Concrete Pavement Repair & Replacement
Solicitation number
20261013022
Issued by
Eau Claire County, Wisconsin

About this file

This is a Special Provisions and Bid Preparation document issued by the Wisconsin Department of Transportation (WisDOT) for highway and structure construction projects in Dunn County. The contract encompasses two primary projects: 1020-05-63 (Menomonie to Eau Claire on IH 94, Wilson Creek to Red Cedar River) and 1021-01-78 (Baldwin to Menomonie East Branch Wilson Creek Bridge B-17-0051 on IH 94). The scope of work includes concrete pavement replacement and repair, HMA pavement work on IH 94 and at Rest Areas 61 and 62, deck repair for Wilson Creek bridge, replacement of expansion joints and girder bearings with concrete deck overlay for Wilson Street bridge, replacement of the north end of East Branch Wilson Creek box culvert, concrete approach slab replacement, concrete sidewalk installation, lighting, storm sewer work, guardrail installation, FTMS (Freeway Traffic Management System), erosion control, traffic control, pavement marking, and permanent signing. The contract must be executed within 10 calendar days after the engineer issues written notice to proceed, with work to be completed within the 2027 construction season. An interim completion deadline of May 28, 2027 is established for approach slabs on structures B-17-174 and B-17-175, with liquidated damages of $5,000 per calendar day for failure to meet this deadline. Rest Areas 61 and 62 may each be closed for a maximum of 21 calendar days but cannot be closed simultaneously.

Bidders must submit proposals using electronic methods (internet submission, printout with diskette/CD ROM, or paper bid with waiver) before 11:45 AM on the last business day preceding the letting. A proposal guaranty bond is required, and all bids must conform to Wisconsin Standard Specifications for Highway and Structure Construction, 2025 Edition. Electronic bidders must have an annual bid bond on file with WisDOT and a digital ID enabled by Info Tech Inc. Paper bids submitted under waiver require a $75 administrative fee. Extensive traffic control restrictions apply, including prohibitions on lane closures during peak travel hours on IH 94 and STH 25, with specific peak hour windows varying by day and season (Memorial Day to Labor Day periods have expanded restrictions). Lane Rental Fee Assessments of $4,000 per lane per direction of travel per hour (in 15-minute increments) apply for closures outside allowable times. Environmental restrictions include fish spawning protections for Wilson Creek (September 15 to May 15), migratory bird nesting season considerations (April 15 to August 31), endangered bat habitat protections with directional lighting requirements, and turtle nesting habitat exclusions (May 20 to September 18) requiring pre-installed exclusion fencing. No instream disturbance is permitted at Wilson Creek Station 24+00 during spawning season. The contract is subject to Wisconsin non-discrimination employment requirements, debarment certification, and compliance with WPDES Transportation Construction General Permit for stormwater discharge (3.146 acres of land disturbance). Holiday work restrictions prohibit work on IH 94 during Easter, Memorial Day, Independence Day, Labor Day, and Thanksgiving periods. Utility coordination is required for multiple service providers including City of Menomonie (water and sanitary sewer), Xcel Energy (gas and electricity), and telecommunications companies, with the City of Menomonie responsible for removing an existing water main from Wilson Street Bridge underside.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

"��#�$�� ����"�"�� !$%&����%'�������())(�*�%+,-����(�."�"��/�/0��1 2010�����1 ���304/�10�4���/��5 ������� 4�65/�%���7�&7)8 �9.:�����,��* ;

�7�<�

@���?�A � 9B��*C !

%��%7�%7,D 'E F��@G� �7�;

=<��"�F������� �:��F��@H �F7%,7��&% 9B��*C !

$I����������=� @�J"I ���H �"�"I G�"I"I �@A K

�"#�����������($I � ��I� @@ ��A �#������G��>#��"I �����A "�#"I ��H �" @���L �"�� �"I �G�"I�"I K "��� @�:� @�"�� �(���������M ��� "J�?

K @���J��� "��#�$�� ����"�"�� N%��=���(�� E""��I����������M

��� "J�� ����>��#�"I����EM<(F�@�.

�+O�����$�� -�P�"�� ��%8=����)%%������:� "���"�:���� %�&����>� H�!�J�E���H @�!���@A� "�H @�F �M��� �Q R���� �� =�E@@� ��=�:�"J=�."�" =�S���:�@ $I����� "���"���� T �����A

���HI"($I���

�"I�""I ���H �J�G�� =��� � "I���U "�"�A �#"I @���A V"I�""I �I�� T��� ��J�� @"I ��@#���"I

��� �=B�HIG�J���>��������=� @����@@

@�=� @I���I @"I ���""� H"I��������������@V� @"I�""I ����H ����J

�I�A �"I �"�J��� @�� �"�J= @� "�� J�H�

@� � J���� ��� =���"I �G�� � J��"�� � �

"�"�A ��@@� H� �� �"�� G�"I"I��������������@(1W�XWY�Z[\X]�XWŶ_[̀a]�W_�Zbcd[Y�Ye[Z��[\ef̂ g��W_h��_WiWẐj�feaX�Zbcd[YY[X\�̂X�ajakY_WX[k�c[l�WX�Yea��XYa_XaYm.

@�� @��G�� �"��� �"I���@�" �nnnnnnnnnnnnnnn+.�H �" =� �"��J�� ��#������ �� -+��� "����$J�

���
=��"��J��

�:�������� �<T��� �- +F�@@ ��.�H �" -+��� "����$J� �F�@@ -+F�@@ -2W_�1aî_YdaXY�6Za��Xjg/gia�Wo��W_hp �"��

��#�EG��@�!�"

�M ��� "J�?

@ �"��J�.

