20261110005proposal (1).pdf

PDF 2 MB Posted

Attached to
Regionwide Tree Clearing
Solicitation number
20261110005
Issued by
Dane County, Wisconsin

About this file

This is a proposal and special provisions document for a Regionwide Tree Clearing project administered by the Wisconsin Department of Transportation (WisDOT). The contract encompasses tree clearing, erosion control, traffic control, and all incidental work across two project areas (Area 12 and Area 13) along USH 14. The work includes site mobilization, traffic control setup for various closure types (shoulder, lane, and ramp closures), semi-permanent restoration with erosion control materials, pedestrian accommodations, and coordination with multiple utility companies operating within the construction limits. The project is subject to minimum notification requirements of three calendar days for shoulder closures and three business days for lane and ramp closures. Holiday and special event work restrictions apply during specified periods from November 2025 through January 2027, including Thanksgiving, Christmas, New Year's Day, and MLK Day. The contract requires WPDES Transportation Construction General Permit (TCGP) coverage for Area 12, which involves more than one acre of land disturbance, while Area 13 requires less than one acre of disturbance and is not subject to TCGP requirements.

The proposal includes multiple special provision bid items with unit prices to be determined, including Site Mobilization (SPV.0060.01), Site Traffic Control (SPV.0060.02), Semi-Permanent Restoration (SPV.0060.03), and various traffic control configurations for different road conditions. The contractor retains ownership of timber salvaged from clearing activities and must properly dispose of or utilize this material rather than burning or burying it on the right-of-way. The contract incorporates comprehensive utility coordination requirements with 16 utility companies and districts, including Alliant Energy, Madison Gas & Electric, AT&T Wisconsin, Frontier Communications, and others, with specific notification periods ranging from 3 working days to 30 calendar days before work near utility facilities. Environmental compliance requirements include adherence to Section 404 Transportation Regional General Permit standards for wetlands work, compliance with Wisconsin's aquatic invasive species control procedures, and proper equipment decontamination protocols. The contract also establishes provisions for prompt subcontractor payment within 10 calendar days of receiving progress payments, with no allowance for retainage withholding.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

"��#�$�� ����"�"�� !$%��&��%'&�&����())(�*�%+,-����(�."�"��/�/0��1 2010�����1 ���304/�10�4���/��5 ������� 4�65/��%��7%)7)8 '9 :

��A���"�� � @9:�B�C .� "D< $D����������?� =�E"D �"�"D <�"D"D �=F G

�"#�����������($D � ��D� == ��F �#������<��H#��"D �����F "�#"D =���I �"�� �"D �<�"D�"D G "��� =�>� =�"�� �(���������J ��� "E�:

G =���E��� "��#�$�� ����"�"�� K&?���(�� 9""��D����������J

��� "E�� ����H��#�"D����9JL(M�=�.

�+A�����$�� -� �F 9�����%N?�&�&,9���;

=�!���=F� "�;

=�M ���L " �J��� �O P���� �� ?�9==� ��?�>�"E?�."�" ?�Q���>�= $D����� "���"���� R �����F ���;D"($D��� �"D�""D �E�<�� ?��� � "D���S "�"�F �#"D =���F T"D�""D �D�� R��� ��E�� ="D ��=#���"D ��� �?B�;D<�E���H��������?� =����== =�?� =D���D �H ="D ���""� ;"D��������������=T� ="D�""D ����E

�D�F �"D �"�E��� =�� �"�E?

=� "�� E�;�

=� � E���� ��� ?���"D "�H � E��"�� � �

"�"�F �"�� <�"D"D��������������=(1U�VUW�XYZV[�VUW\]Ŷ_[�U]�X̀abYW�WcYX��YZcd\e��U]f��]UgUX\h�dc_V�X̀abYWWYVZ�\V�_h_iW]UVYi�aYj�UV�Wc_��VW_]V_Wk.

�"D���=�" �lllllllllllllll+.�; �" ?� �"��E�� ��#������ �� -+��� "����$E�

���
?��"��E��

�>�������� �LR���

�- +M�== -+��� "����$E� �M�== -+M�== -2U]�1_g\]Wb_VW�6X_��Vhe/eg_�Um��U]fn �"�� ��#�9<��=�!�" �J ��� "E�:

= �"��E�.

��o��05�/�2���p�11�5���6����0�

PLEASE ATTACH

PROPOSAL GUARANTY HERE

Effective with November 2007 Letting Proposal Requirements

PROPOSAL REQUIREMENTS AND CONDITIONS

The bidder, signing and submitting this proposal, agrees and declares as a condition thereof, to be bound by the following conditions and requirements.

If the bidder has a corporate relationship with the proposal design engineering company, the bidder declares that it did not obtain any facts, data, or other information related to this proposal from the design engineering company that was not available to all bidders.

The bidder declares that they have carefully examined the site of, and the proposal, plans, specifications and contract forms for the work contemplated, and it is assumed that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of the specifications, special provisions and contract. It is mutually agreed that submission of a proposal shall be considered conclusive evidence that the bidder has made such examination.

The bidder submits herewith a proposal guaranty in proper form and amount payable to the party as designated in the advertisement inviting proposals, to be retained by and become the property of the owner of the work in the event the undersigned shall fail to execute the contract and contract bond and return the same to the office of the engineer within fourteen (14) days after having been notified in writing to do so;

otherwise to be returned.

The bidder declares that they understand that the estimate of quantities in the attached schedule is approximate only and that the attached quantities may be greater or less in accordance with the specifications.

The bidder agrees to perform the said work, for and in consideration of the payment of the amount becoming due on account of work performed, according to the unit prices bid in the following schedule, and to accept such amounts in full payment of said work.

The bidder declares that all of the said work will be performed at their own proper cost and expense, that they will furnish all necessary materials, labor, tools, machinery, apparatus, and other means of construction in the manner provided in the applicable specifications and the approved plans for the work together with all standard and special designs that may be designed on such plans, and the special provisions in the contract of which this proposal will become a part, if and when accepted. The bidder further agrees that the applicable specifications and all plans and working drawings are made a part hereof, as fully and completely as if attached hereto.

The bidder, if awarded the contract, agrees to begin the work not later than ten (10) days after the date of written notification from the engineer to do so, unless otherwise stipulated in the special provisions.

The bidder declares that if they are awarded the contract, they will execute the contract agreement and begin and complete the work within the time named herein, and they will file a good and sufficient surety bond for the amount of the contract for performance and also for the full amount of the contract for payment.

Effective with November 2007 Letting Proposal Requirements

The bidder, if awarded the contract, shall pay all claims as required by Section 779.14, Statutes of Wisconsin, and shall be subject to and discharge all liabilities for injuries pursuant to Chapter 102 of the Statutes of Wisconsin, and all acts amendatory thereto. They shall further be responsible for any damages to property or injury to persons occurring through their own negligence or that of their employees or agents, incident to the performance of work under this contract, pursuant to the Standard Specifications for Road and Bridge Construction applicable to this contract.

In connection with the performance of work under this contract, the contractor agrees to comply with all applicable state and federal statutes relating to non-discrimination in employment. No otherwise qualified person shall be excluded from employment or otherwise be subject to discrimination in employment in any manner on the basis of age, race, religion, color, gender, national origin or ancestry, disability, arrest or conviction record (in keeping with s.111.32), sexual orientation, marital status, membership in the military reserve, honesty testing, genetic testing, and outside use of lawful products. This provision shall include, but not be limited to the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation, and selection for training, including apprenticeship. The contractor further agrees to ensure equal opportunity in employment to all applicants and employees and to take affirmative action to attain a representative workforce.

The contractor agrees to post notices and posters setting forth the provisions of the nondiscrimination clause, in a conspicuous and easily accessible place, available for employees and applicants for employment.

If a state public official (section 19.42, Stats.) or an organization in which a state public official holds at least a 10% interest is a party to this agreement, this contract is voidable by the state unless appropriate disclosure is made to the State of Wisconsin Ethics Board.

Effective with August 2015 Letting Bid Preparation

BID PREPARATION

Preparing the Proposal Schedule of Items A. General

(1) Obtain bidding proposals as specified in section 102 of the standard specifications prior to 11:45 AM of the last business day preceding the letting. Submit bidding proposals using one of the following methods:

1. Electronic bid on the internet.

2. Electronic bid on a printout with accompanying diskette or CD ROM.

3. Paper bid under a waiver of the electronic submittal requirements.

(2) Bids submitted on a printout with accompanying diskette or CD ROM or paper bids submitted under a waiver of the electronic submittal requirements govern over bids submitted on the internet.

(3) The department will provide bidding information through the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx

The contractor is responsible for reviewing this web site for general notices as well as information regarding proposals in each letting. The department will also post special notices of all addenda to each proposal through this web site no later than 4:00 PM local time on the Thursday before the letting. Check the department’s web site after 5:00 PM local time on the Thursday before the letting to ensure all addenda have been accounted for before preparing the bid. When bidding using methods 1 and 2 above, check the Bid ExpressΤΜ on-line bidding exchange at http://www.bidx.com/ after 5:00 PM local time on the Thursday before the letting to ensure that the latest schedule of items Expedite file (*.ebs or *.00x) is used to submit the final bid.

(4) Interested parties can subscribe to the Bid ExpressΤΜ on-line bidding exchange by following the instructions provided at the www.bidx.com web site or by contacting:

Info Tech Inc.

5700 SW 34th Street, Suite 1235 Gainesville, FL 32608-5371 email: mailto:customer.support@bidx.com

(5) The department will address equipment and process failures, if the bidder can demonstrate that those failures were beyond their control.

(6) Contractors are responsible for checking on the issuance of addenda and for obtaining the addenda. Notice of issuance of addenda is posted on the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx or by calling the department at (608) 266-1631. Addenda can ONLY be obtained from the department’s web site listed above or by picking up the addenda at the Bureau of Highway Construction, 4th floor, 4822 Madison Yards Way, Madison, WI, during regular business hours.

(7) Addenda posted after 5:00 PM on the Thursday before the letting will be emailed to the eligible bidders for that proposal. All eligible bidders shall acknowledge receipt of the addenda whether they are bidding on the proposal or not. Not acknowledging receipt may jeopardize the awarding of the project.

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx http://www.bidx.com/ http://www.bidx.com/ mailto:customer.support@bidx.com

B. Submitting Electronic Bids B.1 On the Internet

(1) Do the following before submitting the bid:

4. Have a properly executed annual bid bond on file with the department.

5. Have a digital ID on file with and enabled by Info Tech Inc. Using this digital ID will constitute the bidder's signature for proper execution of the bidding proposal.

(2) In lieu of preparing, delivering, and submitting the proposal as specified in 102.6 and 102.9 of the standard specifications, submit the proposal on the internet as follows:

1. Download the latest schedule of items reflecting all addenda from the Bid ExpressΤΜ web site.

2. Use ExpediteΤΜ software to enter a unit price for every item in the schedule of items.

3. Submit the bid according to the requirements of ExpediteΤΜ software and the Bid ExpressΤΜ web site. Do not submit a bid on a printout with accompanying diskette or CD ROM or a paper bid. If the bidder does submit a bid on a printout with accompanying diskette or a paper bid in addition to the internet submittal, the department will disregard the internet bid

4. Submit the bid before the hour and date the Notice to Contractors designates

5. Do not sign, notarize, and return the bidding proposal described in 102.2 of the standard specifications.

(3) The department will not consider the bid accepted until the hour and date the Notice to Contractors designates.

B.2 On a Printout with Accompanying Diskette or CD ROM

(1) Download the latest schedule of items from the Wisconsin pages of the Bid Express web site reflecting the latest addenda posted on the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx

Use ExpediteΤΜ software to prepare and print the schedule of items. Provide a valid amount for all price fields. Follow instructions and review the help screens provided on the Bid ExpressΤΜ web site to assure that the schedule of items is prepared properly.

(2) Staple an 8 1/2 by 11 inch printout of the Expedite generated schedule of items to the other proposal documents submitted to the department as a part of the bidder's sealed bid. As a separate submittal, not in the sealed bid envelop but due at the same time and place as the sealed bid, also provide the ExpediteΤΜ generated schedule of items on a 3 1/2 inch computer diskette or CD ROM. Label each diskette or CD ROM with the bidder's name, the 4 character department-assigned bidder identification code from the top of the bidding proposal, and a list of the proposal numbers included on that diskette or CD ROM as indicated in the following example:

Bidder Name

BN00

Proposals: 1, 12, 14, & 22

(3) If bidding on more than one proposal in the letting, the bidder may include all proposals for that letting on one diskette or CD ROM. Include only submitted proposals with no incomplete or other files on the diskette or CD ROM.

(4) The bidder-submitted printout of the Expedite generated schedule of items is the governing contract document and must conform to the requirements of section 102 of the standard specifications. If a printout needs to be altered, cross out the printed information with ink or typewriter and enter the new information and initial it in ink. If there is a discrepancy between the printout and the diskette or CD ROM, the department will analyze the bid using the printout information.

(5) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:

1. The check code printed on the bottom of the printout of the ExpediteΤΜ generated schedule of items is not the same on each page.

2. The check code printed on the printout of the ExpediteΤΜ generated schedule of items is not the same as the check code for that proposal provided on the diskette or CD ROM.

3. The diskette or CD ROM is not submitted at the time and place the department designates.

B Waiver of Electronic Submittal

(1) The bidder may request a waiver of the electronic submittal requirements. Submit a written request for a waiver in lieu of bids submitted on the internet or on a printout with accompanying diskette or CD ROM. Use the waiver that was included with the paper bid document sent to the bidder or type up a waiver on the bidder’s letterhead. The department will waive the electronic submittal requirements for a bidding entity (individual, partnership, joint venture, corporation, or limited liability company) for up to 4 individual proposals in a calendar year. The department may allow additional waivers for equipment malfunctions.

(2) Submit a schedule of items on paper conforming to section 102 of the standard specifications.

The department charges the bidder a $75 administrative fee per proposal, payable at the time and place the department designates for receiving bids, to cover the costs of data entry. The department will accept a check or money order payable to: "Wisconsin, Dept. of Transportation."

(3) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:

1. The bidder fails to provide the written request for waiver of the electronic submittal requirements.

2. The bidder fails to pay the $75 administrative fee before the time the department designates for the opening of bids unless the bidder requests on the waiver that they be billed for the $75.

3. The bidder exceeds 4 waivers of electronic submittal requirements within a calendar year.

(4) In addition to the reasons specified in section 102 of the standard specifications, the department may refuse to issue bidding proposals for future contracts to a bidding entity that owes the department administrative fees for a waiver of electronic submittal requirements.

PROPOSAL BID BOND Wisconsin Department of Transportation

DT1303 1/2006

Proposal Number Project Number Letting Date

Name of Principal

Name of Surety State in Which Surety is Organized

We, the above-named Principal and the above-named Surety, are held and firmly bound unto the State of Wisconsin in the sum equal to the Proposal Guaranty for the total bid submitted for the payment to be made; we jointly and severally bind ourselves, our heirs, executors, administrators, successors and assigns. The condition of this obligation is that the Principal has submitted a bid proposal to the State of Wisconsin acting through the Department of Transportation for the improvement designated by the Proposal Number and Letting Date indicated above.

If the Principal is awarded the contract and, within the time and manner required by law after the prescribed forms are presented for signature, enters into a written contract in accordance with the bid, and files the bond with the Department of Transportation to guarantee faithful performance and payment for labor and materials, as required by law, or if the Department of Transportation shall reject all bids for the work described, then this obligation shall be null and void; otherwise, it shall be and remain in full force and effect.

In the event of failure of the Principal to enter into the contract or give the specified bond, the Principal shall pay to the Department of Transportation within 10 business days of demand a total equal to the Proposal Guaranty as liquidated damages; the liability of the Surety continues for the full amount of the obligation as stated until the obligation is paid in full.

