- STH 23 – Lone Rock STH 23 to STH 133 STH 130
- Solicitation number
- 20261208013
- Issued by
- Jackson County, Wisconsin
About this file
This is a proposal and bidding document for a Wisconsin Department of Transportation highway construction contract involving two separate state trunk highway projects in Iowa County, Wisconsin. Project 5770-02-70 covers STH 23 from Lone Rock to STH 133 on STH 130, and Project 5770-02-72 covers STH 23 from Garthwaite Lane to Spring Valley Road on STH 130. The work consists of earthwork, culverts, guardrail installation, select crushed and base aggregate dense materials, HMA paving, signing, pavement marking, and all incidental items necessary for completion as shown in the plans and specifications. The contract must be executed within 14 days of written notification from the engineer, with construction to begin within 10 calendar days thereafter. The construction work is scheduled for the 2027 construction season, with a required time frame to be submitted in writing within one month of contract execution but at least 14 calendar days before the preconstruction conference. STH 130 will be closed to through traffic with a detour utilizing STH 23, USH 14, and STH 133. Work restrictions apply during holiday and special event periods (Memorial Day, Independence Day, and Labor Day weekends). The contract includes multiple environmental and protected species provisions, including protections for Blanchard's cricket frogs, rusty patch bumblebees, federally protected bats, and state special concern turtles, with specific avoidance and minimization measures detailed throughout.
Bidders must submit a proposal guaranty (bid bond) in the amount equal to the total bid, with the guaranty becoming the property of the state if the bidder fails to execute the contract and performance bond within 14 days of notification. Electronic bidding is required through the Bid Express system, with bids due before 11:45 AM on the last business day preceding the letting. A list of proposed subcontractors with estimated values and class of work must be submitted as part of the proposal. Bidders must certify they are not debarred, suspended, or ineligible from federal contracts and agree to comply with all non-discrimination provisions and Wisconsin workers' compensation requirements. The contract specifications reference the Wisconsin Department of Transportation Standard Specifications for Highway and Structure Construction (2025 Edition) and include numerous special provisions addressing traffic control, utility coordination, erosion control, archaeological site protection, blasting requirements, HMA pavement density testing using Quality Management Program protocols, and contaminated soil discovery procedures. Administrative fees of $75 per proposal apply if a waiver of electronic submittal requirements is requested. No set-asides are specified in this bidding document.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
!#��$�%��!����#�#��!"%�&�'���('�'����)**)�+��,-.����)�/#�#��0�01��2 3121�����2 ���4150�21�5���0��6 ������� 5�760�&--�8�'8-� (9 /%:�'��8�;�!
�<� =>/%:�'��#��/%:���� /%:���� ?�@�&--�8�'8-' �?/A��'�'-�*+ /%:�'��8�;�!
�<� =>B��#C@��# �;!�#��/���!D�E��� F�<G /%:���� ?�@� %C����������>� G�F#C !G ���D!
G��GG
�#�#C !#�$%��!����#�#��!>���!� ��G�!
@�#C#C
�GH
G� I
�#$�����������)%C
��GG
�!��C�!GG
��H �����>�!G#�� �$������@��=$��#C �����H !#�$#C G ��D!�# G���J #��!�#C G>��!�� ��G�!
�@�#C�#C !G G����������< I !#���!G�A�!G�#��!�)���������B ���!#F�< I G���F��� !#��$�%��!����#�#��!K���>���)�� 9##� C����������B
���!#F��!��� =��$�#C����9BL)M�G�/
��N>�'�'*��������A�!#�� #�A���� N�����=�!D�"�F�9���D!
G�"���GH�!#�D
G�M ���L!# �B��� �O P���� ��
>�9GG�
��>�A�#F>�/#�# >�Q���A�G %C��� �!#�� #���� R G �����H
���DC#)%C��
�#C�##C !G ���D!
G��GG
�>G �F�@��!>���!� #C���S G� !#�#�H �$#C G���H T#C�##C
��GG
�C�� R���!
G�!G �� ��F�� G#C ��G$���#C
���!�>:�DC@�F���=��������>�!G����GG
!G�>�!GC�� C
G#C �!G
���##�!D#C��������������GT�!G#C�##C
��GG
����D ����F
�C�H �#C �G�� #�F���!G�� #�F> G�!#��!F�D�
G�!�!F ��� ���!>���#C !�!F� #��!�!�
#�#�H
��GG�!D�! �!!
#��!@�#C#C��������������G)2U�VUW�XYZV[�VUW\]Ŷ_[�U]�X̀abYW�WcYX��YZcd\e��U]f��]UgUX\h�dc_V�X̀abYWWYVZ�\V�_h_iW]UVYi�aYj�UV�Wc_��VW_]V_Wk/ G��!G��@��!�#��� �#C���G�# �lllllllllllllll,/�D!�# >� �#��F�� ��$���� �!��!.,���!#����%F�
| � | �� |
| >� | �#��F�� |
�A��������!�LR���
�. ,M�GG
��/�D!�# .,���!#����%F�
�M�GG
.,M�GG
.3U]�2_g\]Wb_VW�7X_��Vhe0eg_�Um��U]fn �#� ��$�9@��G�"�# G "�# �B ���!#F�< G �#��F�/
��o��16�0�3���p�22�6���7����1�
��H���>�q����!D>�B��G�!D>�9DD� D�# >�9��C��#���H !#>�A �H >�M ���B ��G>�L�����!�A�!#���>�� !#�/�D!�!D>�%��$$� A�!#���>���H !#�q��=�!D>�<
PLEASE ATTACH
PROPOSAL GUARANTY HERE
Effective with November 2007 Letting Proposal Requirements
PROPOSAL REQUIREMENTS AND CONDITIONS
The bidder, signing and submitting this proposal, agrees and declares as a condition thereof, to be bound by the following conditions and requirements.
If the bidder has a corporate relationship with the proposal design engineering company, the bidder declares that it did not obtain any facts, data, or other information related to this proposal from the design engineering company that was not available to all bidders.
The bidder declares that they have carefully examined the site of, and the proposal, plans, specifications and contract forms for the work contemplated, and it is assumed that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of the specifications, special provisions and contract. It is mutually agreed that submission of a proposal shall be considered conclusive evidence that the bidder has made such examination.
The bidder submits herewith a proposal guaranty in proper form and amount payable to the party as designated in the advertisement inviting proposals, to be retained by and become the property of the owner of the work in the event the undersigned shall fail to execute the contract and contract bond and return the same to the office of the engineer within fourteen (14) days after having been notified in writing to do so;
otherwise to be returned.
The bidder declares that they understand that the estimate of quantities in the attached schedule is approximate only and that the attached quantities may be greater or less in accordance with the specifications.
The bidder agrees to perform the said work, for and in consideration of the payment of the amount becoming due on account of work performed, according to the unit prices bid in the following schedule, and to accept such amounts in full payment of said work.
The bidder declares that all of the said work will be performed at their own proper cost and expense, that they will furnish all necessary materials, labor, tools, machinery, apparatus, and other means of construction in the manner provided in the applicable specifications and the approved plans for the work together with all standard and special designs that may be designed on such plans, and the special provisions in the contract of which this proposal will become a part, if and when accepted. The bidder further agrees that the applicable specifications and all plans and working drawings are made a part hereof, as fully and completely as if attached hereto.
The bidder, if awarded the contract, agrees to begin the work not later than ten (10) days after the date of written notification from the engineer to do so, unless otherwise stipulated in the special provisions.
The bidder declares that if they are awarded the contract, they will execute the contract agreement and begin and complete the work within the time named herein, and they will file a good and sufficient surety bond for the amount of the contract for performance and also for the full amount of the contract for payment.
Effective with November 2007 Letting Proposal Requirements
The bidder, if awarded the contract, shall pay all claims as required by Section 779.14, Statutes of Wisconsin, and shall be subject to and discharge all liabilities for injuries pursuant to Chapter 102 of the Statutes of Wisconsin, and all acts amendatory thereto. They shall further be responsible for any damages to property or injury to persons occurring through their own negligence or that of their employees or agents, incident to the performance of work under this contract, pursuant to the Standard Specifications for Road and Bridge Construction applicable to this contract.
In connection with the performance of work under this contract, the contractor agrees to comply with all applicable state and federal statutes relating to non-discrimination in employment. No otherwise qualified person shall be excluded from employment or otherwise be subject to discrimination in employment in any manner on the basis of age, race, religion, color, gender, national origin or ancestry, disability, arrest or conviction record (in keeping with s.111.32), sexual orientation, marital status, membership in the military reserve, honesty testing, genetic testing, and outside use of lawful products. This provision shall include, but not be limited to the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation, and selection for training, including apprenticeship. The contractor further agrees to ensure equal opportunity in employment to all applicants and employees and to take affirmative action to attain a representative workforce.
The contractor agrees to post notices and posters setting forth the provisions of the nondiscrimination clause, in a conspicuous and easily accessible place, available for employees and applicants for employment.
If a state public official (section 19.42, Stats.) or an organization in which a state public official holds at least a 10% interest is a party to this agreement, this contract is voidable by the state unless appropriate disclosure is made to the State of Wisconsin Ethics Board.
Effective with August 2015 Letting Bid Preparation
BID PREPARATION
Preparing the Proposal Schedule of Items A. General
(1) Obtain bidding proposals as specified in section 102 of the standard specifications prior to 11:45 AM of the last business day preceding the letting. Submit bidding proposals using one of the following methods:
1. Electronic bid on the internet.
2. Electronic bid on a printout with accompanying diskette or CD ROM.
3. Paper bid under a waiver of the electronic submittal requirements.
(2) Bids submitted on a printout with accompanying diskette or CD ROM or paper bids submitted under a waiver of the electronic submittal requirements govern over bids submitted on the internet.
(3) The department will provide bidding information through the department’s web site at:
https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx
The contractor is responsible for reviewing this web site for general notices as well as information regarding proposals in each letting. The department will also post special notices of all addenda to each proposal through this web site no later than 4:00 PM local time on the Thursday before the letting. Check the department’s web site after 5:00 PM local time on the Thursday before the letting to ensure all addenda have been accounted for before preparing the bid. When bidding using methods 1 and 2 above, check the Bid ExpressΤΜ on-line bidding exchange at http://www.bidx.com/ after 5:00 PM local time on the Thursday before the letting to ensure that the latest schedule of items Expedite file (*.ebs or *.00x) is used to submit the final bid.
(4) Interested parties can subscribe to the Bid ExpressΤΜ on-line bidding exchange by following the instructions provided at the www.bidx.com web site or by contacting:
Info Tech Inc.
5700 SW 34th Street, Suite 1235 Gainesville, FL 32608-5371 email: mailto:customer.support@bidx.com
(5) The department will address equipment and process failures, if the bidder can demonstrate that those failures were beyond their control.
(6) Contractors are responsible for checking on the issuance of addenda and for obtaining the addenda. Notice of issuance of addenda is posted on the department’s web site at:
https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx or by calling the department at (608) 266-1631. Addenda can ONLY be obtained from the department’s web site listed above or by picking up the addenda at the Bureau of Highway Construction, 4th floor, 4822 Madison Yards Way, Madison, WI, during regular business hours.
(7) Addenda posted after 5:00 PM on the Thursday before the letting will be emailed to the eligible bidders for that proposal. All eligible bidders shall acknowledge receipt of the addenda whether they are bidding on the proposal or not. Not acknowledging receipt may jeopardize the awarding of the project.
https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx http://www.bidx.com/ http://www.bidx.com/ mailto:customer.support@bidx.com
B. Submitting Electronic Bids B.1 On the Internet
(1) Do the following before submitting the bid:
4. Have a properly executed annual bid bond on file with the department.
5. Have a digital ID on file with and enabled by Info Tech Inc. Using this digital ID will constitute the bidder's signature for proper execution of the bidding proposal.
(2) In lieu of preparing, delivering, and submitting the proposal as specified in 102.6 and 102.9 of the standard specifications, submit the proposal on the internet as follows:
1. Download the latest schedule of items reflecting all addenda from the Bid ExpressΤΜ web site.
2. Use ExpediteΤΜ software to enter a unit price for every item in the schedule of items.
3. Submit the bid according to the requirements of ExpediteΤΜ software and the Bid ExpressΤΜ web site. Do not submit a bid on a printout with accompanying diskette or CD ROM or a paper bid. If the bidder does submit a bid on a printout with accompanying diskette or a paper bid in addition to the internet submittal, the department will disregard the internet bid
4. Submit the bid before the hour and date the Notice to Contractors designates
5. Do not sign, notarize, and return the bidding proposal described in 102.2 of the standard specifications.
(3) The department will not consider the bid accepted until the hour and date the Notice to Contractors designates.
B.2 On a Printout with Accompanying Diskette or CD ROM
(1) Download the latest schedule of items from the Wisconsin pages of the Bid Express web site reflecting the latest addenda posted on the department’s web site at:
https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx
Use ExpediteΤΜ software to prepare and print the schedule of items. Provide a valid amount for all price fields. Follow instructions and review the help screens provided on the Bid ExpressΤΜ web site to assure that the schedule of items is prepared properly.
(2) Staple an 8 1/2 by 11 inch printout of the Expedite generated schedule of items to the other proposal documents submitted to the department as a part of the bidder's sealed bid. As a separate submittal, not in the sealed bid envelop but due at the same time and place as the sealed bid, also provide the ExpediteΤΜ generated schedule of items on a 3 1/2 inch computer diskette or CD ROM. Label each diskette or CD ROM with the bidder's name, the 4 character department-assigned bidder identification code from the top of the bidding proposal, and a list of the proposal numbers included on that diskette or CD ROM as indicated in the following example:
Bidder Name
BN00
Proposals: 1, 12, 14, & 22
(3) If bidding on more than one proposal in the letting, the bidder may include all proposals for that letting on one diskette or CD ROM. Include only submitted proposals with no incomplete or other files on the diskette or CD ROM.
(4) The bidder-submitted printout of the Expedite generated schedule of items is the governing contract document and must conform to the requirements of section 102 of the standard specifications. If a printout needs to be altered, cross out the printed information with ink or typewriter and enter the new information and initial it in ink. If there is a discrepancy between the printout and the diskette or CD ROM, the department will analyze the bid using the printout information.
(5) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:
1. The check code printed on the bottom of the printout of the ExpediteΤΜ generated schedule of items is not the same on each page.
2. The check code printed on the printout of the ExpediteΤΜ generated schedule of items is not the same as the check code for that proposal provided on the diskette or CD ROM.
3. The diskette or CD ROM is not submitted at the time and place the department designates.
B Waiver of Electronic Submittal
(1) The bidder may request a waiver of the electronic submittal requirements. Submit a written request for a waiver in lieu of bids submitted on the internet or on a printout with accompanying diskette or CD ROM. Use the waiver that was included with the paper bid document sent to the bidder or type up a waiver on the bidder’s letterhead. The department will waive the electronic submittal requirements for a bidding entity (individual, partnership, joint venture, corporation, or limited liability company) for up to 4 individual proposals in a calendar year. The department may allow additional waivers for equipment malfunctions.
(2) Submit a schedule of items on paper conforming to section 102 of the standard specifications.
The department charges the bidder a $75 administrative fee per proposal, payable at the time and place the department designates for receiving bids, to cover the costs of data entry. The department will accept a check or money order payable to: "Wisconsin, Dept. of Transportation."
(3) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:
1. The bidder fails to provide the written request for waiver of the electronic submittal requirements.
2. The bidder fails to pay the $75 administrative fee before the time the department designates for the opening of bids unless the bidder requests on the waiver that they be billed for the $75.
3. The bidder exceeds 4 waivers of electronic submittal requirements within a calendar year.
(4) In addition to the reasons specified in section 102 of the standard specifications, the department may refuse to issue bidding proposals for future contracts to a bidding entity that owes the department administrative fees for a waiver of electronic submittal requirements.
PROPOSAL BID BOND Wisconsin Department of Transportation
DT1303 1/2006
Proposal Number Project Number Letting Date
Name of Principal
Name of Surety State in Which Surety is Organized
We, the above-named Principal and the above-named Surety, are held and firmly bound unto the State of Wisconsin in the sum equal to the Proposal Guaranty for the total bid submitted for the payment to be made; we jointly and severally bind ourselves, our heirs, executors, administrators, successors and assigns. The condition of this obligation is that the Principal has submitted a bid proposal to the State of Wisconsin acting through the Department of Transportation for the improvement designated by the Proposal Number and Letting Date indicated above.
If the Principal is awarded the contract and, within the time and manner required by law after the prescribed forms are presented for signature, enters into a written contract in accordance with the bid, and files the bond with the Department of Transportation to guarantee faithful performance and payment for labor and materials, as required by law, or if the Department of Transportation shall reject all bids for the work described, then this obligation shall be null and void; otherwise, it shall be and remain in full force and effect.
In the event of failure of the Principal to enter into the contract or give the specified bond, the Principal shall pay to the Department of Transportation within 10 business days of demand a total equal to the Proposal Guaranty as liquidated damages; the liability of the Surety continues for the full amount of the obligation as stated until the obligation is paid in full.
The Surety, for value received, agrees that the obligations of it and its bond shall not be impaired or affected by any extension of time within which the Department of Transportation may accept the bid; and the Surety does waive notice of any such extension.
IN WITNESS, the Principal and Surety have agreed and have signed by their proper officers and have caused their corporate seals to be affixed this date: (DATE MUST BE ENTERED)
PRINCIPAL
(Company Name) (Affix Corporate Seal)
(Signature and Title)
(Company Name)
(Signature and Title)
(Company Name)
(Signature and Title)
(Company Name)
(Signature and Title)
NOTARY FOR PRINCIPAL
(Date)
State of Wisconsin ) ) ss.
County )
On the above date, this instrument was acknowledged before me by the named person(s).
(Signature, Notary Public, State of Wisconsin)
(Print or Type Name, Notary Public, State of Wisconsin)
(Date Commission Expires)
Notary Seal
(Name of Surety) (Affix Seal)
(Signature of Attorney-in-Fact)
NOTARY FOR SURETY
(Date)
State of Wisconsin ) ) ss.
County )
On the above date, this instrument was acknowledged before me by the named person(s).
(Signature, Notary Public, State of Wisconsin)
(Print or Type Name, Notary Public, State of Wisconsin)
(Date Commission Expires)
Notary Seal
IMPORTANT: A certified copy of Power of Attorney of the signatory agent must be attached to the bid bond.
CERTIFICATE OF ANNUAL BID BOND Wisconsin Department of Transportation
DT1305 8/2003
Time Period Valid (From/To)
Name of Surety
Name of Contractor
Certificate Holder Wisconsin Department of Transportation
This is to certify that an annual bid bond issued by the above-named Surety is currently on file with the Wisconsin Department of Transportation.
This certificate is issued as a matter of information and conveys no rights upon the certificate holder and does not amend, extend or alter the coverage of the annual bid bond.
Cancellation: Should the above policy be cancelled before the expiration date, the issuing surety will give thirty (30) days written notice to the certificate holder indicated above.
(Signature of Authorized Contractor Representative) (Date)
Effective with March 2010 Letting
LIST OF SUBCONTRACTORS
Section 66.0901(7), Wisconsin Statutes, provides that as a part of the proposal, the bidder also shall submit a list of the subcontractors the bidder proposes to contract with and the class of work to be performed by each. In order to qualify for inclusion in the bidder's list a subcontractor shall first submit a bid in writing, to the general contractor at least 48 hours prior to the time of the bid closing. The list may not be added to or altered without the written consent of the municipality. A proposal of a bidder is not invalid if any subcontractor and the class of work to be performed by the subcontractor has been omitted from a proposal; the omission shall be considered inadvertent or the bidder will perform the work personally.
No subcontract, whether listed herein or later proposed, may be entered into without the written consent of the Engineer as provided in Subsection 108.1 of the Standard Specifications.
Name of Subcontractor Class of Work Estimated Value
Effective with December 2000 Letting Debarment Certification
CERTIFICATION REGARDING DEBARMENT, SUSPENSION, AND OTHER
RESPONSIBILITY MATTERS - PRIMARY COVERED TRANSACTIONS
Instructions for Certification
1. By signing and submitting this proposal, the prospective contractor is providing the certification set out below.
2. The inability of a person to provide the certification required below will not necessarily result in denial of participation in this covered transaction. The prospective contractor shall submit an explanation of why it cannot provide the certification set out below. The certification or explanation will be considered in connection with the department or agency's determination whether to enter into this transaction. However, failure of the prospective contractor to furnish a certification or an explanation shall disqualify such person from participation in this transaction.
3. The certification in this clause is a material representation of fact upon which reliance was placed when the department determined to enter into this transaction. If it is later determined that the contractor knowingly rendered an erroneous certification in addition to other remedies available to the Federal Government the department may terminate this transaction for cause or default.
4. The prospective contractor shall provide immediate written notice to the department to whom this proposal is submitted if at any time the prospective contractor learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.
5. The terms "covered transaction," "debarred," "suspended," "ineligible," "lower tier covered transaction," "participant," "person," "primary covered transaction," "principal," "proposal," and "voluntarily excluded," as used in this clause, have the meanings set out in the Definitions and Coverage sections of the rules implementing Executive Order 12549. You may contact the department to which this proposal is being submitted for assistance in obtaining a copy of those regulations.
6. The prospective contractor agrees by submitting this proposal that, should this contract be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department entering into this transaction.
7. The prospective contractor further agrees by submitting this proposal that it will include the clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered Transaction," which is included as an addendum to PR- 1273 - "Required Contract Provisions Federal Aid Construction Contracts," without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions.
8. The contractor may rely upon a certification of a prospective subcontractor/materials supplier that it is not debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A contractor may decide the method and frequency by which it determines the eligibility of its principals. Each contractor may, but is not required to, check the Disapproval List (telephone # 608/266/1631).
Effective with December 2000 Letting Debarment Certification
9. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render in good faith the certification required by this clause. The knowledge and information of a contractor is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.
10. Except for transactions authorized under paragraph 6 of these instructions, if a contractor in a covered transaction knowingly enters into a lower tier covered transaction with a person who is suspended, debarred, ineligible or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department may terminate this transaction for cause or default.
Certification Regarding Debarment, Suspension, and Other Responsibility Matters - Primary Covered Transactions
1. The prospective contractor certifies to the best of its knowledge and belief, that it and its principals:
(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency;
(b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements or receiving stolen property;
(c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offense enumerated in paragraph (1)(b) of this certification; and
(d) Have not within a three-year period preceding this proposal had one or more public transactions (Federal, State or local) terminated for cause or default.
2. Where the prospective contractor is unable to certify to any of the statements in this certification, such prospective contractor shall attach an explanation to this proposal.
5770-02-70, 5770-02-72 1 of 39
Special Provisions Table of Contents
Article Description Page #
1. General
2. Scope of Work
3. Prosecution and Progress
4. Traffic
5. Holiday and Special Event Work Restrictions
6. Utilities
7. Information to Bidders, U.S. Army Corps of Engineers Section 404 Permit
8. Information to Bidders, WPDES Transportation Construction General Permit (TCGP) for Storm
Water Discharges
9. Environmental Protection, Aquatic Exotic Species Control
10. Erosion Control – Permanent Restoration
11. Environmental Protection, Blanchard’s Cricket Frog
12. Notice to Contractor – Coordination
13. Notice to Contractor – Environmentally Sensitive Areas and In-Stream Disturbances
14. Archaeological Site
15. Health and Safety Requirements for Workers Remediating Petroleum Contamination
16. Inadvertent Contaminated Soil Discovery
17. General Requirements for Blasting Rock
18. Base Aggregate Dense 3/4-Inch, Item 305.0110
19. Base Aggregate Dense 1 1/4-Inch, Item 305.0120
20. QMP HMA Pavement Nuclear Density
21. HMA Percent Within Limits (PWL) Test Strip Volumetrics, Item 460.0105.S; HMA Percent Within
Limits (PWL) Test Strip Density, Item 460.0110.S
22. HMA Pavement Percent Within Limits (PWL) QMP
23. HMA Pavement Longitudinal Joint Density
24. Locating No-Passing Zones, Item 648.0100
25. Pipe Grates 19x30-Inch, Item 611.9850.S.01; Pipe Grates 24-Inch, Item 611.9850.S.02; Pipe
Grates 30-Inch, Item 611.9850.S.03; Pipe Grates 36-Inch, Item 611.9850.S.04; Pipe Grates 38x60-Inch, Item 611.9850.S.05
26. Painting Beam Guard, Item SPV.0090.01
5770-02-70, 5770-02-72 2 of 39
STSP’S Revised July 1, 2026
SPECIAL PROVISIONS
1. General.
Perform the work under this construction contract for the following projects:
5770-02-70 STH 23 – Lone Rock STH 23 to STH 133
STH 130
Iowa County
5770-02-72 STH 23 – Lone Rock Garthwaite Ln to Spring Valley Rd
STH 130
Iowa County
Perform the work as the plans show and execute the work as specified in the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition, as published by the department, and these special provisions.
If all or a portion of the plans and special provisions are developed in the SI metric system and the schedule of prices is developed in the US standard measure system, the department will pay for the work as bid in the US standard system.
100-005 (20260701)
2. Scope of Work.
The work under this contract consists of earthwork, culverts, guardrail, select crushed, base aggregate dense, HMA paving, signing, pavement marking, and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract.
104-005 (20090901)
3. Prosecution and Progress.
Begin work within 10 calendar days after the engineer issues a written notice to do so.
Provide the time frame for construction of the project within the 2027 construction season to the engineer in writing within a month after executing the contract but at least 14 calendar days before the preconstruction conference. Assure that the time frame is consistent with the contract completion time.
Upon approval, the engineer will issue the notice to proceed within ten calendar days before the beginning of the approved time frame.
To revise the time frame, submit a written request to the engineer at least two weeks before the beginning of the intended time frame. The engineer will approve or deny that request based on the conditions cited in the request and its effect on the department’s scheduled resources.
Guardrail Operations Guardrail installation shall occur within 72 hours from when the existing guardrail is initially removed with the exception that no guardrail shall be left partially installed over the weekend or holiday. Traffic Control Drums shall remain until new guardrail has been installed and approved by the engineer. Do not have guardrail out of service simultaneously on shoulders directly across from each other.
Milling and Paving Operations Lower Layer of HMA Pavement to be placed within 7 days of existing pavement removal/milling.
Protection of Endangered Bats Federally protected bats have the potential to inhabit the project limits because they roost in trees, bridges, culverts, and other structures. Roosts may not have been observed on this project, but conditions to support the species exist. The species and all active roosts are protected by the federal Endangered Species Act. If an individual bat or active roost is encountered during construction operations, stop work, and notify the engineer and the WisDOT Regional Environmental Coordinator
(REC).
5770-02-70, 5770-02-72 3 of 39
Ensure all operators, employees, and subcontractors working in areas of known or presumed bat habitat are aware of environmental commitments and avoidance and minimization measures (AMMs) to protect both bats and their habitat.
Direct temporary lighting, if used, away from wooded areas during the bat active season April 15 to October 31, both dates inclusive.
Tree Clearing/Trimming
To avoid adverse impacts upon protected bats, do not perform tree clearing/trimming between April 15 and October 31, both dates inclusive. If the required tree clearing/trimming is not completed by April 14, the department will suspend all tree clearing/trimming and associated work directly impacted by clearing/trimming. Tree clearing/trimming is limited to that which is specified in the plans. Contractor means and methods to remove additional trees/branches will not be allowed. If it is determined that additional trees with a 3-inch or greater diameter at breast height (dbh), or branches of any size on those sized trees, need to be removed beyond contractor means and methods, notify the engineer to coordinate with the WisDOT REC to determine if consultation with United States Fish and Wildlife Service (USFWS) is required. The contractor must be aware that the WisDOT REC and/or USFWS may not permit modifications.
Due to potential for erosion, do not perform grubbing operations at the time of tree clearing unless grading activities will commence in those areas immediately following the tree clearing, or as otherwise approved by the engineer. Provide information for the grubbing and grading activities, including the schedule of operations, in the Erosion Control Implementation Plan (ECIP).
Submit a schedule and description of clearing operations with the ECIP 14 days prior to any clearing operations. The department will determine, based on schedule and scope of work, what additional erosion control measures shall be implemented prior to the start of clearing operations, and list those additional measures in the ECIP.
Branch trimming is incidental to other work if no other tree clearing work is necessary.
Upon approval from the engineer, working day assessments may be suspended once clearing/trimming operations are completed by April 14.
Protection of State Special Concern Turtle A State Special Concern turtle species has the potential to inhabit the project site. Install amphibian and reptile exclusion fencing in the form of silt fence with turn arounds at the end of each section of silt fence to prevent the turtles from accessing the construction zone. The fencing shall be installed prior to the initiation of construction activities beginning, and the fencing shall remain for the duration of construction or until after November 15. The active period for this species begins on March 5 and ends on November 15, both dates inclusive. Install the amphibian and reptile exclusion fencing in the following manner:
• Fencing must be trenched into the soil at least 4 inches and the soils must be carefully compacted against both sides of the fence for its entire length to prevent animals from passing under the fence. Fencing should be installed with turn-arounds at the ends furthest from the wetland habitat and at any access openings needed in the fencing, in order to redirect turtles away from openings.
• Fences must be inspected at least twice weekly on non-consecutive days and after any significant rain event (defined as 1.5 inches of rain in any 24-hour period). Repairs to the fencing must be made within 24 hours of the inspection that first noted a fencing breach, such as a broken stake, hole in the fencing material, material pulled away from a stake, and objects, rain, wind or sediment that cause fences to sag which would allow the turtles to overtop the fence.
• These fences must be maintained throughout the affected species' entire active period or until all construction and landscaping activities have been completed, whichever occurs first. If the project continues into more seasons, fencing must be maintained during the animal's active season until project completion.
• Additional sediment control fencing may be required as part of other Department permit conditions.
Any turtles found on the construction side of the fence must be immediately moved unharmed to the non-construction side of the fence.
5770-02-70, 5770-02-72 4 of 39
Protection of Rusty Patch Bumblebee In all areas of RPBB suitable habitat, use salvaged topsoil and reseed with Seeding Mixture #70A at the following station ranges:
- Stations 113+14 – 113+73 LT/RT
- Stations 302+01 – 302+69 LT/RT
- Stations 338+00 – 375+12 RT
- Stations 346+48 – 348+48 LT
- Stations 349+56 – 350+77 LT
- Stations 358+56 – 359+41 LT
- Stations 442+33 – 442+94 LT/RT
4. Traffic.
Detour Close STH 130 to through traffic. Both projects will utilize the same detour following STH 23 to USH 14 to
STH 133.
General Submit to engineer for approval a detailed traffic control plan for any changes to the proposed traffic control as shown on the plans. Submit the plan 14 days prior to the preconstruction conference, or if after the preconstruction conference, 14 days prior to the intended use of the revised traffic control. A request does not constitute approval.
Conduct operations in such a manner that causes the least interference and inconvenience to the free flow of vehicles and bicyclists on the roadways. This includes the following:
• All construction vehicles and equipment entering or leaving live traffic lanes shall yield to through traffic and bicyclists.
• Equip all vehicles and equipment entering or leaving the live traffic lanes with a hazard identification beam (flashing yellow signal) capable of being visible on a sunny day when viewed without the sun directly on or behind the device from a distance of 1000 feet. Activate the beam when merging into or exiting a live traffic lane.
Display a pre-construction message on portable changeable message signs (PCMS) at the north and south ends of the projects 7 days prior to road closure as shown in the plans. Coordinate specific sign location and message per plan with the engineer.
Provide flagging personnel for all construction operations to assist construction vehicles entering the work zones.
Vehicle Access Contact local and county emergency responders 48 hours prior to closures.
Access shall always be maintained during construction for emergency personnel and for residents to access their property. Contact the property owner 48 hours prior to removing any existing entrance to coordinate temporary closures. Restore private entrances, including a gravel surface, within 12 hours of removal.
Maintain a clearly delineated, suitable driving surface of at least a 12-foot driving lane for residents, businesses, school busses, and emergency vehicles throughout construction. A suitable driving surface is defined as a material capable of withstanding a fully loaded quad axle truck without yielding as approved by the engineer. The 12-foot lane shall be graded to drain and rolled with a smooth drum vibratory roller or other alternate compaction equipment that produces a smooth driving surface.
Provide the engineer and local law enforcement with a 24-hour, 7 days/week contact person responsible for the maintenance of the 12-foot driving lane for residents.
All intersections of STH 130 and side roads shall have a 20-foot driving lane consisting of Base Aggregate Dense 1 ¼-Inch to ensure 2-way cross traffic is maintained. Maintain a width of 15-feet during daylight hours provided that flaggers are present.
5770-02-70, 5770-02-72 5 of 39
Wisconsin Lane Closure System Advance Notification Provide the following advance notification to the engineer for incorporation into the Wisconsin Lane Closure System (LCS).
TABLE 108-1 CLOSURE TYPE AND REQUIRED MINIMUM ADVANCE NOTIFICATION
Closure type with height, weight, or width restrictions (available width, all lanes in one direction < 16 feet) MINIMUM NOTIFICATION
Lane and shoulder closures 7 calendar days
Full roadway closures 7 calendar days
Ramp closures 7 calendar days
Detours 7 calendar days
Closure type without height, weight, or width restrictions (available width, all lanes in one direction > 16 feet) MINIMUM NOTIFICATION
Shoulder Closures 3 calendar days
Lane closures 3 business days
Ramp closures 3 business days
Modifying all closure types 3 business days
Discuss LCS completion dates and provide changes in the schedule to the engineer at weekly project meetings in order to manage closures nearing their completion date.
5. Holiday and Special Event Work Restrictions.
The STH 130 detour will remain in place during holiday/special event restrictions. Hauling and/or work activities will not be allowed to occur outside of the closed work area at any point during the holiday/special event restriction. Clear the work zone of any unnecessary traffic control devices, equipment, or materials that would restrict the movement of local traffic. Holiday/special event periods are listed below:
- From noon Friday, 5/28/27 to 6:00 AM Tuesday, 6/1/27 Memorial Day;
- From noon Friday, 7/2/27 to to 6:00 AM Tuesday, 7/6/27 Independence Day;
- From noon Friday, 9/3/27 to 6:00 AM Tuesday, 9/7/27 Labor Day.
6. Utilities.
This contract comes under the provision of Administrative Rule Trans 220.
The utility work plan includes additional detailed information regarding the location of known discontinued, relocated, or removed utility facilities. These can be requested from the department during the bid preparation process, or from the project engineer after the contract has been awarded and executed.
Some of the utility work described below is dependent on prior work being performed by the contractor at a specific site. In such situations, provide the engineer and the affected utility a good faith notice of when the utility is to start work at the site. Provide this notice 14 to 16 calendar days in advance of when the prior work will be completed and the site will be available to the utility. Follow-up with a confirmation notice to the engineer and the utility not less than 3 working days before the site will be ready for the utility to begin its work.
stp-107-065 (20240703)
Any utility facility locations (stations, offsets, elevations, depths) listed in this article are approximate.
Project ID: 5770-02-70 The following utility owners have facilities within the construction limits, adjustments are anticipated:
5770-02-70, 5770-02-72 6 of 39
Frontier Communications – Communication Line Frontier has underground copper facilities near guardrail installations at Station 645+30 RT and Station 651+24 RT. Frontier will pothole facilities at both locations. Frontier will provide a watch dog to monitor both locations during construction, contact Mark Shannon at 507-327-3679 or mark.shannon1@verizon.com to coordinate watch dog.
Potholing at both locations is anticipated to take two working days and will be completed prior to construction.
The following utility owners have facilities within the construction limits; however, no conflicts are anticipated:
American Transmission Company (ATC) – Transmission/Electricity Alliant Energy - Electricity Bug Tussel – Communication Line
Project ID: 5770-02-72 The following utility owners have facilities within the construction limits, adjustments are anticipated:
Alliant Energy – Electricity Alliant Energy has underground electrical facilities along the East side of STH 130 from Station 309+00 to Station 319+00 RT. The existing underground facilities will remain in place from Station 309+00 to Station 313+50 RT and Station 316+50 to Station 319+00 RT.
Alliant Energy underground facilities from Station 313+50 to Station 316+50 RT will be relocated to avoid conflict with the proposed slope cut. The relocation work will start at Station 313+50, 32’ RT, hence, north to Station 314+00, 65’ RT, hence, north to Station 316+00, 65’ RT, then tie back in with the existing facility at Station 316+50, 57’ RT. Relocated facilities will be buried at a depth of 36 inches.
Alliant Energy underground electrical facility from Station 313+50 to Station 316+50 RT will be discontinued in place.
Facilities will be relocated and discontinued prior to construction. It is anticipated to take 1 working day to complete.
The following utility owners have facilities within the construction limits; however, no conflicts are anticipated:
Frontier Communications - Communication Line
7. Information to Bidders, U.S. Army Corps of Engineers Section 404 Permit.
The department has assumed coverage under the U.S. Army Corps of Engineers Section 404 Transportation Regional General Permit (TRGP). The department has determined that a pre-construction notification (permit application) to U.S. Army Corps of Engineers and their written verification of TRGP coverage is not necessary for this project.
A copy of the Section 404 Transportation Regional General Permit can be obtained on USACE’s website:
https://www.mvp.usace.army.mil/Portals/57/docs/regulatory/RGP/Transportation.pdf
If the contractor requires work outside the proposed slope intercepts, based on their method of operation to construct the project, it is the contractor’s responsibility to determine whether a pre-construction notification (permit application) and written verification from U.S. Army Corps of Engineers under the Section 404 Transportation Regional General permit is required. If written verification under the TRGP is necessary, submit a pre-construction notification to U.S. Army Corps of Engineers and obtain written verification of permit coverage prior to beginning construction operations requiring the permit. No time extensions as discussed in standard spec 108.10 will be granted for the time required to apply for and obtain the written verification of permit coverage. The contractor must be aware that the U.S. Army Corps of Engineers may not grant the permit request.
stp-107-054 (20230629) mailto:mark.shannon1@verizon.com https://www.mvp.usace.army.mil/Portals/57/docs/regulatory/RGP/Transportation.pdf?ver=5-1zbQT8_g_a1pSEGBP2Dg%3d%3d
5770-02-70, 5770-02-72 7 of 39
8. Information to Bidders, WPDES Transportation Construction General Permit (TCGP) for Storm Water Discharges.
The following Project IDs have one acre or more of land disturbing construction activity and are required to obtain coverage under the TCGP. The permit requirements are part of the contract:
Project ID Design Calculated Amount of Land Disturbing Construction Activity (acres)
5770-02-70 1.0
5770-02-72 3.9
This permit is the Wisconsin Pollutant Discharge Elimination System, Transportation Construction General Permit, (WPDES Permit No. WI-S066796-2) and is located at:
https://widnr.widen.net/s/s5mwp2gd7s/finalsignedwisdotcsgp
The department will apply for coverage under the TCGP upon submittal of the complete ECIP from the contractor, and concurrent with the department providing the ECIP to the Department of Natural Resources (DNR). The DNR will convey permit coverage upon the department’s approval of the ECIP and DNR concurrence that the project has met the requirements for coverage under the TCGP.
Do not begin land disturbing construction activity until the ECIP is approved and the DNR conveys TCGP coverage for the project.
A “Certificate of Permit Coverage” will be provided by the DNR upon conveyance of coverage under the permit. Post the “Certificate of Permit Coverage” in a conspicuous place at the construction site.
Stormwater discharge permit coverage for additional land disturbing construction activities related to contractor means and methods, including temporary support activity sites, will be considered as part of the ECIP review and approval process. Coverage under the TCGP for additional land disturbance areas will be considered if the areas meet all of the following:
• Must meet the TCGP applicability criteria.
• Must be for the exclusive use of WisDOT projects.
• Land disturbance first commences after the ECIP approval, and the areas are fully restored to meet the final stabilization criteria of the TCGP upon completion of the work.
Obtain any permits for areas that are not approved by the department for coverage under the TCGP.
Stp-107-056
9. Environmental Protection, Aquatic Exotic Species Control.
Exotic invasive organisms such as VHS, zebra mussels, purple loosestrife, and Eurasian water milfoil are becoming more prolific in Wisconsin and pose adverse effects to waters of the state. Wisconsin State Statutes 30.07, "Transportation of Aquatic Plants and Animals; Placement of Objects in Navigable Waters", details the state law that requires the removal of aquatic plants and zebra mussels each time equipment is put into state waters.
At construction sites that involve navigable water or wetlands, use the follow cleaning procedures to minimize the chance of exotic invasive species infestation. Use these procedures for all equipment that comes in contact with waters of the state and/or infested water or potentially infested water in other states.
Ensure that all equipment that has been in contact with waters of the state, or with infested or potentially infested waters, has been decontaminated for aquatic plant materials and zebra mussels before being used in other waters of the state. Before using equipment on this project, thoroughly disinfect all equipment that has come into contact with potentially infested waters. Guidelines from the Wisconsin Department of Natural Resources for disinfection are available at:
http://dnr.wi.gov/topic/invasives/disinfection.html
Use the following inspection and removal procedures:
https://widnr.widen.net/s/s5mwp2gd7s/finalsignedwisdotcsgp http://dnr.wi.gov/topic/invasives/disinfection.html
5770-02-70, 5770-02-72 8 of 39
1. Before leaving the contaminated site, wash machinery and ensure that the machinery is free of all soil and other substances that could possibly contain exotic invasive species;
2. Drain all water from boats, trailers, bilges, live wells, coolers, bait buckets, engine compartments, and any other area where water may be trapped;
3. Inspect boat hulls, propellers, trailers and other surfaces. Scrape off any attached mussels, remove any aquatic plant materials (fragments, stems, leaves, seeds, or roots), and dispose of removed mussels and plant materials in a garbage can before leaving the area or invested waters; and
4. Disinfect your boat, equipment and gear by either:
4.1. Washing with ~212 F water (steam clean), or
4.2. Drying thoroughly for five days after cleaning with soap and water and/or high pressure water, or
4.3. Disinfecting with either 200 ppm (0.5 oz per gallon or 1 Tablespoon per gallon) Chlorine for
10-minute contact time or 1:100 solution (38 grams per gallon) of Virkon Aquatic for 20- to 30-minute contact time. Note: Virkon is not registered to kill zebra mussel veligers nor invertebrates like spiny water flea. Therefore, this disinfect should be used in conjunction with a hot water (>104º F) application.
Complete the inspection and removal procedure before equipment is brought to the project site and before the equipment leaves the…