should the read-only audit access take?The SAA will perform a Risk Assessment of the selected Offeror's application.No
Restricted rights (H.11–H.12, pp. 20–21). Should proprietary information to be used under the contract be identified in the proposal, and in what format?Proprietary information should be identified, the format is at the discretion of he Offeror.No
Insurance (H.13, p. 21). Must evidence of insurance accompany the proposal, or is a binder required only at award?Refer to requirements in Section L.7.3 VOLUME III – Administrative Proposal. Binder is not listed as a submission requirement.No
8.Past performance (L.7.1.4, pp. 43–44; M.5.3, p. 47). Please confirm that commercial references are accepted, that references for related SaaS services to organizations are acceptable where comparable in scope and complexity, and that a subcontractor’s references count toward Factor 2.Commercial references are acceptable. If the Offeror is proposing subcontract, past performance references are required for both the prime and subcontractor(s) for work or services similar to the solicitation requirements performed within the last five (5) years.No
C.2.79Access codes (C.2.7, p. 9). Are quarterly codes distributed to staff by the SAA or the contractor, and on a fixed calendar date?Quarterly codes will be distributed by the contractor to the SAA/EAP staff designated as application administrators only on a fixed calendar date determined by the SAA.No
L.442Oral presentation (L.4, p. 42). What is the expected window for presentations, and will a live product demonstration be expected?The Senate will provide the specific date, time, and the presentation agenda at the time of notification.No
Approach. The requirement is described as providing, implementing, configuring, hosting, maintaining, and supporting a secure, fully customizable employee wellbeing application. Will the Senate consider an application purpose-built and delivered under this contract, with the Senate holding the resulting software, or does the requirement contemplate an existing commercially available wellbeing platform that the contractor configures and operates? We are a custom software development firm. We do not resell or license a third-party product, so this answer decides whether we offer as a prime or support another offeror.No, the RFP specifically states we are considering proposals for applications that are commercially available application platforms (sold commercially today, hosted and supported by the offeror) that will be configured for the SenateNo
Submission and distribution. We would like to confirm the delivery method and whether the Senate Delivery Procedures attachment governs electronic submission as well as physical delivery. Please also confirm that the complete solicitation package, including the Pricing Table, Past Performance Questionnaire, Section 208 Compliance Certificate, Addendum to Commercial Agreements, Senate Delivery Procedures, and Standard Operating Procedures for Cybersecurity, is the full set, and whether questions are due by a date earlier than the offer deadline.This is all included in the solicitation; proposals should be submitted electronically.No
C.1.24Section C.1.2, p. 4: "commercially available, fully customizable wellbeing application." Will the SAA consider a custom-built, Senate-owned application hosted and supported by the contractor, or must the application be an existing commercial product?The application should be available commercially and flexible to customize to the Senate's requirements.No
F.314Section F.3, p. 14: Place of performance is the U.S. Capitol Complex. Can all implementation, hosting and support be performed remotely, with the kickoff, status meetings and oral presentation held by video?The Senate may permit virtual meetings.No
C.2.9.1 & F.23. Section C.2.9.1 / F.2: Is the 8 AM–8 PM ET help desk required by phone, or may email/in-app support with defined response times satisfy it?Email/in-app support with defined response times will satisfy this requirement provided the offeror provides live support from 8 AM–8 PM ETNo
Attachment 1: Are the license tiers (500 to 8,000 users) alternatives priced per user, or cumulative? What is the expected number of users at launch?Alternatives. The number of users will be determined at the time of award.No
H.13Section H.13: Is automobile liability insurance required for a contract performed entirely remotely?The contract may not be performed entirely remotely.No
C.2.2.3(m)Section C.2.2.3(m): Is an independent security assessment (e.g., SOC 2) required for award, or only provided if available?If applicable, the Contractor shall cooperate with the Senate’s cybersecurity review and authorization processesNo
Attachment 6, SOP for Cybersecurity, 14.3.13.2.1.1 (page 44 of 51), sets the impact level for the cloud services (CS) used to deliver the application at FedRAMP Moderate or High. Please confirm this applies to the underlying cloud infrastructure that hosts the offered application (for example, an infrastructure provider whose services carry an authorization at the High level), and that the offered application itself is reviewed under the Senate's own process in C.2.2.3 rather than needing a separate FedRAMP package at award.The Senate will perform a Risk Assessment of the selected offeror's application, if applicable.No
C.1.24Section C, C.1.2 (page 4 of 48), asks for "a commercially available, fully customizable wellbeing application". Does an application configured for the Senate on the offeror's commercially available application platform (sold commercially today, hosted and supported by the offeror) meet C.1.2, or does the SAA require a packaged wellbeing product already in commercial use?An application configured for the Senate on the offeror's commercially available application platform (sold commercially today, hosted and supported by the offeror) does meet the C.1.2 requirement.No