The Surety, for value received, agrees that the obligations of it and its bond shall not be impaired or affected by any extension of time within which the Department of Transportation may accept the bid; and the Surety does waive notice of any such extension.

IN WITNESS, the Principal and Surety have agreed and have signed by their proper officers and have caused their corporate seals to be affixed this date: (DATE MUST BE ENTERED)

PRINCIPAL

(Company Name) (Affix Corporate Seal)

(Signature and Title)

(Company Name)

(Signature and Title)

(Company Name)

(Signature and Title)

(Company Name)

(Signature and Title)

NOTARY FOR PRINCIPAL

(Date)

State of Wisconsin ) ) ss.

County )

On the above date, this instrument was acknowledged before me by the named person(s).

(Signature, Notary Public, State of Wisconsin)

(Print or Type Name, Notary Public, State of Wisconsin)

(Date Commission Expires)

Notary Seal

(Name of Surety) (Affix Seal)

(Signature of Attorney-in-Fact)

NOTARY FOR SURETY

(Date)

State of Wisconsin ) ) ss.

County )

On the above date, this instrument was acknowledged before me by the named person(s).

(Signature, Notary Public, State of Wisconsin)

(Print or Type Name, Notary Public, State of Wisconsin)

(Date Commission Expires)

Notary Seal

IMPORTANT: A certified copy of Power of Attorney of the signatory agent must be attached to the bid bond.

CERTIFICATE OF ANNUAL BID BOND Wisconsin Department of Transportation

DT1305 8/2003

Time Period Valid (From/To)

Name of Surety

Name of Contractor

Certificate Holder Wisconsin Department of Transportation

This is to certify that an annual bid bond issued by the above-named Surety is currently on file with the Wisconsin Department of Transportation.

This certificate is issued as a matter of information and conveys no rights upon the certificate holder and does not amend, extend or alter the coverage of the annual bid bond.

Cancellation: Should the above policy be cancelled before the expiration date, the issuing surety will give thirty (30) days written notice to the certificate holder indicated above.

(Signature of Authorized Contractor Representative) (Date)

Effective with March 2010 Letting

LIST OF SUBCONTRACTORS

Section 66.0901(7), Wisconsin Statutes, provides that as a part of the proposal, the bidder also shall submit a list of the subcontractors the bidder proposes to contract with and the class of work to be performed by each. In order to qualify for inclusion in the bidder's list a subcontractor shall first submit a bid in writing, to the general contractor at least 48 hours prior to the time of the bid closing. The list may not be added to or altered without the written consent of the municipality. A proposal of a bidder is not invalid if any subcontractor and the class of work to be performed by the subcontractor has been omitted from a proposal; the omission shall be considered inadvertent or the bidder will perform the work personally.

No subcontract, whether listed herein or later proposed, may be entered into without the written consent of the Engineer as provided in Subsection 108.1 of the Standard Specifications.

Name of Subcontractor Class of Work Estimated Value

Effective with December 2000 Letting Debarment Certification

CERTIFICATION REGARDING DEBARMENT, SUSPENSION, AND OTHER

RESPONSIBILITY MATTERS - PRIMARY COVERED TRANSACTIONS

Instructions for Certification

1. By signing and submitting this proposal, the prospective contractor is providing the certification set out below.

2. The inability of a person to provide the certification required below will not necessarily result in denial of participation in this covered transaction. The prospective contractor shall submit an explanation of why it cannot provide the certification set out below. The certification or explanation will be considered in connection with the department or agency's determination whether to enter into this transaction. However, failure of the prospective contractor to furnish a certification or an explanation shall disqualify such person from participation in this transaction.

3. The certification in this clause is a material representation of fact upon which reliance was placed when the department determined to enter into this transaction. If it is later determined that the contractor knowingly rendered an erroneous certification in addition to other remedies available to the Federal Government the department may terminate this transaction for cause or default.

4. The prospective contractor shall provide immediate written notice to the department to whom this proposal is submitted if at any time the prospective contractor learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.

5. The terms "covered transaction," "debarred," "suspended," "ineligible," "lower tier covered transaction," "participant," "person," "primary covered transaction," "principal," "proposal," and "voluntarily excluded," as used in this clause, have the meanings set out in the Definitions and Coverage sections of the rules implementing Executive Order 12549. You may contact the department to which this proposal is being submitted for assistance in obtaining a copy of those regulations.

6. The prospective contractor agrees by submitting this proposal that, should this contract be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department entering into this transaction.

7. The prospective contractor further agrees by submitting this proposal that it will include the clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered Transaction," which is included as an addendum to PR- 1273 - "Required Contract Provisions Federal Aid Construction Contracts," without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions.

8. The contractor may rely upon a certification of a prospective subcontractor/materials supplier that it is not debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A contractor may decide the method and frequency by which it determines the eligibility of its principals. Each contractor may, but is not required to, check the Disapproval List (telephone # 608/266/1631).

Effective with December 2000 Letting Debarment Certification

9. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render in good faith the certification required by this clause. The knowledge and information of a contractor is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.

10. Except for transactions authorized under paragraph 6 of these instructions, if a contractor in a covered transaction knowingly enters into a lower tier covered transaction with a person who is suspended, debarred, ineligible or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department may terminate this transaction for cause or default.

Certification Regarding Debarment, Suspension, and Other Responsibility Matters - Primary Covered Transactions

1. The prospective contractor certifies to the best of its knowledge and belief, that it and its principals:

(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency;

(b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements or receiving stolen property;

(c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offense enumerated in paragraph (1)(b) of this certification; and

(d) Have not within a three-year period preceding this proposal had one or more public transactions (Federal, State or local) terminated for cause or default.

2. Where the prospective contractor is unable to certify to any of the statements in this certification, such prospective contractor shall attach an explanation to this proposal.

5105-16-63 1 of 18

Special Provisions Table of Contents

Article Description Page #

1. General

2. Scope of Work

3. Waiving Bidder Prequalification

4. Consideration of Proposals

5. Prosecution and Progress

6. Traffic

7. Holiday and Special Event Work Restrictions

8. Utilities

9. Information to Bidders, U.S. Army Corps of Engineers Section 404 Permit

10. Information to Bidders, WPDES Transportation Construction General Permit (TCGP) for Storm

Water Discharges

11. Environmental Protection, Aquatic Exotic Species Control

12. Tree Clearing

13. Site Mobilization, Item SPV.0060.01

14. Site Traffic Control, Item SPV.0060.02

15. Semi-Permanent Restoration, Item SPV.0060.03

16. Work on Shoulder or Parking Lane, Item SPV.0060.04

17. Shoulder Closure on Divided Roadway, Item SPV.0060.05

18. Lane Closure with Flagging Operations, Item SPV.0060.06

19. Pedestrian Accommodations, Item SPV.0060.07

5105-16-63 2 of 18

STSP’S Revised July 1, 2026

SPECIAL PROVISIONS

1. General.

Perform the work under this construction contract for the following projects:

5105-16-63 Regionwide Tree Clearing Various Locations

Perform the work as the plans show and execute the work as specified in the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition, as published by the department, and these special provisions.

If all or a portion of the plans and special provisions are developed in the SI metric system and the schedule of prices is developed in the US standard measure system, the department will pay for the work as bid in the US standard system.

100-005 (20260701)

Bidding Information This project follows the Indefinite Delivery/Indefinite Quantity (ID/IQ) procurement method. Specific sites for the initial work order are shown in the project plans for information only. Additional sites may be added by issuance of work orders from the department. The work orders will indicate the work to be performed at each site and the duration of each work order.

Furnish to the department, when and if ordered, the supplies or services specified in the proposal up to and including the quantity designated in the proposal as the Maximum. The department will order under this contract at least the quantity of supplies or services designated in the proposal as the Minimum.

The work will be scheduled by issuance of work orders to the contractor from the department. Each work order will represent an independent collection of work sites. Work orders will specify the work sites, planned items, quantities of work, site-specific requirements, and allowable time to perform the work.

Work orders will be issued. A Notice to Proceed for a specific work order will be once all necessary permits are obtained by the department. Any environmental commitments will be included in the work order(s) special provisions.

The unit prices as bid on the Schedule of Items (SOI) will be assigned to the items in the work orders and shall become the basis of pricing all work orders.

2. Scope of Work.

The work under this contract consists of tree clearing, erosion control, traffic control and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract.

104-005 (20090901)

3. Waiving Bidder Prequalification.

Bidder prequalification is not required; however, prior to awarding a contract, the department may require the bidder to produce financial documentation similar to the prequalification statement (DT1621) and evidence that they have a history of performing work of a similar character in a satisfactory manner.

4. Consideration of Proposals.

Definitions

Contract Time: The number of calendar or working days shown in the proposal representing the time allowed for the completion of the work contemplated in the contract.

5105-16-63 3 of 18

ID/IQ (Indefinite Delivery/Indefinite Quantity): Type of contract that provides for an indefinite quantity of work during a fixed period of time.

Work Order: Document written to specify sites, contract time and scope of work including pay items.

Work Order Item List: Complete list of bid items shown on SOI included in the ID/IQ contract advertisement that the contractor can anticipate being used repetitively to perform the work orders of this ID/IQ contract.

Contract Description There are multiple sites where work shall be performed. There may be multiple work sites included in each work order.

Each work order will be executed separately. Do not begin work prior to execution. A separate Notice to Proceed will be issued for each work order. No work will be allowed to start prior to the Notice to Proceed for each work order.

Estimated Quantities The current estimated Minimum and Maximum contract quantities for Clearing are as follows:

Bid Item Unit Current Contract Amount Minimum Maximum

201.0105 STA 3 STA 200 STA 350 STA

201.0120 ID 82 ID 700 ID 1000 ID

See plans for additional estimated bid item quantities.

Contract Schedule

The department anticipates the following additional contract milestone dates. This schedule subject to revision by the department.

Anticipated first work order: December 21, 2026.

Anticipated second work order: January 15, 2027.

Anticipated third work order: February 15, 2027.

Additional work orders will not be issued after March 1, 2027.

Replace standard spec 103.2(1) with the following:

The department is taking separate bids for the construction of this project under an alternate proposal, identified as project 5105-16-63.

-The award of contract, if awarded, will be to the lowest responsible bidder among all bidders for either proposal, whose proposal complies with all requirements necessary to render it formal as determined conforming to standard spec 103.1.

stp-103-005 (20030820)

5. Prosecution and Progress.

Begin work within 10 calendar days after the engineer issues a written notice to do so.

Provide the start date to the engineer in writing within a month after executing the contract but at least 14 calendar days before the preconstruction conference. Upon approval, the engineer will issue the notification to proceed within ten calendar days before the approved start date.

To revise the start date, submit a written request to the engineer at least two weeks before the intended start date. The engineer will approve or deny that request based on the conditions cited in the request and its effect on the department’s scheduled resources.

The department will not grant time extensions to the contract completion date.

The completion date for clearing trees under this project is set by federal law and will not be modified.

Coordination

The work sites in this contract are referred to as areas. The tree clearing for each area is in preparation for different road projects. The areas and the projects they are in preparation for are listed below:

5105-16-63 4 of 18

AREA PROJ_ID COUNTY HWY

1* 1640-03-05 RICHLAND USH 014

2* 5590-05-00 DANE STH 078

3* 3110-00-05 JEFFERSON STH 059

4* 5571-01-04 ROCK STH 213

5* 5571-01-04 ROCK STH 213

6* 5205-03-09 GRANT STH 133

7* 5573-03-04 SAUK STH 136

8* 5970-03-04 IOWA STH 039

9* 5926-03-02 DANE STH 092

10* 3315-00-04 ROCK USH 014

11* 3576-07-04 JEFFERSON STH 106

12 5155-02-35 DANE USH 014

13 1202-00-33 GRANT USH 151

14* 1104-05-72 DODGE IH 41

15* 1104-01-71 DODGE IH 41

* These projects are not included in the PS&E but will be included in work orders 1 and 2.

Any coordination with utilities, environmental agencies or other outside contacts shall refer to the source project ID listed in the above table, not area.

Migratory Birds Area 12

Swallow or other migratory bird nests have been observed on or under the existing structure(s) listed below. All active nests (when eggs or young are present) of migratory birds are protected from purposeful take under the federal Migratory Bird Treaty Act. The nesting season for swallows and other birds is from April 15 to August 31.

Either prevent active nests from becoming established or prevent birds from nesting by installing and/or maintaining one suitable deterrent device on the following structure(s) prior to nesting season under the bid item Installing and Maintaining Bird Deterrent System:

• B-13-243, Netherwood Street over USH 14

• B-13-248, USH 14 WB over Irish Lane

• B-13-249, USH 14 EB over Irish Lane

• B-13-250, Haight Farm Road over USH 14

• B-13-260, USH 14 over Nine Springs Creek

Area 12

There shall be no instream disturbance of Nine Springs Creek near Station 640+25 EB as a result of construction activity under or for this contract, from March 1 to June 15, both dates inclusive, in order to avoid adverse impacts upon the spawning of fish.

5105-16-63 5 of 18

Any change to this limitation will require submitting a written request by the contractor to the engineer, subsequent review and concurrence by the Department of Natural Resources in the request, and final approval by the engineer. The approval will include all conditions to the request as mutually agreed upon by WisDOT and DNR.

Fish Spawning Area 12

There shall be no instream disturbance of Nine Springs Creek near Station 640+25 EB as a result of construction activity under or for this contract, from March 1 to June 15, both dates inclusive, in order to avoid adverse impacts upon the spawning of fish.

Any change to this limitation will require submitting a written request by the contractor to the engineer, subsequent review and concurrence by the Department of Natural Resources in the request, and final approval by the engineer. The approval will include all conditions to the request as mutually agreed upon by WisDOT and DNR.

Protection of Endangered Bats Federally protected bats have the potential to inhabit the project limits because they roost in trees, bridges, culverts, and other structures. Roosts may not have been observed on this project, but conditions to support the species exist. The species and all active roosts are protected by the federal Endangered Species Act. If an individual bat or active roost is encountered during construction operations, stop work, and notify the engineer and the WisDOT Regional Environmental Coordinator

(REC).

Ensure all operators, employees, and subcontractors working in areas of known or presumed bat habitat are aware of environmental commitments and avoidance and minimization measures (AMMs) to protect both bats and their habitat.

Direct temporary lighting, if used, away from wooded areas during the bat active season April 15 to October 31, both dates inclusive.

Tree Clearing/Trimming:

To avoid adverse impacts upon protected bats, do not perform tree clearing/trimming between April 15 and October 31, both dates inclusive. If the required tree clearing/trimming is not completed by April 14, the department will suspend all tree clearing/trimming and associated work directly impacted by clearing/trimming.Tree clearing/trimming is limited to that which is specified in the plans. Contractor means and methods to remove additional trees/branches will not be allowed. If it is determined that additional trees with a 3-inch or greater diameter at breast height (dbh), or branches of any size on those sized trees, need to be removed beyond contractor means and methods, notify the engineer to coordinate with the WisDOT REC to determine if consultation with United States Fish and Wildlife Service (USFWS) is required. The contractor must be aware that the WisDOT REC and/or USFWS may not permit modifications.

Due to potential for erosion, do not perform grubbing operations at the time of tree clearing unless grading activities will commence in those areas immediately following the tree clearing, or as otherwise approved by the engineer. Provide information for the grubbing and grading activities, including the schedule of operations, in the Erosion Control Implementation Plan (ECIP).

Blanding’s Turtle (Emydoidea blandingii) Area 12

Blanding’s Turtle is a Special Concern species in Wisconsin and has been known to inhabit the project area. Install “J-turns” at all silt fence ends adjacent to waterways to redirect them from the project areas.

6. Traffic.

Submit to engineer for approval a detailed traffic control plan for any changes to the proposed traffic control as shown on the plans. Submit the plan 14 days prior to the preconstruction conference, or if after the preconstruction conference, 14 days prior to the intended use of the revised traffic control. A request does not constitute approval.

If plan details are not provided in the traffic control plan, furnish plans for review by the engineer so that approval, or disapproval, is obtained at least three business days prior to any closure.

5105-16-63 6 of 18

Maintain access to all commercial, private, and field entrances for residents, businesses, and emergency vehicles. If access is to be temporarily closed, notify those affected at least two business days in advance of the closure. Do not restrict or close access to a property without notifying the property owner, resident, or business a minimum of 48 hours in advance.

Conduct operations in such a manner that causes the least interference and inconvenience to the free flow of vehicles and bicyclists on the roadways. This includes the following:

• All construction vehicles and equipment entering or leaving live traffic lanes shall yield to through traffic and bicyclists.

• Equip all vehicles and equipment entering or leaving the live traffic lanes with a hazard identification beam (flashing yellow signal) capable of being visible on a sunny day when viewed without the sun directly on or behind the device from a distance of 1000 feet. Activate the beam when merging into or exiting a live traffic lane.

• Do not deliver or store materials or equipment within open travel lanes or open side roads during any stage of construction. Temporary lane closures and/or halting of traffic within open roadways is not permitted.

Area-Specific Information Area 12

General No full freeway closures are allowed.

Active work zones and lane closures along USH 14 shall be limited to a maximum length of 4 miles at a time. Any lane closure exceeding 4 miles in length must be approved by the engineer.

Only one lane closure in a direction of travel along USH 14 will be allowed at a time.

Equipment, vehicles, and materials are not allowed to remain on the freeway shoulders and ramp shoulders when the contractor is not actively working.

If plan details are not provided in the traffic control plan, furnish plans for review by the engineer so that approval, or disapproval, is obtained at least three business days prior to any closure.

During lane closures, keep drums out of the open lane of traffic. When traffic is reduced to a single lane, drums may be placed in the open lane to shift traffic onto the shoulder only in the immediate vicinity of work with the approval of the engineer. Restore drums immediately after completing work in that area.

Material and equipment delivery is only permitted within lane closures.

Do not use maintenance crossovers to make U-turns unless the inside lanes in both directions are closed and the turn can be made without encroaching into adjacent open lanes. Do not use existing median crossovers for storage of equipment or materials.

Lane / Ramp / Sideroad Closures Allowable lane closure times are shown in the table below.

USH 14 SINGLE LANE CLOSURE HOURS

Closure

Day to Day USH 14 Eastbound USH 14 Westbound

Monday to Tuesday 6 PM Monday to 3 PM Tuesday

(21 hours) 9 AM Monday to 6 AM Tuesday

(21 hours)

Tuesday to Wednesday 6 PM Tuesday to 3 PM Wednesday

(21 hours) 9 AM Tuesday to 6 AM Wednesday

(21 hours)

Wednesday to Thursday 6 PM Wednesday to 3 PM Thursday

(21 hours) 9 AM Wednesday to 6 AM Thursday

(21 hours)

Thursday to Friday 6 PM Thursday to 3 PM Friday

(21 hours) 9 AM Thursday to 6 AM Friday

(21 hours)

Friday to Monday 6 PM Friday to 3 PM Monday

(69 hours) 9 AM Friday to 6 AM Monday

(69 hours)

5105-16-63 7 of 18

Coordinate traffic requirements under this contract with other ongoing department and local community construction projects.

Special Event Restrictions

• University of Wisconsin home football games – closures will not be permitted from five hours prior to game until five hours after the game.

Advance Notification Provide the Wisconsin State Patrol, Dane County Sheriff's Department, the City of Fitchburg Police Department, the City of Madison Police Department, and the engineer a current telephone number with which the contractor or his representative can be contacted during non-working hours in the event a safety hazard develops.

Area 13

Work Restrictions Do not perform work on the following ramps and entirely clear the traveled way and shoulders of such portions of the highway of equipment, barricades, signs, lights, and any other material that might impede the free flow of traffic during the following periods:

On Ramp

- From 6:00 AM to 6:00 PM

Off Ramp

- From 7:00 AM to 8:00 PM

Lane closures are limited to two closures in each direction of travel, each with a maximum length of 4 miles and separated by at least 3 miles. There must be work activities taking place when a lane is closed.

Keep all entrance and exit ramps open to traffic at all times unless stated elsewhere.

Conduct operations in a manner that will cause the least interference to traffic movements on USH 151 and all interchanges and crossroads within the project limits.

Do not haul across, unload material from, stop in, or otherwise interfere with traffic on any portion of USH 151 without a pre-approved traffic control plan and traffic control measures in place.

Have available at all times experienced personnel to promptly install, remove and reinstall the required traffic control devices to route traffic in order to perform the necessary construction operations.

Provide availability of equipment and work forces to promptly restore barricades, lights or other traffic control devices that are damaged or disturbed. In no case shall any barricade, light or other traffic control device be out of service for more than two hours.

Do not directly cross the live lanes of USH 151 with any vehicle or piece of construction equipment.

Flagging operations will not be permitted on USH 151.

Do not use maintenance crossings connecting eastbound and westbound roadways of USH 61 during construction operations unless both median lanes are closed to traffic.

Do not disturb, remove or obliterate any traffic control signs, advisory signs, shoulder delineators or beam guard in place without the approval of the engineer. Replace or repair all damage done to the above, caused by construction operations, at the contractor’s expense.

Wisconsin Lane Closure System Advance Notification Provide the following advance notification to the engineer for incorporation into the Wisconsin Lane Closure System (LCS).

5105-16-63 8 of 18

TABLE 108-1 CLOSURE TYPE AND REQUIRED MINIMUM ADVANCE NOTIFICATION

Closure type with height, weight, or width restrictions (available width, all lanes in one direction < 16 feet) MINIMUM NOTIFICATION

Lane and shoulder closures 7 calendar days

Full roadway closures 7 calendar days

Ramp closures 7 calendar days

Detours 7 calendar days

Closure type without height, weight, or width restrictions (available width, all lanes in one direction > 16 feet) MINIMUM NOTIFICATION

Shoulder Closures 3 calendar days

Lane closures 3 business days

Ramp closures 3 business days

Modifying all closure types 3 business days

Discuss LCS completion dates and provide changes in the schedule to the engineer at weekly project meetings in order to manage closures nearing their completion date.

7. Holiday and Special Event Work Restrictions.

Do not perform work on, nor haul materials of any kind along or across any portion of the highway carrying traffic in this project, and entirely clear the traveled way and shoulders of such portions of the highway of equipment, barricades, signs, lights, and any other material that might impede the free flow of traffic during the following holiday and special event periods:

- noon Friday, November 21, 2025 to 6:00 AM Monday, November 24, 2025 Deer Hunting Season;

- From noon Wednesday, November 25, 2026 to 6:00 AM Monday, November 30, 2026 Thanksgiving;

- From noon Wednesday, December 23, 2026 to 6:00 AM Monday, December 28, 2026 Christmas;

- From noon Wednesday, December 30, 2026 to 6:00 AM Monday, January 4, 2027 New Year’s Day;

- From noon Friday, January 16, 2027 to 6:00 AM Tuesday, January 20, 2027 MLK Day;

stp-107-005 (20210113)

8. Utilities.

This contract does not come under the provision of Administrative Rule Trans 220.

stp-107-066 (20240703)

The utility work plan includes additional detailed information regarding the location of known discontinued, relocated, or removed utility facilities. These can be requested from the department during the bid preparation process or from the project engineer after the contract has been awarded and executed.

Some of the utility work described below is dependent on prior work being performed by the contractor at a specific site. In such situations, provide the engineer and the affected utility a good faith notice of when the utility is to start work at the site. Provide this notice 14 to 16 calendar days in advance of when the prior work will be completed and the site will be available to the utility. Follow-up with a confirmation notice to the engineer and the utility not less than 3 working days before the site will be ready for the utility to begin its work.

Any utility facility locations (stations, offsets, elevations, depths) listed in this article are approximate.

Area 12 Alliant Energy – Electricity has overhead and underground facilities within the construction limits. The existing facilities where beam guard post adjustments may be required are located as follows:

• An underground crossing of USH 14 at Station 244+63EB. Adjust the barrier system to avoid the facility.

5105-16-63 9 of 18

• An underground crossing of USH 14 at Station 711+00WB. Adjust the barrier system to avoid the facility.

No conflicts with the tree clearing project activity.

The existing facilities where no conflicts or beam guard post adjustments are anticipated are as follows:

• A 69 kV overhead crossing of USH 14 at Station 243+00EB

• An underground crossing of USH 14 at Station 349+50EB

• Discontinued crossings of USH 14 at Stations 243+61, 276+55, and 346+86

No conflicts with the tree clearing project activity.

Alliant Energy – Gas has underground facilities within the construction limits. The existing facilities are located as follows:

• An underground crossing of USH 14 at Station 292+20EB

• A discontinued 4” steel main in a 6” casing crossing USH 14 at Station 298+93

No conflicts with the tree clearing project activity.

ANR Pipeline Company – Gas/Petroleum has underground facilities within the construction limits. The existing facilities are located as follows:

• An underground 16” high pressure pipeline crossing of USH 14 at Station 507+70EB

No conflicts with the tree clearing project activity.

AT&T Wisconsin – Communication Line has underground and overhead facilities within the construction limits. The existing facilities are located as follows:

• Underground copper cable crossing USH 14 along the north side of Irish Lane, including a crossing of Irish Lane

• Two underground conduits crossing USH 14 along the north side of Haight Farm Road

• An overhead crossing of USH 14 at Station 551+30EB

Proposed facility adjustments/relocations to resolve conflicts and be completed prior to construction are as follows:

• Underground copper cable crossing USH 14 along the north side of Irish Lane, including a crossing of Irish Lane will be discontinued in place.

This work may take place during the tree clearing activities.

ATC Management – Electricity Transmission has overhead facilities within the construction limits. The existing facilities are located as follows:

• A 69 kV overhead crossing of USH 14 at Station 245+00EB

• A 69 kV overhead line from Station 711+00WB to 880+00WB, RT

• A 69 kV overhead crossing of USH 14 at Station 414+00EB

• A 138 kV overhead crossing of USH 14 at Station 507+50EB

• A 69 kV overhead crossing of USH 14 at Station 628+00EB

No conflicts with the tree clearing project activity.

City of Fitchburg – Utility…

This is the start of the file's text. The full file is on GovTribe.