��q��05�/�2���r�11�5���6����0�

��A���=�;���� H=�M��@� H=�EHH�

H�" ���A "=�E��I��"���A I�����"�"�� =�:

�A ���� @�M G��>=�F ���M "�.�H � H=�$��##���:� "���=���A

"�;��>� H=O�HI"� H=���"

PLEASE ATTACH

PROPOSAL GUARANTY HERE

Effective with November 2007 Letting Proposal Requirements

PROPOSAL REQUIREMENTS AND CONDITIONS

The bidder, signing and submitting this proposal, agrees and declares as a condition thereof, to be bound by the following conditions and requirements.

If the bidder has a corporate relationship with the proposal design engineering company, the bidder declares that it did not obtain any facts, data, or other information related to this proposal from the design engineering company that was not available to all bidders.

The bidder declares that they have carefully examined the site of, and the proposal, plans, specifications and contract forms for the work contemplated, and it is assumed that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of the specifications, special provisions and contract. It is mutually agreed that submission of a proposal shall be considered conclusive evidence that the bidder has made such examination.

The bidder submits herewith a proposal guaranty in proper form and amount payable to the party as designated in the advertisement inviting proposals, to be retained by and become the property of the owner of the work in the event the undersigned shall fail to execute the contract and contract bond and return the same to the office of the engineer within fourteen (14) days after having been notified in writing to do so;

otherwise to be returned.

The bidder declares that they understand that the estimate of quantities in the attached schedule is approximate only and that the attached quantities may be greater or less in accordance with the specifications.

The bidder agrees to perform the said work, for and in consideration of the payment of the amount becoming due on account of work performed, according to the unit prices bid in the following schedule, and to accept such amounts in full payment of said work.

The bidder declares that all of the said work will be performed at their own proper cost and expense, that they will furnish all necessary materials, labor, tools, machinery, apparatus, and other means of construction in the manner provided in the applicable specifications and the approved plans for the work together with all standard and special designs that may be designed on such plans, and the special provisions in the contract of which this proposal will become a part, if and when accepted. The bidder further agrees that the applicable specifications and all plans and working drawings are made a part hereof, as fully and completely as if attached hereto.

The bidder, if awarded the contract, agrees to begin the work not later than ten (10) days after the date of written notification from the engineer to do so, unless otherwise stipulated in the special provisions.

The bidder declares that if they are awarded the contract, they will execute the contract agreement and begin and complete the work within the time named herein, and they will file a good and sufficient surety bond for the amount of the contract for performance and also for the full amount of the contract for payment.

Effective with November 2007 Letting Proposal Requirements

The bidder, if awarded the contract, shall pay all claims as required by Section 779.14, Statutes of Wisconsin, and shall be subject to and discharge all liabilities for injuries pursuant to Chapter 102 of the Statutes of Wisconsin, and all acts amendatory thereto. They shall further be responsible for any damages to property or injury to persons occurring through their own negligence or that of their employees or agents, incident to the performance of work under this contract, pursuant to the Standard Specifications for Road and Bridge Construction applicable to this contract.

In connection with the performance of work under this contract, the contractor agrees to comply with all applicable state and federal statutes relating to non-discrimination in employment. No otherwise qualified person shall be excluded from employment or otherwise be subject to discrimination in employment in any manner on the basis of age, race, religion, color, gender, national origin or ancestry, disability, arrest or conviction record (in keeping with s.111.32), sexual orientation, marital status, membership in the military reserve, honesty testing, genetic testing, and outside use of lawful products. This provision shall include, but not be limited to the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation, and selection for training, including apprenticeship. The contractor further agrees to ensure equal opportunity in employment to all applicants and employees and to take affirmative action to attain a representative workforce.

The contractor agrees to post notices and posters setting forth the provisions of the nondiscrimination clause, in a conspicuous and easily accessible place, available for employees and applicants for employment.

If a state public official (section 19.42, Stats.) or an organization in which a state public official holds at least a 10% interest is a party to this agreement, this contract is voidable by the state unless appropriate disclosure is made to the State of Wisconsin Ethics Board.

Effective with August 2015 Letting Bid Preparation

BID PREPARATION

Preparing the Proposal Schedule of Items A. General

(1) Obtain bidding proposals as specified in section 102 of the standard specifications prior to 11:45 AM of the last business day preceding the letting. Submit bidding proposals using one of the following methods:

1. Electronic bid on the internet.

2. Electronic bid on a printout with accompanying diskette or CD ROM.

3. Paper bid under a waiver of the electronic submittal requirements.

(2) Bids submitted on a printout with accompanying diskette or CD ROM or paper bids submitted under a waiver of the electronic submittal requirements govern over bids submitted on the internet.

(3) The department will provide bidding information through the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx

The contractor is responsible for reviewing this web site for general notices as well as information regarding proposals in each letting. The department will also post special notices of all addenda to each proposal through this web site no later than 4:00 PM local time on the Thursday before the letting. Check the department’s web site after 5:00 PM local time on the Thursday before the letting to ensure all addenda have been accounted for before preparing the bid. When bidding using methods 1 and 2 above, check the Bid ExpressΤΜ on-line bidding exchange at http://www.bidx.com/ after 5:00 PM local time on the Thursday before the letting to ensure that the latest schedule of items Expedite file (*.ebs or *.00x) is used to submit the final bid.

(4) Interested parties can subscribe to the Bid ExpressΤΜ on-line bidding exchange by following the instructions provided at the www.bidx.com web site or by contacting:

Info Tech Inc.

5700 SW 34th Street, Suite 1235 Gainesville, FL 32608-5371 email: mailto:customer.support@bidx.com

(5) The department will address equipment and process failures, if the bidder can demonstrate that those failures were beyond their control.

(6) Contractors are responsible for checking on the issuance of addenda and for obtaining the addenda. Notice of issuance of addenda is posted on the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx or by calling the department at (608) 266-1631. Addenda can ONLY be obtained from the department’s web site listed above or by picking up the addenda at the Bureau of Highway Construction, 4th floor, 4822 Madison Yards Way, Madison, WI, during regular business hours.