C.1.241. C.1.2, page 4: Does the application need to be an existing commercially available product, or can a configured or custom-built platform qualify?No, the RFP specifically states we are considering proposals for applications that are commercially available application platforms (sold commercially today, hosted and supported by the offeror) that will be configured for the SenateNo
L.7.1.444L.7.1.4, page 44: Can past performance references include commercial (non-government) projects?Yes past performance references can be commercial.No
C.2.911C.2.9, page 11: What help desk hours are expected, and roughly how many users are anticipated in the first year?Live phone/email/in-app help desk support is expected from 8 AM–8 PM ET
F.313F.3, page 13: The place of performance is listed as the U.S. Capitol Complex. For a hosted application, may implementation, support, and meetings be performed remotely?Hosting, implementation, meetings and help-desk support may be performed remotely from the contractor’s U.S. location, with on-site presence only if the SAA requests it.No
Attachment 1, Pricing Table: The total formula adds all five license tiers together. Will price be evaluated on one tier at a time, or on the sum of all five tiers as the table is built?Each tier will be will be evaluated separately.YesAttachment 1 - Pricing Table & M.5.4
Attachment 6, Section 14.3.13.2.1.1, page 44: For a software-as-a-service application, does the FedRAMP Moderate requirement apply to the underlying hosting infrastructure only, or must the application itself hold a FedRAMP authorization?The Senate will perform a Risk Assessment of the selected offeror's application, as applicable.No
H.1120H.11, page 20: For a platform the offeror developed at private expense, does the Senate's ownership apply to the Senate-specific configuration and content, with the underlying platform treated as restricted computer software under H.12?Any IP developed at private expense is not subject to the provision in this clause.No
We noticed the documentation mentions both a desire to own the IP and a preference for a commercially available product. Could we propose a custom-built solution that you would fully own, or is your preference to build on top of an existing commercial product? And you own the IP for that API layer aka integration layer?
The SAA is seeking a commercially available, configurable wellbeing application, rather than a fully custom-built solution. The SAA does not intend to acquire ownership of the Contractor's pre-existing software, source code, or underlying intellectual property. However, the Senate shall retain ownership of its branding, organization-provided content, data, and other organization-owned materials incorporated into the application. Any application programming interfaces (APIs), integrations, or configuration components necessary to meet the Statement of Work requirements shall be included in the proposed solution. Ownership and licensing rights for any newly developed, organization-specific integration components shall be clearly identified in the Offeror's proposal and addressed in the resulting contract. The proposed solution must meet all functional, security, integration, and support requirements outlined in the Statement of Work.No
Prime Contractor and Subcontractor Responsibilities
May a prime contractor propose an established commercial wellbeing application through a qualified software-provider subcontractor while retaining responsibility for program management, systems integration, cybersecurity coordination, implementation, and ongoing technical support?YesNo
Past Performance Requirements
Will the Senate consider the combined relevant past performance of the prime contractor and its proposed subcontractors when evaluating the required three references, including federal enterprise IT services, cloud hosting, cybersecurity, and application support?YesNo
FedRAMP Authorization
Does the FedRAMP Moderate or High authorization requirement apply to the underlying cloud-hosting environment only, or must the proposed application itself possess a separate FedRAMP authorization?The Senate will perform a Risk Assessment of the selected Offeror's application, as applicable.No
Commercial Application Requirements
Must all specified application capabilities be commercially available at the time of proposal submission, or may an existing commercial application be configured or enhanced during implementation to satisfy the Senate's requirements?An existing commercial application may be configured or enhanced during implementation to satisfy the Senate's requirements.No
H.11Commercial Software Intellectual Property
Regarding Section H.11, please clarify whether the Senate's software ownership provisions apply to pre-existing commercially licensed software and intellectual property, or exclusively to software and deliverables developed specifically under this contract.H.11 does not apply to pre-existing commercially licensed software. And intellectual property.No
User Population and Pricing Assumptions
Can the Senate provide anticipated numbers of authorized users, concurrent users, and administrative accounts, along with estimated help desk utilization, to support accurate licensing, hosting, and operations pricing?That data and those assumptions are unknown. We do anticipate a minimum of four administrative accounts.No
Cybersecurity Review and Approval

