20261013001proposal.pdf
PDF 1 MB Posted
- Attached to
- Bridges - Terrytown Road to Lehman Road
- Solicitation number
- 20261013001
- Issued by
- Sheboygan County, Wisconsin
About this file
This is a proposal document related to a Wisconsin Department of Transportation bridge improvement project for work on the Terrytown Road to Lehman Road bridge. The project scope includes polymer overlay application on bridge decks, minor concrete structure repairs, pavement marking, and all incidental items necessary to complete the work as specified in the contract plans and proposal documents. The document appears to contain standard proposal formatting and administrative information typical of state transportation construction contracts, though the specific quantities, timelines, and detailed project specifications are not clearly legible in the provided file content.
The proposal document references bidding procedures and contract administration processes consistent with Wisconsin state procurement requirements. However, the specific pricing terms, bid amounts, contractor information, funding sources, and other financial details are not clearly discernible from the available file content. Additional documentation such as the detailed scope of work, contract specifications, and bid tabulation sheets would be necessary to provide comprehensive information regarding contract value, payment terms, and project funding sources.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
"��#�$�� ����"�"�� !$�%�&���'&�&����())(�*��+,-����(�."�"��/�/0��1 2010�����1 ���304/�10�4���/��5 ������� 4�65/��),�7�879& ': ;�������7�.� <�=�">?;��@A �7$ ��>"�B �C@�"��D E�� �C@ F.G���& .� $E����������?� @�>"E ���A �"�"E B�"E"E �@H I
�"#�����������($E � ��E� @@ ��H �#������B��<#��"E �����H "�#"E ��A �" @���J �"�� �"E �B�"E�"E @����������C I "��� @�=� @�"�� �(���������K ��� ">�C I "��#�$�� ����"�"�� L8�?���(�� :""��E����������K
��� ">�� ����<��#�"E����:KM(;�@�.
�+D�����$�� -�N�"�� ���O?�&�&)��������=� "���"�=���� O�����<� A�!�>�:���A @�!���@H� "�A ���M " �K��� �P Q���� �� ?�R���=�@ $E����� "���"���� S �����H
���AE"($E���
�"E�""E ���A �>�B�� ?��� � "E���T "�"�H �#"E @���H U"E�""E �E�� S��� @"E ��@#���"E
��� �?G�AEB�>���<��������?� @����@@
@�?� @E���E @"E ���""� A"E��������������@U� @"E�""E ����A
�E�H �"E @� "�� >�A�
��� ?���"E �B��
"�"�H ��@@� A� �� �"�� B�"E"E��������������@(1V�WVX�YZ[W\�WVX]̂Z_̀\�V̂�YabcZX�XdZY��Z[de]f��V̂g��̂VhVY]i�ed̀W�YabcZXXZW[�]W�̀ìjX̂VWZj�bZk�VW�Xd̀��WX̀ Ŵ̀Xl.
@�� @��B�� �"��� �"E���@�" �mmmmmmmmmmmmmmm+.�A �"
| � | �� |
| ?� | �"��>�� |
�=�������� �MS���
��.�A �" -2V̂�1̀ h]̂Xc ẀX�6Ỳ��Wif/fh̀�Vn��V̂go �"�� ��#�:B��@�!�" �K ��� ">�C
��p��05�/�2���q�11�5���6����0�
�C E�����"�"�� �+���>�
��NH
���>-?�$��##���=� "���?���H "�r��<� A(
PLEASE ATTACH
PROPOSAL GUARANTY HERE
Effective with November 2007 Letting Proposal Requirements
PROPOSAL REQUIREMENTS AND CONDITIONS
The bidder, signing and submitting this proposal, agrees and declares as a condition thereof, to be bound by the following conditions and requirements.
If the bidder has a corporate relationship with the proposal design engineering company, the bidder declares that it did not obtain any facts, data, or other information related to this proposal from the design engineering company that was not available to all bidders.
The bidder declares that they have carefully examined the site of, and the proposal, plans, specifications and contract forms for the work contemplated, and it is assumed that the bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality, and quantities of work to be performed and materials to be furnished, and as to the requirements of the specifications, special provisions and contract. It is mutually agreed that submission of a proposal shall be considered conclusive evidence that the bidder has made such examination.
The bidder submits herewith a proposal guaranty in proper form and amount payable to the party as designated in the advertisement inviting proposals, to be retained by and become the property of the owner of the work in the event the undersigned shall fail to execute the contract and contract bond and return the same to the office of the engineer within fourteen (14) days after having been notified in writing to do so;
otherwise to be returned.
The bidder declares that they understand that the estimate of quantities in the attached schedule is approximate only and that the attached quantities may be greater or less in accordance with the specifications.
The bidder agrees to perform the said work, for and in consideration of the payment of the amount becoming due on account of work performed, according to the unit prices bid in the following schedule, and to accept such amounts in full payment of said work.
The bidder declares that all of the said work will be performed at their own proper cost and expense, that they will furnish all necessary materials, labor, tools, machinery, apparatus, and other means of construction in the manner provided in the applicable specifications and the approved plans for the work together with all standard and special designs that may be designed on such plans, and the special provisions in the contract of which this proposal will become a part, if and when accepted. The bidder further agrees that the applicable specifications and all plans and working drawings are made a part hereof, as fully and completely as if attached hereto.
The bidder, if awarded the contract, agrees to begin the work not later than ten (10) days after the date of written notification from the engineer to do so, unless otherwise stipulated in the special provisions.
The bidder declares that if they are awarded the contract, they will execute the contract agreement and begin and complete the work within the time named herein, and they will file a good and sufficient surety bond for the amount of the contract for performance and also for the full amount of the contract for payment.
Effective with November 2007 Letting Proposal Requirements
The bidder, if awarded the contract, shall pay all claims as required by Section 779.14, Statutes of Wisconsin, and shall be subject to and discharge all liabilities for injuries pursuant to Chapter 102 of the Statutes of Wisconsin, and all acts amendatory thereto. They shall further be responsible for any damages to property or injury to persons occurring through their own negligence or that of their employees or agents, incident to the performance of work under this contract, pursuant to the Standard Specifications for Road and Bridge Construction applicable to this contract.
In connection with the performance of work under this contract, the contractor agrees to comply with all applicable state and federal statutes relating to non-discrimination in employment. No otherwise qualified person shall be excluded from employment or otherwise be subject to discrimination in employment in any manner on the basis of age, race, religion, color, gender, national origin or ancestry, disability, arrest or conviction record (in keeping with s.111.32), sexual orientation, marital status, membership in the military reserve, honesty testing, genetic testing, and outside use of lawful products. This provision shall include, but not be limited to the following: employment, upgrading, demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation, and selection for training, including apprenticeship. The contractor further agrees to ensure equal opportunity in employment to all applicants and employees and to take affirmative action to attain a representative workforce.
The contractor agrees to post notices and posters setting forth the provisions of the nondiscrimination clause, in a conspicuous and easily accessible place, available for employees and applicants for employment.
If a state public official (section 19.42, Stats.) or an organization in which a state public official holds at least a 10% interest is a party to this agreement, this contract is voidable by the state unless appropriate disclosure is made to the State of Wisconsin Ethics Board.
Effective with August 2015 Letting Bid Preparation
BID PREPARATION
Preparing the Proposal Schedule of Items A. General
(1) Obtain bidding proposals as specified in section 102 of the standard specifications prior to 11:45 AM of the last business day preceding the letting. Submit bidding proposals using one of the following methods:
1. Electronic bid on the internet.
2. Electronic bid on a printout with accompanying diskette or CD ROM.
3. Paper bid under a waiver of the electronic submittal requirements.
(2) Bids submitted on a printout with accompanying diskette or CD ROM or paper bids submitted under a waiver of the electronic submittal requirements govern over bids submitted on the internet.
(3) The department will provide bidding information through the department’s web site at:
https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx
The contractor is responsible for reviewing this web site for general notices as well as information regarding proposals in each letting. The department will also post special notices of all addenda to each proposal through this web site no later than 4:00 PM local time on the Thursday before the letting. Check the department’s web site after 5:00 PM local time on the Thursday before the letting to ensure all addenda have been accounted for before preparing the bid. When bidding using methods 1 and 2 above, check the Bid ExpressΤΜ on-line bidding exchange at http://www.bidx.com/ after 5:00 PM local time on the Thursday before the letting to ensure that the latest schedule of items Expedite file (*.ebs or *.00x) is used to submit the final bid.
(4) Interested parties can subscribe to the Bid ExpressΤΜ on-line bidding exchange by following the instructions provided at the www.bidx.com web site or by contacting:
Info Tech Inc.
5700 SW 34th Street, Suite 1235 Gainesville, FL 32608-5371 email: mailto:customer.support@bidx.com
(5) The department will address equipment and process failures, if the bidder can demonstrate that those failures were beyond their control.
(6) Contractors are responsible for checking on the issuance of addenda and for obtaining the addenda. Notice of issuance of addenda is posted on the department’s web site at:
https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx or by calling the department at (608) 266-1631. Addenda can ONLY be obtained from the department’s web site listed above or by picking up the addenda at the Bureau of Highway Construction, 4th floor, 4822 Madison Yards Way, Madison, WI, during regular business hours.
(7) Addenda posted after 5:00 PM on the Thursday before the letting will be emailed to the eligible bidders for that proposal. All eligible bidders shall acknowledge receipt of the addenda whether they are bidding on the proposal or not. Not acknowledging receipt may jeopardize the awarding of the project.
https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx http://www.bidx.com/ http://www.bidx.com/ mailto:customer.support@bidx.com
B. Submitting Electronic Bids B.1 On the Internet
(1) Do the following before submitting the bid:
4. Have a properly executed annual bid bond on file with the department.
5. Have a digital ID on file with and enabled by Info Tech Inc. Using this digital ID will constitute the bidder's signature for proper execution of the bidding proposal.
(2) In lieu of preparing, delivering, and submitting the proposal as specified in 102.6 and 102.9 of the standard specifications, submit the proposal on the internet as follows:
1. Download the latest schedule of items reflecting all addenda from the Bid ExpressΤΜ web site.
2. Use ExpediteΤΜ software to enter a unit price for every item in the schedule of items.
3. Submit the bid according to the requirements of ExpediteΤΜ software and the Bid ExpressΤΜ web site. Do not submit a bid on a printout with accompanying diskette or CD ROM or a paper bid. If the bidder does submit a bid on a printout with accompanying diskette or a paper bid in addition to the internet submittal, the department will disregard the internet bid
4. Submit the bid before the hour and date the Notice to Contractors designates
5. Do not sign, notarize, and return the bidding proposal described in 102.2 of the standard specifications.
(3) The department will not consider the bid accepted until the hour and date the Notice to Contractors designates.
B.2 On a Printout with Accompanying Diskette or CD ROM
(1) Download the latest schedule of items from the Wisconsin pages of the Bid Express web site reflecting the latest addenda posted on the department’s web site at:
https://wisconsindot.gov/Pages/doing-bus/contractors/hcci/bid-let.aspx
Use ExpediteΤΜ software to prepare and print the schedule of items. Provide a valid amount for all price fields. Follow instructions and review the help screens provided on the Bid ExpressΤΜ web site to assure that the schedule of items is prepared properly.
(2) Staple an 8 1/2 by 11 inch printout of the Expedite generated schedule of items to the other proposal documents submitted to the department as a part of the bidder's sealed bid. As a separate submittal, not in the sealed bid envelop but due at the same time and place as the sealed bid, also provide the ExpediteΤΜ generated schedule of items on a 3 1/2 inch computer diskette or CD ROM. Label each diskette or CD ROM with the bidder's name, the 4 character department-assigned bidder identification code from the top of the bidding proposal, and a list of the proposal numbers included on that diskette or CD ROM as indicated in the following example:
Bidder Name
BN00
Proposals: 1, 12, 14, & 22
(3) If bidding on more than one proposal in the letting, the bidder may include all proposals for that letting on one diskette or CD ROM. Include only submitted proposals with no incomplete or other files on the diskette or CD ROM.
(4) The bidder-submitted printout of the Expedite generated schedule of items is the governing contract document and must conform to the requirements of section 102 of the standard specifications. If a printout needs to be altered, cross out the printed information with ink or typewriter and enter the new information and initial it in ink. If there is a discrepancy between the printout and the diskette or CD ROM, the department will analyze the bid using the printout information.
(5) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:
1. The check code printed on the bottom of the printout of the ExpediteΤΜ generated schedule of items is not the same on each page.
2. The check code printed on the printout of the ExpediteΤΜ generated schedule of items is not the same as the check code for that proposal provided on the diskette or CD ROM.
3. The diskette or CD ROM is not submitted at the time and place the department designates.
B Waiver of Electronic Submittal
(1) The bidder may request a waiver of the electronic submittal requirements. Submit a written request for a waiver in lieu of bids submitted on the internet or on a printout with accompanying diskette or CD ROM. Use the waiver that was included with the paper bid document sent to the bidder or type up a waiver on the bidder’s letterhead. The department will waive the electronic submittal requirements for a bidding entity (individual, partnership, joint venture, corporation, or limited liability company) for up to 4 individual proposals in a calendar year. The department may allow additional waivers for equipment malfunctions.
(2) Submit a schedule of items on paper conforming to section 102 of the standard specifications.
The department charges the bidder a $75 administrative fee per proposal, payable at the time and place the department designates for receiving bids, to cover the costs of data entry. The department will accept a check or money order payable to: "Wisconsin, Dept. of Transportation."
(3) In addition to the reasons specified in section 102 of the standard specifications, proposals are irregular and the department may reject them for one or more of the following:
1. The bidder fails to provide the written request for waiver of the electronic submittal requirements.
2. The bidder fails to pay the $75 administrative fee before the time the department designates for the opening of bids unless the bidder requests on the waiver that they be billed for the $75.
3. The bidder exceeds 4 waivers of electronic submittal requirements within a calendar year.
(4) In addition to the reasons specified in section 102 of the standard specifications, the department may refuse to issue bidding proposals for future contracts to a bidding entity that owes the department administrative fees for a waiver of electronic submittal requirements.
PROPOSAL BID BOND Wisconsin Department of Transportation
DT1303 1/2006
Proposal Number Project Number Letting Date
Name of Principal
Name of Surety State in Which Surety is Organized
We, the above-named Principal and the above-named Surety, are held and firmly bound unto the State of Wisconsin in the sum equal to the Proposal Guaranty for the total bid submitted for the payment to be made; we jointly and severally bind ourselves, our heirs, executors, administrators, successors and assigns. The condition of this obligation is that the Principal has submitted a bid proposal to the State of Wisconsin acting through the Department of Transportation for the improvement designated by the Proposal Number and Letting Date indicated above.
If the Principal is awarded the contract and, within the time and manner required by law after the prescribed forms are presented for signature, enters into a written contract in accordance with the bid, and files the bond with the Department of Transportation to guarantee faithful performance and payment for labor and materials, as required by law, or if the Department of Transportation shall reject all bids for the work described, then this obligation shall be null and void; otherwise, it shall be and remain in full force and effect.
In the event of failure of the Principal to enter into the contract or give the specified bond, the Principal shall pay to the Department of Transportation within 10 business days of demand a total equal to the Proposal Guaranty as liquidated damages; the liability of the Surety continues for the full amount of the obligation as stated until the obligation is paid in full.
The Surety, for value received, agrees that the obligations of it and its bond shall not be impaired or affected by any extension of time within which the Department of Transportation may accept the bid; and the Surety does waive notice of any such extension.
IN WITNESS, the Principal and Surety have agreed and have signed by their proper officers and have caused their corporate seals to be affixed this date: (DATE MUST BE ENTERED)
PRINCIPAL
(Company Name) (Affix Corporate Seal)
(Signature and Title)
(Company Name)
(Signature and Title)
(Company Name)
(Signature and Title)
(Company Name)
(Signature and Title)
NOTARY FOR PRINCIPAL
(Date)
State of Wisconsin ) ) ss.
County )
On the above date, this instrument was acknowledged before me by the named person(s).
(Signature, Notary Public, State of Wisconsin)
(Print or Type Name, Notary Public, State of Wisconsin)
(Date Commission Expires)
Notary Seal
(Name of Surety) (Affix Seal)
(Signature of Attorney-in-Fact)
NOTARY FOR SURETY
(Date)
State of Wisconsin ) ) ss.
County )
On the above date, this instrument was acknowledged before me by the named person(s).
(Signature, Notary Public, State of Wisconsin)
(Print or Type Name, Notary Public, State of Wisconsin)
(Date Commission Expires)
Notary Seal
IMPORTANT: A certified copy of Power of Attorney of the signatory agent must be attached to the bid bond.
CERTIFICATE OF ANNUAL BID BOND Wisconsin Department of Transportation
DT1305 8/2003
Time Period Valid (From/To)
Name of Surety
Name of Contractor
Certificate Holder Wisconsin Department of Transportation
This is to certify that an annual bid bond issued by the above-named Surety is currently on file with the Wisconsin Department of Transportation.
This certificate is issued as a matter of information and conveys no rights upon the certificate holder and does not amend, extend or alter the coverage of the annual bid bond.
Cancellation: Should the above policy be cancelled before the expiration date, the issuing surety will give thirty (30) days written notice to the certificate holder indicated above.
(Signature of Authorized Contractor Representative) (Date)
Effective with March 2010 Letting
LIST OF SUBCONTRACTORS
Section 66.0901(7), Wisconsin Statutes, provides that as a part of the proposal, the bidder also shall submit a list of the subcontractors the bidder proposes to contract with and the class of work to be performed by each. In order to qualify for inclusion in the bidder's list a subcontractor shall first submit a bid in writing, to the general contractor at least 48 hours prior to the time of the bid closing. The list may not be added to or altered without the written consent of the municipality. A proposal of a bidder is not invalid if any subcontractor and the class of work to be performed by the subcontractor has been omitted from a proposal; the omission shall be considered inadvertent or the bidder will perform the work personally.
No subcontract, whether listed herein or later proposed, may be entered into without the written consent of the Engineer as provided in Subsection 108.1 of the Standard Specifications.
Name of Subcontractor Class of Work Estimated Value
Effective with December 2000 Letting Debarment Certification
CERTIFICATION REGARDING DEBARMENT, SUSPENSION, AND OTHER
RESPONSIBILITY MATTERS - PRIMARY COVERED TRANSACTIONS
Instructions for Certification
1. By signing and submitting this proposal, the prospective contractor is providing the certification set out below.
2. The inability of a person to provide the certification required below will not necessarily result in denial of participation in this covered transaction. The prospective contractor shall submit an explanation of why it cannot provide the certification set out below. The certification or explanation will be considered in connection with the department or agency's determination whether to enter into this transaction. However, failure of the prospective contractor to furnish a certification or an explanation shall disqualify such person from participation in this transaction.
3. The certification in this clause is a material representation of fact upon which reliance was placed when the department determined to enter into this transaction. If it is later determined that the contractor knowingly rendered an erroneous certification in addition to other remedies available to the Federal Government the department may terminate this transaction for cause or default.
4. The prospective contractor shall provide immediate written notice to the department to whom this proposal is submitted if at any time the prospective contractor learns that its certification was erroneous when submitted or has become erroneous by reason of changed circumstances.
5. The terms "covered transaction," "debarred," "suspended," "ineligible," "lower tier covered transaction," "participant," "person," "primary covered transaction," "principal," "proposal," and "voluntarily excluded," as used in this clause, have the meanings set out in the Definitions and Coverage sections of the rules implementing Executive Order 12549. You may contact the department to which this proposal is being submitted for assistance in obtaining a copy of those regulations.
6. The prospective contractor agrees by submitting this proposal that, should this contract be entered into, it shall not knowingly enter into any lower tier covered transaction with a person who is debarred, suspended, declared ineligible, or voluntarily excluded from participation in this covered transaction, unless authorized by the department entering into this transaction.
7. The prospective contractor further agrees by submitting this proposal that it will include the clause titled "Certification Regarding Debarment, Suspension, Ineligibility and Voluntary Exclusion-Lower Tier Covered Transaction," which is included as an addendum to PR- 1273 - "Required Contract Provisions Federal Aid Construction Contracts," without modification, in all lower tier covered transactions and in all solicitations for lower tier covered transactions.
8. The contractor may rely upon a certification of a prospective subcontractor/materials supplier that it is not debarred, suspended, ineligible, or voluntarily excluded from the covered transaction, unless it knows that the certification is erroneous. A contractor may decide the method and frequency by which it determines the eligibility of its principals. Each contractor may, but is not required to, check the Disapproval List (telephone # 608/266/1631).
Effective with December 2000 Letting Debarment Certification
9. Nothing contained in the foregoing shall be construed to require establishment of a system of records in order to render in good faith the certification required by this clause. The knowledge and information of a contractor is not required to exceed that which is normally possessed by a prudent person in the ordinary course of business dealings.
10. Except for transactions authorized under paragraph 6 of these instructions, if a contractor in a covered transaction knowingly enters into a lower tier covered transaction with a person who is suspended, debarred, ineligible or voluntarily excluded from participation in this transaction, in addition to other remedies available to the Federal Government, the department may terminate this transaction for cause or default.
Certification Regarding Debarment, Suspension, and Other Responsibility Matters - Primary Covered Transactions
1. The prospective contractor certifies to the best of its knowledge and belief, that it and its principals:
(a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, or voluntarily excluded from covered transactions by any Federal department or agency;
(b) Have not within a three-year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission of fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State or local) transaction or contract under a public transaction; violation of Federal or State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements or receiving stolen property;
(c) Are not presently indicted for or otherwise criminally or civilly charged by a governmental entity (Federal, State or local) with commission of any of the offense enumerated in paragraph (1)(b) of this certification; and
(d) Have not within a three-year period preceding this proposal had one or more public transactions (Federal, State or local) terminated for cause or default.
2. Where the prospective contractor is unable to certify to any of the statements in this certification, such prospective contractor shall attach an explanation to this proposal.
1670-04-82 1 of 14
Special Provisions Table of Contents
Article Description Page #
1. General
2. Scope of Work
3. Prosecution and Progress
4. Traffic
5. Holiday and Special Event Work Restrictions
6. Utilities
7. Railroad Insurance and Coordination - Wisconsin and Southern Railroad Company
8. Polymer Overlay, Item 509.5100.S
9. Traffic Control, Item 643.5000
10. Digital Speed Reduction System (DSRS), Item 643.0370.S
11. Basic Traffic Queue Warning System, Item 643.1205.S
1670-04-82 2 of 14
STSP’S Revised July 1, 2026
SPECIAL PROVISIONS
1. General.
Perform the work under this construction contract for the following project:
1670-04-82 Baraboo – Sauk City Bridges-Terrytown Rd to Lehman Rd
USH 12
Sauk County
Perform as the plans show and execute the work as specified in the State of Wisconsin, Department of Transportation, Standard Specifications for Highway and Structure Construction, 2025 Edition, as published by the department, and these special provisions.
100-005 (20260101)
2. Scope of Work.
The work under this contract shall consist of a polymer overlay on bridge decks, minor concrete structure repair, pavement marking, and all incidental items necessary to complete the work as shown on the plans and included in the proposal and contract.
104-005 (20090901)
3. Prosecution and Progress.
Begin work within 10 calendar days after the engineer issues a written notice to do so.
Provide the time frame for construction of the project within the 2027 construction season to the engineer in writing within a month after executing the contract but at least 14 calendar days before the preconstruction conference. Assure that the time frame is consistent with the contract completion time.
Upon approval, the engineer will issue the notice to proceed within ten calendar days before the beginning of the approved time frame.
To revise the time frame, submit a written request to the engineer at least two weeks before the beginning of the intended time frame. The engineer will approve or deny that request based on the conditions cited in the request and its effect on the department’s scheduled resources.
4. Traffic.
Single lane closures are permitted from 6:00 am Monday through 12:00pm Friday. No lane closures or ramp closures are permitted Saturday through Sunday.
Submit any traffic control change request to the engineer at least 72 hours prior to an actual traffic control change. A request does not constitute approval.
Maintain emergency vehicle access at all times.
Wisconsin Lane Closure System Advance Notification Provide the following advance notification to the engineer for incorporation into the Wisconsin Lane Closure System (LCS).
TABLE 108-1 CLOSURE TYPE AND REQUIRED MINIMUM ADVANCE NOTIFICATION
Closure type with height, weight, or width restrictions (available width, all lanes in one direction < 16 feet) MINIMUM NOTIFICATION
Lane and shoulder closures 7 calendar days
Full roadway closures 7 calendar days
1670-04-82 3 of 14
Ramp closures 7 calendar days
Detours 7 calendar days
Closure type without height, weight, or width restrictions (available width, all lanes in one direction > 16 feet) MINIMUM NOTIFICATION
Shoulder Closures 3 calendar days
Lane closures 3 business days
Ramp closures 3 business days
Modifying all closure types 3 business days
Discuss LCS completion dates and provide changes in the schedule to the engineer at weekly project meetings in order to manage closures nearing their completion date.
Temporary Regulatory Speed Limit Reduction Reduce the speed limit to 55 mph on USH 12 during single lane closures when workers are present.
Speed limit to remain 65 mph when lane closures are not in use.
Contact the Region Traffic Section at least 14 calendar days before installing the temporary speed zone.
After installation of the temporary speed zone is complete, notify the Region Traffic Section with field locations of temporary speed zones.
5. Holiday and Special Event Work Restrictions.
Do not perform work on, nor haul materials of any kind along or across any portion of the highway carrying USH 12 traffic, and entirely clear the traveled way and shoulders of such portions of the highway of equipment, barricades, signs, lights, and any other material that might impede the free flow of traffic during the following holiday and special event periods:
- From noon Friday, May 28, 2027 to 6:00 AM Tuesday, June 1 2027 for Memorial Day;
- From noon Friday, July 2, 2027 to 6:00 AM Tuesday, July 6 2027 for Independence Day;
- From noon Friday, September 3, 2027 to 6:00 AM Tuesday, September 7, 2027 for Labor Day.
stp-107-005 (20210113)
6. Utilities.
This contract comes under the provision of Administrative Rule Trans 220.
The utility work plan includes additional detailed information regarding the location of known discontinued, relocated, or removed utility facilities. These can be requested from the department during the bid preparation process, or from the project engineer after the contract has been awarded and executed.
stp-107-065 (20240703)
The following utility owners have facilities within the project area; however, no adjustments are anticipated:
Alliant Energy – Electricity Alliant Energy – Gas/Petroleum ATC Management, Inc. – Electricity/Transmission Brightspeed of Western Wisconsin, LLC – Communication Line Cogent Fiber, LLC – Communication Line MCI – Communication Line
1670-04-82 4 of 14
7. Railroad Insurance and Coordination - Wisconsin and Southern Railroad Company A. Description
Comply with standard spec 107.17 for all work affecting Wisconsin and Southern Railroad Company property and any existing tracks.
A.1 Railroad Insurance Requirements
In addition to standard spec 107.26, provide railroad protective liability insurance coverage as specified in standard spec 107.17.3 Insurance is filed in the name of Watco Companies, L.L.C., and its affiliates, subsidiaries, and assigns.
Notify evidence of the required coverage, and duration to Justin Mahr, Senior Manger Real Estate - Contracts; 315 W. 3rd Street, Pittsburg, KS 66762; Telephone (402) 651-8238; E-mail:
justin.mahr@watco.com
Also send a copy to the following: Scott Willinger, SW LaCrosse Region Railroad Coordinator; 3550 Mormon Coulee Road, La Crosse, WI 54601; Telephone (608) 799-8697; E-mail:
gene.willinger@dot.wi.gov
Include the following information on the insurance document:
- Project ID: 1670-04-82
- Project Location: Baraboo, Wisconsin
- Route Name: USH 12, Sauk County
- Crossing ID: 969 264A
- Railroad Subdivision: Reedsburg Subdivision
- Railroad Milepost: MP 177.32
- Work Performed on or within 50’ of RR ROW: Polymer overlay to bridge deck
A.2 Train Operation
Approximately 2 through freight trains operate daily at up to 25 mph. No switching movements are noted by the railroad on FRA crossing inventory dated 2/5/2024
A.3 Names and Addresses of Railroad Representatives for Consultation and Coordination
Construction Contact Chris Jacobson, Superintendent of Engineering, Wisconsin and Southern Railroad Co.; 1890 East Johnson Street, Madison, WI 53704; Telephone (608) 750-6427; E-mail cjacobson@watco.com for consultation on railroad requirements during construction.
Amend standard spec 108.4 to include the railroad in the distribution of the initial bar chart, and monthly schedule updates. The bar chart shall specifically show work involving coordination with the railroad.
Flagging Contact Send flagging request to flaggingapplication@watco.com Reference the Crossing ID, Wisconsin Milepost and Subdivision found in A.1. Contractor must officially request a railroad flagger a minimum of 15 day prior to scheduled work. If the contractor fails to do so and is required to pay an Expedited Fee, the project will not reimburse the contractor for said fee.
Cable Locate Contact In addition to contacting Diggers Hotline, contact the Construction Contact at least five working days before the locate is needed. Reference the Crossing ID, Wisconsin Milepost and Subdivision found in A.1.
WSOR will only locate railroad owned facilities located in the railroad right-of-way. The railroad does not locate any other utilities.
cc: WisDOT Region Railroad Coordinator referenced in A.1 on all written correspondence with the railroads.
A.4 Work by Railroad
The railroad will perform the work described in this section, except for work described in other special provisions, and will be accomplished without cost to the contractor. None mailto:justin.mahr@watco.com mailto:cjacobson@watco.com mailto:flaggingapplication@watco.com
1670-04-82 5 of 14
A.5 Temporary Grade Crossing If a temporary grade crossing is desired, submit a written request to the railroad representative named in A.3 at least 40 days prior to the time needed. Approval is subject to the discretion of the railroad. The department has made no arrangements for a temporary grade crossing.
stp-107-026 (20260101)
8. Polymer Overlay, Item 509.5100.S.
A Description This special provision describes providing two layers of a two-component polymer overlay system to the bridge decks the plans show.
B Materials B.1 General Furnish materials specifically designed for use over concrete bridge decks. Furnish polymer liquid binders from the department’s approved product list.
B.2 Polymer Resin Furnish a polymer resin base and hardener composed of two-component, 100 percent solids, 100 percent reactive, thermosetting compound with the following properties:
Property Requirements Test Method
Gel Time[1] 15 - 45 minutes @
73° to 75° F
ASTM C881
Viscosity[1] 7 - 70 poises ASTM D2393, Brookfield RVT, Spindle No. 3, 20 rpm
Shore D Hardness[2] 60-75 ASTM D2240
Absorption[2] 1% maximum at 24 hr ASTM D570
Tensile Elongation[2] 30% - 70% @ 7 days ASTM D638
Tensile Strength[2] 2000 to 5000 psi @ 7 days ASTM D638
Chloride Permeability[2] <100 coulombs @ 28 days AASHTO T277 [1] Uncured, mixed polymer binder [2] Cured, mixed polymer binder
Ensure that the polymer resin when mixed with aggregate has the following properties:
Property Requirement[1] Test Method
Minimum Compressive Strength
1,000 psi @ 8 hrs 5,000 psi @ 24 hrs
ASTM C579 Method B, Modified[2]
Thermal Compatibility No Delaminations ASTM C884
Minimum Pull-off Strength 250 psi @ 24 hrs ASTM C1583
[1] Based on samples cured or aged and tested at 75°F [2] Plastic inserts that will provide 2-inch by 2-inch cubes shall be placed in the oversized brass molds.
B.3 Aggregates Furnish natural or synthetic aggregate that is non-polishing; clean; free of surface moisture; fractured or angular in shape; free from silt, clay, asphalt, or other organic materials; and conform to the following:
1670-04-82 6 of 14
Aggregate Properties
Property Requirement Test Method
Moisture Content[1] 1/2 of the measured aggregate absorption, % ASTM C566
Hardness >6.5 Mohs Scale
Fractured Faces 100% with at least 1 fractured face & 80% with at least 2 fractured faces of material retained on No.16 ASTM D5821
Absorption <1% ASTM C128
[1] Sampled and tested by the department before placement.
Gradation
Sieve Size % Passing by Weight
No. 4 100
No. 8 30 – 75
No. 16 0 – 5
No. 30 0 – 1
B.4 Approval of Bridge Deck Polymer Overlay System A minimum of 20 working days before application, submit product data sheets and specifications from the manufacturer, and a certified report of test or analysis from an independent laboratory to the engineer for approval. The department will sample and test the aggregates for gradation and moisture content before placement. If requested, supply the department with samples of the polymer for the purpose of acceptance testing.
B.4.1 Product Data Sheets and Specifications Product data sheets and specifications from the manufacture consists of literature from the manufacturer showing general instructions, application recommendations/methods, product properties, general instructions, or any other applicable information.
B.4.2 Certified Report of Test or Analysis Conform to the following:
Polymer Binder: Submit a certified report of test or analysis from an independent laboratory dated less than 3 years before the date of the project letting showing the polymer binder meets the requirements of section B.2.
Aggregates: Submit a certified report of test or analysis from an independent laboratory dated less than 6 months before the date of the project letting showing the aggregates meet the requirements of section B.3.
C Construction C.1 General Ensure that the overlay system is 1/4 inch thick or thicker.
Conform to the following:
Field Review: Conduct a field review of the existing deck to identify any possible surface preparation and material compatibility issues.
Pre-Installation Meeting: Conduct a pre-installation meeting with the manufacturer's representative and the engineer before construction. Discuss the field review findings, verification testing of the surface preparation and establish procedures for maintaining optimum working conditions and coordination of work. Furnish the engineer a copy of the recommended procedures and apply the overlay system according to the manufacturer’s instructions. Supply for the engineer’s use for the duration of the project, a Concrete Surface Profile (CSP) chip set of 10 from the International Concrete Repair Institute (ICRI).
Manufacturer’s Representative: An experienced manufacturer's representative familiar with the overlay system installation procedures shall be present at all times during surface preparation and overlay placement to provide quality assurance that the work is being performed properly. This requirement may be reduced at the engineer’s discretion.
1670-04-82 7 of 14
Material Storage: Store and handle materials according to the manufacturer’s recommendations. Store resin materials in their original containers in a dry area. Store all aggregates in a dry environment and protect aggregates from contaminants on the job site.
C.2 Deck Preparation C.2.1 Deck Repair Remove all asphaltic patches and unsound or disintegrated areas of the concrete decks as the plans show, or as the engineer directs. Work performed to remove and repair the concrete deck will be paid for under other items.
Use deck patching products that are compatible with the overlay system. Patching materials with magnesium phosphate shall not be used. Place patches after surface is prepared via shot blasting and cleaning as described in Section C.2.2 of this specification. Portland cement concrete patches shall be used for joint repairs and full depth deck repairs with a plan area larger than 4 sf, unless approved otherwise by the Structures Design Section. If rapid-set concrete is used, place patches per the manufacturer’s recommendation. If Portland cement concrete is used, place patches per standard spec 509.3.9.1.
Deck patching shall be filled and properly finished prior to overlay placement. Do not place overlay less than 1 hour, or per the manufacturer’s recommendation, after placing rapid-set concrete patches in the repair areas. Do not place overlay less than 28 days after placing Portland cement concrete patches in the repair areas.
C.2.2 Surface Preparation Determine an acceptable shotblasting machine operation (size of shot, flow of shot, forward speed, and/or number of passes) that provides a surface profile meeting CSP 5 (medium-heavy shotblast) according to the ICRI Technical Guideline No. 310.2. If the engineer requires additional verification of the surface preparation, test the tensile bond strength according to ASTM C1593. The surface preparation will be considered acceptable if the tensile bond strength is greater than or equal to 250 psi or the failure area at a depth of 1/4 inches or more is greater than 50 percent of the test area. Continue adjustment of the shotblasting machine and necessary testing until the surface is acceptable to the engineer or a passing test result is obtained.
Prepare the entire deck using the final accepted adjustments to the shotblasting machine as determined above. Thoroughly blast clean with hand-held equipment any areas inaccessible by the shotblasting equipment. Do not perform surface preparation more than 24 hours before the application of the overlay system.
Protect drains, expansion joints, access hatches, or other appurtenances on the deck from damage by the shot and sand blasting operations and from materials adhering and entering. Tape or form all construction joints to provide a clean straight edge.
Before shot blasting, remove pavement markings within the treatment area using an approved mechanical or blasting method.
Prepare the vertical concrete surfaces adjacent to the deck a minimum of 2” above the overlay according to SSPC-SP 13 (free of contaminants, dust, and loose concrete) by sand blasting, using wire wheels, or other approved method.
Just before overlay placement, clean all dust, debris, and concrete fines from the prepared surfaces including the vertical surfaces with compressed air. When using compressed air, the air stream must be free of oil. Any grease, oil, or other foreign matter that rests on or has absorbed into the concrete shall be removed completely. If prepared surfaces (including the first layer of the polymer overlay) are exposed to rain or dew, lightly sandblast (brush/breeze blast) the exposed surfaces.
The engineer may consider alternate surface preparation methods per the overlay system manufacture’s recommendations. The engineer will approve the final surface profile and deck cleanliness before the contractor placing the polymer overlay.
C.2.3 Transitional Area If the plans show, create a transitional area approaching transverse expansion joints and ends of the deck using an approved mechanical or blasting method. Remove 1/4 inch to 5/16 inch of concrete adjacent to the joint or end of deck and taper a distance of 3 feet.
1670-04-82 8 of 14
If the plans show, create a transitional area on the approach pavement. Prep and place the first lift 3 feet beyond the end of the deck the same width as the deck. Prep and place the second lift 6 feet beyond the end of the deck the same width as the deck.
C.3 Overlay Application Perform the handling and mixing of the polymer resin and hardening agent in a safe manner to achieve the desired results according to the manufacturer’s instructions. Do not apply the overlay system if any of the following exists:
1. Ambient air temperature is below 50 F or above 100 F.
2. Deck temperature is below 50 F.
3. Moisture content in the deck exceeds 4.5 percent when measured by an electronic moisture meter or shows visible moisture after 2 hours when measured in accordance with ASTM D4263.
4. Rain is forecasted during the minimum curing periods listed under C.5.
5. Materials component temperatures below 65 F or above 99 F.
6. Concrete deck age is less than 28 days.
7. The deck temperature exceeds 100 F.
8. If the gel time is 10 minutes or less at the predicted high air temperature for the day.
After the deck has been shotblasted or during the overlay curing period, only necessary surface preparation and overlay application equipment will be allowed on the deck. Provide appropriate protective measures to prevent contamination from equipment allowed on the deck during preparation and application operations. Begin overlay placement as soon as possible after surface preparation operations.
The polymer overlay shall consist of a two-course application of polymer and aggregate. Each of the two courses shall consist of a layer of polymer covered with a layer of aggregate in sufficient quantity to completely cover the polymer. Apply the polymer and aggregate according to the manufacturer’s requirements. Apply the overlay using equipment designed for this purpose. The application machine shall feature positive displacement volumetric metering and be capable of storing and mixing the polymer resins at the proper mix ratio. Disperse the aggregate using a method that provides a uniform, consistent coverage of aggregate and minimizes aggregate rolling or bouncing into final position. First course applications that do not receive enough aggregate before the polymer gels shall be removed and replaced. A second course applied with insufficient aggregate may be left in place, but will require additional applications before opening to traffic.
After completion of each course, cure the overlay according to the manufacturer’s instructions. Follow the minimum cure times listed under C.5 or as prescribed by the manufacturer. Remove the excess aggregate from the surface treatment by sweeping, blowing, or vacuuming without tearing or damaging the surface; the material may be re-used if approved by the engineer and manufacturer. Apply all courses of the overlay system before opening the area to traffic. Do not allow equipment or traffic on the treated area until directed by the engineer.
After the first layer of coating has cured to the point where the aggregate cannot be pulled out, apply the second layer. Before applying the second layer, broom and blow off the first layer with compressed air to remove all loose excess aggregate.
Before opening to traffic, clean expansion joints and joint seals of all debris and polymer. A minimum of 3 days following opening to traffic, remove loosened aggregates from the deck, expansion joints, and approach pavement.
C.4 Application Rates Apply the polymer overlay in two separate courses in accordance with the manufacturer’s instructions, but not less than the following rate of application.
Course Minimum Polymer Rate[1]
(GAL/100 SF)
Aggregate[2]
(LBS/SY)
1 2.5 10+
2 5.0 14+ [1] The minimum total applications rate is 7.5 GAL/100 SF.
[2] Application of aggregate shall be of sufficient quantity to completely cover the polymer.
1670-04-82 9 of 14
C.5 Minimum Curing Periods
As a minimum, cure the coating as follows:
Average temperature of deck, polymer and aggregate components in degrees F
Course 50-54 55-59 60-64 65-69 70-74 75-79 80-84 85-99
1 6 hrs. 5 hrs. 4 hrs. 3 hrs. 2.5 hrs 2 hrs 1.5 hrs. 1 hr.
2 8 hrs. 6.5 hrs. 6.5 hrs. 5 hrs. 4 hrs. 3 hrs. 3 hrs. 3 hrs.
If faster cure times are desired and achievable, submit to the engineer a certified test report from an independent laboratory showing the material is able to reach a compressive strength of 1000 psi as tested per ASTM C 579 Method B within the temperature ranges and cure times for which the product is proposed to be placed. Establish ambient air, material, and substrate temperatures from the manufacturer for field applications. Field applications will not be allowed below the documented temperatures.
C.6 Repair of Polymer Overlay Repair all areas of unbonded, uncured, or damaged polymer overlay for no additional compensation.
Submit repair procedures from the manufacturer to the engineer for approval. Absent a manufacturer’s repair procedures and with the approval of the engineer, complete repairs according to the following: Saw cut the limits of the area to the top of the concrete; remove the overlay by scarifying, grinding, or other approved methods; shot blast or sand blast and air blast the concrete before placement of polymer overlay; and place the polymer overlay according to section C.3.
D Measurement The department will measure Polymer Overlay by the square yard, acceptably completed.
E Payment The department will pay for measured quantities at the contract unit price under the following bid item:
ITEM NUMBER DESCRIPTION UNIT
509.5100.S Polymer Overlay SY
Payment is full compensation for preparing the surface; for tensile bond testing; for creating the transitional area; for providing the overlay; for cleanup; and for sweeping/vacuuming and disposing of excess materials.
The department will pay separately for deck repairs.
stp-509-030 (20200629)
9. Traffic Control, Item 643.5000 Add to standard spec 643.3.9:
Furnish and maintain Truck or Trailer Mounted Attenuators (TMA) conforming to NCHRP Report 350 test level 3 or to MASH crashworthiness criteria in order to protect workers in a work zone. Submit written certification from the manufacturer that the host vehicle/attenuator configuration provided conforms to crashworthiness criteria. Include the federal-aid reimbursement eligibility letter with that submittal.
Provide host vehicles and mount the attenuators conforming to the attenuator…