20272002_A1_Attachment B Drawings.pdf
PDF 29 MB Posted
- Solicitation number
- S-KE0010-00017384
- Issued by
- Oregon
About this file
Summary
This is a set of architectural and engineering drawings for Invitation to Bid (ITB) 20272002 issued by the City of Eugene for the Concourse A Passenger Boarding Bridge Upgrades project located at Eugene Airport (28801 Douglas Drive, Eugene, Oregon 97402). The project involves replacing two existing passenger boarding bridges (PBBs) at Gates A5 and A6, with Gate A6 being relocated eastward to accommodate two additional fixed bridge segments. The scope encompasses procurement of new JBT Aerotech-Jetway A3 Series bridges, civil improvements including pavement demolition and reconstruction, new foundations for bridge pedestals and height restriction signs, electrical and communications infrastructure upgrades, and structural modifications to support the relocated Gate A6. The project is divided into three phases: Phase 1 (45 calendar days) covers asphalt and concrete pavement demolition and new full-depth pavement construction; Phase 2 (15 calendar days) includes Gate A6 bridge installation and commissioning; and Phase 3 (15 calendar days) addresses decommissioning of existing bridges and installation of the proposed Gate A5 bridge. Construction is anticipated to commence in May 2027 with completion anticipated for summer 2027. The drawings are issued for bid as of June 30, 2026, with project number 20245144.006.
The project specifications and design requirements are governed by the 2022 Oregon Structural Specialty Code, 2022 Oregon Mechanical Specialty Code, 2023 Oregon Plumbing Specialty Code, 2023 Oregon Electrical Specialty Code, 2022 Oregon Fire Code, and ICC 117.1-2017 Accessibility Code. The design team includes RS&H, Inc. (prime architect-engineer), Foundation Engineering, Inc. (geotechnical), Mayer Reed (signage), Hohbach-Lewin, Inc. (structural), and KCL Engineering (electrical). The contractor is responsible for all safety and security requirements including personnel badging, vehicle AOA permits, haul route management, utility protection and locates, coordination with airport operations, and compliance with FAA advisory circulars. Significant operational constraints include restrictions on equipment height (maximum 150 feet), maintenance of existing exits and capacities, preservation of fire ratings and life safety features, and continuous coordination with active airport operations. The project requires extensive phasing coordination to minimize disruption to aircraft operations, with specific provisions for closure notifications, aircraft priority on taxiways and runways, and swept pavement maintenance during construction.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOT ISSUED FOR
CONSTRUCTION
AEC PROJECT NUMBER
REVISIONS
6/
/2
7:
:2
PM
C :\U se rs
\D ah lg re c\ Ap pD at a\ Lo ca l\A ut od es k\
R ev it\ Au to de sk R ev it
\C ol la bo ra tio nC ac he \6
2X
KP
JR
9G
G
\e de dd 3a b-af b3 -4
1-
9d
-6 0b
3f ab
9\ e0
7f
6d -5 e-
4c
-9 b2
9-
1d b1
.rv t
20245144.006
CITY OF EUGENE
EUG GATE A6 RELOCATION
28801 DOUGLAS DRIVE
EUGENE, OREGON 97402
ISSUED FOR BID
06/30/2026
FOUNDATION ENGINEERING, INC.
820 NW CORNELL AVE
CORVALLIS, OR 97330
GEOTECHNICAL: SIGNAGE:
MAYER REED
920 SW 6TH AVE
SUITE 425
PORTLAND, OR 97204
STRUCTURAL:
HOHBACH-LEWIN, INC.
296 EAST FIFTH AVE.
SUITE 302
EUGENE, OR 97401
ELECTRICAL:
KCL ENGINEERING
309 W 4TH AVENUE
SUITE 201
EUGENE, OR 97401
BUILDING ID: BLDG. ID
© 2026 RS&H, INC
Copyright © 2026. This drawing is an instrument of service and property of RS&H, Inc. Any use or reproduction without the expressed written consent of this corporation is prohibited. All rights reserved.
NO. DESCRIPTION DATE
CONCOURSE A PASSENGER BOARDING BRIDGE UPGRADES
CODE ANALYSIS
OCCUPANT LOAD (IBC/LSC)
NO CHANGE TO OCCUPANCY LOAD OR
CALCULATION. EXISTING WAITING AREA
CONVERTED TO GATE AREA
FIRE-RATED SEPARATIONS (IBC/LSC)
THE FOLLOWING FIRE RATED SEPARATIONS ARE REQUIRED:
TYPE RATING
SHAFTS (707.3.1) 1 HOUR, NO CHANGE (PER 713.4 FOR BUILDINGS OVER 4
STORIES)
ATRIUM SEPARATION (707.3.6) 1 HOUR, NO CHANGE
NOT RATED PER 1020.1 EXCEPTION 8 IN 2010 OSSC, NO CHANGE
TENANT SEPARATION (708.1) 1 HOUR, NO CHANGE
MEANS OF EGRESS (IBC)
MAXIMUM TRAVEL DISTANCE (TABLE 1016.2)
GROUP A2/ ASSEMBLY - 250 FT
GROUP A3/ ASSEMBLY - 250 FT
GROUP B/ BUSINESS - 300 FT
MAXIMUM DEAD-END CORRIDOR (1018.4)
GROUP A - 20 FT
GROUP B - 50 FT
EGRESS STAIR WIDTH (LSC 7.3.3.2) - .3" PER OCCUPANT
EGRESS WIDTH PER PERSON (LSC 7.3.3.2) - .2" PER OCCUPANT
MINIMUM CORRIDOR WIDTH (LSC12.2.3.8, 38.2.3.2) 44"
THE GENERAL SCOPE OF THE PROJECT INCLUDES REPLACING TWO EXISTING PASSENGER BOARDING BRIDGES (PBB) AND RELOCATING GATE A6 TO AN EXISTING PASSENGER WAITING AREA. THE ADDITION OF A NEW GATE COUNTER WITH ACCESS DOOR WILL BE PROVIDED BUT THERE WILL NOT BE ANY NEW ADDITIONAL SEATING/WAITING AREAS.
NO NEW SPACES OR EXITS ARE ADDED. EXISTING EXITS AND CAPACITIES TO REMAIN.
CODE ANALYSIS
APPLICABLE CODES
MINIMUM STANDARD CODES :
1988 ORIGINAL BUILDING:
1986 OSSC-1985 UBC
2008 RENOVATION:
2006 INTERNATIONAL BUILDING CODE
2007 OREGON STRUCTURAL SPECIALITY CODE
2014 TERMINAL EXPANSION:
2010 OREGON STRUCTURAL SPECIALITY CODE
2010 OREGON MECHANICAL SPECIALITY CODE
2011 OREGON PLUMBING SPECIALITY CODE
2011 OREGON ELECTRICAL SPECIALITY CODE
2010 OREGON FIRE CODE
2010 OREGON ENERGY EFFICIENCY SPECIALITY CODE
2010 OREGON SOLAR INSTALLATION SPECIALITY CODE
2024 CONCOURSE A EXPANSION:
2022 OREGON STRUCTURAL SPECIALITY CODE - CHAPTER
34 EXISTING BUILDINGS
2022 OREGON MECHANICAL SPECIALITY CODE
2023 OREGON PLUMBING SPECIALITY CODE
2023 OREGON ELECTRICAL SPECIALITY CODE
2022 OREGON FIRE CODE
2021 OREGON ENERGY EFFICIENCY SPECIALITY CODE
(OEESC) VIA ASHRAE 90.1-209
2022 NFPA1, 10
2022 NFPA 13
ICC 117.1-2017 ACCESSIBILITY CODE
OCCUPANCY CLASSIFICATION (IBC/LSC)
GROUP M/MERCANTILE: RESTAURANTS, SHOPS (EXISTING UNCHANGED)
GROUP A3/ASSEMBLY: WAITING AREAS (EXISTING UNCHANGED)
GROUP B/BUSINESS: OFFICE AREAS (EXISTING UNCHANGED)
BUILDING DATA
TOTAL GROSS BUILDING SQUARE FOOTAGE: 125,225 SF (EXISTING UNCHANGED)
NUMBER OF FLOORS: 2 (EXISTING UNCHANGED)
HEIGHT OF BUILDING: 37'-8" OVERALL (EXISTING UNCHANGED)
SPRINKLERED: Y (EXISTING UNCHANGED)
PROJECT DESCRIPTION
2026 RENOVATION - TYPE IIIB, NO CHANGE
PREVIOUS CONSTRUCTION TYPE DESIGNATIONS:
2025 RENOVATION - TYPE IIIB, NO CHANGE
2014 RENOVATION - TYPE IIIB (ENTIRE BUILDING), NO CHANGE
2008 RENOVATION - EAST BLDG IIIA AND WEST BLDG IIA
1988 NEW CONSTRUCTION - EAST BLDG TYPEII- 1 HR(SUBSTITUTION PER UBC SECTION 508; WEST
BLDG TYPE III-1HR)
PRIMARY STRUCTURAL FRAME NOT RATED, NO CHANGE
BEARING WALLS,EXTERIOR 2 HOURS, NO CHANGE
BEARING WALLS, INTERIOR NOT RATED, NO CHANGE
NONBEARING PARTITIONS, INTERIOR NOT RATED, NO CHANGE
FLOOR CONSTRUCTION NOT RATED, NO CHANGE
ROOF CONSTRUCTION NOT RATED, NO CHANGE
CONSTRUCTION CLASSIFICATION (IBC)
MINIMUM STANDARD CODES :
CURRENT:
2022 OREGON STRUCTURAL SPECIALITY CODE - CHAPTER
34 EXISTING BUILDINGS
2022 OREGON MECHANICAL SPECIALITY CODE
2023 OREGON PLUMBING SPECIALITY CODE
2023 OREGON ELECTRICAL SPECIALITY CODE
2022 OREGON FIRE CODE
2022 NFPA1, 10
2022 NFPA 13
ICC 117.1-2017 ACCESSIBILITY CODE
2022 OREGON STRUCTURAL SPECIALITY CODE (OSSC)
2025 OREGON ENERGY EFFICIENCY SPECIALITY CODE
(OEESC)
ARCHITECTURAL ABBREVIATIONS PLAN SYMBOLS
BATT INSULATION CONCRETE
EXPOSED & FINISHED WOOD TRIMGYPSUM / PLASTER
PLYWOODRIGID INSULATION
STEEL
MATERIAL SYMBOLS
STUCCO / E.I.F.S.
XX View Name
SCALE:1/8" = 1'-0"
DOOR TAG
CALLOUT HEAD & REGION
A101 A1
SIM
BUILDING SECTION
KEYNOTE
VIEW TITLE LEVEL HEAD
A1 A101
SIM
A1 A101
SIM
A1 A101
SIM
A1
A101
SIM
Name Elevation
ROOM TAG WALL TAG
XXX
DETAIL SECTION
WINDOW & STOREFRONT TAG
MATERIAL TAG
VIEW REFERENCE
REVISION TAG
NORTH ARROW
XX
ELEVATION - EXTERIOR ELEVATION - INTERIOR
WALL SECTION
CEILING TAG
GENERAL NOTES
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
A.