Must the proposed application complete the Senate cybersecurity review before contract award, or may the selected contractor complete the review and obtain approval during implementation before production deployment?

It is required with the Volume III of the Administrative Proposal.No
Past Performance Questionnaire Instructions

Attachment 2 references submission within five days of receipt, while the solicitation identifies November 23, 2026, as the proposal deadline. Additionally, please confirm whether the reference to Solicitation 2026-R-066 in Attachment 2 is a clerical error.

Please clarify the controlling deadline for completed questionnaires.

The Past Performance Questionnaire have been updated with the accurate information.YesAttachment 2- Past Performance Questionnaire
Small-Business and Veteran-Owned Business Participation

As Solicitation 2027-R-007 is identified as unrestricted, will the Senate consider small-business participation, veteran-owned small-business status, or meaningful small-business subcontracting commitments as part of its proposal evaluation? If applicable, please identify the relevant evaluation criteria.

The is open market completion. Evaluation Factors are in section M of the solicitation.No
Pricing TableLines 0001-0005 and 1001-1005, sheet p.1Is the Base Year total evaluated as the sum of all five user-tier lines, or only the tier matching the Senate's initial user count?Each tier will be will be evaluated separately and base, option year(s) will be totaled for each tier.
L.3 p.40 and L.6 p.41In what file format should Volume I and Volume II be submitted, PDF or Word?Either format is acceptable.No
L.5 p.41 and Attachment 1 note 4L.5 requires at least 90 days of proposal acceptance, while Attachment 1 says prices are valid until February 1, 2027. Which validity date governs?Dates have been updated in Amendment 001 on the pricing table and solicitation.No
C.1.23Section C.1.2, page 3. The Contractor is to provide "a commercially available, fully customizable wellbeing application." Will the SAA consider an application that is offered for sale commercially but is newly released and has no prior customer deployments?
No, the SAA requires past performance references as a condition of consideration.No
L.7.1.4 & M.5.343 & 47Section L.7.1.4, page 43, and Section M.5.3, page 47. Prior contracts are to be "comparable in scope and complexity to the efforts described in Section C." Will the SAA accept references for comparable software application work that was not a wellbeing application? How will an Offeror with no past performance on wellbeing applications be rated under Factor 2?An offeror without well-being application experience will not be considered.No
Scope: Is the Senate specifically seeking a comprehensive wellbeing application, or would a platform focused on financial wellness, retirement readiness, and benefits education be considered as part of the solution?No, a platform focused on financial wellness, retirement readiness, and benefits education would not be considered as part of the solution.No
Partnerships: Would the Senate consider a team-based solution where a specialized financial wellness technology provider partners with a broader wellbeing or technology platform?No, we are only considering a comprehensive wellbeing application at this time.No
Technology requirements: Are all specified security and integration requirements mandatory at initial submission, or is there flexibility for vendors working with established, compliant infrastructure providers?All specified security and integration requirements are mandatory at initial submissionNo
Future opportunities: If our platform is better suited as a component of a broader solution, are there other upcoming initiatives or procurement opportunities focused on employee financial wellness or benefits education?Not at this time.No
C.2.2 & 1.21 through I.26Sections C.2.2 and I.21 through I.26 state the cloud infrastructure must generally hold FedRAMP Moderate or High authorization. Please confirm whether a commercially available application hosted on FedRAMP authorized underlying infrastructure meets this requirement when the application itself does not hold its own FedRAMP authorization, or whether the application itself must hold the authorization.The SAA will perform a Risk Assessment of the selected Offeror's application.No
Standard Operating Procedures For Cybersecurity: Is an NDA assumed based on the requirements of this RFP? Some requirements we do not provide without an executed NDA.If NDA is required please email to zemirah_courtney@saa.senate.gov and acquisitions@saa.senate.govNo
L.7.1.4 Section 4 – Past Performance: Is it an option to provide references for Offeror only, of clients that also use our optional subcontractor services? We generally do not provide references on behalf of subcontractors.Yes.No
For pricing, would you like it to be per participant, based on employee count tiers?Yes.No
4.H.11 Intellectual Property Rights, page 20:
a.H.11 (p. 20) transfers "all rights, title, and interest in the software" to the Senate. H.12 (pp. 20–21) provides the Contractor's proprietary software under the Contractor's license. H.1 (p. 16) does not resolve a conflict between them. For a pre-existing commercial SaaS platform, please confirm, by amendment to the solicitation, that:

(a) the platform and its enhancements are restricted computer software under H.12 and are excluded from H.11's title transfer and know-how license;

(b) title transfer applies only to Senate-specific deliverables (Senate content, configuration, reports);

(c) "Developed Work" excludes general platform features the Contractor makes available to other clients; and

(d) the Contractor may use aggregate, de-identified usage data that cannot identify the Senate or its users.The Senate agrees with proposed amendment text. However, contract provisions in the solicitation currently embody these principles such that an amendment is not requiredNo
Attachment 6: do the 24/48/72-hour steps in 14.3.12.4 (pp. 41-42) apply to every security patch in a vendor-managed multi-tenant environment?Yes.No
Attachment 6: what does 'auditor (read only) level access' to the contractor's cloud environment (14.3.13.2.2, p. 44), and physical access to 'any Contractor facility with Senate data' (14.3.13.8.3, p. 47), mean for a multi-tenant environment hosted in a third-party cloud? Will a SOC 2 Type II report, the cloud provider's assurance reports and a remote walkthrough satisfy it?The Senate will perform a Risk Assessment of the selected Offeror's application.No
Attachment 6: 14.3.13.4 (p. 46) refers to malware submission 'instructions provided in the SOP', but none appear. The text after Table 14.3.12.1-1 (p. 40) cites 'Table 14.3.2.1-1'. Please confirm the intended references.See 14.3.14 – Breach Notification. Table reference is correct.No
I.21 (p. 31) and Attachment 4 section 14 require return or destruction within 30 days. Will the Senate accept deletion of live data within 30 days, with backup copies expiring on the standard rotation and the Certificate of Destruction issued when the last backup expires?The Senate contend deletion is equivalent to destruction so long the data is deleted in a manner that it cannot be re-used.No
Attachment 1, instruction 1. The Pricing Table states that the request consists of “this Pricing Table, Solicitation 2026-R-044.” Please confirm that Attachment 1 applies to Solicitation 2027-R-007.Confirming Attachment 1 applies to 2027-R-007.YesAttachment 1.
Attachment 1 and B.5 (p. 4). B.5 sets a 12-month base period. Attachment 1 gives the base year as January 2, 2027 to January 31, 2028, which is 13 months. Which governs? Should support services (line 0007) be priced for 12 months or 13?Period of Performance dates have been updated to March 14, 2027 through March 13, 2028.YesAttachment 1 - Pricing Table
Attachment 1, instruction 4, and L.5 (p. 42). Attachment 1 says price quotes are valid until February 1, 2027. That is 70 days after the November 23, 2026 closing date, while L.5 requires an acceptance period of at least 90 days. Please confirm that the 90-day period in L.5 governs.Amendment 001 of the Pricing Table and solicitation updates the dates.Yes
Attachment 1, lines 0001–0005 and 1001–1005, and C.1.2 (p. 4). The five license lines are user bands, and the sub-total adds all five. Should offerors price every band, with the evaluated price being the sum of all five? Or will the Senate evaluate a single band? Please also confirm that line 0003, labeled “1000-2000 users,” means 1,001 to 2,000. Finally, C.1.2 requires the Senate to be able to increase or decrease the number of users. Is that a cap the application enforces, a count reported to the administrator, or a change of band by contract modification?Confirming it is 1,001. Offeror should provide pricing for each band, only one will be used for evaluation purposes. Changes to number of users will be incorporated via a contract modification.YesAttachment 1 - Pricing Table
