20260512_21-43131_Fire_Station_Cost_Estimate.pdf

PDF 196 KB Posted

Attached to
Fire Station No. 1 Wind Retrofit Project
Solicitation number
26-009
Issued by
Santa Rosa County, Florida

About this file

This is a cost estimate document for the Fire Station No. 1 Wind Retrofit Project prepared for the City of Dania Beach, Florida. The project encompasses structural retrofits and modifications necessary to bring Fire-Rescue Station No. 1, located at 116 West Dania Beach Boulevard, into compliance with current hurricane-resistant standards. The cost estimate serves as a financial planning tool for the wind mitigation upgrades project. No specific response dates, bidder conferences, site visits, or contract term information is detailed within this cost estimate document itself, as it functions as a supporting exhibit rather than the primary solicitation document.

The cost estimate provides the financial framework for the proposed wind retrofit improvements but does not specify pricing terms, contract duration, funding sources, or award details within its scope. This document would be utilized alongside the primary solicitation materials to inform potential bidders and contractors of the anticipated project costs associated with the structural retrofits and hurricane-resistant modifications at the fire station facility.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DATE

5/12/2026

PROJECT TITLE CGA PROJECT NO.

21-4313.1

LOCATION

OWNER

ESTIMATED BY CHECKED BY APPROVED BY

I. GENERAL

1.01 Clearing & Grubbing 1 LS $4,200.00 $4,200.00

1.02 Maintnenance of Traffic, Mobilization/Demobilization 1 LS $40,337.73 $40,337.73

1.03 Stormwater Pollution Prevention 1 LS $4,033.77 $4,033.77

1.04 Testing and Survey 1 LS $4,200.00 $4,200.00

1.05 Permitting Allowance 1 LS $40,337.73 $40,337.73

GENERAL SUBTOTAL $93,109.24

II. INFRASTRUCTURE

2.01 Concrete sidewalk 11 SY $233.10 $2,564.10

2.02 Tree relocation 1 EA $6,300.00 $6,300.00

2.03 Thermoplastic parking striping 71 LF $18.90 $1,341.90

2.04 Asphalt restoration 98 SY $114.66 $11,236.68

2.05 Sod Restoration 77 SY $31.50 $2,425.50

INFRASTRUCTURE SUBTOTAL $23,868.18

III. STRUCTURAL

3.01 Remove Existing Roofing System 9,670 SF $4.00 $38,680.00

3.02 Remove existing roof drains 5 EA $350.00 $1,750.00

3.03 Remove existing overflow scuppers 10 EA $300.00 $3,000.00

3.04 Remove existing hatch and close opening 1 LS $2,250.00 $2,250.00

3.05 Generator concrete slab with thickened edge 246 SF $40.00 $9,840.00

3.06 Reinforcing Steel for Generator Slab 1 LS $5,200.00 $5,200.00

3.07 Reinforced CMU Wall Infill 130 SF $62.00 $8,060.00

3.08 4-ply torch- down roofing over tapered insulation 9,670 SF $27.00 $261,090.00

3.09 Roof Flashing / Coping / Edge metal 1 LS $50,000.00 $50,000.00

3.10 New Roof Drains 5 EA $2,000.00 $10,000.00

3.11 Overflow Scuppers 10 EA $1,400.00 $14,000.00

3.12 HVHZ Aluminum Impact Personnel Doors 7 EA $6,500.00 $45,500.00

3.13 HVHZ Aluminum Impact Roller Doors 5 EA $24,000.00 $120,000.00

3.14 HVHZ Aluminum Louvers 7 EA Varies $24,750.00

3.15 Roof Access Ladders 3 EA $10,000.00 $30,000.00

3.16 Mechanical Equipment Tie-Downs 4 EA $1,500.00 $6,000.00

STRUCTURAL SUBTOTAL $630,120.00

IV. ELECTRICAL

4.01 Install Generator and tank, emergency shut-off and annunciator (CITY Purchased) 1 EA $33,000.00 $33,000.00

4.02 Install 400A 4-Pole ATS Nema 1 (CITY Purchased) 1 EA $5,100.00 $5,100.00

4.03 Install 200A 3-Pole ATS Nema 3R (CITY Purchased) 1 EA $4,500.00 $4,500.00

4.04 Temporary 200kW generator (cables, ATS connections, etc.) 1 EA $22,710.00 $22,710.00

4.05 F&I 500 kCMIL THWN2 546 LF $24.59 $13,423.41

4.06 F&I #3 THWN2 137 LF $4.47 $609.98

4.07 F&I #8 THWN2 273 LF $2.17 $593.09

4.08 F&I #10 THWN2 725 LF $1.60 $1,155.58

4.09 F&I #3/0 THWN24 277 LF $10.64 $2,950.10

4.10 F&I #6 THWN2 80 LF $2.92 $232.62

4.11 F&I #12 THWN2 193 LF $1.38 $265.65

4.12 9841 Belden Cable 242 LF $7.43 $1,793.14

4.13 F&I 4" PVC Sch.40 106 LF $39.33 $4,168.45

4.14 F&I 4" RGS 24 LF $83.12 $1,994.85

4.15 F&I 2" PVC Sch.40 56 LF $19.84 $1,111.11

4.16 F&I 2" RGS 20 LF $35.49 $709.78

4.17 F&I 1" PVC Sch.40 106 LF $13.41 $1,421.06

4.18 F&I 1" EMT 124 LF $9.30 $1,152.58

4.19 F&I 3/4" PVC Sch.40 38 LF $10.90 $414.34

4.20 F&I 3/4" RGS 8 LF $18.05 $144.43

4.21 F&I Open trench and filled - electrical conduits 180 LF $16.80 $3,024.45

4.22 Patch and repair for conduits above ceiling 124 LF $27.50 $3,410.00

4.23 F&I 10'x5/8" ground rod 2 EA $325.33 $650.65

4.24 Generator emergency push button 1 EA $481.25 $481.25

4.25 Pull boxes 6 EA $1,375.00 $8,250.00

4.26 Admin.Bldg. electrical service modification 1 EA $11,000.00 $11,000.00

4.27 Fire Station emergency electrical service modification 1 EA $16,500.00 $16,500.00

ENGINEER'S

OPINION OF

PROBABLE COST

ITEM NO. DESCRIPTION QUANTITY UNIT UNIT PRICE

ESTIMATED

AMOUNT

Dania Beach Fire Station No. 1 Wind Mitigation & Emergency Generator Unit

Dania Beach, FL

City of Dania Beach, FL

DATE

5/12/2026

PROJECT TITLE CGA PROJECT NO.

21-4313.1

LOCATION

OWNER

ESTIMATED BY CHECKED BY APPROVED BY

ENGINEER'S

OPINION OF

PROBABLE COST

ITEM NO. DESCRIPTION QUANTITY UNIT UNIT PRICE

ESTIMATED

AMOUNT

Dania Beach Fire Station No. 1 Wind Mitigation & Emergency Generator Unit

Dania Beach, FL

City of Dania Beach, FL

4.28 Gas pipe removal from previous generator, patch/repair ceilings 1 EA $4,500.00 $4,500.00

4.29 Generator Removal 1 EA $7,500.00 $7,500.00

ELECTRICAL SUBTOTAL $152,766.52

Trades Subtotal $806,754.70

Subtotal for all Trades Plus General $899,863.94

PROFIT 15% $134,979.59

OVERHEAD 5% $44,993.20

TOTAL CONSTRUCTION COST $1,079,836.73

TOTAL PROJECT COST $1,079,836.73