31.
32.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
ALL WORK SHALL CONFORM TO ALL APPLICABLE CODES, STANDARDS AND GOVERNING AUTHORITIES.
ALL DIMENSIONS ARE IN FEET / INCHES UNLESS NOTED OTHERWISE.
THESE GENERAL NOTES ARE NOT INTENDED TO REPLACE SPECIFICATIONS - REFER TO SPECIFICATIONS FOR REQUIREMENTS IN ADDITION TO GENERAL NOTES.
THE TERMS RENOVATE AND REHABILITATE ARE USED INTERCHANGEABLY IN THESE DOCUMENTS.
DO NOT SCALE THE DRAWINGS.
ROOM AREAS AND PERIMETERS ARE APPROXIMATE AND FOR REFERENCE ONLY. VERIFY QUANTITIES AND DIMENSIONS IN FIELD.
NO DEVIATIONS FROM THESE CONTRACT DOCUMENTS MUST BE MADE WITHOUT THE PRIOR WRITTEN APPROVAL OF THE ARCHITECT.
ALL DIMENSIONS ORIGINATE FROM EXISTING FACE OF WALLS & ARE TO FACE OF FRAMING AT NEW WORK OR CENTER OF DOORS, WINDOWS AND OPENINGS UNLESS NOTED OTHERWISE - ALL NON-DIMENSIONED DOOR LOCATIONS MUST BE OFFSET 4" FROM THE ADJACENT WALL TO THE HINGE SIDE OF THE DOOR OPENING. ALL DOORS MUST BE INSTALLED TO MEET ALL APPLICABLE CODES, INCLUDING ADA.
DETAILS SHOWN ON DRAWINGS ARE TYPICAL FOR ALL SIMILAR CONDITIONS.
DRAWING NOTES AND SPECIFICATIONS ARE INSTRUCTIONS TO THE CONTRACTOR AND APPLY TO ALL THE WORK UNLESS MORE SPECIFIC INFORMATION IS SHOWN ELSEWHERE ON THE DRAWINGS OR WRITTEN IN THE SPECIFICATIONS - IN THE EVENT OF CONFLICTING INSTRUCTIONS, THE ARCHITECT MUST DETERMINE WHAT CONTROLS THE CONTRACT DOCUMENTS ARE COMPLEMENTARY WHAT IS REQUIRED BY ONE MUST BE REQUIRED BY ALL.
PRINCIPAL OPENINGS IN THE STRUCTURE ARE SHOWN ON THESE DRAWINGS – EXAMINE THE ARCHITECTURAL, MECHANICAL, ELECTRICAL, AND PLUMBING DRAWINGS FOR REQUIRED OPENINGS. VERIFY SIZE AND LOCATION OF ALL OPENINGS WITH
ALL SUB-CONTRACTORS PRIOR TO CONSTRUCTION.
STRUCTURAL DRAWINGS AND SPECIFICATIONS REPRESENT THE FINISHED STRUCTURE, AND, EXCEPT WHERE SPECIFICALLY SHOWN, DO NOT INDICATE THE METHOD OR MEANS OF CONSTRUCTION - SUPERVISE CONSTRUCTION MEANS, METHODS, PROCEDURES, TECHNIQUES, SEQUENCE, AND APPLICABLE SAFETY REGULATIONS TO BE FOLLOWED.
SCHEDULING AND COORDINATE THE WORK OF THE SUB-CONTRACTORS - COORDINATE WITH THE BUILDING OWNER, TENANT OR HIS REPRESENTATIVES THE DELIVERY AND INSTALLATION OF ITEMS BEING PROVIDED AND INSTALLED BY OTHERS.
ALL MATERIALS, FABRICATION AND INSTALLATION MUST COMPLY WITH THE APPLICABLE REQUIREMENTS AND SPECIFICATIONS FOR EACH DIVISION OF WORK.
ORDER MATERIALS INCLUDED IN THESE CONTRACT DOCUMENTS IN A TIMELY MANNER - SOME ITEMS IN THESE DOCUMENTS MAY REQUIRE LONG LEAD TIMES OR SPECIAL COORDINATION. SUBSTITUTIONS WILL NOT BE ALLOWED FOR MATERIAL NOT
ORDERED IN A TIMELY FASHION.
CHECK AND VERIFY ALL DIMENSIONS AND EXISTING CONDITIONS, (BOTH NEW AND EXISTING) REPORTING ANY DISCREPANCIES TO THE ARCHITECT PRIOR TO ORDERING MATERIALS OR PROCEEDING WITH ANY PHASE OF THE WORK.
CHECK AND VERIFY ALL DIMENSIONS PRIOR TO COMMENCING CONSTRUCTION - ALL DISCREPANCIES MUST BE NOTED AND SENT TO THE ARCHITECT WITH ADEQUATE TIME TO REVIEW PRIOR TO STARTING THAT PORTION OF THE WORK IN ORDER TO
AVOID PROJECT DELAYS.
CLEAN, PATCH AND REPAIR ALL SURFACES DAMAGED BY DEMOLITION, ALTERATION OR INSTALLATION OF THE WORK.
PREPARE ALL WALLS AND PARTITIONS AS REQUIRED BY THE FINISH MANUFACTURER TO RECEIVE THE FINISHES SPECIFIED.
PROVIDE ADDITIONAL FURRING (THE ENTIRE LENGTH OF THE WALL) TO FULLY CONCEAL ALL MECHANICAL, ELECTRICAL, PLUMBING AND STRUCTURAL ITEMS THAT PROJECT FROM THE FACE OF THE WALL OR PARTITION AND ARE NOT SPECIFICALLY
NOTED TO BE SURFACE MOUNTED.
PROVIDE PORTABLE FIRE EXTINGUISHERS IN ACCORDANCE WITH LOCAL JURISDICTION AND NFPA 10. MAXIMUM TRAVEL DISTANCE TO NEAREST FIRE EXTINGUISHER FROM ANY POINT IN THE BUILDING MUST NOT EXCEED 75 FEET. EXISTING FIRE EXTINGUISHERS MUST BE TESTED AND RE-USED IF FULLY OPERATIONAL. FIRE EXTINGUISHERS MUST BE SIZED FOR NO LESS THAN ORDINARY HAZARD.
ALL REQUESTS FROM INFORMATION PROMPTED BY THE BUILDING OFFICIALS MUST INCLUDE A COPY OF THE BUILDING OFFICIALS ’ COMMENTS AND THE BUILDING INSPECTORS FIELD REPORT TO ENSURE AN ACCURATE AND TIMELY RESPONSE.
CONTRACTOR AND SUBCONTRACTOR MUST ALL BE LICENSED TO PERFORM THEIR REQUESTED DUTIES AS REQUIRED IN ACCORDANCE WITH LOCAL STANDARDS.
COMPARE STRUCTURAL SECTIONS WITH ARCHITECTURAL SECTIONS AND REPORT ANY DISCREPANCY TO THE ARCHITECT PRIOR TO FABRICATION OR INSTALLATION OF STRUCTURAL MEMBERS.
ALL EXISTING EQUIPMENT AND FINISHES THAT ARE SCHEDULED OR NOTED TO REMAIN WILL BE PROTECTED BY THE CONTRACTOR. PHOTOGRAPHS OF EXISTING CONDITIONS MUST BE PROVIDED BY THE CONTRACTOR TO DOCUMENT PRE-EXISTING
DAMAGE & FINISH CONDITIONS.
COORDINATE ALL DEMO AND NEW WORK ACTIVITIES WITH THE AIRPORT PRIOR TO PROCEEDING.
MOCK UPS (AS REQUIRED) MUST BE CONSTRUCTED BY THE CONTRACTOR PRIOR TO BEGINNING DEMOLITION WORK.
DO NOT USE ESCALATORS OR STAIRS FOR MOVING EQUIPMENT AND OR MATERIALS UNLESS COORDINATED WITH AIRPORT FACILITIES/OPERATIONS. WHEN USING ELEVATOR, ELEVATOR WALL, SIDES AND CEILING MUST BE PROTECTED FROM DAMAGE, ALL DAMAGE IS THE RESPONSIBILITY OF GENERAL CONTRACTOR AND MUST BE CORRECTED PRIOR TO PROJECT COMPLETION.
PROTECT EXISTING FINISHES, AND MAKE REPAIRS TO THE EXISTING FINISHES AND FIRE PROOFING WHERE DAMAGED OR REQUIRED FOR UNDER SLAB WORK AND CORES, AS PART OF THE NEW WORK ASSOCIATED WITH THIS PROJECT.
WHERE MATERIALS ARE APPLIED TO, OR ARE IN DIRECT CONTACT WITH WORK INSTALLED BY ANOTHER SUBCONTRACTOR, COMMENCEMENT OF WORK IMPLIES ACCEPTANCE OF THE SUBSTRATE AS SUITABLE FOR THE APPLICATION INTENDED.
ISOLATE DISSIMILAR METALS TO PREVENT GALVANIC CORROSION.
OPENINGS IN RATED WALL, FLOOR, CEILING AND ROOF ASSEMBLIES MUST BE SEALED WITH PENETRATION SEALANT SYSTEMS MEETING OR EXCEEDING THE REQUIRED FIRE RESISTIVE RATINGS.
MAINTAIN THE FIRE RATING OF CONSTRUCTION AROUND CABINETS, PANELS, AND BOXES RECESSED IN FIRE RATED WALL, FLOOR, AND CEILING ASSEMBLIES.
PROVIDE CONTINUOUS PERIMETER FIRE SAFING BETWEEN FLOORS AND COORDINATE THE INSTALLATION WITH THE EXTERIOR WALL. FIRE RATING OF SAFING MUST MATCH FIRE RATING OF FLOOR CONSTRUCTION.
FIELD MEASURE AND CONFIRM DIMENSIONS FOR OWNER PROVIDED EQUIPMENT AND FURNISHINGS.
PROVIDE STIFFENERS, BRACING, BACKING PLATES AND BLOCKING REQUIRED FOR SECURE INSTALLATION OF TOILET PARTITIONS, DOORS AND DOOR HARDWARE INCLUDING WALL-MOUNTED DOOR STOPS, HANDRAILS, WALL-MOUNTED SHELVES, OPERABLE PARTITIONS, MISCELLANEOUS EQUIPMENT, AND SUSPENDED MECHANICAL AND ELECTRICAL EQUIPMENT.
COORDINATE ALL BASE AND HOUSEKEEPING PADS WITH MECHANICAL, PLUMBING AND ELECTRICAL EQUIPMENT.
LOCATE ACCESS PANELS AS INDICATED ON DRAWINGS. FOR ACCESS PANELS NOT SHOWN BUT REQUIRED BY PROVISIONS OF THE CONTRACT DOCUMENTS, LOCATED IN ACCORDANCE WITH APPLICABLE CODES. SUBMIT PROPOSED LOCATIONS TO
THE ARCHITECT FOR REVIEW AND ACCEPTANCE PRIOR TO INSTALLATION.
ALL NON-GALVANIZED EXTERIOR EXPOSED STEEL TO RECEIVE HIGH PERFORMANCE COATING.
