2026 Brick Streets Repair Documents.pdf
PDF 6 MB Posted
- Solicitation number
- 26-032
- Issued by
- Schleicher County, Texas
About this file
This is a Capital Improvements Project (CIP) contract document issued by the City of Tyler, Texas (Smith County) for the 2026 Brick Streets Repair Project (Bid Number 26-032). The project encompasses brick street repairs including cleaning and storage of bricks, compacted and stabilized subgrade, flowable fill base, buffer sand, and brick surface layers, along with curb and gutter replacement, driveway approach replacement, headers, valley gutters, and miscellaneous related items. The contract includes utility repair work and rehabilitation of Oakwood Street and Spring Avenue. Specific bid items include block sodding (10 square yards), topsoil placement (2 cubic yards), select fill (85 cubic yards combined), brick street repairs in small areas (180 square yards) and large areas (250 square yards), curb and gutter removal and replacement (100 linear feet), concrete driveway approach replacement (40 square yards), concrete headers (30 linear feet), concrete valley gutters (30 square yards combined), and adjustments for sanitary sewer manholes (7 each) and water valve boxes (6 each). A pre-bid conference is scheduled for Tuesday, August 4, 2026, at 2:00 p.m. at the Water Utilities Administrative Office, 511 West Locust Street, Tyler, Texas. Sealed bids are due by 2:00 p.m. on Tuesday, August 11, 2026, at the Purchasing Office, 304 North Border, Tyler, Texas 75702. Bids will be publicly opened immediately following the deadline in the City Council Chambers. The mandatory project completion date is January 29, 2027, with work to commence within ten calendar days of the written Notice to Proceed.
Bidders must submit a proposal guaranty consisting of either a certified check, cashier's check, or bid bond equal to five percent (5%) of the total maximum bid amount. Contract documents are available for $35.00 per set (non-refundable) or electronically upon emailed request to cbain@tylertexas.com. The contractor must perform at least thirty percent (30%) of the total contract work with its own forces unless waived by the City. A Performance and Maintenance Bond and Payment Bond, each equal to one hundred percent (100%) of the contract amount, are required for contract amounts exceeding $100,000; however, a Payment Bond is required for all projects regardless of value. Contractors must maintain comprehensive insurance coverage including Commercial General Liability, Business Automobile Liability, and Contractor's Professional Errors & Omissions Liability, with the City named as additional insured. All contractors must comply with prevailing wage requirements and non-discriminatory employment practices. The City reserves the right to reject any or all bids and may award the contract to the lowest responsible bidder after tabulated bids are presented to City Council within sixty calendar days of bid opening. Out-of-state contractors must submit copies of their state's preference laws. The project designer is Cody Bain, P.E., reachable at (903) 531-1135 or cbain@tylertexas.com.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP 26-032 Temporary Labor Services for CNS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract Copies:
☐ Original
☐ As Requested
City of Tyler, Texas
Capital Improvements Project (CIP) Contract
CONTRACT DOCUMENTS
FOR
City of Tyler Bid Number 26-032 Project Name 2026 Brick Streets Repair Project
CITY OFFICIALS: PREPARED BY:
Mayor Stuart Hene Project Designer Cody Bain, P.E.
City Council District 1: Central VACANT District 2: West Petra Hawkins District 3: Northwest Shonda Marsh District 4: Northeast Clint Childs District 5: East Lloyd Nichols District 6: South Carleen Dark-Bays
City Manager Edward Broussard
Key Leader Title Stephanie Franklin
CITY OF TYLER, TEXAS – CIP CONTRACT REVISION DATE: 07.25.2024
TABLE OF CONTENTS
SECTION 1 ADDENDA
SECTION 2 NOTICE TO BIDDERS
SECTION 3 INSTRUCTIONS TO BIDDERS
SECTION 4 POLICY STATEMENT ON EEO
SECTION 5 PROPOSAL
SECTION 6 BID BOND
SECTION 7 STANDARD FORM OF AGREEMENT
SECTION 8 PERFORMANCE AND MAINTENANCE BOND AND PAYMENT BOND
SECTION 9 PAYMENT BOND ONLY
SECTION 10 CERTIFICATE(S) OF INSURANCE
SECTION 11 ENDORSEMENTS
SECTION 12 CONTRACTOR’S AFFIDAVIT OF BILLS PAID
SECTION 13 RESERVED
SECTION 14 WAIVER AND RELEASE
SECTION 15 PROCEDURE FOR CORRECTING CONSTRUCTION DEFECTS
SECTION 16 GENERAL CONDITIONS
SECTION 17 SPECIAL CONDITIONS
SECTION 18 TECHNICAL AND/OR SPECIAL SPECIFICATIONS; PLANS AND OTHER
DRAWINGS; OTHER DOCUMENTS AS NEEDED
SECTION 19 CERTIFICATE OF INTERESTED PARTIES
DETAILED TABLE OF CONTENTS
SECTION 1 ADDENDA
SECTION 2 NOTICE TO BIDDERS
SECTION 3 INSTRUCTIONS TO BIDDERS
3.1 PROPOSAL FORM
3.2 EXAMINATION OF PLANS, SPECIFICATIONS AND SITE OF THE WORK
3.3 PRE-BID CONFERENCE
3.4 ADDENDA
3.5 QUANTITIES IN PROPOSAL FORM
3.6 UNIT PRICES
3.7 PROJECT COMPLETION TIME
3.8 ASSIGNMENT AND SUBCONTRACTING
3.9 OUT-OF-STATE CONTRACTORS
3.10 NON-DISCRIMINATORY EMPLOYMENT
3.11 WAGE RATES
3.12 PROPOSAL GUARANTY (BID BOND)
3.13 PREPARATION OF PROPOSAL
3.14 SIGNATURE REQUIREMENTS OF PROPOSAL
3.15 FILING OF BID PACKAGES
3.16 WITHDRAWING OR MODIFYING BID PACKAGES
3.17 OPENING BID PACKAGES
3.18 IRREGULAR PROPOSALS
3.19 DISQUALIFICATION OF BIDDERS
3.20 CONSIDERATION OF PROPOSALS
3.21 CITY MAY REJECT BID PACKAGES
3.22 AWARD OF CONTRACT
3.23 RETURN OF BIDDER’S BOND
3.24 SUBMISSION OF POST BID INFORMATION
3.25 CONTRACT BONDS
3.26 INSURANCE
3.27 EXECUTION OF CONTRACT
3.28 FAILURE TO EXECUTE CONTRACT
3.29 BEGINNING OF WORK
SECTION 4 POLICY STATEMENT ON EEO
SECTION 5 PROPOSAL
SECTION 6 BID BOND
SECTION 7 STANDARD FORM OF AGREEMENT
7.1 DESCRIPTION OF WORK
7.2 CONTRACT DOCUMENTS
7.3 TIME OF COMMENCEMENT AND COMPLETION
7.4 CONTRACT PRICE
7.5 BONDS
7.6 INSURANCE
7.7 CITY AND OTHERS INDEMNIFIED
7.8 VENUE
7.9 AFFIDAVIT OF BILLS PAID AND FINAL PAYMENT TO CONTRACTOR
7.10 RESERVED
7.11 NOTICES
SECTION 8 PERFORMANCE AND MAINTENANCE BOND AND PAYMENT BOND
SECTION 9 PAYMENT BOND ONLY
SECTION 10 CERTIFICATE(S) OF INSURANCE
SECTION 11 ENDORSEMENTS
SECTION 12 CONTRACTOR’S AFFIDAVIT OF BILLS PAID
SECTION 13 RESERVED
SECTION 14 WAIVER AND RELEASE
SECTION 15 PROCEDURE FOR CORRECTING CONSTRUCTION DEFECTS
SECTION 16 GENERAL CONDITIONS
16.1 DEFINITIONS OF TERMS
16.1.1 Addenda
16.1.2 Agreement
16.1.3 Calendar Day
16.1.4 Change Order
16.1.5 City
16.1.6 Contract Documents
16.1.7 Contract Price
16.1.8 Contract Time
16.1.9 Contractor
16.1.10 Extra Work
16.1.11 Field Order
16.1.12 Final Completion (a.k.a. Complete in Full or Completed in Full)
16.1.13 Notice to Proceed
16.1.14 Reserved
16.1.15 Ozone Action Day
16.1.16 Proposal
16.1.17 Project Designer
16.1.18 Project Representative
16.1.19 Rain Day
16.1.20 Standard Specifications
16.1.21 Sub-Contractor
16.1.22 Substantial Completion
16.1.23 Supplier
16.1.24 Traffic Engineer
16.1.25 Work
16.1.26 Working Day
16.1.27 Working Hours
16.1.28 Written Notice
16.2 RESPONSIBILITIES OF THE CITY
16.2.1 Collateral Contracts
16.2.2 Easements and Right-of-Way
16.3 RESPONSIBILITIES OF THE CONTRACTOR
16.3.1 Contractor's Understanding
16.3.2 Keeping Plans and Specifications Accessible
16.3.3 Right of Entry
16.3.4 Contractor's Duty and Superintendence
16.3.5 Character of Workers
16.3.6 Assignment and Subcontracting
16.3.7 Subsurface Conditions
16.3.8 Protection of Materials, Equipment and Work
16.3.9 Protection Against Accident to Employees and the Public
16.3.10 Shop Drawings and Other Submittals
16.3.11 Water for Construction
16.3.12 Contractor's Buildings
16.3.13 Sanitation
16.3.14 Protection Against Claims
16.3.15 Intellectual Property - Payment of Royalties and License Fees
16.3.16 Compliance with Laws and Ordinances
16.3.17 OSHA Requirements
16.3.18 Trench Safety Systems
16.4 RESPONSIBILITIES OF THE PROJECT DESIGNER
16.4.1 Project Designer-City Relationship
16.4.2 Lines and Grades
16.4.3 Initial Determinations
16.4.4 Payments for Work
16.4.5 Objections
16.5 RESPONSIBILITIES OF THE PROJECT REPRESENTATIVES
16.5.1 Project Representative-City Relationship
16.5.2 Professional Inspection by Project Representative
16.6 CONTRACT DOCUMENTS
16.6.1 Ownership of Drawings
16.6.2 Adequacy of Design
16.6.3 Specifications
16.6.4 Discrepancies and Omissions
16.7 BONDS
16.7.1 General
16.7.2 Performance Bond
16.7.3 Maintenance Bond
16.7.4 Payment Bond
16.8 INSURANCE REQUIRED
16.8.1 Contractor Shall Maintain Insurance
16.8.2 Insurance Requirements shall not limit Contractor’s Liabilities and Obligations
16.8.3 Commercial General Liability
16.8.4 Business Automobile Liability
16.8.5 Contractor’s Professional Errors & Omissions Liability
16.8.6 Inland Marine Builder’s Risk Insurance
16.8.7 Contractor’s Pollution Liability
16.8.8 Commercial Umbrella/Excess Liability
16.8.9 Additional Insured Endorsements
16.8.10 Deductibles, Coinsurance Penalties & Self-Insured Retention
16.8.11 Waiver of Subrogation
16.8.12 Right to Revise or Reject
16.8.13 No Representation of Coverage Adequacy
16.8.14 Certificate of Insurance
16.8.15 Workers’ Compensation & Employer’s Liability
16.9 QUALITY OF MATERIALS AND WORKMANSHIP
16.9.1 Materials Approved for Work
16.9.2 Testing of Materials
16.9.3 Defects and Their Remedies
16.9.4 Guarantee
16.10 MAINTENANCE OF SITE
16.10.1 Protection of Adjoining Property
16.10.2 Driveways and Property Access
16.10.3 Traffic Control
16.10.4 Erosion Control Plan
16.10.5 Protection of Survey Monuments
16.10.6 Manhole, Clean-Out, and Water Valve Locations
16.10.7 Water Sprinklers
16.10.8 Existing Mailboxes
16.11 GENERAL PROVISIONS
16.11.1 Damages
16.11.2 Losses From Natural Causes
16.11.3 Public Utilities
16.11.4 Ozone Action Day
16.12 PROSECUTION AND PROGRESS
16.12.1 Time and Order of Completion
16.12.2 Computation of Contract Time for Completion
16.12.3 Liquidated Damages
16.12.4 Extension of Time
16.12.5 Inclement Weather
16.12.6 Hindrances and Delays
16.13 MEASUREMENT AND PAYMENT
16.13.1 Quantities and Measurements
16.13.2 Estimated Quantities
16.13.3 Price of Work
16.13.4 Arrears
16.13.5 Payments Withheld
16.13.6 Partial Payments
16.13.7 Records of Materials Purchased
16.13.8 Use of Completed Portions
16.13.9 Substantial Completion
16.13.10 Final Completion and Acceptance
16.13.11 Final Payment
16.14 EXTRA WORK AND CLAIMS
16.14.1 Changes and Alterations
16.14.2 Change Orders
16.14.3 Minor Changes
16.14.4 Extra Work
16.14.5 Time of Filing Claims
16.15 ABANDONMENT OF CONTRACT
16.15.1 Abandonment by Contractor
SECTION 17 SPECIAL CONDITIONS
SECTION 18 TECHNICAL AND/OR SPECIAL SPECIFICATIONS; PLANS AND OTHER
DRAWINGS; OTHER DOCUMENTS AS NEEDED
SECTION 19 CERTIFICATE OF INTERESTED PARTIES
Section 1 ADDENDA
[Insert Addenda Here If Applicable]
Section 2 NOTICE TO BIDDERS
[Insert Notice to Bidders Here]
NOTICE TO BIDDERS
Sealed bids addressed to the City of Tyler, Texas, will be received in the Purchasing Office, 304 North Border, Tyler, Texas 75702, Attention: Purchasing Manager, until 2:00 p.m., on Tuesday, August 11th, 2026, and will be publicly opened immediately afterwards in the City Council Chambers, 212 North Bonner, City Hall, 2nd Floor.
Sealed bids will be for furnishing all necessary materials, equipment, superintendence, and labor for construction of the following being improvements for the City of Tyler, Texas:
City of Tyler Bid Number: 26-032 Project Name: 2026 Brick Streets Repair Project
The project includes: Brick Street Repairs, bricks cleaned and stored, compacted and stabilized subgrade, flowable fill base, buffer sand, and brick surface layers, curb and gutter replacement, driveway approach replacement, headers, valley gutters, and other miscellaneous items.
Forms of proposal, contract, bonds, insurance, plans and specifications may be obtained at the office of the City Engineer, Water Utilities Administrative Office, 511 West Locust Street, Tyler, Texas, upon deposit of $35.00 per set. The deposit is non-refundable. Mailing costs will not be refunded. Electronic plans, bid tab, and specifications (PDF) are available upon emailed request.
Email requests must be sent to cbain@tylertexas.com. Bid documents are also available on
CIVCAST.
A Pre-Bid Conference will be held on Tuesday, August 4, 2026 at 2:00 pm, located at Water Utilities Administrative Office, 511 West Locust Street, Tyler, Texas, in the Tyler Water Utilities Conference Room. The Pre-Bid Conference will be non-mandatory. Questions concerning this project shall be directed to Cody Bain, P.E., (903) 531-1135.
Please Note: In accordance with House Bill 1295, for certain contracts entered into on or after January 1, 2016, the successful bidder must submit a Certificate of Interested Parties (Form 1295) at the time the signed contract is submitted to the CITY. See Section 19, “Certificate of Interested Parties”.
City of Tyler, Edward Broussard, City Manager
Publish: Tyler Morning Telegraph, Tyler, Texas
PUBLICATION DATES:
First (1st) Publication: Friday, July 24, 2026 Second (2nd) Publication: Friday, July 31, 2026
Section 3 INSTRUCTIONS TO BIDDERS
3.1 PROPOSAL FORM
The CITY will furnish bidders with proposal forms which state the general location and description of the contemplated Work, an approximate estimate of the materials to be furnished and/or Work to be done and upon which bid prices are asked, and the time in which the Work is to be completed. The Proposal form will provide a space for entering the amount of proposal guaranty.
3.2 EXAMINATION OF PLANS, SPECIFICATIONS AND SITE OF THE WORK
Bidders are advised that the plans, specifications, and other documents on file with the CITY will constitute all the information furnished by the CITY. Bidders are required, prior to submitting any bid package, to read the specifications, Proposal, contract and bond forms carefully, to visit the site of the Work, to examine carefully local conditions, to inform themselves by their independent research, tests, and investigations of the difficulties to be encountered and assess for themselves the accessibility of the Work and all attending circumstances affecting the cost of doing the Work and time required for its completion, and obtain all information required to make an intelligent bid. No information given by the CITY or any officials thereof, other than that shown on plans and contained in the specifications, Proposal and other documents, will be binding upon the CITY.
Bidders must rely exclusively upon their own estimates, investigations, tests, and other data which are necessary for full and complete information upon which the bid may be based. It is mutually agreed that submission of a bid package is evidence that the bidder has made the examinations, investigations, and tests required herein. Should a bidder find discrepancies in, or omissions from the plans, specifications or other documents, or be in doubt as to their meaning, the bidder should notify the CITY immediately and obtain a clarification prior to submitting any bid package.
Claims for additional compensation due to variations between conditions actually encountered in construction and as indicated by the plans will not be allowed.
3.3 PRE-BID CONFERENCE
If a Pre-Bid Conference is scheduled, it will be set a minimum of four (4) working days prior to the bid opening time. If attendance at the Pre-Bid Conference is mandatory due to the size or nature of the project, bidders must attend to ensure their understanding of the project scope as well as the CITY’S bidding and contracting requirements; a bidder’s absence from a mandatory Pre-Bid Conference shall result in disqualified from bidding.
3.4 ADDENDA
Should a bidder find discrepancies in, or omissions from the plans or specifications or other contract documents, or should he be in doubt as to their meaning, he should at once notify the Project Designer in order that a written addendum may be sent to all bidders. Bidders desiring further information or interpretations must make request for such information to the Project Designer prior to four (4) working days before the time of the bid opening. The person submitting the request will be responsible for its prompt delivery. Appropriate clarification and addenda will be issued at least forty-eight (48) hours prior to the time of the bid opening. Answers to all such requests will be given in writing to all bidders, in addendum form, and all addenda will be bound with and made a part of the contract documents. No other explanation or interpretation will be considered official or binding. Any addenda issued will be mailed, faxed or delivered to each person to whom a set of such documents has been furnished and receipt of same must be acknowledged by noting the addendum number and date of receipt of said addenda in the space provided on the Proposal form. The proposal, as submitted by the CONTRACTOR, will be so constructed as to include any addenda if such are issued by the Project Designer (prior to forty-eight (48) hours of the bid opening).
3.5 QUANTITIES IN PROPOSAL FORM
The quantities of the Work and materials set forth in the Proposal form or on the plans approximately represent the Work to be performed and materials to be furnished, and are for the purpose of comparing the bids on a uniform basis. Payment will be made by the CITY to the CONTRACTOR only for the actual quantities of Work performed or materials furnished in accordance with the plans and specifications, and it is understood that the quantities may be increased or decreased as provided for in Section 16.13.2 "Estimated Quantities", without in any way invalidating the bid prices.
3.6 UNIT PRICES
Unit prices written in words will be the basis for the award of the proposal. Unit prices are used by the CITY in scheduling interim payments to the CONTRACTOR. The unit price written in words, multiplied by the estimated bid quantity, will be used to determine the item extension and the actual total bid price. All mathematical errors found when the bids are tabulated will be corrected by the CITY, and the bids will be revised to reflect the correct item extension and/or total bid price. The corrected total bid amount will then become the official proposal for that CONTRACTOR. All bidders will be notified of any errors in their bid, and will be notified and given the opportunity to review the official bid tabulation prior to award recommendation.
The unit prices shown in the proposals must be balanced to reflect actual cost of the item, including a fair and reasonable cost for overhead and profit. If the unit price is considered to be unbalanced, the CITY reserves the right to reject the entire proposal. If required by the CITY, the CONTRACTOR must provide documentation to substantiate that the unit prices reflect fair and reasonable material costs, labor costs, overhead and profit, as determined by industry standards.
3.7 PROJECT COMPLETION TIME
Project completion time will be established according to the requirements of the Proposal. The amount bid for the contract will adequately represent the effort required to complete the project within the specified time on the Proposal.
3.8 ASSIGNMENT AND SUBCONTRACTING
The CONTRACTOR will retain full control and will give personal attention to the fulfillment of this contract and will not assign by Power of Attorney or otherwise without the written consent of the CITY.
The CONTRACTOR may utilize the services of specialty subcontractors on those parts of the Work which, under normal contracting practices, are performed by specialty subcontractors.
However, the CONTRACTOR shall not employ any subcontractor against whom the CITY may have a reasonable objection.
The CONTRACTOR must perform, with the CONTRACTOR’S own forces, at least thirty percent (30%) of the total contract, based on unit bid prices, unless this requirement is waived by the CITY.
Subcontracting any portion or feature of the Work, or materials required in the performance of this contract, shall not relieve the CONTRACTOR from his full obligations to the CITY, as provided by this AGREEMENT. The CONTRACTOR will be fully responsible to the CITY for the acts and omissions of subcontractors, and of persons either directly or indirectly employed by them, as the CONTRACTOR is for the acts and omissions of persons directly employed by the
CONTRACTOR.
The CONTRACTOR must cause appropriate provisions to be inserted in all subcontracts relative to the Work, to bind subcontractors to the CONTRACTOR by the terms of the contract documents, insofar as applicable to the Work of the subcontractors, and to give the CONTRACTOR the same power as regards to terminating any subcontract that the CITY may exercise over the CONTRACTOR under any provision of the contract documents.
In the event that a portion of the Work is subcontracted, the CITY will not recognize such subcontractors in supervision of the construction or in making monthly payments for Work accomplished. The CONTRACTOR shall be primarily responsible for all Work, and shall receive all payments. Nothing contained in this contract shall create any contractual relation between any subcontractor and the CITY.
3.9 OUT-OF-STATE CONTRACTORS
All out-of-state CONTRACTORS are required to submit with their bid package a copy of any law from their state of residence which would give a preference to CONTRACTORS domiciled in their state over out-of-state CONTRACTORS.
3.10 NON-DISCRIMINATORY EMPLOYMENT
The City Council adopted on October 21, 1975, a Resolution requiring non-discriminatory employment by persons who contract with the CITY to supply labor, materials, goods, or services to the CITY. A copy of the latest City Manager’s Policy Statement On Equal Employment Opportunity shall be included in the contract documents and is on file in the City Clerk's Office.
The CONTRACTOR and CONTRACTOR’S subcontractors or agents must not engage in any discriminatory employment practices.
3.11 WAGE RATES
Wage rates for the various classes of labor involved in the project shall be not less than those prevailing for each class of labor in this area. Time and one-half shall be paid all workers, whether skilled or semi-skilled, for all labor done in excess of forty (40) hours weekly. The inclusion, if any, of a schedule of minimum wage does not relieve the CONTRACTOR from responsibility to comply with any State or Federal wage law that may be applicable.
The CONTRACTOR shall deduct from all workers’ wages social security, withholding tax, and all deductions required by law and shall not make any deductions other than those required or authorized by law.
3.12 PROPOSAL GUARANTY (BID BOND)
Bidders must submit an acceptable Cashier's or Certified Check upon a national or state bank in the amount of five percent (5%) of the total maximum bid payable without recourse to the City of Tyler, Texas, or an acceptable Bid Bond in the same amount from a reliable surety company, registered by the State Board of Insurance to conduct business in the State of Texas, and acceptable according to the most recent list of the companies holding Certificates of Authority from the Secretary of the Treasury of the United States, shown on the Treasury List, as a guarantee that the bidder will enter into a contract. The proposal guaranty must be enclosed in the same envelope containing the bid package. Bid packages without the required enclosed check or Bid Bond will not be considered. All proposal guaranties will be returned un-negotiated, after the bids are opened, except those of the three (3) lowest bidders, which the CITY may elect to hold until the successful bidder has executed the contract.
3.13 PREPARATION OF PROPOSAL
The bidder has the option of either submitting the proposal on the forms furnished by the CITY in the contract documents, or submitting a computer print-out proposal in lieu of the CITY’S Proposal form.
Preparation of Proposal on forms supplied by CITY:
All blank spaces in the form must be correctly filled in and the bidder must state the prices, typed or written in ink, both in words and numerals, for which the bidder proposes to do the Work contemplated or furnish the material required. It will be the bidder’s responsibility to ensure that all unit prices written in words will be clear and legible. Illegibly written unit prices will result in the proposal being rejected and will not be considered as an irregularity of the proposal. In case of a discrepancy between the unit price written in words, the unit price written in figures, and/or the item extension written in figures, the unit price written in words will govern.
The Total Bid Price must be shown in both numbers and words.
Acknowledgement of all addenda, typed name and title of person signing proposal, authorized signature and date shall also be included.
Preparation of Proposal on computer print-out supplied by bidder:
The computer print-out proposal shall be in spreadsheet format, using software of the bidder’s selection. As a minimum, a computer print-out must include the following information: Bid Item Number, Approximate Quantities, Unit of Measure, Bid Item Description, Written Unit Price, Unit Bid Price, Extended Price (Amount), as well as Total Bid Price. Line items must be in the same order as on the CITY’S Proposal form (see example below).
Bid Item Quantity Unit
Item Description and Written Unit Price
Unit Price Amount
The Total Bid Price must be shown in both numbers and words.
Acknowledgement of all addenda, typed name and title of person signing proposal, authorized signature and date shall also be included.
All computer print-out proposals shall be delivered, in hard copy (i.e. no fax or e-mail submittals) to the designated location, at or before the designated time and include the following certification:
[Insert bidder’s name here] certifies that the unit prices shown on this complete computer print-out for all the bid items and alternates contained in this proposal are the unit prices intended and that its bid will be tabulated using these unit prices and no other information from this print-out. [Insert bidder’s name here] acknowledges and agrees that the total bid amount shown will be read as its total bid and further agrees that the official total bid amount will be determined by multiplying the unit bid prices shown in this print-out by the respective estimated quantities shown in the City of Tyler issued proposal and totaling all of the extended amounts.
Typed Name:
Title:
Signature:
Date:
3.14 SIGNATURE REQUIREMENTS OF PROPOSAL
1. If a proposal is submitted by an individual, the proposal must be signed by the individual or the individual's duly authorized agent.
2. If the proposal is submitted by a firm, association, partnership or company, the name and address of each member must be given and the proposal signed by a member of the firm, association, partnership, company or person duly authorized.
3. If the proposal is submitted by a corporation, the company or corporate name and address must be given and the proposal signed by an official or duly authorized agent and sealed with the corporate seal. Powers of attorney authorizing agents or others to sign proposals must be properly certified and must be in writing and submitted with the proposal.
3.15 FILING OF BID PACKAGES
No bid package will be considered unless it is received in the Purchasing Office, 304 North Border, Tyler, Texas 75702, Attention: Purchasing Manager within the time limit for receiving bid packages as stated in the advertisement. Each bid package must be in a sealed envelope, plainly marked with the word "proposal", and the project name and time and date the bid package is to be opened as designated in the Notice to Bidders.
The bid package must consist of the following items to be considered complete:
1. Acknowledgment of all addenda
2. Proposal
3. Bid Bond
Any bid package received without each of the required items may be rejected and may not be read at the bid opening.
CONTRACTORS building public streets and drainage, water and/or sewer facilities (not including specialty work such as pipeline camera inspection, interior lining of pipes, etc.) shall have a fully executed Contractor’s Qualification Statement on file with the CITY prior to bid opening or include it as part of the CONTRACTOR’S bid package. Forms are available for download at https://www.cityoftyler.org/government/departments/engineering-services/ engineering-and-construction-standards. CONTRACTORS performing any other type of work
(i.e., not public streets, drainage or utilities) are not required to have a Contractor’s Qualification Statement on file or include it as part of the bid package unless required by a City Operational Department. Other information from the CONTRACTOR such as company history, relevant work experience, project references, etc. may be required in lieu of the Contractor’s Qualification Statement.
3.16 WITHDRAWING OR MODIFYING BID PACKAGES
A bidder may withdraw a bid package provided a written request to do so is in the hands of the official indicated in the Notice to Bidders by the time set for opening of bid packages. A bidder may change the unit prices in the proposal provided a written request to do so is in the hands of the Purchasing Agent prior to the time set for opening of bid packages. Requests by telephone or FAX for changes in bid prices or for withdrawal of bid packages will not be considered. No bid packages will be withdrawn within sixty (60) calendar days after the bid opening.
3.17 OPENING BID PACKAGES
The bid package filed with the Purchasing Agent will be opened at the time stated in the Notice to Bidders and publicly read aloud, and will thereafter remain on file with the CITY. Bidders or their agents are invited to be present.
3.18 IRREGULAR PROPOSALS
Proposals will be considered irregular if they show any omissions, alterations of form, additions, or conditions not called for, unauthorized alternate bids, or irregularities of any kind. However, the CITY reserves the right to waive any irregularities and to make the award in the best interests of the CITY.
3.19 DISQUALIFICATION OF BIDDERS
Bidders may be disqualified and their bid package not considered for any of the following specific reasons:
1. Reason to believe collusion exists among the bidders.
2. The bidder is in arrears on any existing contract or has defaulted on a previous contract.
3. The bidder is interested in any litigation against the CITY.
4. Uncompleted Work which in the judgment of the CITY will prevent or hinder the prompt completion of additional Work if awarded.
5. Poor performance in the execution of Work under previous contracts.
6. The bidder is determined to have an unacceptable safety record.
7. Incomplete bid packages (see Section 3.15, “Filing of Bid Packages”).
8. Proposals in which prices are obviously unbalanced (see Section 3.6, “Unit Prices”).
9. Proposals which are irregular (see Section 3.18, “Irregular Proposals”).
10. CONTRACTORS not qualified to perform this Work, as determined by the CITY.
11. CONTRACTOR is not on CITY’S Approved Contractors List or Contractor’s
Qualification Statement is not on file with the CITY prior to bid opening nor included as part of the bid package.
12. Failure to have an authorized agent of the bidder at a Pre-Bid Conference, when attendance is mandatory.
3.20 CONSIDERATION OF PROPOSALS
After bid packages are opened, the proposals will be tabulated for comparison on the basis of the bid prices and quantities shown in the proposal.
3.21 CITY MAY REJECT BID PACKAGES
Until final award of the contract, the CITY reserves the right to reject any or all bid packages, to waive technicalities, and to re-advertise for new bids, or proceed to do the Work otherwise in the best interests of the CITY (TEX. LOC. GOV’T CODE ANN. §252.043(f); §271.027(a)).
3.22 AWARD OF CONTRACT
After all submitted bid packages have been opened and read aloud, the proposals submitted will be reviewed and tabulated in order from low to high bid. Upon request, a copy of the tabulation will be forwarded to each bidder submitting a qualified bid package.
The award of the contract, if it is awarded, will be to the lowest responsible bidder in accordance with the General Conditions. The tabulated bids, along with the recommendation of the Project Designer shall be placed on the agenda of a regularly scheduled City Council Meeting within sixty
(60) calendar days of bid opening.
If the contract is awarded, it will be awarded to the lowest responsible bidder, but the contract may not be awarded to a bidder who is not the lowest bidder unless before the award, the CITY gives notice to each lower bidder of the proposed award and each lower bidder is given an opportunity to appear before the City Council, or the designated representative of the City Council, and present evidence concerning the bidder’s responsibility. TEX. LOC. GOV’T CODE ANN. § 271.027.
Notification of the City Council action will be issued to the affected bidders.
3.23 RETURN OF BIDDER’S BOND
As soon as bid prices have been tabulated for comparison of bids, the CITY may, at its discretion, return the proposal guaranties accompanying the bid packages which, in its judgment, would not be considered in the award; all other proposal guaranties will be retained by the CITY until the required contract and bonds have been executed, after which they will be returned. No proposal guaranties will be returned until at least two (2) calendar days have elapsed from time of opening bid packages.
3.24 SUBMISSION OF POST BID INFORMATION
Upon request by the CITY, the selected bidder must, within seven (7) calendar days thereafter, submit the following:
1. A designation of the Work to be performed by the bidder with the bidder’s own forces.
2. A list of names of the subcontractors or other persons or organizations (including those who are to furnish materials or equipment fabricated to a special design) proposed for such portions of the Work as may be designated in the bidding documents or, if no portions are so designated, the names of the subcontractors proposed for stated portions of the Work.
The bidder will be required to establish to the satisfaction of the Project Designer and the CITY the reliability and responsibility of the proposed subcontractors to furnish and perform such portions of the Work. Prior to the award of the contract, the Project Designer will notify the bidder in writing if either the CITY or the Project Designer, after due investigation, has reasonable and substantial objection to any person or organization on such list. Subcontractors and other persons and organizations proposed by the bidder and accepted by the CITY and the Project Designer must be used on the Work for which they were proposed and accepted and will not be changed except with the written approval of the CITY and the Project Designer.
3.25 CONTRACT BONDS
The CONTRACTOR is required, pursuant to TEX. GOV’T CODE ANN. § 2253.021, and/or the Standard Form of Agreement to execute all bonds before commencing the work. The contract shall not be in effect until CONTRACTOR executes the AGREEMENT and files with the CITY a good and sufficient Statutory Performance and Maintenance Bond and Payment Bond (when applicable) or Payment Bond on standard forms and in the amount equal to one hundred percent (100%) of the total amount of the contract. Such bonds are furnished by the CONTRACTOR and approved by the CITY.
A Performance and Maintenance Bond and Payment Bond shall be required for contract amounts in excess of one hundred thousand dollars ($100,000).
Payment Bond shall be required for all projects regardless of value.
Within fifteen (15) calendar days after written notification of the award of the contract, the CONTRACTOR shall submit Statutory Performance and Maintenance Bond and Payment Bond (when applicable) or Payment Bond to CITY on standard forms as required by the
AGREEMENT.
3.26 INSURANCE
CONTRACTOR agrees, at its sole expense, to maintain on a primary basis during the life of the Contract and the performance of Work, required insurance coverages, limits, and endorsements.
Insurance required by the AGREEMENT for the CITY as additional insured shall be primary insurance and not contributing with any other insurance available to CITY.
CONTRACTOR agrees to provide evidence of the required coverages at execution of contract.
In the event the CONTRACTOR performs any site work, other than testing, then all the insurance required will need to be evidenced prior to commencement of said site work.
3.27 EXECUTION OF CONTRACT
The person(s), partnership, company, firm, association or corporation to whom a contract is awarded must, within fifteen (15) calendar days after receipt of the contract, sign the necessary agreements entering into the required contract with the CITY. No contract will be binding on the CITY until it has been approved by the City Attorney, executed by the City Manager, attested by the City Clerk, and delivered to the CONTRACTOR.
3.28 FAILURE TO EXECUTE CONTRACT
The failure of the bidder to execute the required bonds or to sign the required contract within fifteen (15) calendar days after receipt of the contract will be considered by the CITY as an abandonment of the proposal and the CITY may annul the award. By reason of the uncertainty of the market prices of materials and labor, and it being impracticable and difficult to determine accurately the amount of damages accruing to the CITY by reason of said bidder's failure to execute said bonds and contract within said fifteen (15) calendar days, the proposal guaranty accompanying the proposal will be the agreed amount of damages which the CITY will suffer by reason of such failure on the part of the bidder, and will thereupon immediately be forfeited to the
CITY. The filing of a bid package will be considered as an acceptance of this provision.
3.29 BEGINNING OF WORK
The CONTRACTOR will not begin Work until notified in writing by the CITY to do so.
Section 4 POLICY STATEMENT ON EEO
Section 5 PROPOSAL
[Insert Proposal Here]
CITY OF TYLER, TEXAS – CIP CONTRACT REVISION DATE: 03.22.2017
Page 5-1 of 5-7
Section 5 PROPOSAL
Proposal for CIP Contract to
The City of Tyler, Texas
Date of Bid: _______________
The undersigned, as bidder, in compliance with CITY’S Notice To Bidders for construction of:
City of Tyler Bid Number: 26-032 Project Name: 2026 Brick Street Repair Project for the City of Tyler, Smith County, Texas, declares that the only person or parties interested in this proposal as principals are those named herein, that this proposal is made without collusion with any other person, firm, or corporation, that he has carefully examined the form of contract, Instructions to Bidders, specifications, and the plans therein referred to, and has carefully examined the locations, conditions, and classes of materials of the proposed work; and agrees that he will provide all the necessary labor, machinery, tools, apparatus, and other items incidental to construction, and will do all the work and furnish all the materials called for in the contract and specifications in the manner prescribed therein and according to the requirements of the Engineer as therein set forth, for the following unit prices.
It is understood that the following quantities of work to be done at unit prices are approximate only, and are intended principally to serve as a guide in evaluating bids.
It is further agreed that the following quantities of work to be done at unit prices and materials to be furnished may be increased or decreased as may be considered necessary, in the opinion of the Engineer, to complete the work fully as planned and contemplated, and that all quantities of work, whether increased or decreased are to be performed at the unit prices set forth below except as provided for in the specifications.
It is further agreed that lump sum prices may be increased by change order to cover additional work ordered by the Engineer, but not when on the plans or required by the specifications, or in accordance with the General Conditions and Special Conditions and requirements. Similarly, they may be decreased to cover deletion of work so ordered.
It is further agreed that the unit and lump sum prices shall be shown in words and figures for each item listed in this proposal, and in the event of discrepancy, the words shall control, and should the bid price on any item be completely omitted, the proposal will be considered incomplete, and the proposal will be disqualified. It is understood and agreed that the work is to be completed in full either:
1) ☐ within Enter amount using words, (Enter amount using numbers) Choose an item after the date specified in the written Notice to Proceed, or
2) ☒ on or before the mandatory completion date of January 29, 2027, subject to such extensions of time as are provided by General Conditions.
Page 5-2 of 5-7
Accompanying this proposal is a ☐ Bid Bond, ☐ Certified Check, or ☐ Cashier's Check payable to the City of Tyler for:
AMOUNT:
Dollars and Cents
The undersigned certifies that the bid prices contained in this proposal have been carefully checked and are submitted as correct and final.
Receipt is hereby acknowledged of the following addenda to the Contract Documents:
ADDENDUM NO. 1 Received
ADDENDUM NO. 2 Received
ADDENDUM NO. 3 Received
ADDENDUM NO. 4 Received
ADDENDUM NO. 5 Received
Bidder Street Address
Signature City, State, Zip
Printed Name Telephone Number
Title Date
Page 5-3 of 5-7
BASE BID ITEMS:
Utility Repairs
Bid Item
Quantity Unit Item Description and Written Unit Price
Unit Price
Amount
50-A 10 SY Block Sodding, in place, per square yards, for
Dollars
Cents
50-B 2
CY Furnish and Place Topsoil (4''), in place, per square yards, for
Dollars
Cents
132 25 CY Select Fill for Undercutting and Replacing Unstable Subgrade, 8-inch lifts, in place, as per plans and specifications, per cubic yard, for
Dollars
Cents
700.1-S 180 SY Brick Street Repair w/ flowfill base, small area (< 25 SY), in place, as per plans and specifications, per square yard, for
Dollars
700.1-L 250
SY Brick Street Repair w/ flowfill base, large area (= or > 25 SY), in place, as per plans and specifications, per square yard, for
Dollars
Cents
500 1 LS Mobilization for Base Bid Items, in place, as per plans and specifications, per lump sum, for
Dollars
Cents
502 1 LS Barricades, signs, and traffic control, in place (Base Bid), as per plans and specifications, per lump sum, for
Dollars
Page 5-4 of 5-7
Bid Item
Quantity Unit Item Description and Written Unit Price
Unit Price
Amount
529 100 LF Remove & Replace Curb & Gutter as per plans and specifications in place, per linear foot, for
Dollars
Cents
530-D 40 SY Concrete Driveway 6'' Approach remove & Replace (Class A) as per plans & specifications in place per square yard, for
Dollars
Cents
530-C 30 LF Concrete Header 6'' x 12'' as per plans and speciation's in place per square yard, for, Dollars
Cents
530-V 10 SY Concrete Valley gutter, (Class C or P) as per plans and specifications, in place, per square yard, for
Dollars
Cents
479-A 7 EA Adjust elevation and install concrete pad around existing sanitary sewer manholes, in place, as per plans and specifications, per each, for
Dollars
Cents
479-B 6 EA Adjust elevation and install concrete pad around existing water valve boxes, in place, as per plans and specifications, per each, for
Page 5-5 of 5-7
Oakwood St. and Spring Ave. Rehab
Bid Item
Quantity Unit Item Description and Written Unit Price
Unit Price
Amount
132 60 CY Select Fill for Undercutting and Replacing Unstable Subgrade, 8-inch lifts, in place, as per plans and specifications, per cubic yard, for
Dollars
Cents
351-A 20 TON Flexible Pavement Repair (Type D), in place, as per plans and specifications, per ton, for
Dollars
Cents
360-B 1,475 SY Construct 8” reinforced concrete pavement base with integrated header (4,000- psi HES, with #4 bars @ 18” o.c.), in place, as per plans and specifications, per square yard, for
Dollars
528-B 1,475
SY Brick placement with sand cushion (Rehab Areas), in place, as per plans and specifications, per square yard, for
Dollars
Cents
530-V 20 SY Concrete Valley gutter, (Class C or P) as per plans and specifications, in place, per square yard, for
Page 5-6 of 5-7
Callout Work Order (Additional Charges)
Bid Item
Quantity Unit Item Description and Written Unit Price
Unit Price
Amount
500-C 1 LS Mobilization for each Callout Work Order, in place, as per plans and specifications, per lump sum, for
Dollars
Cents
502-C 1 LS Barricades, signs, and traffic control (for each Callout Work Order), in place, as per plans and specifications, per lump sum, for
Dollars
Cents
800 1 LS Allowance for construction contingency and callout work (used at City’s discretion), as per plans and specification, per lump sum, for
$150,000.00 $150,000.00
Page 5-7 of 5-7
BID SUMMARY
TOTAL BID
and Cents
STATEMENT OF MATERIALS AND OTHER CHARGES
For purposes of complying with TEX. TAX CODE ANN. Title 2., Subtitle E., Chapter 151, Subchapter C. § 151.056; Subchapter H. § 151.301, § 151.309, § 151.311, the CONTRACTOR agrees that the charges for any material incorporated into the project in excess of the estimated quantity provided for herein will be no less than the invoice price for such material to the
CONTRACTOR.
Value of Materials Incorporated Into the Project: $ Value of All Other Charges: $ *Total: $
* This statement may be submitted with Proposal and the total must agree with the total bid figure shown in the Bid Summary section above.
Section 6 BID BOND Check Here if this Section is NOT Used ☐
THE STATE OF TEXAS §
§ BID BOND
COUNTY OF SMITH §
THAT, [contractor], as PRINCIPAL, and [surety], as SURETY, acknowledge their indebtedness and are held and firmly bound unto the City of Tyler (CITY), Texas in Smith County, as OBLIGEE, in the amount of [insert figure using written words], ($ ) [insert numerical figure] payable to the City of Tyler, Texas for the payment of which, the said PRINCIPAL (Contractor) and SURETY bind themselves, and their heirs, administrators, executors, successors, legal representatives, and assigns, jointly and severally, firmly by these presents.
PRINCIPAL (Contractor) is about to submit to OBLIGEE (City) a bid or proposal for:
in accordance with plans and specifications filed in OBLIGEE’S (City’s) office and under the Request for Quotation (RFQ) / Request for Proposal (RFP) / Invitation to Bid therefor.
NOW THEREFORE:
THE CONDITION OF THIS OBLIGATION IS THAT IF:
1) the bid or proposal is rejected, or
2) the bid or proposal of PRINCIPAL (Contractor) is accepted; and
a. the contract for the work is awarded to PRINCIPAL (Contractor) by OBLIGEE (City),
b. PRINCIPAL (Contractor) enters into a written contract in the form of contract provided in these contract documents (properly completed in accordance with the bid),
c. PRINCIPAL (Contractor) furnishes a Performance and Maintenance Bond for the performance of the work as required by law and/or the AGREEMENT,
d. PRINCIPAL (Contractor) furnishes a Payment Bond for the payment of all persons performing labor or furnishing materials in connection therewith as required by law and/or the AGREEMENT, and
e. PRINCIPAL (Contractor) in all other respects performs the agreement created by the acceptance of the bid, then this obligation will be null and void; otherwise, subject to the following limitation, it will remain in full force and effect.
The limitation referred to above is that surety, in any event, will not be liable for a greater amount than the difference between the amount of principal's bid or proposal and the lowest amount in excess of that bid or proposal for which CITY may be able to award the contract within a reasonable time.
The SURETY, for value received, hereby stipulates and agrees that the obligations of said SURETY and its Bond shall be in no way impaired or affected by any extension of the time within which the OBLIGEE (City) may accept such bid; and said SURETY does hereby waive notice of any such extension.
I (WE) CERTIFY that the SURETY is registered by the State Board of Insurance to conduct business in the State of Texas, and acceptable according to the latest list of companies holding Certificates of Authority from the Secretary of the Treasury of the United States, shown on the Treasury List.
I (WE) CERTIFY that the SURETY has reviewed the financial condition of the PRINCIPAL and the PRINCIPAL’S qualification to perform the work required by this project.
IN WITNESS WHEREOF the PRINCIPAL (Contractor) and SURETY have hereunto set their hands and seals, and such of them as are corporations have caused their corporate seals to be hereunto affixed and these presents to be signed by their proper officers, the day and year set forth below.
Signed this day of , 20 .
BOND NUMBER:
PRINCIPAL (Contractor) SURETY
Printed Name of Principal Printed Name of Surety
Physical Address Physical Address
Mailing Address Mailing Address
Telephone Number Telephone Number
By: By:
Signature Signature
Title Title
SURETY’S SEAL:
***** NOTE *****
If signed by an Attorney-in-Fact a copy of the Power of Attorney shall be attached, or
If signed by an officer of the Surety Company a certified extract from the by-laws showing that this person has authority to sign obligation shall be attached.
Section 7 STANDARD FORM OF AGREEMENT
THE STATE OF TEXAS § STANDARD FORM OF AGREEMENT
§ FOR
§ CITY OF TYLER
COUNTY OF SMITH § CAPITAL IMPROVEMENT PROJECT (CIP)
THIS AGREEMENT, made and entered into this day of , 20 , by and between the City of Tyler, Texas, of the County of Smith and State of Texas, hereinafter termed "CITY", acting through the City Manager, and [insert name of Contractor], of the City of , the County of , the State of Texas, hereinafter termed "CONTRACTOR".
THAT FOR AND IN CONSIDERATION of the payments and mutual covenants set forth in this Standard Form of Agreement and under the conditions expressed in the contract documents and in the bond bearing even date herewith, CONTRACTOR hereby agrees with CITY as follows:
WITNESSETH:
7.1 DESCRIPTION OF WORK
CONTRACTOR will perform all the work required by the contract documents and said work shall be done under the supervision of the representative of the CITY. The work will consist of the completion of construction of certain improvements and all extra work in connection therewith, in accordance with the prices and conditions stated in the contract documents and at CONTRACTOR'S cost and expense to furnish all materials, supplies, machinery, equipment, tools, superintendence, labor, insurance, and other accessories and services necessary to complete the said construction.
7.1.1 If the Project is a “civil works” project, as defined by Sec. 2269.351 of Tex. Gov. Code Ann., then the PROCEDURE FOR CORRECTING CONSTRUCTION DEFECTS herein does NOT apply. “Civil works” projects are those related to roads, streets, bridges, utilities, water supply projects, water plants, waste water plants, water distribution and wastewater conveyance facilities, desalination projects, wharves, docks, airport runways and taxiways, storm drainage, flood control projects and transit projects.
7.1.2 If the Project is related to “public works” projects or construction contracts affecting City-owned buildings, then this contract IS SUBJECT TO ADDITIONAL PROVISIONS FOUND IN the PROCEDURE FOR CORRECTING CONSTRUCTION DEFECTS herein.
“Public Works” is defined by Tex. Gov. Code Ann., Sec. 2269.001 (6) as a contract for constructing, altering, or repairing a public building or carrying out any public work.
7.1.3 If the PROCEDURE FOR CORRECTING CONSTRUCTION DEFECTS is applicable and there is a conflict between any other clause in this Agreement and the PROCEDURE, the PROCEDURE shall control.
7.2 CONTRACT DOCUMENTS
The contract documents constitute the entire AGREEMENT between the CITY and CONTRACTOR, and all are as fully a part of the AGREEMENT as if attached to or repeated in this Standard Form of Agreement.
The contract documents are as follows:
Notice to Bidders, All addenda issued prior to execution of this Standard Form of Agreement, Instructions to Bidders, CITY Policy Statement on Equal Opportunity Employment, Proposal, Bid Bond and Special Bonds (if any), Standard Form of Agreement, Statutory Performance and Maintenance Bond and Payment Bond (if applicable), Payment Bond, Certificate(s) of Insurance, Endorsements, Contractor’s Affidavit of Bills Paid and Waiver and Lien Releases, Procedure for Correcting Construction Defects (if applicable) General Conditions, Special Conditions, CITY specifications governing water and/or sanitary sewer installation within the CITY titled City of Tyler Standard Specifications, Trench Safety Systems, Plans and other drawings and printed or written explanatory matter thereof, and All field orders and change orders issued after execution of this Standard Form of
Agreement.
In case of conflict between any of the contract documents, priority of interpretation shall be in the following order:
1. Signed Standard Form of Agreement,
2. Performance and Maintenance Bond and Payment Bond (if applicable) and/or Payment
Bond,
3. Special Bonds (if any),
4. Proposal,
5. Special Conditions,
6. Special Specifications,
7. City of Tyler Standard Specifications,
8. Technical Specifications,
9. Plans, and
10. General Conditions.
7.3 TIME OF COMMENCEMENT AND COMPLETION
CONTRACTOR hereby agrees to commence work within ten (10) calendar days after the date specified in the Notice to Proceed, to diligently pursue the work without extended interruption and to complete in full the same either:
1) ☐ within Enter amount using words, (Enter amount using figures) Choose an item after the date specified in the written Notice to Proceed, or
2) ☒ on or before the mandatory completion date of January 29, 2027,…