2026_0914_BFHQ- Meeting Agenda 003~1.pdf
PDF 121 KB Posted
- Attached to
- General Contractor Prequalification Services â? ? Town of Boylston New Fire Headquarters
- Solicitation number
- BD-26-1967-BOYL1-BOYL1-133378
- Issued by
- Massachusetts
About this file
This is a project meeting agenda for the Town of Boylston Fire Station Headquarters project, involving Colliers Project Leaders as the project management entity. The document outlines the procurement schedule for general contractor prequalification and bidding services for the construction of a new fire headquarters facility. Interested firms must submit qualifications through COMMBUYS by September 24, 2026 at 2:00 PM. Following qualification submissions, the Town will conduct owner and general contractor reviews with a prequalification committee through November 6, 2026. The RFP with bid documents will be issued to approved bidders on November 13, 2026, with a pre-bid conference scheduled for November 19, 2026. General contractor bids are due January 8, 2026, with an anticipated Notice to Proceed on or about January 19, 2026. The schedule allows for clarifications during November 5-6, 2026, with the last day for questions set for November 30, 2026. Committee approvals are required to approve prequalified bidders, and the Town recommends maintaining at least 2-3 weeks between bidder approval and bid submission to provide contractors adequate time to price the work.
The document does not contain detailed pricing terms, set-aside information, incumbent contractor details, or specific funding amounts and sources. The Town of Boylston reserves the right to reject any or all responses, waive informalities, and accept the submission determined to be in the best interest of the agency. All updates, addenda, and procurement information are available through COMMBUYS, and interested firms are responsible for monitoring that platform for changes throughout the procurement process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Boylston FDHQ RFQ-General-Contractor-Prequalification~1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MEETING AGENDA
1 Colliers Project Leaders | Town of Boylston: Fire Station Headquarters
Town of Boylston Fire Station Headquarters
Project Meeting 003
Date: September 14, 2026 Location: Teams Remote
Time: 1:00 pm Phone #: +1 862-294- 3398,,538821424#
Code: Meeting ID: 288 282 276 209 Passcode:
WgykRC
Schedule for 2026 – Review Bid Due Deadlines
Milestone Recommended Date
Owner Issues Filed Sub-bid/General Contractor RFQ September 11, 2026
FSB/GC submits qualifications September 24, 2026
Owner/GC review and evaluate w/ Prequal Committee September 25–November 6, 2026
Clarifications November 5, 6 2026
RFP Bid documents issued to approved bidders November 13, 2026
Pre-bid Conference November 19, 2026
Bids due December 6 18 2026
Last Day for questions November 30, 2026
Addendum 1 Issued December 2, 2026
Filed Sub-bids Issued to General Contractor December 4, 2026
Addendum 2 Issued (if required) December 9, 2026
Filed Sub-bids Due December 18, 2026
General Contractor Bids Due January 8, 2026
NTP (on or about) January 19, 2026
• Committee approvals are required to approve prequalified bidder.
• At least 2–3 weeks between bidder approval and bid submission to allow contractors adequate time to price the work.