DO NOT OBSTRUCT ACCESS TO EXISTING EXITS, OR REDUCE THE WIDTH OF PUBLIC CORRIDORS.
PENETRATIONS IN THE EXTERIOR BUILDING WALL ARE NOT ALLOWED, INCLUDING THOSE REQUIRED FOR OUTLETS AND BLOCKING.
FULLY LAY OUT GRID, WALL, AND OPENING PLACEMENT IN AN AREA PRIOR TO START OF PARTITION CONSTRUCTION. VERIFY THAT DIMENSIONS ARE CONSISTENT WITH REQUIREMENTS INDICATED IN THE DOCUMENTS. REFER ANY DIMENSIONAL INCONSISTENCIES TO THE ARCHITECT FOR RESOLUTION PRIOR TO THE START OF PARTITION CONSTRUCTION.
FINISH FLOOR ELEVATIONS ARE TO TOP OF CONCRETE UNLESS OTHERWISE NOTED.
LEVEL FLOORS THAT EXCEED 1/4" VARIANCE IN A 10'-0" RADIUS.
COORDINATE INSTALLATION OF DIFFUSERS, SPEAKERS, SPRINKLER HEADS, AND ACCESS PANELS WITH LIGHTING LAYOUT. REPORT ANY CONFLICTS TO THE ARCHITECT PRIOR TO INSTALLATION.
EXIT SIGNS AND SMOKE DETECTORS LOCATED IN HARD CEILINGS MUST BE POSITIONED AS REQUIRED BY THE AUTHORITY HAVING JURISDICTION AND MUST BE CENTERED IN CORRIDORS AND LOCATED A DISTANCE OF 1'-0" FROM THE WALL TO THE
CENTER OF THE FIXTURE UNLESS OTHERWISE NOTED.
GANG MULTIPLE SWITCHES TOGETHER INTO ONE BOX WITH A SINGLE COVER PLATE WHENEVER POSSIBLE. MULTIPLE SWITCHES, WHICH CANNOT BE GANGED TOGETHER IN THE SAME BOX, MUST BE LOCATED S CLOSE TOGETHER AS POSSIBLE AND
MOUNTED AT THE SAME HEIGHT.
APPROVE FLOOR OUTLET LOCATIONS WITH ARCHITECT AND BUILDING MANAGEMENT PRIOR TO CORE DRILLING.
WALL OUTLETS MUST BE INSTALLED AT 18" AFF UNLESS OTHERWISE NOTED. INSTALL SWITCH PLATES AT 42" AFF UNLESS OTHERWISE NOTED.
DO NOT INSTALL OUTLET OR J-BOXES BACK-TO-BACK ON OPPOSITE SIDES OF THE WALL. BOXES MUST BE SEPARATED BY A STUD.
ALL ROOF PENETRATIONS REQUIRED FOR INSTALLATION OF MECHANICAL UNITS, EQUIPMENT CURBS, VENTS, ETC. MUST BE DONE PER MANUFACTURER'S RECOMMENDATIONS TO ENSURE ALL WARRANTIES ARE MAINTAINED. PROVIDE FLASHING, COUNTER FLASHING, SEALANT, ETC. AS REQUIRED TO PROVIDE WATERPROOF CONDITION, TYPICAL AT ALL ROOF PENETRATIONS.
12'-0"
XXXX
CEILING HEIGHT
CEILING TYPE
*NOTE - REFER TO PARTITION TYPE SHEET FOR INFO ON TAG
PT-1
FURNITURE & EQUIPMENT TAG TOILET ACCESSORY TAG
1i 1i
ROOM NAME
N
PN
X#-X
A-101
A-101
A
1 2 3 4 5 6
2 3 4 5 6
B
C
D
E
REVISIONS
DATE ISSUED:
REVIEWED BY:
DRAWN BY:
DESIGNED BY:
PROJECT NUMBER:
PROJECT STATUS:
SHEET ID:
SHEET TITLE:
PROJECT ADDRESS:
PROJECT TITLE:
SEAL:
6/
/2
7:
:2
PM
C :\U se rs
\D ah lg re c\ Ap pD at a\ Lo ca l\A ut od es k\
R ev it\ Au to de sk R ev it
\C ol la bo ra tio nC ac he \6
2X
KP
JR
9G
G
\e de dd 3a b-af b3 -4
1-
9d
-6 0b
3f ab
9\ e0
7f
6d -5 e-
4c
-9 b2
9-
1d b1
.rv t
ISSUED FOR BID
CD
MIP
28801 DOUGLAS DRIVE
EUGENE, OREGON 97402
EUG GATE A6 RELOCATION
20245144.006
06/30/2026
CD/ MIP
G002
SHEET INDEX, CODE
ANLYSIS, GENERAL
NOTES
© 2026 RS&H, INC
Copyright © 2026. This drawing is an instrument of service and property of RS&H, Inc. Any use or reproduction without the expressed written consent of this corporation is prohibited. All rights reserved.
303-409-9700
RS&H Oregon Architects - Engineers - Planners, P.C.
4582 S. Ulster St., Suite 1100 Denver, CO 80237 www.rsandh.com Oregon Registration No. 0871AF
SHEET INDEX
SHEET NUMBER SHEET NAME
00 GENERAL
G001 COVER SHEET
G002 SHEET INDEX, CODE ANLYSIS, GENERAL NOTES
G022 SURVEY CONTROL PLAN
02 CIVIL
C004 SAFETY & SECURITY NOTES & DETAILS
C005 CONTRACT LAYOUT PLAN
C010 OVERALL PHASING PLAN
C011 PHASING PLAN - PHASE 1
C012 PHASING PLAN- PHASE 2
C013 PHASING PLAN - PHASE 3
C020 BORING LOCATION PLAN
C021 GEOTECHNICAL BORING LOGS
C100 CIVIL DEMOLITION PLAN
C121 DEMOLITION TYPICAL SECTIONS
C200 PROPOSED CIVIL PLAN
C221 PROPOSED TYPICAL SECTIONS AND DETAILS (SHEET 1 OF 4)
C222 PROPOSED TYPICAL SECTIONS AND DETAILS (SHEET 2 OF 4)
C223 PROPOSED TYPICAL SECTIONS AND DETAILS (SHEET 3 OF 4)
C224 PROPOSED TYPICAL SECTIONS AND DETAILS (SHEET 4 OF 4)
C300 PROPOSED BOARDING BRIDGE PLAN
C500 GRADING PLAN
C700 PAVEMENT MARKING PLAN
C721 PAVEMENT MARKING DETAILS
03 STRUCTURAL
S001 STRUCTURAL GENERAL NOTES
S101 FOUNDATION PLAN
S102 SECOND FLOOR FRAMING PLAN
S103 ROOF FRAMING PLAN
S501 CONCRETE DETAILS
& AND
@ AT
A/C AIR CONDITIONER
AB ANCHOR BOLT
ACT ACOUSTICAL CEILING TILE
ADJ ADJUSTABLE
AFF ABOVE FINISHED FLOOR
AFS ABOVE FLOOR SLAB
AHU AIR HANDLING UNIT
ALUM ALUMINUM
ANOD ANODIZED
ANSI AMERICAN NATIONAL STANDARDS INSTITUTE
APPROX APPROXIMATE OR APPROXIMATELY
ARCH ARCHITECTURE, ARCHITECTURAL
AVG AVERAGE
AWI ARCHITECTURAL WOODWORK INSTITUTE
BHMI BUILDER'S HARDWARE MANUFACTURER'S ASSOCIATION, INC
BID BAGGAGE INFORMATION DISPLAY
BIM BUILDING INFORMATION MODELING
BLDG BUILDING
BM BEAM
BO BOTTOM OF
BUR BUILT-UP ROOFING
CFMF COLD FORMED METAL FRAMING
CJ CONTROL JOINT
CL CENTERLINE
CL OTS CENTERLINE OF TENANT SEPARATION
CLG CEILING
CLO CLOSET
CLR CLEAR
CMU CONCRETE MASONRY UNIT
COL COLUMN
COLS COLUMNS
CONC CONCRETE
CONT CONTINUOUS
DIA DIAMETER
DR DOOR
DS DOWNSPOUT
DTL OR DET DETAIL
DWG DRAWING
EA EACH
EFS EXTERIOR FACE OF SHEATHING
EJ EXPANSION JOINT
ELEC ELECTRIC, ELECTRICAL
ELEV ELEVATION
ENG ENGINEER, ENGINEERING
EOS EDGE OF SLAB
EP ELECTRICAL PANEL
EPDM ETHYLENE PROPYLENE DIENE MONOMER
EQ EQUAL
EQUIP EQUIPMENT
ERD EMERGENCY ROOF DRAIN
ETD ESTIMATED TRAVEL DISTANCE
EWC ELECTRIC WATER COOLER
EXIST EXISTING
EXP EXPANSION, EXPOSED
EXT EXTERIOR
FD FIRE DAMPER, FLOOR DRAIN
FDC FIRE DEPARTMENT CONNECTION
FDN FOUNDATION
FE FIRE EXTINGUISHER
FEC FIRE EXTINGUISHER CABINET
FF FINISHED FLOOR
FFE FINISHED FLOOR ELEVATION
FHC FIRE HOSE CABINET
FID FLIGHT INFORMATION DISPLAY
FIN. FINISH, FINISHED
FLR FLOOR
FO FACE OF
FOB FACE OF BRICK
FOP FACE OF POST
FRP FIBER REINFORCED PANEL
FT FEET
FTG FOOTING
FV FIELD VERIFY
GA GAUGE
GALV GALVANIZED
GBF GYPSUM BOARD FURRING
GID GATE INFORMATION DISPLAY
GL GLASS
GP GLOSSY PAINT
GWB GYPSUM WALL BOARD
GYP GYPSUM
HB HOSE BIB
HDW HARDWARE
HGT OR HT HEIGHT
HKS HOOKS
HM HOLLOW METAL
HORIZ HORIZONTAL
HVAC HEATING VENTILATION & AIR CONDITIONING
i.e. THAT IS, SUCH AS
ID INSIDE DIAMETER
IFS INTERIOR FACE OF STUD
IN. INCH, INCHES
INSUL INSULATION
INT INTERIOR
JAN. JANITOR
JST JOIST
JT JOINT
KP KICK PLATE
LAM LAMINATE
LAV LAVATORY
LB POUND
LDG LANDING
LONG. LONGITUDINAL
LRV LOUVER
LT LIGHT
LTG LIGHTING
LVP LUXURY VINYL PLANK
LVT LUXURY VINYL TILE
MATL MATERIAL
MAX. MAXIMUM
MECH MECHANICAL
MEP MECHANICAL, ELECTRICAL, & PLUMBING
MFGR MANUFACTURER
MGR MANAGER
MIN MINIMUM
MO MASONRY OPENING
MOD MODIFIED
MSC MISCELLANEOUS
MTL METAL
MUFID MULTI-USER FLIGHT INFORMATION DISPLAY
N/A NOT APPLICABLE
NFPA NATIONAL FIRE PROTECTION ASSOCIATION
NIC NOT IN CONTRACT
NO NUMBER
NTS NOT TO SCALE
OC ON CENTER
OD OUTSIDE DIAMETER
OFCI OWNER FURNISHED CONTRACTOR INSTALLED
OPG OPENING
OPP OPPOSITE
OSHA OCCUPATIONAL SAFETY AND HEALTH ACT
OVHD OVERHEAD
PBB PASSENGER BOARDING BRIDGE
PDU POWER DISTRIBUTION UNIT
PLAM PLASTIC LAMINATE
PLYWD PLYWOOD
PNL PANEL
PR PAIR
PRE-FAB PRE-FABRICATED
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
PT PAINT, PRESSURE TREATED
PVC POLYVINYL CHLORIDE
QT QUARRY TILE
R RADIUS
RAF RAISED ACCESS FLOOR
RAG RETURN AIR GRILLE
RB RUBBER BASE
RD ROOF DRAIN
RECEP RECEPTION, RECEPTIONIST
REF REINFORCING, REINFORCEMENT
REQ'D REQUIRED
REV REVISED, REVISION
RO ROUGH OPENING
SC SEALED CONCRETE
SCHED SCHEDULE
SCW SOLID CORE WOOD
SECT SECTION
SF SQUARE FEET
SFRM SPRAYED FIRE RESISTIVE MATERIAL
SGP SEMI-GLOSS PAINT
SHT SHEET
SHTS SHEETS
SIM SIMILAR
SPECS SPECIFICATIONS
SQ SQUARE
SQ IN. SQUARE INCHES
SS SERVICE SINK
STC SOUND TRANSMISSION CLASS
STD STANDARD
STL STEEL
STOR STORAGE
STRUCT STRUCTURAL, STRUCTURE
SUSP SUSPENDED
T&G TONGUE & GROOVE
TEL TELEPHONE
TG TEMPERED GLASS
TO STL TOP OF STEEL
TOB TOP OF BRICK, TOP OF BEAM
TOS TOP OF STEEL, TOP OF SLAB
TOSH TOP OF SHEATHING
TOW TOP OF WALL
TYP TYPICAL
UL UNDERWRITERS LABORATORIES
UON UNLESS OTHERWISE NOTED
VB VAPOR BARRIER
VCT OR VT VINYL COMPOSITION TILE
VDC VIRTUAL DESIGN & CONSTRUCTION
VERT VERTICAL
VR VIRTUAL REALITY
W/ WITH
WC WATER CLOSET
WCO WALL CLEANOUT
WD WOOD
WMP WIRE MESH PARTITION
WWF WELDED WIRE FABRIC
YD YARD
Ø DIAMETER
NO. DESCRIPTION DATE
SHEET INDEX
SHEET NUMBER SHEET NAME
07 ARCHITECTURAL
AD101 PARTIAL FIRST FLOOR DEMOLITION PLAN & INTERIOR DEMOLITION ELEVATION
A101 PARTIAL FLOOR PLAN & INTERIOR ELEVATION
A501 FINISH LEGEND, DOOR SCHEDULE, DETAILS
A701 INTERIOR MILLWORK SECTIONS AND DETAILS
A801 SIGNAGE PLAN
A850 SIGN MESSAGE SCHEDULE, SIGN COUNTS
A851 SIGN FAMILIES
A852 COLORS & TYPOGRAPHY
A860 SIGN TYPES - A2, A7, C4
26 ELECTRICAL
E000 GENERAL NOTES & SYMBOLS
E100 LEVEL 1 FLOOR PLANS
E102 GATE A6 - LEVEL 2 FLOOR PLAN
27 COMMUNICATIONS
T001 COMMUNICATIONS GENERAL NOTES, SYMBOLS AND ABBREVIATIONS
TD102 OVERALL SECOND FLOOR DEMOLITION PLAN- COMMUNICATIONS
TD102B SECOND FLOOR DEMOLITION PLAN AREA B- COMMUNICATIONS
T101 OVERALL FIRST FLOOR PLAN- COMMUNICATIONS
T101A FIRST FLOOR NEW PLAN AREA A- COMMUNICATIONS
T101B FIRST FLOOR NEW PLAN AREA B- COMMUNICATIONS
T102 OVERALL SECOND FLOOR COMMUNICATIONS PLAN
T102B SECOND FLOOR NEW PLAN AREA B- COMMUNICATIONS
T501 COMMUNICATIONS DETAILS
T701 COMMUNICATIONS BLOCK DIAGRAM
28 SECURITY
TY001 SECURITY GENERAL NOTES, SYMBOLS AND ABBREVIATIONS
TY101 OVERALL FIRST FLOOR SECURITY NEW PLAN
TY101B FIRST FLOOR NEW AREA PLAN B - SECURITY
TY102 OVERALL SECOND FLOOR SECURITY NEW PLAN
TY102B SECOND FLOOR NEW PLAN AREA B - SECURITY
TY501 SECURITY DETAILS
TY701 SECURITY SYSTEM BLOCK DIAGRAM
CONCOURSE A PASSENGER
BOARDING BRIDGE UPGRADES
S103 ROOF FRAMING PLAN
S901 COLD-FORMED STEEL FRAMING DETAILS
B
BB
B
B
B B
B
B
B B
B
B
B B
B B B
B
B B
B
B
B B
B
B
B B
B
B
B
B
B
B B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
TERMINAL
CONCOURSE A
GATE A6
CONTROL POINT TABLE
POINT #
DESCRIPTION
NTW/TARGET
NTW/TARGET
NTW/TARGET
NTW/SCRIB X 103=15
NTW/TARGET
NTW/TARGET
NORTHING
905626.30
905584.43
905553.76
905700.66
905536.35
905557.39
EASTING
4208755.05
4208815.86
4208873.31
4208707.14
4208698.16
4208646.62
ELEVATION
375.28
374.07
374.00
367.87
374.38
376.40
G022
SURVEY CONTROL
PLAN
SCALE: 1" = 10'-0"
0 10 2010
REVISIONS
DATE ISSUED:
REVIEWED BY:
DRAWN BY:
DESIGNED BY:
PROJECT NUMBER:
PROJECT STATUS:
SHEET ID:
SHEET TITLE:
PROJECT ADDRESS:
PROJECT TITLE:
SEAL:
CITY OF EUGENE
5/
/2
:0 1:
P
M Au to de sk D oc s:
//2
_E U
G T er m
E xp
P h
C on c
A Se at in g R am p/
7_
EU
G
_P h
C on c
A Se at in g_ A_
R
.rv t
ISSUED FOR BID
EJS
DJA
28801 DOUGLAS DRIVE
EUGENE, OREGON 97402
EUG GATE A6 RELOCATION
20245144006
06/30/2026
RET
Copyright © 2024. This drawing is an instrument of service and property of RS&H, Inc. Any use or reproduction without the expressed written consent of this corporation is prohibited. All rights reserved.
© 2026 RS&H, INC
303-409-9700
RS&H Oregon Architects - Engineers - Planners, P.C.
www.rsandh.com Oregon Registration No. 0871AF
4582 S. Ulster St., Suite 1100 Denver, CO 80237
NO. DESCRIPTION DATE
1 ISSUED FOR BID 06/30/2026
NORTH
NOTES:
LEGEND:
1. GROUND SURVEY AND CONTROL POINTS PROVIDED
BY EMERIO DESIGN LLC, FALL 2024.
2. HORIZONTAL VALUES ARE BASED UPON STATE
PLANE COORDINATES, OREGON SOUTH ZONE (3602).
3. ELEVATIONS SHOWN ARE BASED UPON THE NORTH
AMERICAN VERTICAL DATUM OF 1988 (NAVD 88).
4. THE CONTRACTOR SHALL VERIFY, PRIOR TO
COMMENCEMENT OF CONSTRUCTION ACTIVITIES,
ANY CONTROL POINTS TO BE USED FOR
CONSTRUCTION. ANY DISCREPANCIES SHALL BE
REPORTED TO THE ENGINEER IMMEDIATELY. THE
CONTRACTOR SHALL USE ONLY THE CONTROL
POINTS LISTED.
SURVEY CONTROL POINTS
CONCOURSE A PASSENGER
BOARDING BRIDGE
UPGRADES
C004
SAFETY &
SECURITY NOTES
& DETAILS
REVISIONS
DATE ISSUED:
REVIEWED BY:
DRAWN BY:
DESIGNED BY:
PROJECT NUMBER:
PROJECT STATUS:
SHEET ID:
SHEET TITLE:
PROJECT ADDRESS:
PROJECT TITLE:
SEAL:
CITY OF EUGENE
5/
/2
:0 1:
P
M Au to de sk D oc s:
//2
_E U
G T er m
E xp
P h
C on c
A Se at in g R am p/
7_
EU
G
_P h
C on c
A Se at in g_ A_
R
.rv t
ISSUED FOR BID
EJS
DJA
28801 DOUGLAS DRIVE
EUGENE, OREGON 97402
EUG GATE A6 RELOCATION
20245144006
06/30/2026
RET
Copyright © 2024. This drawing is an instrument of service and property of RS&H, Inc. Any use or reproduction without the expressed written consent of this corporation is prohibited. All rights reserved.
© 2026 RS&H, INC
303-409-9700
RS&H Oregon Architects - Engineers - Planners, P.C.
www.rsandh.com Oregon Registration No. 0871AF
4582 S. Ulster St., Suite 1100 Denver, CO 80237
NO. DESCRIPTION DATE
1 ISSUED FOR BID 06/30/2026
CONTRACTOR'S SAFETY AND SECURITY REQUIREMENTS
SECURITY
1. GENERAL INTENT: IT IS INTENDED THAT THE CONTRACTOR SHALL COMPLY WITH ALL REQUIREMENTS OF THE AIRPORT SECURITY PLAN AND WITH THE SECURITY REQUIREMENTS SPECIFIED HEREIN, IN THE SPECIFICATIONS AND BY EUG. THE CONTRACTOR SHALL DESIGNATE TO THE ENGINEER AND EUG, IN WRITING, THE NAME OF HIS "CONTRACTOR SAFETY AND SECURITY OFFICER (CSSO)." THE CSSO SHALL BE FULL TIME AND SHALL BE ABLE TO
REPRESENT THE CONTRACTOR ON THE SECURITY REQUIREMENTS FOR THE CONTRACT.
2. CONTRACTOR PERSONNEL SECURITY ORIENTATION: THE CSSO SHALL BE RESPONSIBLE FOR BRIEFING ALL CONTRACTOR, SUBCONTRACTOR, AND VENDOR PERSONNEL ON SECURITY REQUIREMENTS. ALL NEW CONTRACTOR PERSONNEL SHALL BE BRIEFED ON SECURITY REQUIREMENTS PRIOR TO WORKING IN THE
CONSTRUCTION AREA.
3. MATERIALS DELIVERY TO THE SITE: ALL CONTRACTOR'S MATERIAL ORDERS FOR DELIVERY TO THE WORK SITE WILL USE AS A DELIVERY ADDRESS, THE STREET NAME ASSIGNED TO THE ACCESS POINT AT THE CONTRACTOR'S STAGING SITE AT THE AIRPORT. THE CONTRACTOR SHALL TAKE STEPS TO PREVENT DELIVERY TRUCKS FROM
ENTERING INTO THE TERMINAL COMPLEX.
4. CONSTRUCTION AREA LIMITS: THE LIMITS OF CONSTRUCTION, MATERIAL STORAGE AREAS, PLANT SITE, EQUIPMENT STORAGE AREA, PARKING AREA AND OTHER AREAS DEFINED AS REQUIRED FOR THE CONTRACTOR'S EXCLUSIVE USE DURING CONSTRUCTION SHALL BE MARKED BY THE CONTRACTOR, REFER TO CONTRACT LAYOUT PLAN (C005) AND CSPP FOR LOCATIONS. TEMPORARY BARRICADES, FLAGGING AND FLASHING WARNING LIGHTS WILL BE REQUIRED AT CRITICAL ACCESS POINTS, SEE CONTRACT LAYOUT PLAN AND CSPP FOR LOCATIONS. TYPE OF MARKING AND WARNING DEVICES SHALL BE APPROVED BY THE AIRPORT ENGINEER AND BY EUG.
5. IDENTIFICATION--PERSONNEL: ALL EMPLOYEES, AGENTS, VENDORS, INVITEES, ETC. OF THE CONTRACTOR OR SUBCONTRACTORS REQUIRING ACCESS TO THE CONSTRUCTION SITE SHALL, IN ACCORDANCE WITH THE EUG SECURITY PROGRAM, BE REQUIRED TO DISPLAY AIRPORT ISSUED IDENTIFICATION OR BE UNDER ESCORT BY PROPERLY BADGED PERSONNEL. AT THE COMPLETION OF THE CONTRACT ALL BADGES WILL BE RETURNED TO THE AIRPORT. AS PART OF THE BADGE APPLICATION PROCESS, EACH APPLICANT WILL BE FINGERPRINTED FOR USE IN AN FBI CRIMINAL RECORDS SEARCH. ANY PERSON WHOSE CRIMINAL RECORD REVEALS OFFENSES LISTED BY FAA AS DISQUALIFYING OFFENSES WILL BE DENIED A BADGE AND WILL BE PROHIBITED FROM UNESCORTED ACCESS TO
THE PROJECT SITE. SEE SPECIAL CONDITIONS SECTION 1.
6. IDENTIFICATION--VEHICLES: THE CONTRACTOR, THROUGH THE CSSO, SHALL ESTABLISH AND MAINTAIN A LIST OF CONTRACTOR AND SUBCONTRACTOR VEHICLES AUTHORIZED TO OPERATE ON THE SITE AND EUG OPERATIONS SHALL ISSUE AN AOA PERMIT TO EACH VEHICLE TO BE DISPLAYED ON THE FRONT WINDSHIELD. THE DEPOSIT FOR THE AOA VEHICLE PERMIT IS $50. CONTRACTOR EMPLOYEE VEHICLES SHALL BE RESTRICTED TO THE CONTRACTOR'S EMPLOYEE PARKING AREA AND ARE NOT ALLOWED ON THE AOA AT ANY TIME. NO PERSONAL VEHICLES SHALL BE ALLOWED ON THE AIRFIELD. ALL CONSTRUCTION VEHICLES SHALL HAVE ITS CORPORATE NAME PROMINENTLY ON BOTH SIDES OF THE VEHICLE AT A SIZE THAT CAN BE EASILY DISTINGUISHED AT A DISTANCE OF 50'.
7. SIDA AREA ACCESS: ALL VEHICLES WILL BE SUBJECT TO INSPECTION WHEN ENTERING THE SIDA AREA. VEHICLES WAITING TO ENTER THE SIDA AREA MAY NOT QUEUE ON AIRCRAFT PAVEMENTS OR AT THE SIDA GATE; VEHICLES MUST WAIT OUTSIDE THE EXTERIOR AOA GATE. GATES SHALL BE SECURED WITH A GATE GUARD WHILE IN USE AND
ALL ENTRIES AND EXITS SHALL BE TRACKED.
8. SEE SPECIAL CONDITIONS FOR DETAILED SECURITY REQUIREMENTS.
1. THE CONTRACTOR SHALL ACQUAINT THEIR SUPERVISORS AND EMPLOYEES OF THE AIRPORT ACTIVITY AND OPERATIONS THAT ARE INHERENT TO THIS ACTIVE AIR CARRIER AIRPORT AND SHALL CONDUCT THE CONSTRUCTION ACTIVITIES TO CONFORM TO ALL ROUTINE AND EMERGENCY AIR TRAFFIC REQUIREMENTS AND
GUIDELINES ON SAFETY AS SPECIFIED IN THE CONTRACT DOCUMENTS.
2. ALL CONTRACTOR VEHICLES OR EQUIPMENT THAT ARE AUTHORIZED TO OPERATE ON THE AIRPORT IN THE AIRCRAFT OPERATIONS AREA (AOA) SHALL DISPLAY IN FULL VIEW A FLASHING AMBER (YELLOW) DOME-TYPE LIGHT OR ABOVE THE VEHICLE A 3' X 3' OR LARGER, ORANGE AND WHITE CHECKERBOARD FLAG, EACH CHECKERBOARD COLOR BEING 1-FOOT SQUARE, (SEE CONSTRUCTION SAFETY FLAG DETAIL THIS SHEET). ANY VEHICLE OR EQUIPMENT OPERATING IN THE AOA DURING THE HOURS OF DARKNESS SHALL BE EQUIPPED WITH A FLASHING AMBER (YELLOW) DOME LIGHT, MOUNTED ON TOP OF THE VEHICLE AND OF SUCH INTENSITY TO CONFORM TO
LOCAL CODES AND AC 150/5370-2G.
3. ALL NON-RADIO EQUIPPED CONTRACTOR VEHICLES THAT ARE REQUIRED TO OPERATE ON OR ACROSS ACTIVE RUNWAYS, TAXIWAYS, APRONS AND RUNWAY APPROACH AND PROTECTION ZONES SHALL DO SO UNDER THE DIRECT CONTROL OF A RADIO EQUIPPED ESCORT VEHICLE. ESCORT VEHICLES, OPERATORS, AND RADIO EQUIPMENT SHALL BE APPROVED BY EUG. ESCORT VEHICLES SHALL BE MARKED AND LIGHTED AS DESCRIBED IN PARAGRAPH NO. 2 ABOVE AND SHALL BE EQUIPPED WITH AN APPROVED AVIATION BAND RADIO. RADIO EQUIPPED VEHICLES SHALL CONTINUOUSLY MONITOR GROUND CONTROL FREQUENCY, AS DIRECTED BY EUG OPERATIONS.
ALL AIRCRAFT TRAFFIC ON RUNWAYS, TAXIWAYS AND APRONS SHALL HAVE PRIORITY OVER CONTRACTOR'S
TRAFFIC.
4. NO RUNWAY, TAXIWAY, APRON OR AIRPORT ROADWAY SHALL BE CLOSED WITHOUT WRITTEN APPROVAL OF EUG OPERATIONS. TO ENABLE NECESSARY "NOTICES TO AIR MISSIONS" (NOTAM) OR ADVISORIES TO AIRPORT SERVICES OR TENANTS, A MINIMUM OF 72 HOURS WRITTEN NOTICE REQUESTING CLOSURE SHALL BE DIRECTED TO THE
ENGINEER WHO WILL COORDINATE THE REQUEST WITH EUG OPERATIONS.
5. ANY CONSTRUCTION ACTIVITY WITHIN 48 FEET OF AN ACTIVE TAXIWAY EDGE (ADG III) OR OPEN EXCAVATIONS IN EXCESS OF THREE INCHES DEEP WITHIN THE ABOVE AREA, WILL REQUIRE CLOSURE OF THE AFFECTED TAXIWAY, UNLESS OTHERWISE APPROVED BY EUG. CLOSURE REQUIRES THE SAME PROVISIONS AS NOTE 4 ABOVE.
6. OPEN FLAME WELDING OR TORCH CUTTING OPERATIONS ARE PROHIBITED UNLESS ADEQUATE FIRE AND SAFETY
PRECAUTIONS HAVE BEEN TAKEN AND THE PROCEDURE APPROVED BY EUG.
7. STOCKPILED MATERIAL SHALL BE CONSTRAINED TO THE AREAS SHOWN AND APPROVED IN THE CSPP.
STOCKPILE HEIGHT SHALL BE LESS THAN 15 FEET, AND SHALL BE LOCATED OUTSIDE THE ACTIVE RUNWAY AND TAXIWAY OBJECT FREE AREAS. STOCKPILED MATERIAL IS ALLOWED WITHIN SAFETY AREAS OF CLOSED TAXIWAYS.
8. ANY TEMPORARY WASTE AREA SHALL BE APPROVED BY THE ENGINEER AND SHALL BE KEPT IN A NEAT CONDITION. EUG MAY DIRECT THE CONTRACTOR TO REMOVE WASTE IF NOT PROPERLY MAINTAINED. WASTE
SHALL BE DISPOSED OF AT THE CONTRACTORS EXPENSE.
10. DEBRIS, WASTE AND LOOSE MATERIAL CAPABLE OF CAUSING DAMAGE TO AIRCRAFT LANDING GEARS, PROPELLERS OR BEING INGESTED IN JET ENGINES SHALL NOT BE ALLOWED ON ACTIVE AIRCRAFT MOVEMENT AREAS. IF THESE MATERIALS ARE OBSERVED TO BE ON ACTIVE AIRCRAFT MOVEMENT AREAS, THEY SHALL BE
REMOVED IMMEDIATELY AND CONTINUOUSLY MONITORED DURING CONSTRUCTION.
11. THE ENGINEER WILL ARRANGE WITH EUG FOR INSPECTION PRIOR TO OPENING FOR AIRCRAFT USE ANY RUNWAY OR TAXIWAY THAT HAS BEEN CLOSED FOR WORK, ON OR ADJACENT THERETO, OR THAT HAS BEEN USED
FOR A CROSSING POINT OR HAUL ROUTE BY THE CONTRACTOR.
12. THE CONTRACTOR IS DIRECTED TO COMPLY WITH AND ACQUAINT THEIR EMPLOYEES WITH THE FOLLOWING
SAFETY GUIDELINES, RELATED MATERIALS AND FAA ADVISORY CIRCULARS:
150/5200-18D "AIRPORT SAFETY-SELF INSPECTION"
150/5210-5D "PAINTING, MARKING & LIGHTING OF VEHICLES USED ON AIRPORTS"
150/5370-2G "OPERATIONAL SAFETY ON AIRPORTS DURING CONSTRUCTION"
13. THE CONTRACTOR'S SAFETY AND SECURITY OFFICER (CSSO) WILL BE RESPONSIBLE FOR ALL SAFETY PRECAUTIONS. PRIOR TO COMMENCEMENT OF WORK, THE CSSO SHALL PROVIDE THE ENGINEER AN OUTLINE OF A PROPOSED ACCIDENT AND FIRE PROTECTION PLAN FOR ALL WORK CONTEMPLATED UNDER THE CONTRACT AND CONDUCT AT LEAST ONE SAFETY MEETING EACH MONTH FOR EACH SHIFT AND REQUIRE THE ATTENDANCE OF ALL SUPERVISORS AT SUCH MEETINGS. COPIES OF THE MINUTES OF SAFETY MEETINGS SHALL BE KEPT ON FILE IN THE CONTRACTOR'S FIELD OFFICE, COPY TO ENGINEER AND BE MADE AVAILABLE UPON DEMAND BY THE AIRPORT.
14. CONSTRUCTION DURING THE PROJECT MAY BE HALTED AT ANY TIME BY THE ENGINEER, AND/OR EUG IF IT IS DETERMINED TO BE IN THE BEST INTEREST OF EUG OR SAFETY. THE CONTRACTOR MAY BE DIRECTED TO REMOVE EQUIPMENT AND/OR EVACUATE THE SITE IN ORDER TO ENABLE AIRCRAFT OPERATIONS. NECESSARY EXTENSIONS IN CONTRACT TIME MAY BE GRANTED OR A STOP WORK ORDER WILL BE ISSUED DUE TO THESE DELAYS, HOWEVER, THERE WILL BE NO ADJUSTMENTS IN CONTRACT PRICE DUE TO THESE DELAYS.
15. ALL COMMUNICATION WITH THE AIR TRAFFIC CONTROL TOWER OR OTHER ELEMENTS OF THE AIRPORT SHALL
BE THROUGH THE ENGINEER AND EUG.
16. THE EMERGENCY NUMBER TO CALL FOR ANY INCIDENT ON THE PROJECT OR AIRPORT SHALL BE 541-682-5430 OR 541-954-6584 UNLESS OTHERWISE NOTIFIED BY EUG. EUG OPERATIONS WILL THEN DISPATCH THE
APPROPRIATE AUTHORITIES.
17. CONSTRUCTION SAFETY PHASING PLAN COMPLIANCE. THE CONTRACTOR SHALL PROVIDE A SAFETY PLAN COMPLIANCE DOCUMENT (SPCD) THAT OUTLINES HOW THE CONTRACTOR WILL COMPLY WITH THE REQUIREMENTS OF THE CONSTRUCTION SAFETY PHASING PLAN (CSPP). THIS REQUIREMENT IS DETAILED IN THE PROJECT
SPECIFICATION G-100, SAFETY AND SECURITY.
18. A DAILY SAFETY AND PROGRESS MEETING SHALL BE HELD BETWEEN THE ENGINEER, EUGENE OPERATIONS, AND THE CONTRACTOR'S SUPERINTENDENT TO DISCUSS REQUIREMENTS FOR THE NEXT NIGHTTIME WORK PERIOD.
NIGHT WORK IS ONLY ALLOWED WITH 7 DAY APPROVAL FROM AIRPORT OPERATIONS. THE CONTRACTOR SHALL PREPARE A SAFETY PLAN SPECIFIC TO NIGHTTIME CONSTRUCTION OPERATIONS, AS WELL AS A CONTINGENCY
PLAN TO ADDRESS CASES OF ABNORMAL FAILURES OR UNEXPECTED OCCURRENCES.
19. HAUL ROUTES ON THE AIRFIELD SHALL BE DELINEATED WITH LIGHTED BARRICADES AS APPLICABLE, AND AS PRACTICAL TO GUIDE CONSTRUCTION TRAFFIC BUT NOT TO IMPEDE AIRCRAFT MOVEMENT. OTHER MEANS TO
CLEARLY MARK THE ROUTES TO THE WORK SITE MAY BE APPROVED BY THE ENGINEER.
20. EQUIPMENT TALLER THAN 25' SHALL NOT BE USED UNLESS SPECIFICALLY APPROVED BY EUG.
21. CONSTRUCTION EQUIPMENT AND VEHICLES SHALL NOT BE PARKED WITHIN THE LIMITS OF RUNWAY AND TAXIWAY OBJECT FREE AREAS, REGARDLESS OF OPEN OR CLOSED STATUS OF RUNWAYS OR TAXIWAYS.
22. THE CONTRACTOR IS RESPONSIBLE FOR ENSURING AFFECTED ELECTRICAL CIRCUITS ARE DE-ENERGIZED, AND PROTECTED FROM BEING RE-ENERGIZED DURING CONSTRUCTION BY UTILIZING LOCK OUT PROCEDURES IMPACTING ELECTRICAL SYSTEMS, PER L-105, MODIFICATION, REMOVAL, AND DEMOLITION OF AIRFIELD LIGHTING SYSTEMS, AND/OR LOCAL CODES. CONTRACTOR IS NOT TO USE, TERMINATE, OPERATE OR INTERRUPT THE
AIRFIELD CIRCUITRY WITHOUT SPECIFIC WRITTEN APPROVAL OF EUG.
NOTE:
SAFETY FLAG SHALL BE
PROMINENTLY DISPLAYED
ABOVE ROOFLINE ON ALL
CONSTRUCTION EQUIPMENT
AND CONSTRUCTION VEHICLES.
NOTES:
1. LOW LEVEL, LIGHTED BARRICADES SHALL BE PLACED AROUND ALL OPEN EXCAVATIONS, HOLES, TRENCHES, PAVEMENT DROPOFFS, INFIELD SEPARATIONS, AND AREAS IDENTIFIED ON THE PHASING PLAN.
2. BARRICADES SHALL BE SHERWIN INDUSTRIES LOW-PROFILE BARRICADES MODEL AR-10X96 OR APPROVED EQUAL.
3. BARRICADES SHALL BE CONTINUOUSLY LINKED UNLESS OTHERWISE NOTED (SEE PHASING PLANS)
4. BARRICADES SHALL BE WEIGHTED WITH SAND OR WATER TO PREVENT MOVEMENT FROM JET OR PROP BLAST.
5. CONTRACTOR SHALL MAINTAIN AN INSPECTION LOG FOR BARRICADE CHECKS. BARRICADE CHECKS SHALL BE COMPLETED A MINIMUM OF ONCE A CONSTRUCTION SHIFT AND AFTER ANY CHANGE TO THE BARRICADE
POSITIONING. ANY DAMAGED BARRICADES SHALL BE PROMPTLY REPLACED.
6. THE CONTRACTOR WILL PROVIDE A SUFFICIENT NUMBER OF BARRICADES TO CLOSE THE AFFECTED CONSTRUCTION AREAS. ALL COSTS FOR THE BARRICADES, MAINTENANCE, RE-POSITIONING FOR PHASES, ETC.
SHALL BE INCLUDED IN G-100-5.1 SAFETY, SECURITY, AND TEMPORARY ITEMS. CONTRACTOR RESPONSIBLE FOR
MAINTAINING LIGHTS AND FLAGS AND PREVENT DAMAGE.
SAFETY
ORANGE BASE
6"X72" ORANGE AND WHITE
REFLECTIVE STRIPING
(BOTH SIDES)
360° RED LAMP
(SOLAR OR BATTERY POWERED)
(2 PER BARRICADE MIN.)
3'
MIN.
3' MIN.
AVIATION ORANGE
AVIATION WHITE
1. EMPLOYEE PARKING: NO CONTRACTOR'S PERSONAL EMPLOYEE VEHICLES WILL BE ALLOWED WITHIN THE AOA. THE CONTRACTOR SHALL REQUIRE EMPLOYEES TO PARK PERSONAL VEHICLES IN THE DESIGNATED
STAGING AREA OUTSIDE THE AOA FENCE.
2. UTILITY ACCESS: WATER MAY BE AVAILABLE FROM THE HYDRANT(S) IDENTIFIED ON THE PLAN. THE CONTRACTOR SHALL OBTAIN PERMISSION FROM THE LOCAL WATER UTILITY TO USE SUCH HYDRANTS. AN INSPECTION OF THE HYDRANT(S) SHALL BE CONDUCTED BY THE AIRPORT, ENGINEER, AND THE CONTRACTOR PRIOR TO USE. THE CONDITION OF THE HYDRANT(S) SHALL BE DOCUMENTED AND ANY DAMAGE TO THE HYDRANT(S) AFTER USE WILL BE FIXED AT THE CONTRACTOR'S EXPENSE. USE OF THE HYDRANT(S) IDENTIFIED ON THE PLAN WILL REQUIRE WATER TRUCKS TO FILL IN CLOSE PROXIMITY WITH THE HYDRANT(S).
PIPING TO A LOCATION NEAR THE STAGING AREA TO FILL WATER TRUCKS, ETC. WILL NOT BE PERMITTED.
ERECTION OF A WATER TOWER WILL NOT BE PERMITTED NEAR THE HYDRANT(S). CONSTRUCTION SIGNS WARNING OF WATER FILLING ACTIVITIES SHOULD BE PLACED ON EITHER SIDE OF HYDRANT. CONTRACTOR RESPONSIBLE FOR EUGENE WATER AND ELECTRIC BOARD (EWEB) COORDINATION OR TO PROVIDE
GENERATORS, AS REQUIRED.
3. SITE ACCESS: THE CONTRACTOR STAGING AREA IS OUTSIDE THE AOA FENCE AS SHOWN ON SHEET C005.
ENTRANCE TO THE WORK SITE SHALL BE THROUGH THE AOA ACCESS GATES AS CALLED OUT ON CONTRACT
LAYOUT PLAN. NO OTHER ACCESS POINTS SHALL BE ALLOWED UNLESS APPROVED BY EUG. ALL
CONTRACTOR TRAFFIC AUTHORIZED TO ENTER THE SITE SHALL BE EXPERIENCED IN THE ROUTE OR GUIDED BY CONTRACTOR PERSONNEL. THE CONTRACTOR SHALL BE RESPONSIBLE FOR TRAFFIC CONTROL TO AND FROM THE VARIOUS CONSTRUCTION AREAS ON THE SITE, AND FOR THE OPERATION AND SECURITY OF THE ACCESS GATES TO THE SITE. A CONTRACTOR'S FLAG PERSON OR TRAFFIC CONTROL PERSON SHALL MONITOR AND COORDINATE ALL CONTRACTOR TRAFFIC AT EACH ACCESS GATE AS SHOWN ON THE PLANS.
THE CONTRACTOR SHALL NOT PERMIT ANY UNAUTHORIZED CONSTRUCTION PERSONNEL OR TRAFFIC ON THE SITE. ACCESS GATES TO THE SITE SHALL BE LOCKED OR SECURED AT ALL TIMES WHEN NOT ATTENDED BY THE CONTRACTOR. IF THE CONTRACTOR CHOOSES TO LEAVE ANY ACCESS GATE OPEN, IT SHALL BE ATTENDED BY THE CONTRACTOR'S SECURITY GUARDS WHO ARE FAMILIAR WITH THE REQUIREMENTS OF THE EUG SECURITY PROGRAM AND BADGED APPROPRIATELY. HAUL ROUTE MONITORS ARE REQUIRED TO ESCORT
UNBADGED DELIVERY DRIVERS. HAUL ROUTE MONITORS ARE ONLY NEEDED DURING HAUL ROUTE
OPERATIONS.