(7) Addenda posted after 5:00 PM on the Thursday before the letting will be emailed to the eligible bidders for that proposal. All eligible bidders shall acknowledge receipt of the addenda whether they are bidding on the proposal or not. Not acknowledging receipt may jeopardize the awarding of the project.

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx http://www.bidx.com/ http://www.bidx.com/ mailto:customer.support@bidx.com

B. Submitting Electronic Bids B.1 On the Internet

(1) Do the following before submitting the bid:

4. Have a properly executed annual bid bond on file with the department.

5. Have a digital ID on file with and enabled by Info Tech Inc. Using this digital ID will constitute the bidder's signature for proper execution of the bidding proposal.

(2) In lieu of preparing, delivering, and submitting the proposal as specified in 102.6 and 102.9 of the standard specifications, submit the proposal on the internet as follows:

1. Download the latest schedule of items reflecting all addenda from the Bid ExpressΤΜ web site.

2. Use ExpediteΤΜ software to enter a unit price for every item in the schedule of items.

3. Submit the bid according to the requirements of ExpediteΤΜ software and the Bid ExpressΤΜ web site. Do not submit a bid on a printout with accompanying diskette or CD ROM or a paper bid. If the bidder does submit a bid on a printout with accompanying diskette or a paper bid in addition to the internet submittal, the department will disregard the internet bid

4. Submit the bid before the hour and date the Notice to Contractors designates

5. Do not sign, notarize, and return the bidding proposal described in 102.2 of the standard specifications.

(3) The department will not consider the bid accepted until the hour and date the Notice to Contractors designates.

B.2 On a Printout with Accompanying Diskette or CD ROM

(1) Download the latest schedule of items from the Wisconsin pages of the Bid Express web site reflecting the latest addenda posted on the department’s web site at:

https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx

Use ExpediteΤΜ software to prepare and print the schedule of items. Provide a valid amount for all price fields. Follow instructions and review the help screens provided on the Bid ExpressΤΜ web site to assure that the schedule of items is prepared properly.

(2) Staple an 8 1/2 by 11 inch printout of the Expedite generated schedule of items to the other proposal documents submitted to the department as a part of the bidder's sealed bid. As a separate submittal, not in the sealed bid envelop but due at the same time and place as the sealed bid, also provide the ExpediteΤΜ generated schedule of items on a 3 1/2 inch computer diskette or CD ROM. Label each diskette or CD ROM with the bidder's name, the 4 character department-assigned bidder identification code from the top of the bidding proposal, and a list of the proposal numbers included on that diskette or CD ROM as indicated in the following example:

Bidder Name

BN00

Proposals: 1, 12, 14, & 22

(3) If bidding on more than one proposal in the letting, the bidder may include all proposals for that letting on one diskette or CD ROM. Include only submitted proposals with no incomplete or other files on the diskette or CD ROM.

(4) The bidder-submitted printout of the Expedite generated schedule of items is the governing contract document and must conform to the requirements of section 102 of the standard specifications. If a printout needs to be altered, cross out the printed information with ink or typewriter and enter the new information and initial it in ink. If there is a discrepancy between the printout and the diskette or CD ROM, the department will analyze the bid using the printout information.

(5) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:

1. The check code printed on the bottom of the printout of the ExpediteΤΜ generated schedule of items is not the same on each page.

2. The check code printed on the printout of the ExpediteΤΜ generated schedule of items is not the same as the check code for that proposal provided on the diskette or CD ROM.

3. The diskette or CD ROM is not submitted at the time and place the department designates.

B Waiver of Electronic Submittal

(1) The bidder may request a waiver of the electronic submittal requirements. Submit a written request for a waiver in lieu of bids submitted on the internet or on a printout with accompanying diskette or CD ROM. Use the waiver that was included with the paper bid document sent to the bidder or type up a waiver on the bidder’s letterhead. The department will waive the electronic submittal requirements for a bidding entity (individual, partnership, joint venture, corporation, or limited liability company) for up to 4 individual proposals in a calendar year. The department may allow additional waivers for equipment malfunctions.

(2) Submit a schedule of items on paper conforming to section 102 of the standard specifications.

The department charges the bidder a $75 administrative fee per proposal, payable at the time and place the department designates for receiving bids, to cover the costs of data entry. The department will accept a check or money order payable to: "Wisconsin, Dept. of Transportation."

(3) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:

1. The bidder fails to provide the written request for waiver of the electronic submittal requirements.

2. The bidder fails to pay the $75 administrative fee before the time the department designates for the opening of bids unless the bidder requests on the waiver that they be billed for the $75.

3. The bidder exceeds 4 waivers of electronic submittal requirements within a calendar year.

(4) In addition to the reasons specified in section 102 of the standard specifications, the department may refuse to issue bidding proposals for future contracts to a bidding entity that owes the department administrative fees for a waiver of electronic submittal requirements.

PROPOSAL BID BOND Wisconsin Department of Transportation

DT1303 1/2006

Proposal Number Project Number Letting Date

Name of Principal

Name of Surety State in Which Surety is Organized

We, the above-named Principal and the above-named Surety, are held and firmly bound unto the State of Wisconsin in the sum equal to the Proposal Guaranty for the total bid submitted for the payment to be made; we jointly and severally bind ourselves, our heirs, executors, administrators, successors and assigns. The condition of this obligation is that the Principal has submitted a bid proposal to the State of Wisconsin acting through the Department of Transportation for the improvement designated by the Proposal Number and Letting Date indicated above.

If the Principal is awarded the contract and, within the time and manner required by law after the prescribed forms are presented for signature, enters into a written contract in accordance with the bid, and files the bond with the Department of Transportation to guarantee faithful performance and payment for labor and materials, as required by law, or if the Department of Transportation shall reject all bids for the work described, then this obligation shall be null and void; otherwise, it shall be and remain in full force and effect.

In the event of failure of the Principal to enter into the contract or give the specified bond, the Principal shall pay to the Department of Transportation within 10 business days of demand a total equal to the Proposal Guaranty as liquidated damages; the liability of the Surety continues for the full amount of the obligation as stated until the obligation is paid in full.

The Surety, for value received, agrees that the obligations of it and its bond shall not be impaired or affected by any extension of time within which the Department of Transportation may accept the bid; and the Surety does waive notice of any such extension.

IN WITNESS, the Principal and Surety have agreed and have signed by their proper officers and have caused their corporate seals to be affixed this date: (DATE MUST BE ENTERED)

PRINCIPAL

(Company Name) (Affix Corporate Seal)

(Signature and Title)

(Company Name)

(Signature and Title)

(Company Name)

(Signature and Title)

(Company Name)

(Signature and Title)

NOTARY FOR PRINCIPAL

(Date)

State of Wisconsin ) ) ss.

County )

On the above date, this instrument was acknowledged before me by the named person(s).

(Signature, Notary Public, State of Wisconsin)

(Print or Type Name, Notary Public, State of Wisconsin)

(Date Commission Expires)

Notary Seal

(Name of Surety) (Affix Seal)

(Signature of Attorney-in-Fact)

NOTARY FOR SURETY

(Date)

State of Wisconsin ) ) ss.

County )

On the above date, this instrument was acknowledged before me by the named person(s).

(Signature, Notary Public, State of Wisconsin)

(Print or Type Name, Notary Public, State of Wisconsin)

(Date Commission Expires)

Notary Seal

IMPORTANT: A certified copy of Power of Attorney of the signatory agent must be attached to the bid bond.

CERTIFICATE OF ANNUAL BID BOND Wisconsin Department of Transportation

DT1305 8/2003

Time Period Valid (From/To)

Name of Surety

Name of Contractor

Certificate Holder Wisconsin Department of Transportation

This is to certify that an annual bid bond issued by the above-named Surety is currently on file with the Wisconsin Department of Transportation.

This certificate is issued as a matter of information and conveys no rights upon the certificate holder and does not amend, extend or alter the coverage of the annual bid bond.

Cancellation: Should the above policy be cancelled before the expiration date, the issuing surety will give thirty (30) days written notice to the certificate holder indicated above.

(Signature of Authorized Contractor Representative) (Date)

Effective with March 2010 Letting

LIST OF SUBCONTRACTORS

Section 66.0901(7), Wisconsin Statutes, provides that as a part of the proposal, the bidder also shall submit a list of the subcontractors the bidder proposes to contract with and the class of work to be performed by each. In order to qualify for inclusion in the bidder's list a subcontractor shall first submit a bid in writing, to the general contractor at least 48 hours prior to the time of the bid closing. The list may not be added to or altered without the written consent of the municipality. A proposal of a bidder is not invalid if any subcontractor and the class of work to be performed by the subcontractor has been omitted from a proposal; the omission shall be considered inadvertent or the bidder will perform the work personally.

No subcontract, whether listed herein or later proposed, may be entered into without the written consent of the Engineer as provided in Subsection 108.1 of the Standard Specifications.

Name of Subcontractor Class of Work Estimated Value

Effective with December 2000 Letting Debarment Certification

CERTIFICATION REGARDING DEBARMENT, SUSPENSION, AND OTHER

RESPONSIBILITY MATTERS - PRIMARY COVERED TRANSACTIONS

Instructions for Certification

1. By signing and submitting this proposal, the prospective contractor is providing the certification set out below.

2. The inability of a person to provide the certification required below will not necessarily result in denial of participation in this covered transaction. The prospective contractor shall submit an explanation of why it cannot provide the certification set out below. The certification or explanation will be considered in connection with the department or agency's determination whether to enter into this transaction. However, failure of the prospective contractor to furnish a certification or an explanation shall disqualify such person from participation in this transaction.

3. The certification in this clause is a material representation of fact upon which reliance was placed when the department determined to enter into this transaction. If it is later determined that the contractor knowingly rendered an erroneous certification in addition to other remedies available to the Federal Government the department may terminate this transaction for cause or default.

4. The prospective contractor shall provide immediate written notice to the department to whom this proposal is submitted if at any time the prospective contractor learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.

5. The terms "covered transaction," "debarred," "suspended," "ineligible," "lower tier covered transaction," "participant," "person," "primary covered transaction," "principal," "proposal," and "voluntarily excluded," as used in this clause, have the meanings set out in the Definitions and Coverage sections of the rules implementing Executive Order 12549. You may contact the department to which this proposal is being submitted for assistance in obtaining a copy of those regulations.

6. The prospective contractor agrees by submitting this proposal that, should this contract be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department entering into this transaction.

7. The prospective contractor further agrees by submitting this proposal that it will include the clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered Transaction," which is included as an addendum to PR- 1273 - "Required Contract Provisions Federal Aid Construction Contracts," without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions.

8. The contractor may rely upon a certification of a prospective subcontractor/materials supplier that it is not debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A contractor may decide the method and frequency by which it determines the eligibility of its principals. Each contractor may, but is not required to, check the Disapproval List (telephone # 608/266/1631).

Effective with December 2000 Letting Debarment Certification

9. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render in good faith the certification required by this clause. The knowledge and information of a contractor is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.

10. Except for transactions authorized under paragraph 6 of these instructions, if a contractor in a covered transaction knowingly enters into a lower tier covered transaction with a person who is suspended, debarred, ineligible or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department may terminate this transaction for cause or default.

Certification Regarding Debarment, Suspension, and Other Responsibility Matters - Primary Covered Transactions

1. The prospective contractor certifies to the best of its knowledge and belief, that it and its principals:

(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency;

(b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements or receiving stolen property;

(c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offense enumerated in paragraph (1)(b) of this certification; and

(d) Have not within a three-year period preceding this proposal had one or more public transactions (Federal, State or local) terminated for cause or default.

2. Where the prospective contractor is unable to certify to any of the statements in this certification, such prospective contractor shall attach an explanation to this proposal.

1020-05-63, 1021-01-78 1 of 61

Special Provisions Table of Contents

Article Description Page #

1. General

2. Scope of Work

3. Prosecution and Progress

4. Lane Rental Fee Assessment

5. Traffic

6. Work by Others

7. Utilities

8. Holiday and Special Event Work Restrictions

9. Information to Bidders, U.S. Army Corps of Engineers Section 404 Permit

10. Information to Bidders, WPDES Transportation Construction General Permit (TCGP) for Storm

Water Discharges

11. Environmental Protection, Aquatic Exotic Species Control

12. Erosion Control Structures

13. Notice to Contractor, Signal Timing Modifications

14. Notice to Contractor, Rest Area Closure

15. Notice to Contractor, Rest Area Playground Rings

16. Notice to Contractor, Rest Area Historical Markers

17. Notice to Contractor, Asbestos Containing Materials on Structure

18. Notice to Contractor, Notification of Demolition and/or Renovation No Asbestos Found

19. Notice to Contractor, Verification of Asbestos Inspection, No Asbestos Found

20. Construction Over or Adjacent to Navigable Waters

21. Public Convenience and Safety

22. Nighttime Work Lighting-Stationary

23. General Requirements for Electrical Work

24. Intelligent Transportation Systems (ITS) – Control of Materials

25. Signing

26. Removing Street Light Assembly, Item 204.9060.S.01

27. Removing Wireless Traffic Sensor Access Point, Item 204.9060.S.02

28. Removing Wireless Traffic Sensor Repeater, Item 204.9060.S.03

29. Removing Electrical Conductors from Existing Conduit, Item 204.9090.S.01

30. Diamond Grinding

31. QMP HMA Pavement Nuclear Density

32. Removing Bearings, B-17-40, Item 506.7050.S

33. Cleaning Decks to Reapply Concrete Masonry Overlay, Item 509.0505.S

34. Sawing Pavement Deck Preparation Areas, Item 509.0310.S

35. Concrete Masonry Deck Repair, Item 509.2100.S

36. Removing Concrete Masonry Deck Overlay B-17-40, Item 509.9005.S

1020-05-63, 1021-01-78 2 of 61

37. Concrete Staining B-17-29, Item 517.1010.S

38. Architectural Surface Treatment B-17-29, Item 517.1050.S

39. Reseal Crushed Aggregate Slope Paving, Item 604.9015.S

40. Cover Plates Temporary, Item 611.8120.S

41. Wisconsin Historical Marker, Item 615.1000

42. Digital Speed Reduction System (DSRS), Item 643.0370.S

43. Portable Automated Real-Time Traffic Queue Warning System, Item 643.1200.S

44. Basic Traffic Queue Warning System, Item 643.1205.S

45. Install Conduit Into Existing Item, Item 652.0700.S

46. Adjusting Pull Boxes, Item 653.0900

47. Lamp, Ballast, LED, Switch Disposal by Contractor, Item 659.5000.S

48. Removing CCTV Camera, Item 677.9200.S

49. Installing and Maintaining Climbing Turtle Exclusion Fence, Item 999.2100.S

50. Repair Embankment, Item SPV.0060.01

51. Reset and Retie End Section, Item SPV.0060.02

52. Remove Stone Sign Supports, Item SPV.0060.03

53. Remove Playground Landscaping, Item SPV.0060.04

54. Modify Existing Lighting Controls, Item SPV.0060.05

55. Temporary Street Lighting System (Rest Area #61), Item SPV.0060.06; Temporary Street

Lighting System (Rest Area #62), Item SPV.0060.07

56. Install Wireless Traffic Sensor, Item SPV.0060.08

57. Install Wireless Traffic Sensor Access Point, Item SPV.0060.09

58. Install Wireless Traffic Sensor Repeater, Item SPV.0060.10

59. Fence Repairs B-17-29, Item SPV.0060.11

60. Bearing Maintenance B-17-29, Item SPV.0060.12

61. Temporary Water Diversion, Structure B-17-51, Item SPV.0060.13

62. Cleaning Box Culvert B-17-51, Item SPV.0060.14

63. Culvert Pipe Replacement Limits Exploration and Removal, Item SPV.0060.15

64. Cleaning Ditch, Item SPV.0090.01

65. Fiber Wrap Reinforcing Non-Structural, Item SPV.0165.01

66. PreStressed Girder Surface Repair, Item SPV.0165.02

67. Rapid Concrete Pavement Repair, Item SPV.0180.01; Rapid Concrete Pavement Replacement, Item SPV.0180.02

1020-05-63, 1021-01-78 3 of 61

STSP’S Revised April 1, 2026

SPECIAL PROVISIONS

1. General.

Perform the work under this construction contract for the following projects:

1020-05-63 Menomonie – Eau Claire Wilson Creek to Red Cedar River

IH 94

Dunn County

1021-01-78 Baldwin - Menomonie East BR Wilson CR Bridge, B-17-0051

IH 94

Dunn County

Perform the work as the plans show and execute the work as specified in the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition, as published by the department, and these special provisions.

If all or a portion of the plans and special provisions are developed in the SI metric system and the schedule of prices is developed in the US standard measure system, the department will pay for the work as bid in the US standard system.

100-005 (20260401)

2. Scope of Work.

The work under this contract consists of concrete pavement replacement, concrete pavement repair, HMA pavement on IH 94 and at Rest Areas 61 and 62; deck repair for Wilson Creek bridge, replace expansion joints and girder bearings with a concrete deck overlay for Wilson Street bridge; replace north end of East Branch Wilson Creek box culvert; concrete approach slab replacement; concrete sidewalk;

lighting; storm sewer; culvert pipe reinforced concrete; guardrail; FTMS; erosion control; traffic control;

pavement marking; permanent signing; restoration; and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract.

104-005 (20090901)

3. Prosecution and Progress.

Begin work within 10 calendar days after the engineer issues a written notice to do so.

Provide the time frame for construction of the project within the 2027 construction season to the engineer in writing within a month after executing the contract but at least 14 calendar days before the preconstruction conference. Assure that the time frame is consistent with the contract completion time.

Upon approval, the engineer will issue the notice to proceed within ten calendar days before the beginning of the approved time frame.

To revise the time frame, submit a written request to the engineer at least two weeks before the beginning of the intended time frame. The engineer will approve or deny that request based on the conditions cited in the request and its effect on the department’s scheduled resources.

Interim Completion and Liquidated Damages – B-17-174 and B-17-175 Approach Slabs: May 28, Complete construction operations on the approach slabs for structures B-17-174 and B-17-175 to the stage necessary to reopen it to through traffic by May 28, 2027. Do not reopen until completing the following work: removal of existing approach slabs and installing new approach slabs.

This work cannot be started until April 4, 2027.

If the contractor fails to complete the work necessary to reopen all lanes of IH-94 to traffic by May 28, 2027, the department will assess the contractor $5,000 in interim liquidated damages for each calendar day the contract work remains incomplete beyond 12:01 AM on May 28, 2027. An entire calendar day will be charged for any period of time within a calendar day that the road remains closed beyond 12:01 AM.

1020-05-63, 1021-01-78 4 of 61

If contract time expires prior to completing all work specified in the contract, additional liquidated damages will be affixed according to standard spec 108.11.

Construction Staging Replace or repair any concrete pavement removed on the same day.

Guardrail shall be removed and constructed on the same day for each individual location unless other barrier protection is in place.

B-17-29 (STH 25) & B-17-40 (Wilson Street) Bridge structures B-17-29 and B-17-40 may not be closed simultaneously.

Notify City of Menomonie David Schofield, Director of Public Works, (715) 619-6246, prior to closure of each structure.

Notify Dunn County Transit Commission, Austin Witt (awitt@dunncountywi.gov), (715) 235-7433, at least 7 calendar days prior to closure of B-17-40 for alteration of Community Bus Route.

Rest Area #61 & Rest Area #62 Rest areas #61 & #62 may not be closed simultaneously.

Each rest area may be closed to public for a maximum of 21 calendar days.

Rest area entrances to be closed at least 8 hours prior to start of work to allow trucks and automobiles in rest area to exit.

Maintain access to each rest area as well as the maintenance garages throughout construction for Bureau of Highway Maintenance service provider maintenance vehicles.

B-17-208 & B-17-209 (On IH 94 Over Red Cedar River) No work to be done on structures. Concrete curb and gutter and concrete surface drains abut structures.

Protect existing bike path on the south side of B-17-208.

IH 94 Culvert Pipe Replacement Culvert pipe replacement under IH 94 eastbound travel lanes to be replaced in a manner to provide for traffic being reopened for peak hours detailed in the traffic section. Culvert exploration is anticipated to determine the exact location of the existing angle in the pipe and limits of the concrete replacement.

Fish Spawning There shall be no instream disturbance of Wilson Creek at Station 24+00 as a result of construction activity under or for this contract, from September 15th to May 15th both dates inclusive, in order to avoid adverse impacts upon the spawning of Trout and other aquatic species.

Any change to this limitation will require submitting a written request by the contractor to the engineer, subsequent review and concurrence by the Department of Natural Resources in the request, and final approval by the engineer. The approval will include all conditions to the request as mutually agreed upon by WisDOT and DNR.

Migratory Birds No evidence of swallow or other migratory bird nests have been observed on or under the following structures(s) during the preconstruction inspection. However, if nesting is later observed prior to or during construction, the contractor shall implement avoidance/deterrent measures when feasible, as directed by the engineer. Measures may include removal of unoccupied or partially constructed nests by scraping or pressure washing. The engineer will determine if the avoidance/deterrent measures cannot be reasonably implemented.

The nesting season for swallows and other birds is from April 15 to August 31. All active nests (when eggs or young are present) of migratory birds are protected from purposeful take under the federal Migratory Bird Treaty Act. Prior to any activity that may result in active nest take, the engineer will contact the WisDOT region environmental coordinator to complete coordination with the U.S. Fish and Wildlife Service (USFWS). The engineer will complete any required follow up notification to USFWS for FAST Act compliance.

• B-17-0029, B-17-0040, B-17-0051, B-17-0174, B-17-0175 mailto:awitt@dunncountywi.gov

1020-05-63, 1021-01-78 5 of 61

Protection of Endangered Bats Federally protected bats have the potential to inhabit the project limits because they roost in trees, bridges, culverts, and other structures. Roosts may not have been observed on this project, but conditions to support the species exist. The species and all active roosts are protected by the federal Endangered Species Act. If an individual bat or active roost is encountered during construction operations, stop work, and notify the engineer and the WisDOT Regional Environmental Coordinator

(REC).

Ensure all operators, employees, and subcontractors working in areas of known or presumed bat habitat are aware of environmental commitments and avoidance and minimization measures (AMMs) to protect both bats and their habitat.

Direct temporary lighting, if used, away from wooded areas during the bat active season April 15 to October 31, both dates inclusive.

Tree Clearing:

Tree clearing is limited to that which is specified in the plans. Contractor means and methods to remove additional trees will not be allowed. If it is determined that additional trees with a 3-inch or greater diameter at breast height (dbh) need to be removed beyond contractor means and methods, notify the engineer to coordinate with the WisDOT REC to determine if consultation with United States Fish and Wildlife Service (USFWS) is required. The contractor must be aware that the WisDOT REC and/or USFWS may not permit modifications.

Submit a schedule and description of clearing operations with the ECIP 14 days prior to any clearing operations. The department will determine, based on schedule and scope of work, what additional erosion control measures shall be implemented prior to the start of clearing operations, and list those additional measures in the ECIP.

Climbing Turtle General

Turtles are known to inhabit Red Cedar River and Wilson Creek, and suitable habitat exists within 1,000 ft of that location. It is assumed turtles are present at or near the project site during construction.

When within 1,000 ft of Red Cedar River, Sta 158+00, and Wilson Creek, Sta 24+00, use the following erosion mat types as shown on the plans or directed by the engineer, to minimize animal entrapment:

Erosion Mat Urban Class I Type A Erosion Mat Urban Class I Type B Erosion Mat Class II Type C

Furnish mat of these classes from the WisDOT Erosion Control Product Acceptability List (PAL).

Nesting Habitat

No ground disturbance, heavy equipment operation or supply/equipment storage shall occur within 200 ft of the Red Cedar River, Station 158+00 to 164+00, or Wilson Creek, Station 23+00 to 24+50 during the turtle nesting season from May 20 to September 18, both dates inclusive, unless exclusion fencing has been installed prior to May 20 to keep turtles from entering the work area. Install and/or maintain exclusion fencing in accordance with the Turtle Exclusion Fencing, Climbing Turtle bid item included in the contract.

Installation of exclusion fencing from May 20 to September 18 is not allowed, even if a turtle survey is conducted, as it must be assumed that turtles have established nests as of May 20. A survey is not sufficient to identify established nests, resulting in potential egg mortality. Adjustment of these dates will not be considered.

Nesting Habitat

No ground disturbance, heavy equipment operation or supply/equipment storage shall occur within 200 ft of the Red Cedar River, Station 158+00 to 164+00, or Wilson Creek, Station 23+00 to 24+50, during the turtle nesting season from May 20 to September 18, both dates inclusive, unless exclusion fencing has been installed prior to May 20 to keep turtles from entering the work area. Install and/or maintain exclusion fencing in accordance with the Turtle Exclusion Fencing, Climbing Turtle bid item included in the contract.

Installation of exclusion fencing from May 20 to September 18 is not allowed, even if a turtle survey is conducted, as it must be assumed that turtles have established nests as of May 20. A survey is not

1020-05-63, 1021-01-78 6 of 61 sufficient to identify established nests, resulting in potential egg mortality. Adjustment of these dates will not be considered.

Overwintering Habitat

There shall be no in-water disturbance or drawdowns of the Red Cedar River or Wilson Creek during the turtle overwintering period. The overwintering period runs from October 1 to April 30, both dates inclusive.

Requests for date adjustments will only be considered if they coincide with WDNR’s weather-dependent activity periods found at this link: https://dnr.wisconsin.gov/topic/Wildlifehabitat/HerpRegulations. Submit requests to the engineer for approval. The engineer will consult with the WDNR Endangered Resources Liaison, Stacy Rowe. Other date adjustment requests will not be approved.

In-water disturbance includes, but is not limited to, streambank/rip rap installation, ford installations, open cut trenching, barge spudding, dredging, filling, and other in-water actions commonly associated with culvert replacement or maintenance, and bridge demolition or construction.

4. Lane Rental Fee Assessment.

A General The contract designates some lane closures to perform the work. The contractor will not incur a Lane Rental Fee Assessment for closing lanes during the allowable lane closure times. The contractor will incur a Lane Rental Fee Assessment for each lane closure outside of the allowable lane closure times. If a lane is obstructed at any time due to contractor operations, it is considered a closure. The purpose of lane rental is to enforce compliance of lane restrictions and discourage unnecessary closures.

The allowable lane closure times are shown in the Traffic article.

Submit the dates of the proposed lane, ramp, and roadway restrictions to the engineer as part of the progress schedule.

B Lane Rental Fee Assessment The Lane Rental Fee Assessment incurred for each lane closure, each ramp closure, and each full closure of a roadway, per direction of travel, is as follows:

- $4,000 per lane, per direction of travel, per hour broken into 15-minute increments

The Lane Rental Fee Assessment represents a portion of the cost of the interference and inconvenience to the road users for each closure. All lane, roadway, or ramp closure event increments 15 minutes and less will be assessed as a 15-minute increment.

The engineer, or designated representative, will be the sole authority in determining time period length for the Lane Rental Fee Assessment.

Lane Rental Fee Assessments will not be assessed for closures due to crashes, accidents, or emergencies not initiated by the contractor.

The department will assess Lane Rental Fee Assessment by the dollar under the administrative item Failing to Open Road to Traffic. The total dollar amount of Lane Rental Fee Assessment will be computed by multiplying the Lane Rental Assessment Rate by the number of 15-minute increments of each lane closure event as described above.

Lane Rental Fee Assessment will be in effect from the time of the Notice to Proceed until the department issues final acceptance. If interim completion time or contract time expires before the completion of specified work in the contract, additional liquidated damages will be assessed as specified in standard spec 108.11 or as specified within this contract.

stp-108-065 (20161130)

5. Traffic.

Advance Notification Portable changeable message signs provided under this contract will be used for incident management or as required by the project engineer and are to be operated by the Wisconsin State Patrol and the Traffic Management Center (TMC). Place the required portable changeable message signs at the specified https://dnr.wisconsin.gov/topic/Wildlifehabitat/HerpRegulations

1020-05-63, 1021-01-78 7 of 61 locations in the plan at least one week prior to construction. Contact the TMC at (414) 227-2142 (tmc@dot.wi.gov) for communications system integration and testing.

Temporary Regulatory Speed Limit Reduction During engineer-approved regulatory speed limit reductions, install temporary speed limit signs on the inside and outside shoulders of divided roadways to enhance visibility. On two-lane, two-way roadways, install temporary speed limit signs on shoulders. When construction activities impede the location of a post-mounted regulatory speed limit sign, relocate the sign for maximum visibility to motorists. If work lasts less than seven days, mount the regulatory speed limit sign on a portable sign support.

Post temporary regulatory speed limit signs in work zone only during continuous worker activity. During periods of no work activity or when the traffic controls are removed from the roadway, cover or remove the temporary speed limit signs.

Posted Speed Limit When Work Not Being Performed:

IH 94: 70 MPH

STH 25: 45 MPH

Temporary Speed Limits During Work Operations:

IH 94: 55 MPH

STH 25: 35 MPH

IH 94 Mainline Temporary single lane closures are permitted on IH-94 and STH 25 interchange ramps during IH 94 off-peak travel hours. Temporary lane closures will not be permitted on IH-94 and the STH 25 interchange ramps during the IH 94 peak travel hours shown below:

IH 94 EB Peak Hours

Day Pre-Memorial Day Memorial Day to Labor Day

After Labor Day

Monday 10:00 AM – 3:00 PM 9:00 AM – 5:00 PM 9:00 AM – 4:00 PM

Tuesday None 10:00 AM – 5:00 PM None

Wednesday 2:00 PM – 5:00 PM 10:00 AM – 6:00 PM 2:00 PM – 5:00 PM*

Thursday 10:00 AM – 6:00 PM 10:00 AM – 6:00 PM 10:00 AM – 6:00 PM**

Friday 9:00 AM – 7:00 PM 9:00 AM – 7:00 PM 9:00 AM – 7:00 PM

Saturday 8:00 AM – 2:00 PM 9:00 AM – 2:00 PM 9:00 AM – 2:00 PM

Sunday 10:00 AM – 6:00 PM 10:00 AM – 6:00 PM 10:00 AM – 6:00 PM

*3rd Wednesday in October: 9:00 AM – 6:00 PM

**3rd Thursday in October: 8:00 AM – 6:00 PM

IH 94 WB Peak Hours

Day Pre-Memorial Day Memorial Day to Labor Day

After Labor Day

Monday 2:00 PM – 5:00 PM 12:00 PM – 6:00 PM 2:00 PM – 5:00 PM

Tuesday None 2:00 PM – 6:00 PM None

Wednesday 2:00 PM – 5:00 PM 2:00 PM – 6:00 PM None

Thursday 2:00 PM – 6:00 PM 12:00 PM – 6:00 PM 2:00 PM – 6:00 PM

Friday 11:00 AM – 7:00 PM 10:00 AM – 7:00 PM 11:00 AM – 7:00 PM

Saturday 10:00 AM – 5:00 PM 10:00 AM – 5:00 PM 10:00 AM – 5:00 PM

Sunday 10:00 AM – 8:00 PM 10:00 AM – 8:00 PM 10:00 AM – 8:00 PM mailto:tmc@dot.wi.gov

1020-05-63, 1021-01-78 8 of 61

B-17-174 & B-17-175 (On IH 94 Over Wilson Creek) IH 94 lane closures for the bridge work on B-17-174 and B-17-175 will be permitted to have continuous lane closures with the following restrictions:

Continuous closures for approach slabs to be completed prior to Memorial Day.

No lane closures from Friday noon to Sunday at 9:00 p.m.

Closure may be extended along IH 94 during the approach slab work to do concrete patching. Closures to be limited to area where patching is taking place.

IH 94 & STH 25 Interchange Ramps Temporary ramp closures allowed during IH-94 off peak hours. Temporary ramp closures will not be permitted during the peak travel hours.

Rest Area #61 & Rest Area #62 Rest areas #61 & #62 may not be closed simultaneously.

Each rest area may be closed to public for a maximum of 21 calendar days.

Rest area entrances to be closed at least 8 hours prior to start of work to allow trucks and automobiles in rest area to exit.

Maintain access to each rest area as well as the maintenance garages throughout construction for Bureau of Highway Maintenance service provider maintenance vehicles.

Notify WisDOT Bureau of Highway Maintenance Roadside Facilities Unit 7 calendar days prior to closure of Rest Area. Contact Joseph Coughlin (608) 261-8975, Joseph.Coughlin@dot.wi.gov

Notify WisDOT Field Operations, Russell Lewis (608) 516-5754, Russell.lewis@dot.wi.gov 7 calendar days prior to closure of rest area to coordinate replacement of pavement loops located at rest area exit with pavement replacement work.

Wisconsin Lane Closure System Advance Notification Provide the following advance notification to the engineer for incorporation into the Wisconsin Lane Closure System (LCS).

TABLE 108-1 CLOSURE TYPE AND REQUIRED MINIMUM ADVANCE NOTIFICATION

Closure type with height, weight, or width restrictions (available width, all lanes in one direction < 16 feet) MINIMUM NOTIFICATION

Lane and shoulder closures 7 calendar days

Full roadway closures 7 calendar days

Ramp closures 7 calendar days

Detours 7 calendar days

Closure type without height, weight, or width restrictions (available width, all lanes in one direction > 16 feet) MINIMUM NOTIFICATION

Shoulder Closures 3 calendar days

Lane closures 3 business days

Ramp closures 3 business days

Modifying all closure types 3 business days

Discuss LCS completion dates and provide changes in the schedule to the engineer at weekly project meetings in order to manage closures nearing their completion date.

mailto:Joseph.Coughlin@dot.wi.gov mailto:Russell.lewis@dot.wi.gov

1020-05-63, 1021-01-78 9 of 61

IH 94 Traffic Staging

PROJECT ID 1020-05-63

IH 94 Bridge Work

STAGE 1 TRAFFIC

Utilize inside lane closures on IH-94 EB and WB to facilitate stage 1 bridge work.

Maintain traffic on the outside lanes with traffic control drums and concrete barrier temporary precast

STAGE 2 TRAFFIC

Utilize outside lane closures on IH-94 EB and WB to facilitate stage 1 bridge work.

Maintain traffic on the inside lanes with traffic control drums and concrete barrier temporary precast

IH 94

STAGE 1…