2026 T_SPLOST Paving.pdf
PDF 117 KB Posted
- Attached to
- 2026 T-SPLOST Paving
- Solicitation number
- PE-66412-NONST-2026-000000017
- Issued by
- Dooly County, Georgia
About this file
This is a Request for Bids issued by the City of Elberton, Georgia for asphalt milling, resurfacing, and striping services. The project encompasses work on eleven city streets totaling 3.43 miles and three public parking lots. Specific work items include milling and resurfacing of Lake Forest Drive (5,170 linear feet), Brookside Drive (1,630 linear feet), Edwards Street (870 linear feet), Johnson Drive structural repairs (355 linear feet), Worley Street (385 linear feet), McGinty Street (340 linear feet), Lake Forest Circle (1,650 linear feet), South McIntosh (2,830 linear feet), East Church Street (3,850 linear feet), Grogan Circle (650 linear feet), and Martin Luther King Jr Boulevard (360 linear feet), as well as milling and patching work on Burke Street (1,250 linear feet). Additionally, the project includes restoration of Downtown Public Parking Lot (Swift Lot), Elbert Theatre Parking Lot, and Blackwell Cultural Center Parking Lot. Sealed bids were issued on Tuesday, June 23, 2026, with a deadline for submission on Thursday, July 23, 2026 at 2:00 p.m. at City Hall, 203 Elbert Street. Questions regarding the project must be submitted by Thursday, July 16, 2026. Digital bid documents are available upon email request to Natalie Pifer at 861np@ppi.us. No bids may be withdrawn for sixty calendar days after the bid opening.
All work must conform to Georgia DOT Standard Specifications for Construction of Transportation Systems, 2021 edition, with asphalt mix specified as Type 1 with Lime. Work on Johnson Drive must be completed on weekends to accommodate the adjacent Elbert County Elementary School. The total project budget is $1,400,000, with the City reserving the right to reduce the scope of work to remain within this funding limit. The successful bidder will be required to furnish Performance and Payment Bonds each in the amount of 100 percent of the total bid amount. The City reserves the right to reject any or all bids, waive formalities, and award the contract in its best interest. Contact for bidding procedures is Cindy Churney, City Clerk, at cchurney@cityofelberton.net, and contact for project questions is Kris Burton, Public Works Director, at kburton@cityofelberton.net.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF ELBERTON, GEORGIA
REQUESTS FOR BIDS
BID TITLE 2026 T-SPLOST Paving ISSUE DATE Tuesday, June 23, 2026 DUE DATE Thursday, July 23, 2026 at 2:00 p.m.
The City of Elberton is seeking competitive bids for asphalt milling, resurfacing and striping services as specified on the enclosed bid summary sheet. Services must conform to Georgia DOT Standard Specifications for Construction of Transportation Systems, 2021 edition and any amendments thereto.
Sealed bids will be received by the City Clerk of the City of Elberton until 2:00 pm local time on the date above at which time they will be publicly opened and read aloud. The bid opening will begin promptly at the appointed time at City Hall located at 203 Elbert Street. No bids may be submitted after the bid opening begins. The bidder is solely responsible for submission of his bid.
Copies of documents can be obtained by email request to Natalie Pifer at 861np@ppi.us.
Only digital versions are available. Deadline for questions is Thursday, July 16, 2026.
No bid may be withdrawn for a period of sixty (60) calendar days after the bid opening.
The City of Elberton reserves the right to evaluate bids, to reject any and all bids, to waive formalities within the scope of authority, and further specifically, the City reserves the right to make award in the best interest of the City of Elberton.
Direct all questions on bidding procedures to: Cindy Churney, City Clerk 203 Elbert Street Elberton, Georgia 30635-0070 cchurney@cityofelberton.net
Direct all questions on the project to: Kris Burton, Public Works Director 105 Gordon St.
Elberton, Georgia 30635-0070 kburton@cityofelberton.net mailto:861np@ppi.us mailto:cchurney@cityofelberton.net mailto:kburton@cityofelberton.net
2026 T-SPLOST Paving City of Elberton
Elberton, Georgia
Sealed Bids for furnishing all materials, labor, tools, equipment and appurtenances necessary for milling and asphalt paving on eleven City streets totaling 3.43 miles, and resurfacing three public parking lots will be received by the Owner at the City of Elberton Municipal Building, 203 Elbert Street, Elberton, Georgia, until 2:00 p.m., local time, on Thursday, July 23, 2026 and then at said office publicly opened and read aloud.
The Project consists of the following major elements. Note asphalt mix shall be Type 1, with Lime.
1. Milling and asphalt paving on Lake Forest Drive from South Oliver Street to Jones Street (5,170 LF). The work shall include asphalt milling, removal and disposal to a depth of 1.5”, and 1.5” of new 9.5 mm asphalt resurfacing with normal crown section to provide 2% positive drainage from centerline to gutter line. Existing asphalt to be removed from gutter line. Mill through cross street intersections. Replace three stop bars (24” thermoplastic), and double yellow (5” paint) centerline striping. No edge striping required. Replace one speed table in accordance with attached detail, including striping.
2. Asphalt paving on Brookside Drive from Heard Drive to Cardinal Drive (1,630 LF). The work shall include a 1.0” structural course of Permaflex/OGI pavement, followed by 1.0” surface course of 9.5 mm asphalt resurfacing with normal crown section to provide 2% positive drainage from centerline to edge of pavement. Replace one stop bar (24” thermoplastic), double yellow (5” paint) centerline striping, and white edge striping (5” paint).
3. Milling and asphalt paving on Edwards Street from South Tusten Street to Springdale Road (870 LF). The work shall include asphalt milling, removal and disposal to a depth of 1.5” using special care to retain existing granite curb, and 1.5” of new 9.5 mm asphalt resurfacing with normal crown section to provide 2% positive drainage from centerline to gutter line. Replace two stop bars (24” thermoplastic), and double yellow (5” paint) centerline striping. No edge striping required.
4. Johnson Drive @ Athens Tech Road Structural Repairs and Resurfacing: (1) Sawcut and remove existing damaged concrete pavement for a distance of 80’ on Johnson Drive (290 SY), from the edge of pavement on Athens Tech Road east (To be marked by City). Prepare and compact subgrade and place 6” of 19 mm asphalt paving/binder to replace the concrete pavement removed. (2) Sawcut and remove a 20’ section of damaged concrete pavement on Johnson Drive (50 SY), east of the first entrance to Elbert County Elementary School where the existing concrete pavement meets asphalt (to be marked by City). Prepare and compact subgrade and place 6” of 19 mm asphalt paving/binder to replace the concrete pavement removed. (3) Apply tack coat, place and compact 1.5 inches of 9.5 mm asphalt paving over the repaired areas and existing concrete paving, from Athens Tech Road to the existing asphalt pavement joint east of the school entrance (355 LF). Mill Asphalt Pavement to provide flush joints at Athens Tech Road, the Johnson Drive tie in, and the Elementary School entrance. Replace white (5” paint) edge striping, double yellow (5” paint) centerline striping, and 24” thermoplastic stop bar on Johnson Drive at Athens Tech Road. (4) All work on Johnson Drive must be completed on weekends (Saturday or Sunday), when school is not in session. Structural repairs and final resurfacing can be completed in consecutive weekends, or during the same weekend.
5. Milling and asphalt paving on Worley Street from College Avenue (SR 72) to West Railroad Street (385 LF). The work shall include asphalt milling, removal and disposal to a depth of 2.0”, and 2.0” of new 12.5 mm asphalt resurfacing with normal crown section to provide 2% positive drainage from centerline to edge of pavement. Replace one stop bar at West Railroad Street intersection (24” thermoplastic), and double yellow (5” paint) centerline striping. No edge striping required. Start milling at existing asphalt joint north of College Avenue (SR 72). No work to be performed within GaDOT Right-of-Way.
6. Milling and asphalt paving on McGinty Street (340 LF) from College Avenue (SR 72) to West Railroad Street (340 LF). The work shall include asphalt milling, removal and disposal to a depth of 2.0”, and 2.0” of new 12.5 mm asphalt resurfacing with normal crown section to provide 2% positive drainage from centerline to edge of pavement. Replace one stop bar at West Railroad Street intersection (24” thermoplastic), and double yellow (5” paint) centerline striping. No edge striping required. Start milling at existing asphalt joint north of College Avenue (SR 72). No work to be performed within GaDOT Right-of-Way.
7. Milling and asphalt paving on Lake Forest Circle from Lake Forest Drive to Lake Forest Drive
(1,650 LF). The work shall include asphalt milling to a depth of 1.5”, and 1.5” of new 9.5 mm asphalt resurfacing with normal crown section to provide 2% positive drainage from centerline to gutter line and/or edge of pavement. Replace one stop bar (24” thermoplastic), white (5” paint) edge striping, and double yellow (5” paint) centerline striping. Remove and replace one speed table in accordance with attached detail, including paint and traffic striping.
8. Milling and asphalt paving on South McIntosh (2,830 LF) from East Church Street south to Dead End. The work shall include asphalt milling, removal and disposal to a depth of 1.5” using special care to retain existing granite curb, and 1.5” of new 9.5 mm asphalt resurfacing with normal crown section to provide 2% positive drainage from centerline to gutter line.
Replace three stop bars (24” thermoplastic), and double yellow (5” paint) centerline striping.
No edge striping required.
9. Milling and asphalt paving on East Church Street (3,850 LF) from South Tusten Street to Elbert Street (SR 17/72). The work shall include asphalt milling, removal and disposal to a depth of 1.5”, and 1.5” of new 9.5 mm asphalt resurfacing with normal crown section to provide 2% positive drainage from centerline to gutter line and/or edge of pavement. Existing asphalt to be removed from gutter line. Replace two stop bars (24” thermoplastic), double yellow (5” paint) centerline striping, and white (5” paint) edge striping to match existing conditions.
10. Patching and Asphalt paving on Grogan Circle (650 LF). The work shall include milling and deep patching (4” depth) as directed by the City, and 1.25” of new 9.5 mm asphalt resurfacing.
Replace one stop bar (24” thermoplastic), double yellow (5” paint) centerline striping, and white edge line striping (5” paint).
11. Asphalt milling, resurfacing and restriping of Downtown Public Parking Lot (Swift Lot) located between Elbert Street and Heard Street, located behind McIntosh Coffee Shop and adjacent to 115 Heard Street. The work shall include asphalt milling, removal and disposal to a depth of 1.5”, placement and compaction of 1.5” of new 9.5 mm asphalt resurfacing, and restriping of parking lot to match existing conditions including handicap spaces.
12. Patch, crack seal, seal coat, and restripe Elbert Theatre Parking Lot located at 100 South Oliver Street. The work shall include surface cleaning and preparation, milling and deep patching of areas identified by City staff, crack sealing, application of polymer-modified asphalt emulsion sealer (Sealmaster PMM Ultra or approved equal), and restriping of parking lot to match existing conditions including handicap spaces.
13. Patch, crack seal, seal coat, and restripe Blackwell Cultural Center Parking Lot located at 375 Mill Street. The work shall include surface cleaning and preparation, milling and deep patching of areas identified by City staff, crack sealing, application of polymer-modified asphalt emulsion sealer (Sealmaster PMM Ultra or approved equal), and restriping of parking lot to match existing conditions including handicap spaces. Contractor to remove, repaint, and replace concrete wheel stops to match existing conditions.
14. Milling and asphalt paving on Martin Luther King Jr Boulevard (360 LF) from Heard Street to south of Elbert Street (SR 17/72). The work shall include asphalt milling to a depth of 1.5”, and 1.5” of new 9.5 mm asphalt paving with normal crown section to provide 2% positive drainage from centerline to gutter line. Contractor shall begin milling operations south of the existing signal loops, to avoid impacts to signal operations. Replace stop bar and add pedestrian crosswalk at Heard Street intersection (White Thermoplastic). Replace double yellow (5” thermoplastic) centerline striping, white edge line striping (5” thermoplastic), and traffic marking arrows (thermoplastic) to match existing conditions.
15. Milling and asphalt paving on Burke Street (1,250 LF) from Almond Street to Dead End. The work shall include asphalt milling, removal and disposal to a depth of 1.5”, and 1.5” of new
9.5 mm asphalt resurfacing with normal crown section to provide 2% positive drainage from centerline to gutter line. Replace one stop bar (24” thermoplastic), and double yellow (5” paint) centerline striping. No edge striping required. Remove and re-install two sets of rubber speed bumps.
All work shall be completed in accordance with Plans, Special Provisions, and the latest edition of the Georgia Department of Transportation Standard Specifications, applicable Supplemental Specifications, and the latest edition of the Manual on Uniform Traffic Control Devices (MUTCD).
The work will be awarded in one Contract, subject to total available funding of $1,400,000.
The City reserves the right to reduce the project scope of work to limit total expenses to $1,400,000.
Copies of documents and plans can be obtained by email request to Natalie Pifer at 861np@ppi.us. Only digital versions are available.
Payments, Applications for Payment, Certificates for Payment, and retainage shall be in accordance with the provisions of the Contract Documents.
The successful Bidder for this Contract will be required to furnish a satisfactory Performance Bond and Payment Bond each in the amount of 100 Percent (100%) of the total bid amount.
The Owner reserves the right to reject any or all Bids, to waive informalities and to readvertise.
*****end***** mailto:861np@ppi.us