Solicitation number
P045372, P045373, P045374
Issued by
Spartanburg County, South Carolina

About this file

This is a Notice to Contractors issued by the South Carolina Department of Transportation (SCDOT) for the 2027 Spartanburg County Pavement Improvements project. The project encompasses approximately 14.15 miles of pavement work in Spartanburg County, with a completion deadline of November 30, 2027. Work items include mobilization, removal and disposal of existing pavement, borrow excavation, cement-modified recycled base installation, asphalt paving in multiple courses, milling of existing pavement, full-depth asphalt patching, traffic control, permanent construction signage, pavement markings in various configurations (fast-dry paint, epoxy paint, and thermoplastic materials), rumble strips, conduit and wire installation, concrete sidewalk construction, detectable warning materials, pedestrian ramp construction, and guardrail systems. The project comprises three related project numbers (P045372, P045373, and P045374) with extensive quantities across all work categories. Electronic bids will be publicly opened on September 9, 2026, at 2:00 p.m. at SCDOT Headquarters in Columbia, South Carolina. Proposal bid forms, plans, and project documents are available on the Bid Express website (www.bidx.com) beginning August 9, 2026, and hardcopy plans and proposals may be obtained from Engineering Publications for nominal fees.

Bidders must submit a bid bond equal to 5% of the approximate bid amount from a surety satisfactory to the department, submitted electronically through the Bid Express system using Form 674. The project carries a 0.00% Disadvantaged Business Enterprise (DBE) goal. Only contractors holding a valid prequalification certificate from SCDOT are eligible to submit bids. The project is federally funded under Title 23, United States Code, and is subject to Davis-Bacon Act prevailing wage requirements, Work Hours and Safety Act regulations, and federal equal employment opportunity requirements. Contractors must comply with Title VI of the Civil Rights Act of 1964 and related federal nondiscrimination provisions. Electronic bids may be declared irregular for various deficiencies, including incomplete or improperly formatted bid items, missing DBE information, unchecked acknowledgment boxes, or improper bid bond submission. SCDOT reserves the right to reject any or all proposals and waive any technicalities. All bid totals will be posted on the SCDOT website, Bid Express, and the Construction Extranet immediately following the bid opening.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION

NOTICE TO CONTRACTORS

For September 09, 2026

Letting Location:

SCDOT Headquarters Building

Conference Room 331 955 Park Street, Columbia, SC

Electronic Bids for the contracts listed herein will be publicly opened. All bid totals will be printed and posted on the SCDOT web site, Bid Express, and the Construction Extranet immediatley after bids are opened.

The following items will be made available on August 9, 2026 unless otherwise noted:

• Proposal bid forms on the Bid Express website (www.bidx.com)

• Construction Standards can be found under Business via SCDOT web site (www.scdot.org)

Access the Construction Extranet (https://www.scdot.org/business/constructionletting-extranet.aspx). for the following items:

• Proposals

• Plans

• Announcements

• Bids as Received

• CPM Schedule Templates

• Contractor Discussin Board

Contractors are encouraged to utilize the Discussion Board to make contact with other Prime and Subcontractors to request/offer quotes. There is no charge to access this site, but you must register for a user name and password.

Certain projects will require bidders to have a minimum quarterly CPS (Contractor Performance Score) issued by SCDOT. These projects will be noted accordingly to include the minimum score and quarter issued. Contractors wishing to verify their CPS may call SCDOT Construction Data Support at (803)737- 2031.

Hardcopy plans and proposals are available via Engineering Publications:

o Printed upon request only, call ahead for pickup orders o Located in room G23 SCDOT Headquarters o Email PlanStorage@scdot.org /Phone (803)737-4533/ Fax (803)737-4530 o Proposals are $15 and Plans are $2 per sheet o Cash, check, money order, VISA/MC accepted payable to SCDOT (No refunds) o Contractors do not have to buy plans to be able to bid o The Voluntary Plan Holders List is available on BIDX.

Please contact the Contract Administration Office at (803)737-7469 with all Letting related questions.

Call No.: 180 Letting Date: September 09, 2026 Letting Time: 2:00 pm Page: 1

South Carolina Department of Transportation 8/3/2026

SC File NO(S).: 4276800

DBE Goal Percent: 0.00%

Approx. Length (miles):14.1500

CO(S).: Spartanburg Description: 2027 SPARTANBURG COUNTY PAVEMENTS

Completion Date: 11/30/2027 Days Funding: ST

ITEMS OF WORK INCLUDE THE FOLLOWING:

P045372P045372PCN: Project No.:

P045373P045373PCN: Project No.:

P045374P045374PCN: Project No.:

Description Quantity Units

MOBILIZATION 1.000 LS

BONDS AND INSURANCE 1.000 LS

CONSTRUCTION STAKES, LINES & GRADES 3.000 EA

RAILROAD INSURANCE AND FLAGGING NS 1.000 LS

REMOVAL & DISPOSAL OF EXISTING PAVEMENT 723.000 SY

REMOVAL OF EXIST. GUARDRAIL 800.000 LF

BORROW EXCAVATION 2,484.000 CY

EXCAVATION FOR SHOULDER PAVING 74.448 STA

HAULING OF EXCAVATED SHOULDER MATERIAL 74.448 STA

MAINTENANCE STONE 216.000 TON

CEMENT MODIFIED RECYCLED BASE (10" UNIF)-CURING METHOD B 157,515.000 SY

PORTLAND CEMENT FOR CEMENT MODIFIED RECYCLED BASE COURSE 5,277.000 TON

HMA SHOULDER WIDENING COURSE 496.320 TON

LIQUID ASPHALT BINDER PG64-22 1,663.832 TON

ARAMID FIBER 1,659.000 LB

FULL DEPTH ASPH. PAV. PATCHING 8" UNIF 11,600.000 SY

MILLING EXISTING ASPHALT PAVEMENT 1.75" 8,976.000 SY

MILLING EXISTING ASPHALT PAVEMENT 2.0" 53,924.000 SY

MILLING EXISTING ASPHALT PAVEMENT (VARIABLE) 8,440.000 SY

ASPHALT SURFACE COURSE TYPE C 24,354.050 TON

DRIVEWAY PAVING-SURFACE TYPE C 1,662.100 TON

TRAFFIC CONTROL 1.000 LS

PERMANENT CONSTRUCTION SIGNS (GROUND MOUNTED) 3,388.000 SF

4" WHITE BROKEN LINES -(GAPS EXCLUDED)-FAST DRY PAINT 1,720.000 LF

4" WHITE SOLID LINES (PVT. EDGE LINES)-FAST DRY PAINT 297,498.000 LF

8"WHITE SOLID LINES(CROSSWALK&CHANNELIZATION)FAST DRY PAINT 2,960.000 LF

12" WHITE SOLID LINES - FAST DRY PAINT 724.000 LF

24" WHITE SOLID LINES (STOP/DIAGONAL LINES)-FAST DRY PAINT 1,244.000 LF

WHITE SINGLE ARROW (LEFT, STRAIGHT, RIGHT)-FAST DRY PAINT 8.000 EA

WHITE COMBINATION ARROW(STR.& RT.OR STR.& LT.)FAST DRY PAINT 2.000 EA

RAILROAD CROSSING SYMBOLS - FAST DRY PAINT 4.000 EA

4" YELLOW BROKEN LINES(GAPS EXC) - FAST DRY PAINT 14,400.000 LF

Call No.: 180 Letting Date: September 09, 2026 Letting Time: 2:00 pm Page: 2

South Carolina Department of Transportation 8/3/2026

Description Quantity Units

4"YELLOW SOLID LINE(PVT.EDGE&NO PASSING ZONE)-FAST DRY PAINT 523,596.000 LF

6" YELLOW SOLID LINE ON CURB/MEDIAN - FAST DRY PAINT 620.000 LF

WHITE WORD MESSAGE"YIELD"-FAST DRY PAINT 8.000 EA

4" WHITE SOLID LINES (PVT. EDGE LINES) EPOXY PAINT SLOW CURE 1,240.000 LF

4" YELLOW BROKEN LINES(GAPS EXC) EPOXY PAINT SLOW CURE 80.000 LF

4"YELLOW SOLID LINES-PVT.EDGE&NO PASSING ZONE - EPOXY PAINT SLOW

CURE

680.000 LF

4" WHITE BROKEN LINES(GAPS EXCL.)THERMOPLASTIC- 90 MIL. 690.000 LF

4" WHITE SOLID LINES (PVT. EDGE LINES) THERMO.- 90 MIL. 148,749.000 LF

8" WHITE SOLID LINES THERMOPLASTIC - 125 MIL. 1,480.000 LF

12" WHITE SOLID LINES - THERMO. - 125 MIL. 362.000 LF

24IN X 36IN WHITE TRIANG. YIELD BAR (GAPS EXC)THERMO-125MIL 65.000 LF

24" WHITE SOLID LINES (STOP/DIAG LINES)-THERMO.-125 MIL 622.000 LF

WHITE SINGLE ARROWS (LT, STRGHT, RT) THERMO.-125 MIL. 4.000 EA

WHITE WORD MESSAGE"YIELD"-THERMO-125MIL 4.000 EA

WHITE COMBINATION ARROWS(STR&RT.OR STR&LT)THERMO-125MIL 1.000 EA

WHITE COMBINATION FISH HOOK ARROW THERMO-125MIL 3.000 EA

RAILROAD CROSSING SYMBOLS - THERMOPLASTIC - 125 MIL. 2.000 EA

4" YELLOW BROKEN LINES(GAPS EXC)THERMOPLASTIC - 90 MIL. 3,600.000 LF

4" YELLOW SOLID LINES(PVT.EDGE LINES) THERMO-90 MIL. 130,899.000 LF

PERMANENT CLEAR PAVEMENT MARKERS- MONO-DIR.- 4"X4" 7.000 EA

PERMANENT YELLOW PAVEMENT MARKERS BI-DIR.- 4"X4" 949.000 EA

MILLED-IN RUMBLE STRIP 18.920 MI

FURNISH & INSTALL 1.0" SCHEDULE 80 PVC CONDUIT 210.000 LF

FURNISH & INSTL NO. 14 COPPER WIRE,1-CONDUCTOR FOR LOOP WIRE 3,770.000 LF

SAWCUT FOR LOOP DETECTOR 1,370.000 LF

F&I-13"X24"X18"D.ELEC.FLUSH UNDGRD.ENCLOS-(STR.POLY.CONC.)HD 3.000 EA

TEMPORARY ADJUSTMENT OF TRAFFIC SIGNAL EQUIPMENT 1.000 EA

CONCRETE SIDEWALK(4" UNIFORM) 336.000 SY

DETECTABLE WARNING MATERIAL 137.500 SF

PEDESTRIAN RAMP CONSTRUCTION 275.000 SY

SURFACE APPLIED DETECTABLE WARNING 190.000 SF

PREMASH RESET W-BEAM STRONG POST SYSTEM 1,000.000 LF

PREMASH TYPE T TL3 LEADING 50' 16.000 EA

PERMANENT GRASSING FOR NON-PERMITTED RESURFACING PROJECTS 11.259 ACRE

Notice is hereby given that in addition to the Standard Specifications for Highway Construction, Edition of 2025, the "Supplemental Specifications", and the "Project Special Provisions", the following govern SCDOT Highway Lettings:

STATUTES, CODES, AND REGULATIONS. The Federal-Aid Projects embraced in this advertisement contemplates the expenditure of funds pursuant to Title 23, United States Code, "Highways.

The Contractor's attention is called to the fact that the SC Department of Transportation, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78) Sta. 252 and the Regulations of the Federal Highway Administration (15 C.F.R., Part 8), issued pursuant to such act, hereby notifies all bidders that it will affirmatively insure that in any contract entered into pursuant to this advertisement minority business enterprises will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, sex, religion or national origin in consideration for award. All bidders on Federal Aid Projects must comply with the Instructions to Bidders and Special Provision covering Disadvantaged and Women Business Enterprise (DBE/WBE) included as a part of the proposal.

Attention is directed to the Fair Labor Standards Act of 1938, as amended. Contractors will be responsible for carrying out all of the provisions of this Act, which may affect these contracts. Attention is also called to the fact that any Federal Aid Project or Projects included in this notice will be subject to the Work Hours and Safety Act of 1962 as amended, PL 87-581, PL 91-54 and implementing regulations.

PREQUALIFICATION. The Contractor's attention is called to the requirements of the SC Department of Transportation for Prequalification. ONLY CONTRACTORS WHO HAVE BEEN ISSUED A

PREQUALIFICATION CERTIFICATE BY THE SC DEPARTMENT OF TRANSPORTATION WILL BE

ALLOWED TO SUBMIT BIDS. Information concerning prequalification can be obtained at the Contracts Administration office, Room 332 in the Headquarters building, 955 Park Street, Columbia, SC, or by contacting Maria Devito at (803)737-2043 or Prequal@scdot.org.

BID BONDS FOR SCDOT WORK. Unless otherwise indicated in the advertisement, no proposal will be considered unless accompanied by a bid bond in the amount of 5% of the APPROXIMATE BID AMOUNT, written by a SURETY satisfactory to the Department, properly executed in South Carolina Department of Transportation Form 674 (furnished by the Department in each proposal).

SUBMISSION OF BID BONDS. Bid Bonds must be submitted electronically, utilizing the Bid Bonds feature within the BidX Bid Form. The Bond ID number must be provided on the Surety 2000 or Tinubu (SurePath) Network electronic bond form. NO OTHER FORM OF PROPOSAL GUARANTY WILL BE ACCEPTED.

IRREGULAR ELECTRONIC BIDS. Electronic bids may be declared irregular for any of the following reasons:

1. In the schedule of Prices,

(a) alteration of a part of bid item except for the unit price; or

(b) failure to enter a bid item unit price; or

(c) a bid item unit price is not in the proper form or is incomplete.

2. In the DBE Folder, when a project has a DBE goal, in the DBE's subcontractors information, work items, unit prices, or the other required information has not been entered in the proper form fields or is incomplete.

3. In the PROPOSAL FORM,

(a) the box at the end of the form indicating acknowledgement and acceptance of the conditions set forth in the form is not checked.

4. In the Bid Bond section of the PROPOSAL FORM, the required information for appropriate form fields is not furnished.

5. A properly executed Bid Bond is not furnished in accordance with the selected manner of submission.

TIME OF THE LETTING. The Contract Administrator, or designee, at the site of the letting shall be the sole judge of determining the local time and the arrival of the designated time for the opening and reading of the bids.

THE SOUTH CAROLINA DEPARTMENT OF TRANSPORTATION RESERVES THE RIGHT TO REJECT

ANY OR ALL PROPOSALS AND WAIVE ANY TECHNICALITIES.

MINIMUM WAGE RATES FOR FAP CONTRACTS HAVE BEEN PREDETERMINED BY THE SECRETARY

OF LABOR IN ACCORDANCE WITH THE TERMS OF THE DAVIS BACON ACT AS AMENDED AND THE

FEDERAL HIGHWAY ACT OF 1956, AND LATER ACTS, AND THESE RATES WILL BE SET FORTH IN

THE PROPOSAL FORM. THIS CONTRACT IS ALSO SUBJECT TO THE WORK HOURS AND SAFETY

ACT OF 1962 AS AMENDED, PL 87-581, PL 91-54, AND IMPLEMENTING REGULATIONS.

CONTRACTORS ATTENTION IS ALSO CALLED TO THE FEDERAL REQUIREMENTS GOVERNING

SPECIFIC EQUAL EMPLOYMENT OPPORTUNITY RESPONSIBILITIES, WHICH WILL BE INCLUDED IN

THIS CONTRACT.

Information in this notice is the latest available at the time of its publication. The information contained in the proposals, plans, and any addenda issued shall govern over this notice. Quantities shown herein are approximate for information only and should not be used for bidding purposes. The Department reserves the right to change these quantities without notice.

Issued by: Travis Driggers Contract Administrator

File details come from the government source that posted it. Updated .