This is a Performance Work Statement (PWS) for wet well pumping services at Hanscom Air Force Base prepared by 66 ABG/CEOES, effective 22 October 2026.
Hanscom AFB requires temporary wastewater hauling capabilities to prevent sanitary sewer overflows, maintain environmental compliance, and support operational continuity during lift station pump failure and replacement at Building 1306. The contractor must provide continuous 24/7 on-site presence of certified vacuum/tanker trucks (minimum 3,000 to 5,000-gallon capacity) with qualified operators, direct suction and extraction of raw sewage from the designated lift station wet well, over-the-road transport of domestic wastewater along authorized public transit routes between Hanscom AFB in Bedford/Lexington, Massachusetts and the Town of Lexington municipal discharge location, and safe controlled discharge into the Town of Lexington receiving pump station. Services commence immediately upon issuance of the Notice to Proceed and continue uninterrupted 24/7 until official notice of de-mobilization is provided by the Contracting Officer.
The contractor must maintain continuous shift coverage consisting of at least three primary operators/drivers per active vehicle, with shift changeovers occurring on-site with a minimum 15-minute overlap. The contractor must provide dedicated primary vehicles and immediate backup vehicle availability to ensure mechanical breakdown does not result in interruption exceeding 15 minutes. All equipment, hoses, fittings, and suction lines must be rated for raw municipal wastewater and equipped with positive containment to prevent drips. The contractor must adhere to federal, Department of Defense, Department of the Air Force, state, and local standards including AFI 32-1067, DAFMAN 91-203, 29 CFR 1910.120 and 1910.146, 40 CFR Part 503, 49 CFR Parts 100-185, Massachusetts Department of Environmental Protection 314 CMR 12.00, and Hanscom AFB's Integrated Spill Prevention, Control, and Countermeasure Plan. The contractor must maintain a zero-tolerance standard for accidental spills and discharge protocols require coordination with the Town of Lexington Department of Public Works with metered or logged batch load discharge records. All contractor personnel must possess RCRA environmental and safety training certificates and comply with confined space entry requirements including pre-briefs with the contractor, Contracting Officer's Representative, Safety Office, and Fire Department prior to service commencement.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF1449 Cover Letter FA283527Q0004.pdf | ||
| Performance Work Statement .pdf | ||
| Solicitation - FA283527Q0004.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CUI
PERFORMANCE WORK
STATEMENT
FOR
Wet Well Pumping
PREPARED BY:
66 ABG/CEOES
22 October 2026
1. DESCRIPTION OF SERVICES:
1.1. Scope: The contractor shall provide all labor, tools, equipment, hoses, gauges, test equip-ment, hearing protection, eye protection including prescription safety glasses, materials, sup-plies and parts, transportation and other incidentals necessary to travel to Hanscom AFB, MA to pump wet wells at Building 1306. The contractor shall be responsible for insuring all services and parts provided under this contract are in accordance with the terms and conditions outlined herein and conform to the manufacturer’s equipment specifications and this Performance Work Statement (PWS).
1.2. Requested Service: Hanscom AFB requires temporary wastewater hauling capabilities to prevent sanitary sewer overflows (SSOs), maintain environmental compliance, and support operational continuity during lift station pump failure, replacement. The objective is to main-tain wet well liquid levels at safe operating thresholds continuously until primary pumping system is restored.
1.3 Scope of Work
Services encompass:
1. Continuous 24/7 on-site presence of certified vacuum/tanker truck(s) and qualified op-erators.
2. Direct suction and extraction of raw sewage and effluent from the designated HAFB lift station wet well(s) at Building 1306
3. Over-the-road transport of domestic wastewater along authorized public transit routes between HAFB and the Town of Lexington municipal discharge location.
4. Safe, controlled discharge into the Town of Lexington receiving pump station in com-pliance with municipal and state discharge authorizations.
5. Implementation of spill prevention, traffic management, and emergency response pro-tocols.
1.4 Period of Performance (PoP)
The period of performance shall commence immediately upon issuance of the Notice to Pro-ceed (NTP) / Task Order and shall continue uninterrupted 24/7 until official notice of de-mo-bilization is provided by the Contracting Officer (KO).
1.5 Place of Performance
Loading Site (Origin): Building 1306 Wet Well, Hanscom Air Force Base, Bed-ford/Lexington, MA 01731.
Offloading Site (Destination): Town of Lexington Pump Station / Lexington, MA.
1.6 APPLICABLE REGULATIONS AND DIRECTIVES
The Contractor shall adhere to all applicable federal, Department of Defense (DoD), Depart-ment of the Air Force (DAF), state, and local standards, including but not limited to:
Air Force Instruction (AFI) 32-1067: Water and Wastewater Systems Department of the Air Force Manual (DAFMAN) 91-203: Air Force Occupational Safety, Fire, and Health Standards Code of Federal Regulations (CFR):
o 29 CFR 1910.120 (Hazardous Waste Operations and Emergency Response /
HAZWOPER)
o 29 CFR 1910.146 (Permit-Required Confined Spaces) o 40 CFR Part 503 (Standards for the Use or Disposal of Sewage Sludge) o 49 CFR Parts 100–185 (DOT Hazardous Materials and Commercial Vehicle
Regulations) Massachusetts Department of Environmental Protection (MassDEP): 314 CMR
12.00 (Operation and Maintenance and Pretreatment Standards for Wastewater Treatment Works) Hanscom AFB Integrated Spill Prevention, Control, and Countermeasure (SPCC) Plan
1.7 SPECIFIC TECHNICAL REQUIREMENTS
1.7.1 Continuous Operations and Staffing Coverage
24/7 Shift Coverage: The Contractor shall maintain continuous shift coverage con-sisting of at least three (3) primary operators/drivers on-site per active vehicle 24 hours per day, including weekends and federal holidays.
Shift Handover: Shift changeovers shall occur on-site without interruption to pump-ing or transport cycles. An overlap period of no less than fifteen (15) minutes shall be observed to conduct operational status handoffs.
Response and Cycle Time: The Contractor shall cycle between extraction, transit, discharge, and return such that the target wet well level never exceeds the maximum allowable emergency operating level established by the COR (e.g., maintaining level at or below high-water alarm trigger point).
1.8 Equipment Specifications and Readiness
Pumper / Vacuum Tanker Fleet: The Contractor shall provide road-worthy, Depart-ment of Transportation (DOT)-certified vacuum pumper trucks or liquid tanker units with a minimum capacity of 3,000 to 5,000 gallons each.
Reserve / Redundancy: The Contractor shall maintain dedicated primary vehicles and immediate backup vehicle availability to ensure that mechanical breakdown does not result in an interruption exceeding fifteen (15) minutes.
Pumps and Hoses: All hoses, fittings, camlocks, and suction lines shall be rated for raw municipal wastewater, watertight, and equipped with positive containment to pre-vent drips during connection and disconnection.
Auxiliary Equipment: Trucks shall be equipped with functional auxiliary scene light-ing, amber safety strobes, and spill containment kits capable of capturing minor drips or connection leaks.
1.9 Extraction, Transport, and Discharge Operations
Wet Well Extraction: Suction shall be conducted without causing physical damage to existing wet well components, level transducers, float switches, guide rails, or base in-frastructure.
Spill Mitigation During Hookup: Contractor personnel shall deploy drip pans or sec-ondary containment under all hose connections prior to commencing suction or dis-charge.
Hauling & Transport: All transport must follow designated commercial transit routes adhering strictly to local Town of Lexington, MassDOT, and HAFB traffic or-dinances. Speed limits on base shall be strictly observed.
Discharge Protocols: Wastewater offloading at the Town of Lexington pump station shall be carried out in coordination with Town of Lincoln Department of Public Works (DPW) / Water & Sewer Division requirements. Discharge must be metered or logged by batch load to record total gallons discharged.
1.10 Spill Response and Environmental Protection
Zero Discharge / No Spill Standard: The Contractor shall maintain a zero-tolerance standard for accidental spills, line ruptures, or unauthorized discharges.
Spill Kit Requirements: Every active truck on-site shall carry a rapid-response spill kit containing absorbent booms, pads, granular absorbent, drain covers, and personal protective equipment (PPE)
1.11 Confined Space: This contract has the potential for entry into permitted and non-per-mitted confined space areas. Permit required confined space areas will require, IAW AFI 91-203, The U.S. Air Force Mishap Prevention Program, and AFFARS Clause 5352.223-9001, Health and Safety on Government Installations, a prebrief prior to the start of any service which includes the contractor, COR, Safety Office and Fire Department. It is the contractor’s sole responsibility for compliance with OSHA (Public Law 91-956. The prebrief will inform the contractor of any known hazards and the contents of the space. Additionally, the contractor will be briefed on precautions and procedures implemented by 66 ABG/CE to protect Air Force workers. The Fire Chief will coordinate the confined space entry contract and either approves or disapproves use of the rescue team supplied by the installation FES Flight. At the conclusion of the contract, an after-action brief will be required where the con-tractor will provide information regarding hazards encountered or created in the space(s).The COR will contact the CO and ABG/SE immediately if an unsafe act or procedure is per-formed by the contractor.
1.12 HOLIDAYS. Hanscom AFB recognizes the following holidays:
New Years (observed)
Martin Luther King Jr. Birthday Presidents’ Day Memorial Day
Juneteenth Independence Day (observed)
Labor Day Columbus Day Veterans’ Days Thanksgiving
Christmas
1.13 Contractor Personnel: The contractor shall designate in writing the name of the Contract Manager (CM) and any alternate(s) who shall act for the contractor when the manager is absent and their telephone numbers where they may be contacted any time to the CO and the COR within five (5) calendar days after contract award. The CM or alternate shall have full authority to act for the contractor on all matters relating to operation of this contract at Hanscom AFB.
The CM or alternate shall be available to meet on the installation with government personnel designated by the CO to discuss problem areas.
1.13.1 Listing of Contractor Employees: The contractor shall provide a CM who can read, write, speak, and understand English fluently. The contractor shall provide an initial listing of contractor employees’ names and position titles to CO and COR prior to contract start date.
The contractor shall also provide an updated listing of personnel to the CO and COR within ten (10) work days when employees affecting the work of this contract have a status or posi-tion change.
1.13.2. The contractor shall not employ persons: on this contract if such employee is identi-fied to the contractor as a potential threat to the health, safety, security and general well being or operational mission of the installation and its population. The contractor shall not employ any person who is an employee of the United States Government if the employment of that person would create a conflict of interest, nor shall the contractor employ any person who is an employee of the Department of the Air Force, either military or civilian, unless such person seeks and receives approval according to the DoD 5500.7-R Joint Ethics Regulations (JER). In addition, the contractor shall not employ any person who is an employee of the Department of the Air Force if such employment would be contrary to the policies contained in AFI 64-106, Air Force Industrial Labor Relations Activities. The contractor shall be prohibited from em-ploying off-duty COR’s who are surveilling any contracts/subcontracts awarded to the Contrac-tor. All contract employees depending on particular condition, occasion or place, or job assign-ment shall require professional, suitable attire. All contractor employees shall conduct them-selves in a professional, courteous manner. The selection, assignment, reassignment, transfer, supervision, management, and control of contractor employees in performance of this PWS shall be the responsibility and prerogative of the contractor; however, the contractor shall com-ply with the requirements set forth in this PWS and Hanscom AFB regulations concerning con-duct of employees as referenced herein. The contractor shall employ and maintain a technically trained and experienced work force.
1.14 Environmental Protection and Safety: The contractor shall be knowledgeable of and comply with all applicable federal, state and local laws, regulations and requirements regard-ing environmental protection and occupational safety and health. The contractor shall comply with any laws or regulation changes during the term of this contract. The contractor shall fol-low manufacturer’s guidelines and professional recommendations for control of humidity, temperature, cleanliness and materials handling (including hazardous materials).
1.14 Hazardous Material (HAZMAT): The contractor shall not store chemicals/HAZMAT on Hanscom AFB. All chemicals/HAZMAT shall be approved prior to being transported on base for use by any contractor. The contractor shall prepare and submit to the COR, ten (10) Calendar Days: after contract award date, one (1) each, Chemical/Hazardous Material Re-quest Authorization Form (Air Force Form 3952) and Safety Data Sheets (SDS) for each chemical, material and substance proposed to be used in performance of this PWS. The COR will forward the completed AF Form 3952(s) and SDS to 66 ABG/CEIE for approval. The contractor shall not transport or use any chemical, material or substance on Hanscom AFB be-fore written approval is provided by 66 ABG/CEIE. Contractor shall maintain copies of SDS(s) for all chemicals. The SDS(s) shall correspond with the manufacturers of the chemi-cals on hand. Manufacturer, material, and SDS shall match. NOTE: SDS refers to manufac-turer SDS. Once material is approved for use, contractor shall contact base Environmental Management (EM) (66 ABG/CEIE) and provide a list of all material. 66 ABG/CEIE shall de-termine any additional material requirements based on the hazard code of the material.
1.15 Hazardous Waste: Hazardous waste (e.g., chemical solutions and used rags in waste drums) is not to be disposed to solid waste dumpsters. For assistance in making determina-tions as to what waste is hazardous, please contact the Environmental Branch. If wastes is de-termined to be hazardous, then the hazardous waste manifests need to be signed by the Environmental Branch.
1.15.1 Hazardous Waste Cont. : Massachusetts requirements. 310 CMR
15.230. Mass. State law for grease traps. Per Massachusetts requirements, traps require cleanout if over 25% of the effective depth of the trap, or at least three months, whichever is sooner.
Oil/grease is regulated by the State of Massachusetts as a hazardous waste under 310 CMR 30.000, The contractor must manifest it on a hazardous waste manifest form to be signed by CEIE under 310 CMR 30.000. Must follow HMOP guidelines.
1.16 Discharges: Any discharges into industrial waste treatment plant (IWTP) or sanitary sewer shall be done in accordance with Hanscom Industrial Waste Water Discharge Permit as instructed by 66 ABG/CEIE. The contractor shall maintain records of written authorization issued by 66 ABG/CEIE for discharges into IWTP and sanitary sewer.
1.17 The Subject Tanks: are used in industrial applications with non-potable water and vary-ing levels of heavy metals. HAFB will designate what sewer manholes are appropriate for disposal of non-RCRA wastes. The Environmental Branch can assist in reviewing the POTW permits to make a determination as to what is allowable per the permits (i.e., pH limits and duration, parameters VOCs).
1.18 Spills: Upon occurrence of any spills that could enter the storm system or cause any harmful environment effects, the contractor shall immediately call 911 to report the incident.
When possible, the contractor shall use a base telephone to receive help from Hanscom AFB
911. If using a cell phone, request Hanscom AFB 911. The contractor shall submit a verbal notification immediately after the incident is discovered, not to exceed 30 minutes so that the Environmental Branch can meet state 2-hour notification requirements. The contractor should not respond unless RCRA certification allows for them to cleanup and respond to a spill. The contractor shall report all environmental violations to the COR.
1.19 Environmental and Safety Training: The contractor personnel shall have Resource Conservation Recovery Act (RCRA) environmental and safety training required by the state and federal government. The training shall be IAW the following regulations: Resource Con-servation Recovery Act (RCRA) 40 Code of Federal Regulation (CFR) 265.16 “Personal Training”, Occupational Safety and Health Administration (OSHA) Hazardous Waste Opera-tions and Emergency Response Standard Title 29, CFR Part 1910.120 “Hazardous Waste Op-erations and Emergency Reponses”, Hazardous Waste Management Instruction, Section 13, and Air Force Instruction (AFI) 32-7042, “Solid and Hazardous Waste Compliance”, Section
2. The contractor shall provide the environmental and safety training certificate for all em-ployees to the CO and COR, after contract award date. The Environmental Branch will review the RCRA certificates to make a determination of their ability to respond to spills prior to their arrival.
1.20 Forms and Publications, TO, AFI and AFMCI: The contractor shall obtain the forms and publications expressly required to perform the work in this contract via internet at www.e-publishing.af.mil In the event that a form or publication is not available online, the COR will provide the form, instruction, or publication to the contractor upon written request (e-mail is acceptable) by the contractor. In the event that laws, regulations, TO’s, AFI, AFMCI’s change during the term of this contract, the contractor is required to comply as such changes come into effect. Contractors delivering or handling official USAF records shall comply with the applicable records management regulations AFI 33-322, Air Force Manual (AFMAN) 33-363, and AFI 37-138 (in their entirety).
1.21 Housekeeping: The contractor shall keep the work areas clean and neat in accordance with Industry Standards, Occupational, Safety and Health Administration (OSHA), fire and safety standards and this PWS.
1.22 Privately Owned Motor Vehicles (POV): Contractor personnel shall comply with the directives pertaining to operation of POVs on Hanscom AFB per AFI 31-204 (in its entirety), Motor Vehicle Traffic supervision.
1.23 Visitor Pass:
The contractor shall comply with requirement and procedures IAW FAR 5353.242-9000, Contractor Access to Air Force Installations. Prior to coming to Hanscom AFB to perform any work, Contractor shall contact the Civil Engineering Government Representative to coor-dinate access to the base as well as to the building (s) where the work shall be performed. A list of the names of the workers will be required to gain access, and passes shall be distributed at the visitor’s building at Vandenberg Gate. Workers shall have proof of identification as well as a valid license. If bringing a vehicle on base, the contractor will need proof of registra-tion and insurance of that vehicle. Contractor employees must have identification that readily identifies them as contractors. During the course of the contract, certain areas/sites may be restricted or closed to contractor personnel. The contractor shall comply with all require-ments for entry. In addition, unscheduled gate closures may occur at any time and personnel entering or exiting the installation may experience delays.
1.24 Foreign National(s): The contractor shall notify the COR before sending a Foreign Na-tional representative to perform services. Special rules apply for foreign national(s) visiting a US Government facility.
1.25 Health and Safety on Government Installation: In performing work under this contract on a Government installation, the contractor shall comply with federal, state and local regula-tions regarding occupational safety and health. The contractor shall notify the COR of any injuries that occur to contractor personnel while on the installation. The contractor shall notify the COR of damage to government property or equipment during the execution of the contract.
1.26 Emergency Procedures: Contractor employees shall follow the direction of Government employees in regards to emergency evacuation procedures, i.e. fire, tornado, active shooter and bomb threats. It is the contractors’ responsibility to account for their employees following an emergency evacuation. Contractor personnel shall participate with government personnel in all fire and tornado drills and at no additional cost to the government.
SECTION 2
GOVERNMENT-FURNISHED PROPERTY AND SERVICES
2.1. Government Furnished Property (GFP): Government Furnished Property is not appli-cable to the in the performance of this contract.
2.2. Reserved.
2.3. Government Furnished Services: Government Furnished Services are applicable dur-ing the performance of this contract.
2.3.1. Security Police: The government will provide general on base Security Forces service.
The Security Forces’ telephone number is 911 for emergencies, for crime in progress 781-225- 5613 and 781-225-5613 for non-emergency calls.
2.3.2. Fire and Emergency Services: The government will provide general on-base fire pro-tection services. The contractor shall comply with fire prevention rules and regulations en-forced by the Hanscom AFB Fire Prevention Branch. Call 911 for emergencies. For routine fire prevention matters and/or calls to dispatch, call 781-225-3330.
2.3.3. Emergency Medical Service: The government will provide 24 hour on-base state cer-tified paramedic level emergency response and patient transport services for contractor per-sonnel who are injured or become seriously ill while on Hanscom AFB. The telephone num-ber is 911 for emergencies.
Note: Calling 911 from a cell phone will be received by off base emergency 911 systems, caus-ing a delay in response time by emergency personnel. When possible use a base telephone to receive on base help.
2.3.4. Utilities: The government will furnish utility services. These utilities include natural gas, electricity, water and sewer for the sole purpose of accomplishing this contract. If the contractor requires additional utility services, it shall be the contractor’s responsibility to pro-vide. Contractor shall use due care and diligence in efforts to conserve utilities to reduce utility costs.
2.3.5. Refuse Collection: The government will provide refuse collection services limited to the extent provided in the Base Refuse Collection Contract for government provided facilities.
The government will only allow non-hazardous refuse to be emptied into the nearest authorized refuse dumpster for trash collection. Do not use the government dumpsters for collection of construction debris.
2.3.6. Workspace: The government will provide adequate workspace around the equipment area.