4. ESCORTING: CONTRACTOR WILL BE REQUIRED TO HAVE AN ESCORT FOR ANY WORK THAT OCCURS IN AN ACTIVE MOVEMENT AREA. CONTRACTOR SHALL COORDINATE WITH THE AIRPORT TO ENSURE THAT AN
ESCORT IS AVAILABLE.
5. WASTE DISPOSAL AND BORROW AREAS: CONCRETE RUBBLE AND UNSUITABLE EXCAVATION WASTE MATERIAL REMOVED FROM THE CONSTRUCTION AREA SHALL BE DISPOSED OF OFF THE AIRPORT PROPERTY. NO MATERIAL SHALL BE WASTED ON THE AIRPORT SITE UNLESS APPROVED BY AIRPORT OPERATIONS. WASTE AND DISPOSAL AREAS SHALL BE SEEDED AND RESTORED IN A SMOOTH GRADED AND DRAINABLE CONDITION.
6. CONSTRUCTION LIMITS AND FLAG PERSON: ALL CONTRACTOR VEHICLES AND TRAFFIC SHALL REMAIN WITHIN THE DESIGNATED CONSTRUCTION LIMITS OR HAUL ROUTES. IT IS THE CONTRACTOR'S RESPONSIBILITY TO HAVE AN OREGON LICENSED LAND SURVEYOR LAYOUT THE PHASING LIMITS FOR EACH PHASE. ALL FLAG PERSONS WILL BE ODOT CERTIFIED, AND CONDUCT FLAGGING OPERATIONS TO ODOT STANDARDS. IT ITS THE CONTRACTOR'S RESPONSIBILITY TO PROVIDE CERTIFIED FLAGGERS. OBSERVERS AND SPOTTERS SHALL
COMPLETE ADDITIONAL TRAINING PROVIDED BY AIRPORT OPERATIONS.
ALL FLAGGERS, SPOTTERS, AND OBSERVERS CONTROLLING EQUIPMENT CROSSING ACTIVE AIRCRAFT AREAS ARE REQUIRED TO HAVE A FULLY OPERATIONAL CELLULAR TELEPHONE TO CONTACT AIRPORT OPERATIONS (541-954-6584) TO REPORT ANY PROBLEMS THAT MAY AFFECT AIRCRAFT OPERATIONS. ALL OBSERVERS AND FLAGGERS WILL IMMEDIATELY CONTACT AIRPORT OPERATIONS IF ANY EQUIPMENT BECOMES DISABLED OR IS
UNABLE TO YIELD TO AIRCRAFT FOR ANY REASON.
IF APPROVED BY THE AIRPORT OPERATIONS MANAGER, VEHICLE AND PEDESTRIAN CROSSINGS OF ACTIVE TAXIWAYS AND HIGH-USE OR CONGESTED RAMP AREAS MAY BE PERMITTED IF THE FOLLOWING PROVISIONS
ARE MET:
A. THE AIRPORT OPERATIONS MANAGER IS NOTIFIED BEFORE ANY ACTIVITY BEGINS AND WHEN THE
ACTIVITY ENDS EVERY DAY.
B. AIRPORT OPERATIONS HAS COORDINATED THE ACTIVITY WITH AIR TRAFFIC CONTROL AND HAS
ADVISED THE ENGINEER OR CONTRACTOR WHEN TO BEGIN CROSSINGS.
C. AN AIRPORT REPRESENTATIVE IS AVAILABLE TO CONTACT AIR TRAFFIC CONTROL IF THERE ARE ANY
PROBLEMS.
D. ALL INVOLVED PERSONNEL UNDERSTAND THAT ALL EQUIPMENT AND PEDESTRIANS MUST YIELD TO
ALL AIRCRAFT. AIRCRAFT ALWAYS HAVE THE RIGHT OF WAY.
E. WHEN FLAGGING OPERATIONS ARE ESTABLISHED TO CROSS ACTIVE TAXIWAYS, A FLAGGER IS
REQUIRED ON EACH SIDE OF THE TAXIWAY.
F. A DESIGNATED SWEEPER AND SWEEPER OPERATOR SHALL BE WITHIN THE
CONSTRUCTION AREA WHEN THE CONTRACTOR IS WORKING.
7. COORDINATION OF CONSTRUCTION ACTIVITIES: THE CONTRACTOR SHALL BE RESPONSIBLE FOR MAINTAINING CONSTANT COORDINATION BETWEEN THE SUBCONTRACTORS IN ADDITION TO COORDINATION WITH THE ENGINEER. OTHER CONTRACTORS CONSTRUCTION ACTIVITIES SHALL ALSO BE COORDINATED THROUGH AIRPORT OPERATIONS. ALL CONSTRUCTION ACTIVITIES PLANNED BY THE CONTRACTOR SHALL BE REVIEWED AND APPROVED BY AIRPORT OPERATIONS REPRESENTATIVES 48 HOURS IN ADVANCE OF PLANNED
ACTIVITIES.
8. AOA SPEED LIMIT: THE CONTRACTOR SHALL OPERATE WITHIN SPEED LIMITS AS DICTATED BY AIRPORT
OPERATIONS.
9. UTILITY LOCATES: THE CONTRACTOR IS REQUIRED TO HIRE A PRIVATE LOCATE COMPANY AND IS RESPONSIBLE FOR THE LOCATION AND PROTECTION OF ALL UTILITIES AND STRUCTURES IN THE PROJECT
AREA.
10. RESTORATION: ALL BORROW, STOCKPILE STORAGE, AND HAUL ROUTE AREAS, SHALL BE RESTORED BY THE CONTRACTOR BY TOPSOILING AND SEEDING PER THE SPECIFICATIONS. THIS WORK WILL BE CONSIDERED
INCIDENTAL TO MOBILIZATION ITEM.
11. WORKING HOURS: COORDINATE WORKING HOURS WITH AIRPORT OPERATIONS. INTERIOR WORK HOURS MAY BE RESTRICTED TO NIGHTTIME HOURS ONLY. EXTERIOR WORK WILL HAVE NO RESTRICTIONS ON WORK HOURS, BUT SHALL BE COORDINATED WITH THE AIRPORT TO ENSURE NO IMPACTS TO AIRPORT OR AIRCRAFT
OPERATIONS. SEE PHASING SHEETS FOR MORE DETAILED WORK HOUR RESTRICTIONS.
12. HAUL ROUTES: IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO COORDINATE OFF-SITE HAUL ROUTES (STATE HIGHWAYS, COUNTY ROADS OR CITY STREETS) WITH THE APPROPRIATE OWNER WHO HAS JURISDICTION OVER THE AFFECTED ROUTE. ON-SITE HAUL ROUTES SHALL BE MAINTAINED BY THE CONTRACTOR AND SHALL BE RESTORED TO THEIR ORIGINAL CONDITION UPON COMPLETION OF BEING USED AS A HAUL ROUTE. THE BEFORE AND AFTER CONDITION OF ON-SITE HAUL ROUTES SHALL BE JOINTLY INSPECTED AND DETERMINED BY THE CONTRACTOR, THE ENGINEER AND AIRPORT REPRESENTATIVES.
FENCING, DRAINAGE, GRADING AND OTHER MISCELLANEOUS CONSTRUCTION REQUIRED TO CONSTRUCT TEMPORARY HAUL ROUTES OR ACCESS POINTS ON THE AIRPORT WILL BE THE CONTRACTOR'S TOTAL RESPONSIBILITY AND SHALL BE APPROVED BY THE AIRPORT OPERATIONS PRIOR TO THE WORK. ALL ON-SITE FAA ACCESS ROADS TO FAA FACILITIES SHALL REMAIN OPEN AND MAINTAINED AT ALL TIMES. PHOTOGRAPHS AND A VIDEO OF THE HAUL ROUTES SPECIFIED BY THE PLANS MUST BE PROVIDED BY THE CONTRACTOR BEFORE AND AFTER CONSTRUCTION TO THE AIRPORT ADMINISTRATION. THE CONTRACTOR IS RESPONSIBLE
FOR REPAIRING ANY DAMAGE TO HAUL ROUTES RESULTING FROM CONSTRUCTION TRAFFIC.
13. HAUL ROUTE SIGNAGE: CONTRACTOR SHALL PROVIDE SIGNAGE FOR THE PROJECT HAUL ROUTES ALONG ALL VEHICLE SERVICE ROADS AND AT ALL VEHICLE SERVICE ROAD (VSR) CROSSINGS. ALL HAUL ROUTES SHALL BE SIGNED IN ACCORDANCE WITH STATE AND CITY LAWS AND REGULATIONS. HAUL ROUTE SIGNS SHALL APPROPRIATELY IDENTIFY THOSE ROUTES USED BY HEAVY CONSTRUCTION TRAFFIC. ROAD SIGNS SHALL BE MADE OF ALUMINUM AND SHALL BE MOUNTED ON SUITABLE SUPPORTS (GALVANIZED STEEL OR ALUMINUM). ALL SIGNS SHALL BE WEATHER PROOFED WITH A REFLECTORIZED AND SMOOTH SURFACE. ALL SIGNS SHALL CONFORM TO THE REQUIREMENTS OF THE MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD, 2009). SIGNS SHALL BE ADEQUATELY MOUNTED TO ENSURE STABILITY WHILE IN USE.
14. TRACKED EQUIPMENT: TRACKED CONSTRUCTION EQUIPMENT SHALL NOT BE USED ON EXISTING AIRCRAFT PAVEMENT TO REMAIN OR PROPOSED AIRCRAFT PAVEMENT. ANY DAMAGE TO VEHICLE SERVICE ROADS OR
AIRCRAFT PAVEMENT SHALL BE REPAIRED BY CONTRACTOR AT THEIR EXPENSE.
15. AIRFIELD HAUL ROUTES: THERE IS NO RESTRICTION TO THE NUMBER OF TRUCKS THAT MAY BE BROUGHT ONTO THE AIRFIELD AT ONE TIME, AS LONG AS THE SITE CAN ACCOMMODATE THEM WITHOUT IMPACTING EXIT
ROUTES, ONGOING CONSTRUCTION OPERATIONS, OR NORMAL AIRPORT OPERATIONS.
GENERAL CONTRACT NOTES
96"
SCALE:3 TYPE 1 - LOW PROFILE SAFETY BARRICADE
NTS
SCALE:2 CONSTRUCTION SAFETY FLAG
NTS
ECOLOGY BLOCK EVERY SECOND
PANEL CONNECTION, PLACED ON
AIRFIELD SIDE OF FENCE
FOUR SIDED FENCE
PANEL WITH 1.9" O.D.
PERIMETER PIPE RAIL,
TYP. EACH PANEL
(3) BOLTED CONNECTIONS AT
EACH PANEL. BOLTS ON
AIRFIELD SIDE OF FENCE
CHAIN LINK FENCE FABRIC
WITH VISUAL SCREENING FABRIC
TYP. PIPE RAIL BASE
(3) BOLTED CONNECTIONS
AT EACH PANEL. BOLTS ON
AIRFIELD SIDE OF FENCE
6'-0"
4" MAXIMUM GAP AT FENCE BOTTOM
RED FLASHING REFLECTOR
(SOLAR OR BATTERY POWERED)
(2 PER PANEL MIN.)
2'-0" MIN.
NOTES:
1. IF HALF SIZED ECONOMY BLOCKS ARE USED, THEY SHALL BE PLACED ON EACH PLATFORM.
2. GATES OR OTHER OPENINGS IN FENCE SHALL BE SECURELY LOCKED WHEN CONTRACTOR
PERSONNEL ARE NOT ON SITE.
SCALE:1 TEMPORARY CONSTRUCTION FENCE
NTS
12/31/2027
CONCOURSE A PASSENGER
X
X
X
X
X
X
X
X
X
X X
X
X X
X X
X
X X X
X
X X
X X
X X
X X
X X
X X
X X
X X
X
X
X X
X
X
X X X
X X
X X X
X X
X
X
X
X
X
X
X X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
XX
X
X
X
X
BB
B
B
B
B
B
B
B
B
B
B
B
B
B
BB
B
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
BBBBBB
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B B
B
B
B
B
B
B
B
B B
B
B
B
B
B
B B
B B
B B
B B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
BBBB
BBB
B
B
B
B
B
BBBBBBBBBBBBBBBBBB
B
B B
B B
B B
B B
BBBBBBBBB
B
BBBBBB
BBBBBB
B
B
B
B
B
BBB
B
BB
B
B
B B
B
B
B B
B
B
B B
B B B
B
B B
B
B
B B
B
B
B B
B
B
B B
B
B B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
TAXIWAY G
TERMINAL TAXILANE
CONCOURSE A TERMINAL
GATE B2
GATE B3
GATE A1
GATE A2
GATE A3
GATE A4
GATE A5
GATE A6
ATCT
AIRPORT
OPS BLDG
GATE B1
TAXIW
AY A
RUNW
AY 16R-34L
OLD AIRPORT RD.
BOEING DR.
DOUGLAS DR.
NORTHROP DR.
CONTRACTOR
ACCESS GATE 80
EXISTING
HYDRANT
LOCKHEED DR
CONTRACTOR
ACCESS GATE 97
GATE C1
1. THE CONTRACTOR SHALL MAINTAIN THE HAUL ROUTES USED
AS NECESSARY THROUGHOUT CONSTRUCTION. THIS WORK
SHALL BE PERFORMED IN ACCORDANCE WITH APPLICABLE
PROJECT SPECIFICATIONS.
2. CONTRACTOR'S ACCESS TO THE SITE SHALL BE AS SHOWN
ON THE PLANS. NO OTHER ACCESS POINTS SHALL BE
ALLOWED UNLESS APPROVED BY EUG. ALL CONTRACTOR
TRAFFIC AUTHORIZED TO ENTER THE SITE SHALL BE
EXPERIENCED IN THE ROUTE OR GUIDED BY CONTRACTOR
PERSONNEL. THE CONTRACTOR SHALL BE RESPONSIBLE
FOR TRAFFIC CONTROL TO AND FROM THE VARIOUS
CONSTRUCTION AREAS ON THE SITE, AND FOR THE
OPERATION AND SECURITY OF THE ACCESS GATES TO THE
SITE. A CONTRACTOR'S FLAG PERSON OR TRAFFIC CONTROL
PERSON SHALL MONITOR AND COORDINATE ALL
CONTRACTOR TRAFFIC AT EACH ACCESS GATE AS SHOWN
ON PLANS. THE CONTRACTOR SHALL NOT PERMIT ANY
UNAUTHORIZED CONSTRUCTION PERSONNEL OR TRAFFIC ON
THE SITE. ACCESS GATES TO THE SITE SHALL BE LOCKED
AND SECURED AT ALL TIMES WHEN NOT ATTENDED BY THE
CONTRACTOR. IF THE CONTRACTOR CHOOSES TO LEAVE
ANY ACCESS GATE OPEN, IT SHALL BE ATTENDED BY THE
CONTRACTORS SECURITY GUARDS WHO ARE FAMILIAR WITH
THE REQUIREMENTS OF THE EUG SECURITY PROGRAM AND
BADGED APPROPRIATELY. HAUL ROUTE MONITORS ARE
REQUIRED TO ESCORT UNBADGED DELIVERY TRUCK
DRIVERS. HAUL ROUTE MONITORS ARE ONLY NEEDED
DURING HAULING OPERATIONS.
3. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO
COORDINATE OFF-SITE HAUL ROUTES (STATE HIGHWAYS,
COUNTY ROADS OR CITY STREETS) WITH THE APPROPRIATE
OWNER WHO HAS JURISDICTION OVER THE AFFECTED
ROUTE. ON-SITE HAUL ROUTES SHALL BE MAINTAINED BY
THE CONTRACTOR AND SHALL BE RESTORED TO THEIR
ORIGINAL CONDITION UPON COMPLETION OF BEING USED AS
A HAUL ROUTE. THE BEFORE AND AFTER CONDITION OF
ON-SITE HAUL ROUTES SHALL BE JOINTLY INSPECTED AND
DETERMINED BY THE CONTRACTOR, THE ENGINEER AND
AIRPORT REPRESENTATIVES. FENCING, DRAINAGE, GRADING
AND OTHER MISCELLANEOUS CONSTRUCTION REQUIRED TO
CONSTRUCT TEMPORARY HAUL ROUTES OR ACCESS POINTS
ON THE AIRPORT WILL BE THE CONTRACTOR'S TOTAL
RESPONSIBILITY AND SHALL BE APPROVED BY THE AIRPORT
OPERATIONS PRIOR TO THE WORK. ALL ON-SITE FAA
ACCESS ROADS TO FAA FACILITIES SHALL REMAIN OPEN AND
MAINTAINED AT ALL TIMES. PHOTOGRAPHS AND A VIDEO OF
THE HAUL ROUTES SPECIFIED BY THE PLANS MUST BE
PROVIDED BY THE CONTRACTOR BEFORE AND AFTER
CONSTRUCTION TO THE AIRPORT ADMINISTRATION. THE
CONTRACTOR IS RESPONSIBLE FOR REPAIRING ANY DAMAGE
TO HAUL ROUTES RESULTING FROM CONSTRUCTION
TRAFFIC.
4. CONTRACTOR SHALL PROVIDE SIGNAGE FOR THE PROJECT
HAUL ROUTES ALONG ALL VEHICLE SERVICE ROADS AND AT
ALL VEHICLE SERVICE ROAD (VSR) CROSSINGS. ALL HAUL
ROUTES SHALL BE SIGNED IN ACCORDANCE WITH STATE AND
CITY LAWS AND REGULATIONS. HAUL ROUTE SIGNS SHALL
APPROPRIATELY IDENTIFY THOSE ROUTES USED BY HEAVY
CONSTRUCTION TRAFFIC. ROAD SIGNS SHALL BE MADE OF
ALUMINUM AND SHALL BE MOUNTED ON SUITABLE SUPPORTS
(GALVANIZED STEEL OR ALUMINUM). ALL SIGNS SHALL BE
WEATHER PROOFED WITH A REFLECTORIZED AND SMOOTH
SURFACE. ALL SIGNS SHALL CONFORM TO THE
REQUIREMENTS OF THE MANUAL ON UNIFORM TRAFFIC
CONTROL DEVICES (MUTCD, 2009). SIGNS SHALL BE
ADEQUATELY MOUNTED TO ENSURE STABILITY WHILE IN USE.
5. TRACKED CONSTRUCTION EQUIPMENT SHALL NOT BE USED
ON EXISTING AIRCRAFT PAVEMENT TO REMAIN OR
PROPOSED AIRCRAFT PAVEMENT. ANY DAMAGE TO VEHICLE
SERVICE ROADS OR AIRCRAFT PAVEMENT SHALL BE
REPAIRED BY CONTRACTOR AT THEIR EXPENSE.
6. HAUL ROUTE CROSSES ACTIVE AIRCRAFT AREA. AIRCRAFT
HAVE THE RIGHT OF WAY AT ALL TIMES. FLAGGERS SHALL BE
USED AS NECESSARY WHERE HAUL ROUTE CROSSES ACTIVE
AIRCRAFT ROUTES. ACTIVE AIRCRAFT AREA USED FOR
HAULING SHALL BE KEPT CLEAN AND CLEAR OF FOD AND
OTHER DEBRIS AT ALL TIMES.
NOTES:
LEGEND:
C005
CONTRACT
LAYOUT PLAN
CONTRACTOR STAGING AREA
REVISIONS
DATE ISSUED:
REVIEWED BY:
DRAWN BY:
DESIGNED BY:
PROJECT NUMBER:
PROJECT STATUS:
SHEET ID:
SHEET TITLE:
PROJECT ADDRESS:
PROJECT TITLE:
SEAL:
CITY OF EUGENE
5/
/2
:0 1:
P
M Au to de sk D oc s:
//2
_E U
G T er m
E xp
P h
C on c
A Se at in g R am p/
7_
EU
G
_P h
C on c
A Se at in g_ A_
R
.rv t
ISSUED FOR BID
EJS
DJA
28801 DOUGLAS DRIVE
EUGENE, OREGON 97402
EUG GATE A6 RELOCATION
20245144006
06/30/2026
RET
Copyright © 2024. This drawing is an instrument of service and property of RS&H, Inc. Any use or reproduction without the expressed written consent of this corporation is prohibited. All rights reserved.
© 2026 RS&H, INC
303-409-9700
RS&H Oregon Architects - Engineers - Planners, P.C.
www.rsandh.com Oregon Registration No. 0871AF
4582 S. Ulster St., Suite 1100 Denver, CO 80237
NO. DESCRIPTION DATE
1 ISSUED FOR BID 06/30/2026
GATE GUARD
PROJECT WORK AREA
CONTRACTOR HAUL ROUTE
12/31/2027
CONCOURSE A PASSENGER
XXX
X
XXX
X X
X
B
BB
B
B
B B
B
B
B B
B
B
B B
B B B
B
B B
B
B
B B
B
B
B B
B
B
B
B
B
B B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
B
TERMINAL
CONCOURSE A
GATE A6
GATE A5
GATE A4
GATE C1
PHASE 1
C010
OVERALL PHASING
PLAN
SCALE: 1" = 10'-0"
0 10 2010
REVISIONS
DATE ISSUED:
REVIEWED BY:
DRAWN BY:
DESIGNED BY:
PROJECT NUMBER:
PROJECT STATUS:
SHEET ID:
SHEET TITLE:
PROJECT ADDRESS:
PROJECT TITLE:
SEAL:
CITY OF EUGENE
5/
/2
:0 1:
P
M Au to de sk D oc s:
//2
_E U
G T er m
E xp
P h
C on c
A Se at in g R am p/
7_
EU
G
_P h
C on c
A Se at in g_ A_
R
.rv t
ISSUED FOR BID
EJS
DJA
28801 DOUGLAS DRIVE
EUGENE, OREGON 97402
EUG GATE A6 RELOCATION
20245144006
06/30/2026
RET
Copyright © 2024. This drawing is an instrument of service and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .