2026 Sewer Line Repair 801 Manteo Circle.pdf
PDF 644 KB Posted
- Attached to
- “City of Havelock, 2026 Sewer Line Repair”
- Solicitation number
- 294-29403182026
- Issued by
- Cumberland County, Hiddenite CDP, North Carolina
About this file
This is an Invitation to Bid issued by the City of Havelock, North Carolina for a sewer line repair project located at 801 Manteo Circle. The project involves the replacement of two 60-foot sections of sewer line (one 8-inch VCP and one 6-inch Ductile Iron Sewer Pipe), 60 lineal feet of combined curb and gutter (30 feet on each side of the road), and 100 square feet of sidewalk. The work includes excavation and replacement of pipes at approximately 7 feet depth, installation of 12 inches of stone bedding, asphalt restoration covering approximately 38 square yards, and concrete restoration. Bids must be submitted by 11:00 AM EST on Wednesday, April 15, 2026, addressed to Kimberly Walters, Finance Director, and may be submitted by mail, email, fax, or hand delivery. A site visit is recommended but not mandatory. The performance period is 30 calendar days from issuance of the Notice to Proceed, with work hours established as 8:00 AM to 5:00 PM Monday through Friday. Written questions regarding bid specifications must be received by 5:00 PM EST on Friday, March 27, 2026, with City responses provided by 5:00 PM EST on Tuesday, April 7, 2026.
Bids must include an itemized schedule by quantity, unit price, and total for each work element and are valid for 75 days after opening. The contractor must hold a North Carolina general contractor's license, provide proof of E-Verify compliance through a notarized affidavit, and verify compliance with the Iran Divestment Act and Companies Boycotting Israel Act. Out-of-state corporations, limited liability companies, or partnerships must obtain a Certificate of Authority to Transact Business in North Carolina. The contractor is responsible for all materials, labor, equipment, utility locates, dewatering, shoring design, traffic control plan approval, erosion and sediment control, bypass pumping of sewage, and site restoration. A one-year warranty is required on all materials and workmanship. Liquidated damages of $300 per day apply for work extending beyond the 30-day performance period. The City reserves the right to reject any or all proposals and may purchase items from state contracts at its discretion.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CITY OF HAVELOCK
Post Office Box 368
Havelock, NC 28532
INVITATION TO BID
Pursuant to North Carolina General Statutes §143-131, the City of Havelock invites informal bids on the following:
Bids must be submitted in accordance with the attached specifications. Bids must include an itemized schedule (including quantity, unit price and total) for each work element. Bids can be submitted by mail, email, fax or hand delivered. Cover sheets, envelopes, etc. should be clearly marked with the words:
“City of Havelock, 2026 Sewer Line Repair” 801 Manteo Cir.
Havelock, NC 28532
Address Bids to: Kimberly Walters, Finance Director City of Havelock P.O. Box 368 1 Governmental Ave.
Havelock, NC 28532 Fax: 252-447-0126 Email: Bids@havelocknc.us
Bids will be accepted until 11:00 AM (EST) on Wednesday, April 15, 2026, at which time they will be reviewed in the office of the City Finance Officer. Quotes are not subject to public inspection until the contract is awarded.
The bids are good for 75 days after opening. The winning bidder will be issued a Notice To Proceed (NTP) along with a Purchase Order. The performance period is 30 calendar days from the NTP.
Bidders are cautioned not to submit bids until the proposed requirements and specifications have been carefully examined. It will be considered that bidders will have satisfied themselves as to the accuracy of the specifications. No proposal will be considered unless prices are submitted for all items requested in any section. The City reserves the right to change the amount of quantities.
All bids submitted should be to the desired specifications. Any exceptions to the specifications will be evaluated based on the best interest of the City. Any deviation from specifications indicated herein must be clearly pointed out; otherwise, it will be considered that items offered are in strict compliance with these specifications, and bidder will be held responsible therefore. Deviations shall be explained in detail.
The bidder shall not construe this paragraph as inviting deviation or implying that any deviation will be acceptable.
The names of certain brands or makes denote quality standard in the article desired, but do not restrict bidders to the specific brand, make or manufacturer named. They are meant to convey to prospective bidders the general style, type, character and quality of the article desired.
The successful bidder on all construction contracts will be required to conduct the operation in accordance with all Federal, State, and Municipal health and safety rules, regulations and laws applicable to the operation. The successful bidder may be asked to provide the City with a copy of the company's safety plan prior to commencing work. For all projects over $30,000, a general contractor’s license must be furnished to the City if applicable.
Certificate to Transact Business in North Carolina: As a condition of contract award, each out-of-State Vendor that is a corporation, limited-liability company or limited-liability partnership shall have received, and shall maintain throughout the term of The Contract, a Certificate of Authority to Transact Business in North Carolina from the North Carolina Secretary of State, as required by North Carolina law. A contract requiring only an isolated transaction completed within a period of six months, and not in the course of a number of repeated transactions of like nature, shall not be considered as transacting business in North Carolina and shall not require a Certificate of Authority to Transact Business.
The City will not sell bid packages. Plans, specifications, and addenda may be viewed and obtained online at www.havelocknc.us. Click on: “Bid on a Contract”; “Current Bids”. The Bidder’s List is maintained by Vendor Registry. Registration for the Bidder’s List is made online at www.havelocknc.us. Click on: “Bid on a Contract”; “Vendor login/Registration”.
N.C.G.S. (North Carolina General Statutes), specifically §160A-20.1(b), prohibit the City from entering into contracts with contractors and subcontractors who have not complied with the requirement of Article 2 or Chapter 64. The Contractor shall submit the E-Verify Affidavit, located in the Bid Proposal section, with their bid. Bids that do not include this Affidavit will be considered non-responsive.
N.C.G.S 147-86.42-84 requires that contractors with a North Carolina Local Government must not utilize any subcontractor found on the State Treasurer’s Iran Divestment list or Companies Boycotting Israel list. The referenced lists can be found on the State Treasurer’s website at the address www.nctreasurers.com and will be updated every 180 days.
The City of Havelock reserves the right to reject any or all proposals and to purchase items from the state contract in the efforts to award the contract to the bidder it deems to be for the best interest of the City.
MODIFICATION AND WITHDRAWAL OF BIDS. Bids may be modified or withdrawn by an appropriate document duly executed (in the manner that a Bid must be executed) and delivered to the place where Bids are to be submitted at any time prior to the opening of Bids. A request to withdraw a bid may be made to the Owner within 72 hours after Bids are opened in accordance with NCGS § 143-129.1 Requests to withdraw a Bid will be subject to the requirements of NCGS §143-129.1 and in the sole discretion of the City of Havelock Finance Officer.
This institution is an equal opportunity provider, and employer.
Contact person(s) for information on this bid:
For questions in regards to the bid specifications, the City requires and only responds to questions submitted in writing and sent via email to: Bids@havelocknc.us
Questions must be received by 5:00 PM (EST) on Friday, March 27, 2026. If questions are received, the City will respond no later than 5:00 PM (EST) on Tuesday, April 7, 2026.
This is the 18th day of March 2026
Published: Vendor Registry March 18, 2026
Kimberly Walters Finance Director http://www.havelocknc.us/ http://www.havelocknc.us/ file://coh-fp01/Finance/BIDS/Bid%20Cover%20letters,%20Tab%20sheets,%20Vendor%20list%20&%20forms/Cover%20letters%20and%20Addendum%20Templates/www.nctreasurers.com
STATE OF NORTH CAROLINA
AFFIDAVIT
I, ___________________________ (the individual attesting below), being duly authorized by and on behalf of __________________________________ (the entity hereinafter “Employer”) after first being duly sworn hereby swears or affirms as follows:
1. Employer understands that E-Verify is the federal E-Verify program operated by the United States Department of Homeland Security and other federal agencies, or any successor or equivalent program used to verify the work authorization of newly hired employees pursuant to federal law in accordance with
NCGS §64-25(5).
2. Employer understands that Employers Must Use E-Verify. Each employer, after hiring an employee to work in the United States, shall verify the work authorization of employee through E-Verify in accordance with NCGS §64-26(a).
3. Employer is a person, business entity, or other organization that transacts business in the State and that employs 25 or more employees in this State. (mark Yes or No)
a. YES_____, or
b. NO_____
4. Employer’s subcontractors comply with E-Verify, and if Employer is the winning bidder on this project, Employer will ensure compliance with E-Verify by any subcontractors subsequently hired by Employer.
This _________ day of ________________________, 20________.
Signature of Affiant: _______________________________________
Print or Type Name: _______________________________________
State of North Carolina County of ____________________________
Signed and sworn to (or affirmed) before me, this the
_________ day of _____________________________, 20________.
Signature of Notary Printed Name of Notary
Bid Sheet
Base Bid: _____________________________
NC Sales Tax: _____________________________
Delivery Cost (if applicable): _____________________________
Total Cost to City: _____________________________
Bids must include an itemized schedule by quantity, unit price and total for each work element.
Company Name: ______________________________________________
Company Address: ______________________________________________
Contact Person: ______________________________________________
Telephone Number: ______________________________________________
Email Address: ______________________________________________
NC Contractor’s License Type and Number: ______________________________________________
Number of Addendums Acknowledged (circle one): N/A 1 2 3 4
As of the date listed below, the vendor or bidder listed above is compliant with N.C.G.S. 147-86.42-84, the
Iran Divestment Act and the Companies Boycotting Israel Act.
Authorized Signature: ____________________________________________________
Print Name of Authorized Signature: ____________________________________________________
Title: ____________________________________________________
Address Bid to: Kimberly Walters, Finance Director City of Havelock P.O. Drawer 368 1 Governmental Avenue Havelock, NC 28532
Bids@Havelocknc.us Please indicate the Bid name on the outside of the envelope.
2026 Sewer Line Repair 801 Manteo Cir.
Havelock, NC 28532 Objective:
Replacement of two 60’ sections of sewer line, 60 lineal feet of Curb and Gutter, and 100 square feet of sidewalk within Manteo Circle.
Scope:
There are two sewer lines extending underneath the asphalt road on the North side of Manteo Circle, see figure 2 for location. Each of these two lines are to be excavated and replaced for a total lineal footage of 60 feet per line. The first of the two lines is assumed to be 8” VCP.
The second of the two lines is assumed to be 6” Ductile Iron Sewer Pipe. Both lines are approximately 7’ deep and shall be excavated and replaced beginning at 16’ from the North side of Manteo Cir. and the replacement shall terminate 16’ on the South side of Manteo Cir. The roadway including the curb and gutter is a total of 28’ wide. The bedding for the replaced lines shall be 12” of 57 stone, the 57 stone shall be placed to 12” above the top of the newly installed pipe. Excavated spoils shall in no case utilized for compactable materials, all excavated spoils shall be hauled and disposed of on a daily basis. All OSHA regulations including trench box safety shall be followed during the course of this project.
There are two sections of curb and gutter and one section of sidewalk that are to be replaced, the first section of curb and gutter shall be on the North side of the road and shall be 30 lineal feet in length, the second section of curb and gutter shall be on the South side of the road and shall be 30 lineal feet in length. The style of curb and gutter to be replaced is Combined Curb and Gutter, see image 3 for dimensions. The replaced curb and gutter shall match the existing in both height, width, and depth. The sidewalk to be replaced shall be a total of 100 square feet at a width of 5’ wide and 20’ long. All concrete restoration shall follow the specifications within section 9.
The asphalt utility cut within the roadway shall be backfilled from the top of the 57 stone utilizing either select fill or ABC Stone to 3” from the top of the asphalt roadway. All backfill material shall be compacted to 98% standard proctor in 8” lifts. The asphalt utility cut will be approximately 12’ X 28’ for approximately 38 square yards. The contractor will be responsible for concrete curb and gutter, sidewalk, and asphalt restoration.
A site visit is highly recommended but not mandatory. All measurements are approximate contractor to verify. Utility Locates shall be the responsibility of the contractor, utilities damaged during the course of this project shall be the responsibility of the contractor to remediate before the completion of the project. Contractor is to supply all labor, materials, equipment to complete this project, unless otherwise specified in writing. The City of Havelock shall not be held responsible for omissions or errors in description.
1. Gravity Sewer Materials:
a. PVC SDR35 Gravity Sewer Pipe: Pipe shall conform to all requirements of
AWWA and shall be capable of withstanding the overburden pressures determined by the depth of burial in the field.
b. Non-pressure-type Pipe Couplings: Couplings for joining new PVC pipe to existing pipe shall be solid sleeve type suitable for all types of pipe. When applicable, material shall be ductile iron with gaskets suitable for sewer service.
Coupling shall be Maxadaptor coupling or equal, per AWWA C605.
c. Solid Wall Plastic Pipe Cutting: Cutting of pipe lengths shall be performed using tools and or equipment that will provide a neat, perpendicular cut without damage to the plastic. All burrs shall be removed using a file, knife or abrasive paper. Ends on the cut pipe shall be beveled to prevent gasket damage.
2. Asphalt Pavement Repair
a. The pavement edge shall be defined by a straight edge formed by a machined saw cut leaving no jagged edges.
b. There shall be a 12” Key-In around utility cut s which is excavated to a minimum depth of 3”.
c. The new ABC stone or select fill backfill material shall be compacted to a density equal to 100% of that obtained by compacting a sample of the material in accordance with AASHTO T-80 as modified by NCDOT. Bituminous base or binder may be substituted if approved by a representative of the City of Havelock.
d. The removed asphalt, pavement, debris and concrete shall be removed from site, hauled, and disposed of in accordance with all local, state, and federal requirements.
e. The entire thickness / vertical edge of the existing asphalt shall be tacked in accordance with section 605 asphalt tack coat of the NCDOT Standard Specifications for Roads and Structures.
f. The asphalt surface course shall be S9.5B per NCDOT Standards for Roads and Structures. The same depth of pavement material which exists shall be reinstalled, but in no case shall the asphalt be less than 3” thick.
g. The asphalt pavement material shall be installed and compacted thoroughly and rolled with a smooth drum roller to achieve a smooth, level patch. See figure 1 for standard details.
h. Any striping that is damaged or removed during the utility cut repairs shall be restored to an as was condition or better before the project is completed.
i. The asphalt shoulder shall be straight, level and even. Top soil shall be utilized for shoulder treatment and shall begin at the same elevation as the newly installed asphalt pavement transitioning into the shoulder on a 3 to 1 slope. The shoulder treatment shall be seeded and straw placed on top.
j. Access to residents’ driveways must remain as accessible as possible during the course of this project.
3. Dewatering:
a. The contractor shall dewater until completion of work. Excavation shall be kept free of water at all times during pipe removal, pipe replacement, and backfill operation.
b. A dewatering plan shall be submitted to the City of Havelock for approval prior to the beginning of the project.
c. All dewatering shall flow through a sediment filter bag. Sediment filter bags shall be of Polypropylene non-woven geotextile fabric with a sewn-in sleeve of sufficient size to accept a 4-inch diameter discharge hose. The discharge hose shall be extended into the sleeve a minimum of six (6) inches and be tightly secured with a hose clamp or other suitable device to prevent leakage. Contractor shall size sediment filter bags as necessary to dewater excavations. Effluent to be directed to adjacent stormwater conveyance areas and Contractor shall remove any accumulation of sediment from such areas following dewatering operations.
d. Upon removal of any dewatering header pipe system the contractor shall be responsible for filling the header pipe hole with filter sand to 50% of the depth of the hole while compacting to 95% standard proctor in 8” lifts. Grout shall be utilized to fill to 90% of the depth of the hole and the remaining 10% shall be topsoil, or select fill.
e. The usage of water from a hydrant will only be accomplished by use of a Hydrant Meter which will be issued from Customer Service at City Hall within the City of Havelock. The Hydrant Meter must be returned to Customer Service at City Hall within the City of Havelock at the completion of the project.
f. Upon submission of the Hydrant Meter Application there will be a $ 500.00 dollar deposit due. The Hydrant Meter will be delivered to the project site upon the contractor calling 1-252-670-0663 and scheduling the delivery. Hydrant Meters are subject to availability.
g. Upon return of the Hydrant Meter, usage will be read and the metered charge will be applied. If the metered charge is less than the deposit the contractor will receive a refund which will be minus the metered charge, if the metered charge is over the deposit amount a usage bill will be issued to the contractor for the balance over the deposit amount.
4. Excavation and Shoring:
a. Contractor is responsible for the design and protection of all excavation and shoring. Standard shoring practices including trench boxes, which can be used if certified/stamped by manufacturer. If required, shoring shall be designed and sealed by a professional engineer registered in the State of North Carolina, as required by OSHA, CFR1926.
b. Contractor shall notify NC 811 for utility locations prior to any excavations.
c. In no case shall excavations exceed that which cannot be backfilled by the end of the work day.
5. Backfill and Compaction:
a. All excavations shall be backfilled with select fill or ABC Stone material.
Contractor shall be responsible for removal and disposal of all excavation material and construction debris. Excavated spoils shall be hauled and disposed of on a daily basis.
b. Compaction in embankment shall be compacted to 95% standard proctor in 8” lifts.
c. Compaction in roadways, driveways, and sidewalks shall be compacted to 98% standard proctor in 8” lifts.
6. Pipe and Manhole Bedding:
a. Pipe bedding shall consist of a twelve-inch (12”) depth of # 57 stone under pipe and #57 or ABC stone to 12” above the top of pipe.
7. Erosion and Sediment Control and Restoration:
a. The contractor shall be responsible for the installation and maintenance of all erosion and sediment control in accordance with the NC DEQ Erosion and Sediment Control Manual.
b. Construction activities shall be completed in such a manner that erosion of disturbed areas and off-site sedimentation is absolutely minimized.
c. All disturbed areas shall be restored as soon as construction is complete. Seed or sod type shall match existing grass in maintained areas. Follow the NC DEQ Erosion and Sediment Control Manual for type or as directed by City of Havelock representative.
8. Bypass Pumping:
a. Sewage bypass pumping shall be required for completion of repairs. If required, contractor shall design and furnish all material, labor, equipment, power, fuel, fuel storage, maintenance, etc. to implement a temporary bypass arrangement for the purpose of diverting flow around the work area on a daily basis for the duration of the repair. The bypass system shall meet the requirements of all codes and regulatory agencies having jurisdiction. Contractor shall be held liable for any and all fines imposed by local, State, and/or Federal agencies for failure to maintain flows or contain spills and/or overflows.
9. Traffic Control
a. Contractor shall submit a Traffic Control Plan for any operations affecting traffic including but not limited to lane closures. City must approve the traffic plan prior to implementation, particularly 24-hour notice prior to any lane closure.
b. Access to residences for local traffic shall be maintained throughout contract. Contractor shall provide a minimum of 24-hour notice to City of Havelock for any road closure.
10. Concrete Restoration
a. Any concrete rubble from removal of the sidewalks, driveway aprons, and curbing will be the responsibility of the contractor to haul on a daily basis and dispose of in accordance with all local, state, and federal regulations.
b. Concrete is to be 3500-pound fiber reinforced concrete mix.
c. The foundation for the concrete shall be compacted to 98% standard proctor in no more than 8” lifts before the concrete is poured.
d. The concrete driveway aprons and sidewalks shall be no less than four inches thick.
e. The concrete driveway aprons and sidewalks will require no wire mesh or rebar.
f. The seams where the new concrete meets the old concrete will be tooled to a ½” radius.
g. The seams where the new concrete meets the existing concrete shall have a ½” expansion joint between the existing and newly poured concrete.
h. Until completely cured the contractor will supply signage “No walking, Wet concrete”.
11. Site Restoration
a. Disturbance of existing landscape features shall be held to a minimum and all disturbed areas returned to a condition equal or better when repair is complete. Care shall be taken so as not to damage existing features to remain such as roadways, curbs, driveways, sidewalks, etc. All features removed or damaged shall be replaced or repaired to existing condition or better. All demolished material shall become the property of the contractor and shall be removed from the work site and disposed of in accordance with all local State, and Federal requirements. As-built documentation shall include a description of materials used and repair procedures completed at each site.
b. Damage to any residential or commercial property shall be immediately reported to a representative of the City of Havelock. Remediation of damage to any residential or commercial property shall be caried out as an immediate priority and completed in a manner satisfactory to the City of Havelock. If remediation of commercial or residential property is not preformed within a timeframe deemed satisfactory by the City, the City of Havelock may undertake the necessary corrective action, and all associated costs shall be borne by the contractor.
12. Performance Period
a. It will be the contractor’s responsibility to set a start date with a representative from the City of Havelock to begin a project within thirty
(30) days from the issuance of a Notice of Award - Proceed.
b. The performance period is 30 days from the listed date on the Notice to Proceed.
c. The contractor shall work diligently to complete the project from the arranged start date. Work hours shall be 8am to 5pm, Monday through Friday. No work shall be performed on City holidays. Work outside established work hours must be scheduled with the City, 48 hours in advance and is subject to approval.
d. The contractor will be responsible for contacting a representative of the City of Havelock in the event that a project will be extended outside of the arranged performance period. Contact must be in the form of an email and acceptance of the extension of the performance period from a representative of the City of Havelock must also be in the form of an email.
13. Access:
a. Access to project site is within existing City of Havelock right of way.
14. Termination Clause:
a. Any agreement and issuance of purchase orders shall be terminated upon the expiration of (90) ninety days without work commencing. At the end of ninety days the City of Havelock will give written notice to the other party of its intention to terminate.
b. Any intent to begin a project ninety (90) days or more after a purchase order has been issued must be submitted in writing and approved by a representative of the City of Havelock.
15. Warranty:
a. Contractor will be held responsible for the materials and workmanship utilized within this project for a term of one year from the time that the equipment is put back into service.
b. The City of Havelock will be responsible for the warranty of any materials that are supplied to the contractor by the City of Havelock during the course of this project.
General Provisions:
a. Contractor shall comply with all requirements of OSHA 1926.
b. Work hours shall be 8am to 5pm, Monday through Friday. No work shall be performed on City holidays. Work outside established work hours must be scheduled with the City, 48 hours in advance and is subject to approval.
c. Contractor will obtain all necessary permits. Permits required by City of Havelock are provided free of charge.
d. Roadway repair is the responsibility of the contractor.
e. Contractor shall control erosion and sediment release while this project is under construction.
f. The contractor is to clean and remove all debris at the end of each work day.
g. All underground utilities are to be 811 located, prior to work being started.
h. Contractor is responsible for all damage to existing roads, driveways, drainage, or utilities that occur as a result of the construction project.
i. Contractor is responsible for all damage to City property that occurs as a result of the construction of the project.
j. Contractor shall provide safety measures during the entire length of the project.
k. Contractor is responsible for the storage and safety of materials and equipment on jobsite.
l. Submittals must be approved by the City of Havelock prior to any work starting.
m. The performance period is 30 days from the Notice to Proceed.
Liquidated Damages:
a. The Contractor agrees to pay the owner $300 per day in liquidated damages for each day beyond the period of performance.
Figure 1: Work area map.
Figure 2: Locations of Pipe and work area
Figure 3: Asphalt Restoration Specifications
| CITY OF HAVELOCK |