C.1.24C.1.2 (p. 4). The solicitation asks for a “commercially available, fully customizable” application. Will the Senate consider this requirement met by an offeror’s existing software platform, licensed commercially and configured and branded for the Senate, with Senate-specific content, workgroups and integrations delivered through configuration?An existing commercial application may be configured or enhanced during implementation to satisfy the Senate's requirements.No
B.2 & C.3.23 & 8B.2 (p. 3) and C.2.3.2 (p. 8). Does the SAA or the Senate EAP currently use a wellbeing, challenge or communications application, or license wellbeing content? Should the new application integrate with it, link to it or replace it? Does the Senate expect the application to work alongside the Congressional Physical Activity Challenge, and is any wearable-based activity feed wanted?This requirement will not be linked to any other well-being application.No
C.2.1.66C.2.1.6 (p. 6). Does “mobile” require a native iOS or Android application, or is a mobile-browser and installable web experience acceptable?The requirement is a native iOS or Android application experience.No
C.2.1.4 & C.2.8.16 & 8C.2.1.4 (p. 6) and C.2.3.1 (p. 8). Are email and push notifications to employees permitted? If so, from what sender address or domain? Do Senate-managed devices restrict installable web applications or web push?Email and push notifications would be permitted however the Senate will control message distribution. No, Senate-managed devices do not restrict installable web applications or web pushes at this time.No
C.2.1.2 & C.2.8.15 & 11C.2.1.2 (p. 5) and C.2.8.1 (p. 11). How many offices and workgroups does the Senate expect at launch? Will administration be limited to central EAP staff, or will staff in individual offices also administer their own workgroups?The amount of offices and workgroups at launch are unknown and administration will be limited to EAP staff.No
C.2.8.211C.2.8.2 (p. 11). Reporting: what is the smallest group for which a report may show a count? Does the Senate want any individual-level reporting, or aggregate reporting only? Does anyone beyond the central EAP need individual-level data?Aggregate data only. No one beyond EAP will have access to reporting or data.No
C.2.2.47C.2.2.4 (p. 7). Will the Senate provide a SAML 2.0 or OIDC connection through Okta? Which assertion attributes will identify an employee’s office and workgroup? Will the Senate send the identity provider metadata file? When an employee leaves the Senate, will Okta notify the application (SCIM or a periodic export of active users), or does the application learn of a departure only at the employee’s next sign-in? What maximum session length and idle timeout does the Senate set?The Senate will perform a Risk Assessment of the selected Offeror's application.No
C.2.7.110C.2.7.1 (p. 10). Is Senate Okta single sign-on sufficient as the “Senate-specific access method,” or does the Senate also require a registration or access code, changed quarterly?We will not share an employee eligibility file with the contractor therefore we will need an access code that changes quarterly so ineligible employees will be unable to access the application post-departure.No
13.2.2.2, H.10, I.47, 19, 2413.C.2.2 (p. 7), H.10 (p. 19), I.4 (p. 24) and Attachment 6 §14.3.13.2 (pp. 43–44). Attachment 6 requires cloud infrastructure authorized at FedRAMP Moderate or High.

(a) Is a vendor-operated environment on FedRAMP-authorized infrastructure acceptable, or does the Senate require hosting within its own environment?

(b) Does the Senate require the offeror’s application itself to hold a FedRAMP authorization, or is hosting on FedRAMP-authorized infrastructure sufficient?

(c) Does the SAA CIO waiver in §14.3.13.2.2 apply to either?The SAA will perform a Risk Assessment of the selected Offeror's application.No
I.26 (p. 33) and Attachment 6 §§14.3.5.3 (p. 33) and 14.3.14 (p. 48). Incident reporting differs between these provisions. I.26 requires a report within 24 hours to (202) 228-7620 and a follow-up within 72 hours. Section 14.3.14 requires a report within 72 hours to (202) 228-2927, option 1. Section 14.3.5.3 requires notice “immediately.” Which timing, telephone number and email address govern for this contract?Both are correct: 14.3.5.3 Cybersecurity Incident Reporting is 14.3.14 Breach NotificationNo
Attachment 6 §§14.3.8 and 14.3.9 (pp. 35–36). The remote access and contractor account procedures read as written for software installed in Senate offices. Which of these provisions apply to an application the offeror hosts?The SAA will perform a Risk Assessment of the selected Offeror's application.
Attachment 3. The Section 208 Compliance Certificate asks an OEM to certify compliance. For a hosted software service, who is the OEM? What FIPS 199 impact level does the Senate assign to this application?The OEM is the manufacturer of the application.No
C.2.4.4 & C.39 & 12C.2.4.4 (p. 9) and C.3 (p. 12). C.2.4.4 makes the weekly status report due one business day before each status meeting. C.3 makes it due at the end of each work week. Which governs?C.2.4.4 is accurate.YesC.3
Section J (p. 36). Attachment 2 (Past Performance Questionnaire) and Attachment 4 (Addendum to Commercial Agreements) were not available on the posting. Please provide them.Both are attached to the solicitation in sam.gov.
H.11, Intellectual Property Rights (pages 20–21), and Section H.12, Restricted Rights Software (page 21). Our offering is a commercially available, software-as-a-service platform developed at private expense and licensed to many customers. Please confirm that the transfer of "all rights, title, and interest in the software" in H.11 applies only to "Developed Work" created specifically for, and paid for by, the Senate under this contract. Please also confirm that the pre-existing commercial platform, including its source code, is treated as restricted computer software under H.12 and remains the Contractor's property, licensed to the Senate for the contract term.The Senate is purchasing licenses not the application.No
Section H.11 (pages 20–21). The final paragraph grants the Senate a perpetual license to "ideas, know-how, or techniques... including any enhancements made to the Contractor's software source code." Please confirm that this paragraph does not require the Contractor to deliver or license source code to the Senate. Please also confirm that general product enhancements made available to all of the Contractor's customers, including features developed during this contract to meet a Section C requirement, remain the Contractor's property.Confirmed.No
C.2.8.3, C.2.8.4, H.1110 & 20Sections C.2.8.3–C.2.8.4 (page 10) and H.11 (page 20). Please confirm the intended split of ownership: the Senate owns Senate-created content, Senate branding, Senate-provided resources and Senate data, while the Contractor retains its platform, standard templates and standard content library.Yes, that is correct. The Senate owns Senate-created content, Senate branding, Senate-provided resources and Senate data, while the Contractor retains its platform, standard templates and standard content library.No
Section H.11 (page 20). Our standard library includes wellbeing videos and courses licensed from third-party content providers. Please confirm that the Senate's rights to this licensed content are limited to use during the contract term, and that ownership remains with the content providers.Confirmed.No
Section L.7.3.3(g) (page 45) and Section M.2 (page 46). If an Offeror identifies an exception to H.11 limited to pre-existing commercial software, as described above, will that exception be considered in evaluation? Or would the proposal be treated as not meeting the solicitation's requirements?per L.7.3.3(g) the offeror should provide a summary identifying and explaining exceptions to, or conditions for any solicitation provision or contract clause, if any. Rationale for the exception and/or condition shall be fully provided as well as referenced to the respective provision or clause.No
Section B, Attachment 1 – Pricing Table (line items 0001–0005 and 1001–1005). Should each license unit price be stated per user per year? Are the user tiers cumulative, or will the Senate purchase a single tier based on the actual number of users?The Senate will purchase a single tier based on the number of users with the option to increase the number of users.No
Section B.5 (page 3) and Attachment 1. The base year runs from January 2, 2027 to January 31, 2028 (13 months). Should base-year license prices cover the full 13-month period?The period of performance dates have been updated.Yes
C.1.23Section C.1.2 (page 3). How many users does the Senate expect at launch, and how many employees are eligible for the EAP wellbeing program?To be determined at the time of award.No
Section I.4, Data Transfer (page 23). Senate data will be stored and processed only in U.S. data centers. Does I.4 also prohibit Contractor support or engineering personnel located outside the United States from accessing Senate data hosted in the U.S.? If so, will the Senate accept a commitment that only U.S.-based personnel will access Senate data?All Senate Data shall be stored and processed only in U.S. data centers. I.4 does not necessarily prohibit Contractor support or engineering personnel located outside the United States from accessing Senate data hosted in the U.S. however, it depends. The Senate will accept a commitment that only U.S.-based personnel will access Senate data. See H.10.2.1: Contractor personnel are required to be citizens of the United States of America (U.S.) or meet the eligibility requirements for Government of the United States employee compensation as specified in Public Law 111-117, Section 704.No
C.2.6.19Section C.2.6.1 (page 9). Which accessibility standard applies, for example, Section 508 / WCAG 2.1 Level AA? Should a Voluntary Product Accessibility Template (VPAT) be included in the proposal?It is the Contractor's responsibility to know and ensure its website complies with all applicable federal data security, privacy, and accessibility laws and standards.No
C.2.7.1 & C.2.7.29 & 6Sections C.2.7.1–C.2.7.2 (page 9) and C.2.2.4 (page 6). Is the Senate-specific access code required in addition to Okta single sign-on? Or is the access code intended for users who cannot sign in through Okta?The Senate-specific access code required is in addition to Okta single sign-on.No
Attachment 4, Addendum to Commercial Agreements. Will the Senate accept the Contractor's standard subscription terms, attached to the proposal and modified by the Addendum, as the license agreement for this contract?The Senate does not anticipate modifying the Addendum to Commercial Agreements. The Offerors shall submit its applicable T&C's.No
B.1 & C.2.2.3®2 & 6Section B.1 Scope (p.2): You state that the application shall be primarily a well-being resource navigation, communication and employee engagement platform and (C.2.2.3.r, p.6) require only “reasonable and necessary” data collection. Can you please clarify the role, if any, of a Health Risk Assessment or a Lifestyle Questionnaire? Would you ask participants to complete a questionnaire, provide it as an option for self-guided exploration, or neither (hide the questionnaires)?Reasonable and necessary means only collecting data related to application access eligibility, activity recordation, and content engagement. All health questionnaires will be required to be hidden from use.No
B.12Section B.1 Scope (p.2): Will any biometric data be collected or stored in the portal?No biometric data should be collected or stored.No
Intellectual property (H.11, p. 20; H.12, pp. 20–21; C.1.2, p. 3). C.1.2 calls for a “commercially available” application. H.11 gives the Senate rights in all data and products delivered “except for restricted computer software,” and H.12 covers an offeror’s proprietary software provided under its license. However, later paragraphs of H.11 state that “all intellectual and data rights in the software shall become the exclusive property of the U.S. Senate” and define “Software” to include source code. Please confirm that:Confirmed:
a) An offeror’s pre-existing commercial platform, including its source code and ongoing product updates, is “restricted computer software” under H.11 and H.12, and its ownership does not transfer to the Senate.No
b) The transfer of ownership in H.11 applies only to “Developed Work,” meaning software created specifically for the Senate under this contract. Senate content, branding, configuration and data remain Senate property under C.2.8.3–C.2.8.4.No
c) The perpetual license in H.11’s final paragraph, which covers “any enhancements made to the Contractor’s software source code,” means the Senate may keep using enhancements delivered to it. It does not give the Senate rights to the source code of the offeror’s commercial product.No
C.12Number of users (C.1.2, p.3). You have requested pricing for a variety of user count tiers as well as the ability for admins to raise or lower it. With a fixed price, what happens if the admin raises the number of users from one tier to the next? Does moving up a tier trigger a modification or will it just be priced per user on the existing tier?The SAA will issue a modification if the number of users change.No
C.2.9 & C.2.9.310,11Help desk scope (C.2.9, p.10–11). In the Help Desk Scope section, you refer to a “Call Center,” but C.2.9.3 also lists email or a portal/app help system. Is phone support required? Is an AI chatbot with triage to email acceptable?Email/in-app support will satisfy this requirement provided the offeror provides live support from 8 AM–8 PM ET. An AI chatbot will not be an acceptable solution.No
C.2.2.4 & C.2.76, 7, 9Sign-on (C.2.2.4, p.6-7) vs. access codes (C.2.7, p.9). If users log in through Okta, it’s unclear what the access codes are for. SSO is often used to implement account creation in SaaS portals, either with credentials automatically creating a new account or a back-end check against an eligibility file. In either scenario, an access code isn’t necessary. Are access codes a fallback for users without Okta? If so, which one is the primary way users sign up?The code will be to remove ineligible users as we will not be sharing an eligibility file.No
C.2.2.46 & 7Eligibility File (C.2.2.4, p.6-7). Will you be providing an eligibility file to use as the source of valid accounts – either to create accounts on import or to validate SSO credentials?We will not be sharing an eligibility file.No
C.2.23.1(l)7Rewards (C.2.3.1(l), p.7). Do you plan for rewards to be non-monetary only (badges, points)? If physical or monetary prizes are used, who funds and delivers them, given Senate gift rules?There will be no monetary rewards given, only in application recognition such as recognition badges.No
C.2.8.110Sensitive Information (C2.8.1, p.10) and Rewards. If prizes are used, will EAP admins need individual-level reports to fulfill them?No prizes will be issued.No
Breach notification (C.2.2.3(i), p.6, I.12.3, p.25, I.26, p.32). I.12.3 says to notify the “applicable Senate Office,” while I.26 says to report “only” to the SAA Security Operations Center. Can we assume that SAA Security Operations is the “applicable” office?i) states notify the Senate of confirmed or reasonably suspected security incidents affecting organizational information in accordance with the timeframe established by the contract. Your first level Senate contact is the EAP COR.No
F.3 & B.313Where the work happens (F.3, p.13). F.3 names the Capitol Complex as the place of performance, and B.3 refers to local travel. We typically perform all work on our site and deliver it via the Web. Is fully remote delivery of this sort acceptable, including the kickoff and training?Support, including the kick off meeting and training, may be performed remotely from the contractor’s U.S. location, with on-site presence only if the SAA requests it.No
C.2.4.38Senate EAP Dependencies (C.2.4.3.C, p.8). Please clarify the nature of “Senate EAP Dependencies”. Are these links to existing content and/or EAP tools?Refers to Senate personnel we depend on to implement technologies in our environment.No
B.12Administration (B.1, p. 2). Section B.1 says offices see only their own information. Does this apply to administrators as well as participants? In other words, do individual Senate offices get their own administrators, or does the central EAP team manage everything?The central EAP team will manage everything.No
F.313Remote delivery — Section F.3 (p.13) names the Capitol Complex as the place of performance. Which activities require an on-site presence? May our project lead work entirely remotely from the United States if other approved team members cover any required on-site activities?Support may be performed remotely from the contractor’s U.S. location, with on-site presence only if the SAA requests it.No
References — Section L.7.1.4 (pp.43–44) requests three references for the offeror and subcontractors. Must each entity independently provide three references, or may relevant, accurately attributed key-personnel experience be considered for a newly formed entity? Please also clarify when the five-reference requirement in Section I.18 (p.28) applies.L.7.1.4 is accurate, three within the last five years.YesI.28
Cloud security — Attachment 6, Section 14.3.13.2.1.1 (p.44), specifies FedRAMP Moderate or High authorization for underlying cloud infrastructure. Must the SaaS application itself also hold a separate authorization? Please confirm whether the attached October 2021 cybersecurity SOP is the applicable version.The Senate will perform a Risk Assessment of the selected Offeror's application. Attachment 6 is the applicable version.No
Pricing tiers — Should the five license tiers in Attachment 1 be priced as alternative enrollment levels or cumulative purchases? What initial enrollment and tier-evaluation method should bidders use?They should be priced as alternative. The initial tier-level will be determined at the time of award.No
Contract dates and forms — Section B.5 (p.3) describes a 12-month base, while Attachment 1 lists January 2, 2027–January 31, 2028. Please confirm the intended dates and launch target. Will corrected forms also address the workbook's February 1, 2027 quote-validity date versus the RFP's minimum 90 days (p.41), and the older solicitation numbers in the pricing table and questionnaire?The anticipated start date is revised to March 14, 2027, Pricing valid date revised to April 3, 2026.YesPricing Worksheet.
G.414 & 15Billing and acceptance — Under Section G.4 (pp.14–15), may accepted subscription activation, implementation/training and recurring support be invoiced separately, with recurring support billed monthly? What acceptance and payment-processing timelines should bidders use for planning?The awardees shall submit invoices after product/services are received by the SAA.No
To help us evaluate the requirements, could you please share:
1. Training and project scope: Official statement of work and curriculum, roles and experience of participants, headcount, cohort structure, number of sessions, hands-on projects and expected materials, assessment or reporting outputs.The SOW is section C of the solicitation.No
2. Dates and format: Proposed programmed start, number of delivery days and session hours, location or virtual platform, training language, rehearsal or preparation needs and travel arrangements. The workbook indicates 2026-11-23 as the deadline or relevant date; please confirm.The anticipated start date is March 14, 2027. The proposal due date is extended to 12/4/2026.YesPricing Worksheet, Section L.3
3. Trainer and technical requirements: Credentials, industry references, sample sessions and mandatory conditions including federal cybersecurity, Section 508, privacy, mobile deployment, reporting and government vendor eligibility.Reference Section C, L, and M of the solicitation. Section 508 is not part of this solicitation.No
4. Pricing: Expected trainer day rate or project budget, currency, taxes, licensing and lab costs, materials, travel, invoicing and payment schedule.The offeror shall provide pricing per the solicitation.No
5. Application process: Whether company delivery partners and overseas vendors are eligible, applicable registration, closing date, evaluation criteria and appropriate decision maker.All of this information is provided in the solicitation.No

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .