Southwest Region, Bridge Rehabs Rock River B-53-172 & B-53-104 STH 081
Solicitation number
20261208014
Issued by
Rusk County, Wisconsin

About this file

This document is a proposal and scope of work for bridge rehabilitation projects in Wisconsin's Southwest Region involving the Wisconsin Department of Transportation (WisDOT) and Rock County. The work encompasses replacement of bridge decks, joint replacement, concrete surface repair, backwall rehabilitation, polymer overlay application, approach slab replacement, HMA paving, guardrail replacement, and street lighting on County Town Highway Q (Structure B-53-104) and State Trunk Highway 81 (Structure B-53-172) over the Rock River. The project includes numerous special provisions covering closure notifications (3 calendar days for shoulder closures, 3 business days for lane and ramp closures), holiday and special event work restrictions from May 28, 2027 through July 6, 2028, utility coordination with Alliant Energy, City of Beloit, and Town of Beloit, and comprehensive environmental compliance including U.S. Army Corps of Engineers Section 404 permit considerations, WPDES Transportation Construction General Permit compliance with 0.4 acres of land disturbance, and Rock River navigable waterway markers. Additional requirements include coordination with the concurrent ADA Curb Ramps project (Project 5989-03-73) under Construction PM Adam Kopp, asbestos abatement for Structure B-53-104 containing 101 square feet of regulated asbestos-containing material in gasket locations, and contaminated soil management at Station 27+20.

The document specifies material requirements for modular expansion devices (utilizing high-strength low-alloy grade 50 steel, neoprene seals with minimum tensile strength of 2000 psi, stainless steel sliding surfaces, and galvanization per ASTM A123), concrete deck repair using Grade C or E concrete, and polymer overlay systems with two-component, 100 percent solids composition meeting Shore D hardness of 60-75. Contractor responsibilities include obtaining pre-construction notification verification from the U.S. Army Corps of Engineers if work extends beyond proposed slope intercepts, submitting completed DNR Form 4500-113 (Notification of Demolition and/or Renovation) at least 10 working days before asbestos abatement work, coordinating with Eagle Creek Renewable Energy regarding the downstream Beloit Dam (FERC License 2348) and maintaining access to dam walkways, and arranging a public coordination meeting at least one week before work commencement with at least 2 weeks' notice to the engineer. The contractor must also provide a technical representative from the modular expansion device manufacturer during installation and ensure compliance with all local asbestos requirements and municipal ordinances regarding waterway marker placement.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

!#��$�%��!����#�#��!"%�&�'���('�'����)**)�+��,-.����)�/#�#��0�01��2 3121�����2 ���4150�21�5���0��6 ������� 5�760�&+8+9�:98� (; /� ?��!@�A��B?

<���@>� C�>�D ��A9&:9�-'�E�A9&:9��� /%F��8� >� C B�G#< !B

B��BB

!#�$%��!����#�#��!@���!� ��B�!

�BD

B� H

��BB

�!��<�!BB

��D �����@�!B#�� �$������=��C$��#< �����D B B���I B@��!�� ��B�!

!B B����������> H !#���!B�J�!B�#��!�)���������K ���!#G�> H B���G��� !#��$�%��!����#�#��!L'*�@���)�� ;##� <����������K

���!#G��!��� C��$�#<����;KM)A�B�/

�,N� ���%��

��8@�'�'*��������J�!#�� #�J���� �#��8@�'�'8;���?!

B�"���BD�!#�?

B�A ���M!# �K��� �O P���� ��

@�;BB�

��@�J�#G@�/#�# @�Q���J�B R B �����D !B

B��BB

�@B �G�=��!@���!� #<���S B� !#�#�D B���D T#<�##<

��BB

R���!

B�!B �� ��G�� B#< ��B$���#<

���!�@F�?<=�G���C��������@�!B����BB

!B�@�!B<�� < C B#< �!B

���##�!?#<��������������BT�!B#<�##<

��BB

����G

�<�D �B�� #�G���!B�� #�G@ B�!#��!G�?�

B�!�!G ��� #�C !�!G� #��!�!�

#�#�D

��BB�!?�! �!!

#��!=�#<#<��������������B)2U�VUW�XYZV[�VUW\]Ŷ_[�U]�X̀abYW�WcYX��YZcd\e��U]f��]UgUX\h�dc_V�X̀abYWWYVZ�\V�_h_iW]UVYi�aYj�UV�Wc_��VW_]V_Wk/ B��!B��=��!�#��� �#<���B�# �lllllllllllllll,/�?!�# @� �#��G�� ��$���� �!��!.,���!#����%G�

���
@��#��G��

�J��������!�MR���

�. ,A�BB

.,���!#����%G�

�A�BB

.,A�BB

.3U]�2_g\]Wb_VW�7X_��Vhe0eg_�Um��U]fn �#� ��$�;=��B�"�# B "�# �K ���!#G�> B �#��G�/

��o��16�0�3���p�22�6���7����1�

��D���@�K��B�!?@�;??� @�J�! � ���D !#@�;��<��#���D <�����#�#��!@�J ����!B�K �@�J�! � �/�B =��C@/#����/ �@�A ���K ��B@�M�����!�J�!#���@�� !#�/�?!�!?@�%��$$� �J�!#���@���D !#�q��C�!?@�N�?<#�!?@�%��$$� �/�?!���@>

PLEASE ATTACH

PROPOSAL GUARANTY HERE

Effective with November 2007 Letting Proposal Requirements

PROPOSAL REQUIREMENTS AND CONDITIONS

The bidder, signing and submitting this proposal, agrees and declares as a condition thereof, to be bound by the following conditions and requirements.

If the bidder has a corporate relationship with the proposal design engineering company, the bidder declares that it did not obtain any facts, data, or other information related to this proposal from the design engineering company that was not available to all bidders.

The bidder declares that they have carefully examined the site of, and the proposal, plans, specifications and contract forms for the work contemplated, and it is assumed that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of the specifications, special provisions and contract. It is mutually agreed that submission of a proposal shall be considered conclusive evidence that the bidder has made such examination.

The bidder submits herewith a proposal guaranty in proper form and amount payable to the party as designated in the advertisement inviting proposals, to be retained by and become the property of the owner of the work in the event the undersigned shall fail to execute the contract and contract bond and return the same to the office of the engineer within fourteen (14) days after having been notified in writing to do so;

otherwise to be returned.

The bidder declares that they understand that the estimate of quantities in the attached schedule is approximate only and that the attached quantities may be greater or less in accordance with the specifications.

The bidder agrees to perform the said work, for and in consideration of the payment of the amount becoming due on account of work performed, according to the unit prices bid in the following schedule, and to accept such amounts in full payment of said work.

The bidder declares that all of the said work will be performed at their own proper cost and expense, that they will furnish all necessary materials, labor, tools, machinery, apparatus, and other means of construction in the manner provided in the applicable specifications and the approved plans for the work together with all standard and special designs that may be designed on such plans, and the special provisions in the contract of which this proposal will become a part, if and when accepted. The bidder further agrees that the applicable specifications and all plans and working drawings are made a part hereof, as fully and completely as if attached hereto.

The bidder, if awarded the contract, agrees to begin the work not later than ten (10) days after the date of written notification from the engineer to do so, unless otherwise stipulated in the special provisions.

The bidder declares that if they are awarded the contract, they will execute the contract agreement and begin and complete the work within the time named herein, and they will file a good and sufficient surety bond for the amount of the contract for performance and also for the full amount of the contract for payment.

Effective with November 2007 Letting Proposal Requirements

The bidder, if awarded the contract, shall pay all claims as required by Section 779.14, Statutes of Wisconsin, and shall be subject to and discharge all liabilities for injuries pursuant to Chapter 102 of the Statutes of Wisconsin, and all acts amendatory thereto. They shall further be responsible for any damages to property or injury to persons occurring through their own negligence or that of their employees or agents, incident to the performance of work under this contract, pursuant to the Standard Specifications for Road and Bridge Construction applicable to this contract.

In connection with the performance of work under this contract, the contractor agrees to comply with all applicable state and federal statutes relating to non-discrimination in employment. No otherwise qualified person shall be excluded from employment or otherwise be subject to discrimination in employment in any manner on the basis of age, race, religion, color, gender, national origin or ancestry, disability, arrest or conviction record (in keeping with s.111.32), sexual orientation, marital status, membership in the military reserve, honesty testing, genetic testing, and outside use of lawful products. This provision shall include, but not be limited to the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation, and selection for training, including apprenticeship. The contractor further agrees to ensure equal opportunity in employment to all applicants and employees and to take affirmative action to attain a representative workforce.

The contractor agrees to post notices and posters setting forth the provisions of the nondiscrimination clause, in a conspicuous and easily accessible place, available for employees and applicants for employment.

If a state public official (section 19.42, Stats.) or an organization in which a state public official holds at least a 10% interest is a party to this agreement, this contract is voidable by the state unless appropriate disclosure is made to the State of Wisconsin Ethics Board.

Effective with August 2015 Letting Bid Preparation

BID PREPARATION

Preparing the Proposal Schedule of Items A. General

(1) Obtain bidding proposals as specified in section 102 of the standard specifications prior to 11:45 AM of the last business day preceding the letting. Submit bidding proposals using one of the following methods:

1. Electronic bid on the internet.

2. Electronic bid on a printout with accompanying diskette or CD ROM.

3. Paper bid under a waiver of the electronic submittal requirements.

(2) Bids submitted on a printout with accompanying diskette or CD ROM or paper bids submitted under a waiver of the electronic submittal requirements govern over bids submitted on the internet.

(3) The department will provide bidding information through the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx

The contractor is responsible for reviewing this web site for general notices as well as information regarding proposals in each letting. The department will also post special notices of all addenda to each proposal through this web site no later than 4:00 PM local time on the Thursday before the letting. Check the department’s web site after 5:00 PM local time on the Thursday before the letting to ensure all addenda have been accounted for before preparing the bid. When bidding using methods 1 and 2 above, check the Bid ExpressΤΜ on-line bidding exchange at http://www.bidx.com/ after 5:00 PM local time on the Thursday before the letting to ensure that the latest schedule of items Expedite file (*.ebs or *.00x) is used to submit the final bid.

(4) Interested parties can subscribe to the Bid ExpressΤΜ on-line bidding exchange by following the instructions provided at the www.bidx.com web site or by contacting:

Info Tech Inc.

5700 SW 34th Street, Suite 1235 Gainesville, FL 32608-5371 email: mailto:customer.support@bidx.com

(5) The department will address equipment and process failures, if the bidder can demonstrate that those failures were beyond their control.

(6) Contractors are responsible for checking on the issuance of addenda and for obtaining the addenda. Notice of issuance of addenda is posted on the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx or by calling the department at (608) 266-1631. Addenda can ONLY be obtained from the department’s web site listed above or by picking up the addenda at the Bureau of Highway Construction, 4th floor, 4822 Madison Yards Way, Madison, WI, during regular business hours.

(7) Addenda posted after 5:00 PM on the Thursday before the letting will be emailed to the eligible bidders for that proposal. All eligible bidders shall acknowledge receipt of the addenda whether they are bidding on the proposal or not. Not acknowledging receipt may jeopardize the awarding of the project.

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx http://www.bidx.com/ http://www.bidx.com/ mailto:customer.support@bidx.com

B. Submitting Electronic Bids B.1 On the Internet

(1) Do the following before submitting the bid:

4. Have a properly executed annual bid bond on file with the department.

5. Have a digital ID on file with and enabled by Info Tech Inc. Using this digital ID will constitute the bidder's signature for proper execution of the bidding proposal.

(2) In lieu of preparing, delivering, and submitting the proposal as specified in 102.6 and 102.9 of the standard specifications, submit the proposal on the internet as follows:

1. Download the latest schedule of items reflecting all addenda from the Bid ExpressΤΜ web site.

2. Use ExpediteΤΜ software to enter a unit price for every item in the schedule of items.

3. Submit the bid according to the requirements of ExpediteΤΜ software and the Bid ExpressΤΜ web site. Do not submit a bid on a printout with accompanying diskette or CD ROM or a paper bid. If the bidder does submit a bid on a printout with accompanying diskette or a paper bid in addition to the internet submittal, the department will disregard the internet bid

4. Submit the bid before the hour and date the Notice to Contractors designates

5. Do not sign, notarize, and return the bidding proposal described in 102.2 of the standard specifications.

(3) The department will not consider the bid accepted until the hour and date the Notice to Contractors designates.

B.2 On a Printout with Accompanying Diskette or CD ROM

(1) Download the latest schedule of items from the Wisconsin pages of the Bid Express web site reflecting the latest addenda posted on the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx

Use ExpediteΤΜ software to prepare and print the schedule of items. Provide a valid amount for all price fields. Follow instructions and review the help screens provided on the Bid ExpressΤΜ web site to assure that the schedule of items is prepared properly.

(2) Staple an 8 1/2 by 11 inch printout of the Expedite generated schedule of items to the other proposal documents submitted to the department as a part of the bidder's sealed bid. As a separate submittal, not in the sealed bid envelop but due at the same time and place as the sealed bid, also provide the ExpediteΤΜ generated schedule of items on a 3 1/2 inch computer diskette or CD ROM. Label each diskette or CD ROM with the bidder's name, the 4 character department-assigned bidder identification code from the top of the bidding proposal, and a list of the proposal numbers included on that diskette or CD ROM as indicated in the following example:

Bidder Name

BN00

Proposals: 1, 12, 14, & 22

(3) If bidding on more than one proposal in the letting, the bidder may include all proposals for that letting on one diskette or CD ROM. Include only submitted proposals with no incomplete or other files on the diskette or CD ROM.

(4) The bidder-submitted printout of the Expedite generated schedule of items is the governing contract document and must conform to the requirements of section 102 of the standard specifications. If a printout needs to be altered, cross out the printed information with ink or typewriter and enter the new information and initial it in ink. If there is a discrepancy between the printout and the diskette or CD ROM, the department will analyze the bid using the printout information.

(5) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:

1. The check code printed on the bottom of the printout of the ExpediteΤΜ generated schedule of items is not the same on each page.

2. The check code printed on the printout of the ExpediteΤΜ generated schedule of items is not the same as the check code for that proposal provided on the diskette or CD ROM.

3. The diskette or CD ROM is not submitted at the time and place the department designates.

B Waiver of Electronic Submittal

(1) The bidder may request a waiver of the electronic submittal requirements. Submit a written request for a waiver in lieu of bids submitted on the internet or on a printout with accompanying diskette or CD ROM. Use the waiver that was included with the paper bid document sent to the bidder or type up a waiver on the bidder’s letterhead. The department will waive the electronic submittal requirements for a bidding entity (individual, partnership, joint venture, corporation, or limited liability company) for up to 4 individual proposals in a calendar year. The department may allow additional waivers for equipment malfunctions.

(2) Submit a schedule of items on paper conforming to section 102 of the standard specifications.

The department charges the bidder a $75 administrative fee per proposal, payable at the time and place the department designates for receiving bids, to cover the costs of data entry. The department will accept a check or money order payable to: "Wisconsin, Dept. of Transportation."

(3) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:

1. The bidder fails to provide the written request for waiver of the electronic submittal requirements.

2. The bidder fails to pay the $75 administrative fee before the time the department designates for the opening of bids unless the bidder requests on the waiver that they be billed for the $75.

3. The bidder exceeds 4 waivers of electronic submittal requirements within a calendar year.

(4) In addition to the reasons specified in section 102 of the standard specifications, the department may refuse to issue bidding proposals for future contracts to a bidding entity that owes the department administrative fees for a waiver of electronic submittal requirements.

PROPOSAL BID BOND Wisconsin Department of Transportation

DT1303 1/2006

Proposal Number Project Number Letting Date

Name of Principal

Name of Surety State in Which Surety is Organized

We, the above-named Principal and the above-named Surety, are held and firmly bound unto the State of Wisconsin in the sum equal to the Proposal Guaranty for the total bid submitted for the payment to be made; we jointly and severally bind ourselves, our heirs, executors, administrators, successors and assigns. The condition of this obligation is that the Principal has submitted a bid proposal to the State of Wisconsin acting through the Department of Transportation for the improvement designated by the Proposal Number and Letting Date indicated above.

If the Principal is awarded the contract and, within the time and manner required by law after the prescribed forms are presented for signature, enters into a written contract in accordance with the bid, and files the bond with the Department of Transportation to guarantee faithful performance and payment for labor and materials, as required by law, or if the Department of Transportation shall reject all bids for the work described, then this obligation shall be null and void; otherwise, it shall be and remain in full force and effect.

In the event of failure of the Principal to enter into the contract or give the specified bond, the Principal shall pay to the Department of Transportation within 10 business days of demand a total equal to the Proposal Guaranty as liquidated damages; the liability of the Surety continues for the full amount of the obligation as stated until the obligation is paid in full.

The Surety, for value received, agrees that the obligations of it and its bond shall not be impaired or affected by any extension of time within which the Department of Transportation may accept the bid; and the Surety does waive notice of any such extension.

IN WITNESS, the Principal and Surety have agreed and have signed by their proper officers and have caused their corporate seals to be affixed this date: (DATE MUST BE ENTERED)

PRINCIPAL

(Company Name) (Affix Corporate Seal)

(Signature and Title)

(Company Name)

(Signature and Title)

(Company Name)

(Signature and Title)

(Company Name)

(Signature and Title)

NOTARY FOR PRINCIPAL

(Date)

State of Wisconsin ) ) ss.

County )

On the above date, this instrument was acknowledged before me by the named person(s).

(Signature, Notary Public, State of Wisconsin)

(Print or Type Name, Notary Public, State of Wisconsin)

(Date Commission Expires)

Notary Seal

(Name of Surety) (Affix Seal)

(Signature of Attorney-in-Fact)

NOTARY FOR SURETY

(Date)

State of Wisconsin ) ) ss.

County )

On the above date, this instrument was acknowledged before me by the named person(s).

(Signature, Notary Public, State of Wisconsin)

(Print or Type Name, Notary Public, State of Wisconsin)

(Date Commission Expires)

Notary Seal

IMPORTANT: A certified copy of Power of Attorney of the signatory agent must be attached to the bid bond.

CERTIFICATE OF ANNUAL BID BOND Wisconsin Department of Transportation

DT1305 8/2003

Time Period Valid (From/To)

Name of Surety

Name of Contractor

Certificate Holder Wisconsin Department of Transportation

This is to certify that an annual bid bond issued by the above-named Surety is currently on file with the Wisconsin Department of Transportation.

This certificate is issued as a matter of information and conveys no rights upon the certificate holder and does not amend, extend or alter the coverage of the annual bid bond.

Cancellation: Should the above policy be cancelled before the expiration date, the issuing surety will give thirty (30) days written notice to the certificate holder indicated above.

(Signature of Authorized Contractor Representative) (Date)

Effective with March 2010 Letting

LIST OF SUBCONTRACTORS

Section 66.0901(7), Wisconsin Statutes, provides that as a part of the proposal, the bidder also shall submit a list of the subcontractors the bidder proposes to contract with and the class of work to be performed by each. In order to qualify for inclusion in the bidder's list a subcontractor shall first submit a bid in writing, to the general contractor at least 48 hours prior to the time of the bid closing. The list may not be added to or altered without the written consent of the municipality. A proposal of a bidder is not invalid if any subcontractor and the class of work to be performed by the subcontractor has been omitted from a proposal; the omission shall be considered inadvertent or the bidder will perform the work personally.

No subcontract, whether listed herein or later proposed, may be entered into without the written consent of the Engineer as provided in Subsection 108.1 of the Standard Specifications.

Name of Subcontractor Class of Work Estimated Value

Effective with December 2000 Letting Debarment Certification

CERTIFICATION REGARDING DEBARMENT, SUSPENSION, AND OTHER

RESPONSIBILITY MATTERS - PRIMARY COVERED TRANSACTIONS

Instructions for Certification

1. By signing and submitting this proposal, the prospective contractor is providing the certification set out below.

2. The inability of a person to provide the certification required below will not necessarily result in denial of participation in this covered transaction. The prospective contractor shall submit an explanation of why it cannot provide the certification set out below. The certification or explanation will be considered in connection with the department or agency's determination whether to enter into this transaction. However, failure of the prospective contractor to furnish a certification or an explanation shall disqualify such person from participation in this transaction.

3. The certification in this clause is a material representation of fact upon which reliance was placed when the department determined to enter into this transaction. If it is later determined that the contractor knowingly rendered an erroneous certification in addition to other remedies available to the Federal Government the department may terminate this transaction for cause or default.

4. The prospective contractor shall provide immediate written notice to the department to whom this proposal is submitted if at any time the prospective contractor learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.

5. The terms "covered transaction," "debarred," "suspended," "ineligible," "lower tier covered transaction," "participant," "person," "primary covered transaction," "principal," "proposal," and "voluntarily excluded," as used in this clause, have the meanings set out in the Definitions and Coverage sections of the rules implementing Executive Order 12549. You may contact the department to which this proposal is being submitted for assistance in obtaining a copy of those regulations.

6. The prospective contractor agrees by submitting this proposal that, should this contract be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department entering into this transaction.

7. The prospective contractor further agrees by submitting this proposal that it will include the clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered Transaction," which is included as an addendum to PR- 1273 - "Required Contract Provisions Federal Aid Construction Contracts," without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions.

8. The contractor may rely upon a certification of a prospective subcontractor/materials supplier that it is not debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A contractor may decide the method and frequency by which it determines the eligibility of its principals. Each contractor may, but is not required to, check the Disapproval List (telephone # 608/266/1631).

Effective with December 2000 Letting Debarment Certification

9. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render in good faith the certification required by this clause. The knowledge and information of a contractor is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.

10. Except for transactions authorized under paragraph 6 of these instructions, if a contractor in a covered transaction knowingly enters into a lower tier covered transaction with a person who is suspended, debarred, ineligible or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department may terminate this transaction for cause or default.

Certification Regarding Debarment, Suspension, and Other Responsibility Matters - Primary Covered Transactions

1. The prospective contractor certifies to the best of its knowledge and belief, that it and its principals:

(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency;

(b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements or receiving stolen property;

(c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offense enumerated in paragraph (1)(b) of this certification; and

(d) Have not within a three-year period preceding this proposal had one or more public transactions (Federal, State or local) terminated for cause or default.

2. Where the prospective contractor is unable to certify to any of the statements in this certification, such prospective contractor shall attach an explanation to this proposal.

5989-03-84 1 of 43

Special Provisions Table of Contents

Article Description Page #

1. General

2. Scope of Work

3. Prosecution and Progress

4. Traffic

5. Holiday and Special Event Work Restrictions

6. Utilities

7. Other Contracts

8. Information to Bidders, U.S. Army Corps of Engineers Section 404 Permit

9. Information to Bidders, WPDES Transportation Construction General Permit (TCGP) for Storm

Water Discharges

10. Construction Over or Adjacent to Navigable Waters

11. Notice to Contractor, Contamination Beyond Construction Limits

12. Notice to Contractor, Verification of Asbestos Inspection, No Asbestos Found

13. Notice to Contractor – Beloit Dam

14. Coordination with Businesses and Residents

15. Removing Structure over Waterway Minimal Debris B-53-104

16. Abatement of Asbestos Containing Material B-53-104, Item 203.0211.S

17. Expansion Device Modular, Item 502.3111.S

18. Removing Bearings B-53-104, Item 506.7050.S

19. Sawing Pavement Deck Preparation Areas, Item 509.0310.S

20. Concrete Masonry Deck Repair, Item 509.2100.S

21. Polymer Overlay, Item 509.5100.S

22. Epoxy Injection Crack Repair, Item 509.9025.S; Cored Holes 2-Inch Diameter, Item 509.9026.S

23. Structure Repainting General

24. Preparation and Coating of Top Flanges B-53-104, Item 517.0901.S

25. Structure Overcoating Cleaning and Priming B-53-104, Item 517.3001.S

26. Containment and Collection of Waste Materials B-53-104, Item 517.4001.S

27. Portable Decontamination Facility, Item 517.6001.S

28. Traffic Signals General

29. Loop Detector Cable, Item 655.0700

30. Incentive Strength Concrete Structures, Item 715.0502; Incentive Air Content Concrete

Structures, SPV.0055.01

31. Installing and Maintaining Bird Deterrent System Station 20+42, Item 999.2000.S.01; Installing and Maintaining Bird Deterrent System Station 25+86, 999.2000.S.02; Installing and Maintaining Bird Deterrent System Station 32+00, Item 999.2000.S.03

32. Temporary Rectangular Rapid Flashing Beacon With Push Button, Item SPV.0060.01

33. Top of Girder Survey B-53-104, Item SPV.0060.02

34. Salvage Lighting Units, Item SPV.0060.03

5989-03-84 2 of 43

35. Cored Holes 6-Inch, Item SPV.0060.04

36. Concrete Curb and Gutter 60-Inch Type A, Item SPV.0090.01

37. Excavation, Hauling, and Disposal of Metals Contaminated Soil, Item SPV.0195.01

5989-03-84 3 of 43

STSP’S Revised July 1, 2026

SPECIAL PROVISIONS

1. General.

Perform the work under this construction contract for the following projects:

Project ID 5989-03-84 Southwest Region, Bridge Rehabs Rock River B-53-172 & B-53-104

STH 081

Rock County

Perform the work as the plans show and execute the work as specified in the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition, as published by the department, and these special provisions.

If all or a portion of the plans and special provisions are developed in the SI metric system and the schedule of prices is developed in the US standard measure system, the department will pay for the work as bid in the US standard system.

100-005 (20260701)

2. Scope of Work.

The work under this contract consists of replacement of the deck, joint replacement, spot painting of girders, concrete surface repair, backwall rehab, polymer overlay, approach slab replacement, HMA paving, guardrail replacement, base aggregate, select crushed material, and street lighting on CTH Q (B- 53-104); and joint replacement, abutment backwall replacement, concrete surface repair, spot painting of parapets, polymer overlay, and approach slab replacement on STH 81 (B-53-172) and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract.

104-005 (20090901)

3. Prosecution and Progress.

Begin work within 10 calendar days after the engineer issues a written notice to do so.

Provide the start date to the engineer in writing within a month after executing the contract but at least 14 calendar days before the preconstruction conference. Upon approval, the engineer will issue the notice to proceed within ten calendar days before the approved start date.

To revise the start date, submit a written request to the engineer at least two weeks before the intended start date. The engineer will approve or deny that request based on the conditions cited in the request and its effect on the department’s scheduled resources.

Complete polymer overlay and permanent pavement marking on CTH Q in 2028. Close CTH Q for a maximum of 14 calendar days after June 18, 2028 to complete this work.

Interim Completion and Liquidated Damages – CTH Q, All work items except polymer overlay and permanent pavement marking: November 15, 2027 Complete construction operations on CTH Q to the stage necessary to reopen it to through traffic by November 15, 2027. Do not reopen until completing the following work: Complete all work except polymer overlay and permanent pavement marking.

If the contractor fails to complete the work necessary to reopen CTH Q to traffic by November 15, 2027, the department will assess the contractor $2,800 in interim liquidated damages for each calendar day the contract work remains incomplete beyond 12:01 AM on November 16, 2027. An entire calendar day will be charged for any period of time within a calendar day that the road remains closed beyond 12:01 AM.

If contract time expires prior to completing all work specified in the contract, additional liquidated damages will be affixed according to standard spec 108.11.

5989-03-84 4 of 43

Migratory Birds Swallow or other migratory bird nests have been observed on or under the existing structure(s) listed below. All active nests (when eggs or young are present) of migratory birds are protected from purposeful take under the federal Migratory Bird Treaty Act. The nesting season for swallows and other birds is from April 15 to August 31.

Either prevent active nests from becoming established or prevent birds from nesting by installing and/or maintaining one suitable deterrent device on the following structure(s) prior to nesting season under the bid item Installing and Maintaining Bird Deterrent System:

• B-53-172 (STH 81 – West End)

• B-53-072 (STH 81 – East End)

• B-53-104 (CTH Q)

Fish Spawning There shall be no instream disturbance of the Rock River at Station 23+14.62 on STH 81 (B-53-172) and at Station 31+80 on CTH Q (B-53-104) as a result of construction activity under or for this contract, from March 15th to June 15th both dates inclusive, in order to avoid adverse impacts upon the spawning of aquatic species.

Any change to this limitation will require submitting a written request by the contractor to the engineer, subsequent review and concurrence by the Department of Natural Resources in the request, and final approval by the engineer. The approval will include all conditions to the request as mutually agreed upon by WisDOT and DNR.

Spudding barges at the CTH Q bridge will not be considered an instream disturbance.

Staged Construction Schedule of operations shall conform to the construction staging concept and schedule provided in the plan unless the engineer approves modifications in writing. The stages listed below are shown in the plan.

Major items of work associated with each stage are identified.

STH 81 (Portland Ave) – Stage 1

• Remove and replace concrete approach slabs on EB lanes

• Replace backwall and joint

• Concrete surface repairs

STH 81 (Portland Ave) – Stage 2

• Remove and replace concrete approach slabs on WB lanes

• Replace backwall and joint

• Concrete surface repairs

STH 81 (Portland Ave) – Stage 3A

• Polymer overlay placement on outside EB lane, bike lane, and sidewalk

• Pavement marking

STH 81 (Portland Ave) – Stage 3B

• Polymer overlay placement on inside EB lane

• Pavement marking

STH 81 (Portland Ave) – Stage 4A

• Polymer overlay placement on inside WB lane

• Pavement marking

STH 81 (Portland Ave) – Stage 4B

• Polymer overlay placement on outside WB lane, bike lane, and sidewalk

• Pavement marking

5989-03-84 5 of 43

CTH Q (Newark Rd) - Stage 1

• Redeck, joint replacement, replace railing, paint at joints, permanent pavement marking on approaches, temporary pavement marking on bridge

CTH Q (Newark Rd) - Stage 2

• Polymer overlay, permanent pavement marking on bridge

Contractor shall not leave STH 81 site for more than seven (7) calendar days without work occurring except for cure time.

4. Traffic.

Close CTH Q (Newark Rd.) to through traffic during construction. Detour CTH Q through traffic using CTH D, Maple Ave/Henry Ave and USH 51.

STH 81 (Portland Ave.) will be open to through traffic with traffic control during construction.

Traffic Operations STH 81 – Stage 1

• STH 81 EB lanes closed

• STH 81 EB traffic shifted to existing WB side

• 1 lane of traffic open for STH 81 EB and WB traffic

STH 81 – Stage 2

• STH 81 WB lanes closed

• STH 81 WB traffic shifted to existing EB side

• 1 lane of traffic open for STH 81 EB and WB traffic

STH 81 – Stage 3A

• STH 81 EB outside lane and sidewalk closed and traffic shifted to center of bridge with barrels

• STH 81 WB inside lane closed and traffic on existing outside lane

• 1 lane of traffic open for STH 81 EB and WB traffic

STH 81 – Stage 3B

• STH 81 EB sidewalk and inside lane closed and traffic on existing outside lane

• STH 81 WB inside lane closed and traffic on existing outside lane

• 1 lane of traffic open for STH 81 EB and WB traffic

STH 81 – Stage 4A

• STH 81 EB sidewalk and inside lane closed and traffic on existing outside lane

• STH 81 WB inside lane closed and traffic on existing outside lane

• 1 lane of traffic open for STH 81 EB and WB traffic

STH 81 – Stage 4B

• STH 81 EB inside lane closed and traffic on existing outside lane

• STH 81 WB outside lane and sidewalk closed and traffic shifted to center of bridge with barrels

• 1 lane of traffic open for STH 81 EB and WB traffic

CTH Q (Newark Rd.)

• Bridge will be closed for the duration of the project with a posted detour.

Single lane closures on STH 81 will be allowed for setting concrete barrier wall temporary precast and for permanent pavement marking.

5989-03-84 6 of 43

PCMS Prewarn Place Portable Changeable Message Signs (PCMS) 7 days prior to construction.

Wisconsin Lane Closure System Advance Notification Provide the following advance notification to the engineer for incorporation into the Wisconsin Lane Closure System (LCS).

TABLE 108-1 CLOSURE TYPE AND REQUIRED MINIMUM ADVANCE NOTIFICATION

Closure type with height, weight, or width restrictions (available width, all lanes in one direction < 16 feet) MINIMUM NOTIFICATION

Lane and shoulder closures 7 calendar days

Full roadway closures 7 calendar days

Ramp closures 7 calendar days

Detours 7 calendar days

Closure type without height, weight, or width restrictions (available width, all lanes in one direction > 16 feet) MINIMUM NOTIFICATION

Shoulder Closures 3 calendar days

Lane closures 3 business days

Ramp closures 3 business days

Modifying all closure types 3 business days

Discuss LCS completion dates and provide changes in the schedule to the engineer at weekly project meetings in order to manage closures nearing their completion date.

5. Holiday and Special Event Work Restrictions.

Do not perform work on, nor haul materials of any kind along or across any portion of the highway carrying STH 81 traffic and CTH Q traffic, but leave traffic control equipment, barricades, signs, and lights in place during the following holiday and special event periods:

- From noon Friday, May 28, 2027 to 6:00 AM Tuesday, June 1, 2027 for Memorial Day;

- From noon Friday, July 2, 2027 to 6:00 AM Tuesday, July 6, 2027 for Independence Day;

- From noon Friday, September 3, 2027 to 6:00 AM Tuesday, September 7, 2027 for Labor Day;

- From noon Friday, June 30, 2028 to 6:00 AM Wednesday, July 5, 20228 for Independence Day.

stp-107-005 (20210113)

6. Utilities.

This contract does not come under the provision of Administrative Rule Trans 220.

The utility work plan includes additional detailed information regarding the location of known discontinued, relocated, or removed utility facilities. These can be requested from the department during the bid preparation process or from the project engineer after the contract has been awarded and executed.

Some of the utility work described below is dependent on prior work being performed by the contractor at a specific site. In such situations, provide the engineer and the affected utility a good faith notice of when the utility is to start work at the site. Provide this notice 14 to 16 calendar days in advance of when the prior work will be completed and the site will be available to the utility. Follow-up with a confirmation notice to the engineer and the utility not less than 3 working days before the site will be ready for the utility to begin its work.

stp-107-066 (20240703)

Any utility facility locations (stations, offsets, elevations, depths) listed in this article are approximate.

Alliant Energy – Electricity has four 6-Inch conduits attached to the underside of the STH 81 bridge.

The conduits extend between the girders and through the existing backwalls. The existing 750AL 25KV

5989-03-84 7 of 43 cable, occupying two of the existing four conduits, will be removed from the conduits and all bridge abutments. New crossings will be directionally drilled south of the bridge between the existing Alliant Energy-owned lattice towers in December 2026. Work will take approximately 60 days to complete in conjunction with the Alliant Energy gas relocation. Existing conduits attached to the bridge will be discontinued in place.

The existing overhead electric line at approximate Station 123+55, west of the CTH Q bridge, was removed in late 2025.

Alliant Energy – Gas has a 115# 8-Inch steel main, within a casing, attached to the underside of the STH 81 bridge. The line extends between the girders and through the existing backwalls. This gas main will be removed from the bridge and a new crossing directionally drilled south of the bridge between the existing Alliant Energy-owned lattice towers in December 2026. Work will take approximately 60 days to complete in conjunction with the Alliant Energy electric relocation. Existing casing attached to the bridge will be discontinued in place.

City of Beloit – Electricity has a line attached to the underside of the STH 81 bridge. The line extends between the girders and through the existing backwalls. This line will remain in place and active during construction. Work around the line during removal and replacement of the backwalls.

City of Beloit – Water has a 16-Inch line attached to the underside of the STH 81 bridge. The line extends between the girders and through the existing backwalls. This line will remain in place and active during construction. Work around this water line during removal and replacement of the backwalls.

Town of Beloit – Sewer has an unused sewer system on the west approach to CTH Q. The three manholes and two adjoining pipes will remain in place during construction.

Town of Beloit – Electricity has underground conduit and electric lines running from the corner of USH 51 to the CTH Q bridge to feed the bridge lighting. The Town relocated these lines further south of the bridge work as of September 2026. The Town of Beloit will de-energize their lines once CTH Q is closed to traffic and remove their existing pull box and protective posts. New line and conduit will be placed with the project. Contact the Town of Beloit in advance of CTH Q being closed to traffic.

The following utility companies have facilities within the project area; however, no adjustments or conflicts are anticipated:

• ATC Management Inc. – Electricity

7. Other Contracts.

The contractor is notified that the following projects will be going on during this project:

- Project 5989-03-73, USH 51, Southwest Region, ADA Curb Ramps, City of Beloit Various Locations. The WisDOT Construction PM is Adam Kopp, 608-576-8551, adam.kopp@dot.wi.gov.

The project will upgrade curb ramps in the City of Beloit, including at the STH 81/USH 51 intersection. Coordinate traffic control for the STH 81 lane closures with the project team.

8. Information to Bidders, U.S. Army Corps of Engineers Section 404 Permit.

The department has assumed coverage under the U.S. Army Corps of Engineers Section 404 Transportation Regional General Permit (TRGP). The department has determined that a pre-construction notification (permit application) to U.S. Army Corps of Engineers and their written verification of TRGP coverage is not necessary for this project.

A copy of the Section 404 Transportation Regional General Permit can be obtained on USACE’s website:

https://www.mvp.usace.army.mil/Portals/57/docs/regulatory/RGP/Transportation.pdf

If the contractor requires work outside the proposed slope intercepts, based on their method of operation to construct the project, it is the contractor’s responsibility to determine whether a pre-construction notification (permit application) and written verification from U.S. Army Corps of Engineers under the Section 404 Transportation Regional General permit is required. If written verification under the TRGP is necessary, submit a pre-construction notification to U.S. Army Corps of Engineers and obtain written verification of permit coverage prior to beginning construction operations requiring the permit. No time extensions as discussed in standard spec 108.10 will be granted for the time required to apply for and mailto:adam.kopp@dot.wi.gov https://www.mvp.usace.army.mil/Portals/57/docs/regulatory/RGP/Transportation.pdf?ver=5-1zbQT8_g_a1pSEGBP2Dg%3d%3d

5989-03-84 8 of 43 obtain the written verification of permit coverage. The contractor must be aware that the U.S. Army Corps of Engineers may not grant the permit request.

stp-107-054 (20230629)

9. Information to Bidders, WPDES Transportation Construction General Permit (TCGP) for Storm Water Discharges.

The following Project IDs have less than one acre of land disturbing construction activity and do not require coverage under the TCGP:

Project ID Design Calculated Amount of Land Disturbing Construction Activity (acres)

5989-03-84 0.4

If additional land disturbance is necessitated for the project due to proposed contractor means and methods, including temporary support activity sites, and the additional land disturbance results in a total cumulative land disturbance for the project of one acre or more, TCGP coverage will need to be obtained.

The department will be responsible for obtaining TCGP coverage for the project following department approval of the associated ECIP and DNR concurrence that the project has met the requirements for coverage under the TCGP. Do not begin land disturbing construction activity until the ECIP is approved and the DNR conveys TCGP coverage for the project.

Contractor necessitated changes resulting in the need for permit coverage will not be cause for schedule delays or other damages.

Stormwater discharge permit coverage for additional land disturbing construction activities related to contractor means and methods, including temporary support activity sites, will be considered as part of the ECIP review and approval process. Coverage under the TCGP for additional land disturbance areas will be considered if the areas meet all the following:

• Must meet the TCGP applicability criteria.

• Must be for the exclusive use of a WisDOT project.

• Land disturbance first commences after the ECIP approval, and the areas are fully restored to meet the final stabilization criteria of the permit upon completion of the work.

If TCGP coverage is deemed necessary and obtained for the project, conform to all permit requirements and post the “Certificate of Permit Coverage” in a conspicuous place at the construction site.

Permit coverage, if necessary, will be under the Wisconsin Pollutant Discharge Elimination System, Transportation Construction General Permit, (WPDES Permit No. WI-S066796-2), and is located at: :

https://widnr.widen.net/s/s5mwp2gd7s/finalsignedwisdotcsgp

Obtain any permits for areas that are not approved by the department for coverage under the TCGP.

stp-107-056 (20260701)

10. Construction Over or Adjacent to Navigable Waters.

The Rock River is classified as a state navigable waterway under standard spec 107.19.

stp-107-060 (20171130)

Navigational aids in the Rock River are required for construction.

• Please fill out the Waterway Marker Application and Permit form:

http://dnr.wi.gov/files/PDF/forms/8700/8700-058.pdf. Please identify The Wisconsin Department of Transportation as the applicant.

• Include an aerial map-diagram or engineered-diagram of the work location and the placement of the waterway markers (buoys). If proposed GPS coordinates for each buoy are not provided, then markers placed on the diagram must show distance (in feet) from each marker location and from one permanent fixture as a benchmark.

• Forward the signed application/permit to the DNR’s Regional WisDOT Liaison.

https://widnr.widen.net/s/s5mwp2gd7s/finalsignedwisdotcsgp http://dnr.wi.gov/files/PDF/forms/8700/8700-058.pdf

5989-03-84 9 of 43

• If controlling/restrictive navigational markers are required, also provide the completed application/permit to the local municipality having jurisdictional authority over the area in which the waterway markers will be placed. Consult with the local municipality regarding their ordinance adoption process.

The DNR’s Regional WisDOT Liaison will communicate with the local Warden and Recreational Safety Warden in processing and finalizing the permit. If the permit application is incomplete, or additional information is needed, the Recreation Safety Warden will work with DNR’s Regional WisDOT Liaison to resolve.

11. Notice to Contractor, Contamination Beyond Construction Limits.

The department completed testing for soil and ground water contamination for locations within this project where excavation is required. Testing indicated that petroleum-contaminated soil is present at the following sites:

1. Station 27+20 to 396 feet RT of centerline.

The contaminated soils at the above sites are expected to be beyond the excavation limits necessary to complete the work under this project. Control construction operations at these locations to ensure that they do not extend beyond the excavation limits indicated in the plans. If contaminated soils are encountered at these sites or elsewhere on the project during excavation, terminate excavation in the area and notify the engineer.

The Hazardous Materials Report is available by contacting: Joshua Nelson, Joshua.nelson@dot.wi.gov, 608-246-3857.

stp-107-100 (20230113)

12. Notice to Contractor, Verification of Asbestos Inspection, No Asbestos Found.

John Roelke, License Number AII-119526, inspected Structure B-53-172 for asbestos on April 11, 2023.

No regulated Asbestos Containing Material (RACM) was found on this structure. A copy of the inspection report is available from Joshua Nelson, 608-246-3857.

stp-107-127 (20220628)

A copy of the inspection report is available from Joshua Nelson, Joshua.nelson@dot.wi.gov, 608-246- 3857.

13. Notice to Contractor – Beloit Dam.

This project falls within the FERC project boundary of the Beloit Dam, commonly referred to as the Blackhawk Dam, located downstream of the STH 81 bridge crossing. This dam is owned by Eagle Creek Renewable Energy and is operated under FERC License 2348. Coordinate in-water work with DNR FERC Coordinator Cheryl Laatsch, 920-387-7869, Cheryl.Laatsch@wisconsin.gov. Access must be maintained to the Beloit Dam walkways at all times.

Contact the Beloit Dam during ECIP coordination and at least 2 weeks prior to in-water work beginning to confirm in-water work approach.

Melissa Rondou

Eagle Creek Renewable Energy

920-293-2628

Melissa.rondou@eaglecreekre.com

14. Coordination with Businesses and Residents.

The contractor shall arrange and conduct a meeting between the contractor, the department, affected residents, local officials and business people to…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .