2026-05-11 - IFB HOME CONNECTIONS - MT ZION RUSTIC SEWER REPLACEMENT.docx

DOCX document 148 KB Posted

Attached to
MT ZION HOME CONNECTIONS
Solicitation number
IFB-120011
Issued by
Carroll County, Virginia

About this file

This is an Invitation for Bid (IFB) issued by Charles City County, Virginia for the MT. Zion Rustic Sewer Replacement project under the HOME CONNECTIONS program. The project involves connecting a newly installed Low-Pressure Sewer system with 97 simplex grinder pump stations to approximately 97 existing residential properties along Wilcox Neck Road in Charles City County. The work consists of both plumbing and electrical connections, with plumbing scope including hand digging to locate existing sewer lines, cutting and connecting lines to grinder stations, capping abandoned pipes, installing up to 20 feet of 4-inch Schedule 40 PVC lateral per home, installing cleanouts at redirected gravity laterals, and backfilling and seeding all excavations. Electrical work includes installation of one 30-amp, 120/240-volt, 4-wire circuit per grinder pump station, with all associated inspection fees, coordination with County Building Inspection, upgrades to existing electrical distribution equipment as required, installation of safety switches, and construction of pump control panel mounts and backboards using pressure-treated lumber with specified dimensions.

The document does not specify response dates, bid due dates, site visit requirements, bidders conferences, award dates, contract terms, pricing terms, set-asides, incumbent information, or funding sources and amounts. These details would typically appear in additional bid solicitation documents or amendments not included in this project scope summary.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH OF VIRGINIA COUNTY of CHARLES CITY

BOARD OF SUPERVISORS

THE HONORABLE BYRON ADKINS SR. THE HONORABLE RYAN PATTERSON THE HONORABLE MICHAEL HILL

County administrator keith c. rogers, jr

May 11, 2026

RE: PROJECT INFORMATION AND PROJECT SCOPE -

MT ZION SEWER REPLACEMENT – HOME CONNECTIONS

Dear Bidders:

The Project includes the following Work:

The existing Mt. Zion AirVac system along Wilcox Neck Road has been replaced with a new conveyance system that includes initial installation of a Low-Pressure Sewer with 97 simplex grinder pump stations for the existing homes along Wilcox Neck Road. Operation of the new Low Pressure Sewer system requires the grinder stations to be connected to the residential property’s plumbing and electrical.

The work generally consists of connecting the new low pressure pump system to the existing sewer lateral and connecting to the existing panel for approximately 97 homes in Charles City County. The plumbing and electrical scopes will require the following:

Plumbing Connections: Hand dig to find the existing sewer line between home and existing Air Vacuum pit, cut and connect the existing sewer line to the grinder station, and cap remaining pipe to abandon in place. Run new lateral assumed 4-inch PVC to grinder pump station up to a maximum of 20 feet of Schedule 40 PVC, per home. Cleanouts will be required at all redirected gravity laterals. Backfill existing and proposed line with soils/fill dirt. Topsoil seed and straw all excavations.

Electrical Connections: Installation of one (1) 30 Amp, 120/240 V, 4 wire circuit for grinder pump. This includes all inspection fees and coordination with County Building Inspection, upgrades to existing electrical distribution equipment where required, to include Buck Boosters, install circuit from the building to the backboard/control panel, installation of safety switch, and wiring from safety switch to pump controller. The breakers inside the pump controller (pump and alarm) shall be left in the open position upon completion. The pump control panel mount and backboard shall be constructed of PT lumber to hold the electrical panel and disconnect for each property (Installation of Pump Control Panel and Disconnect to the PT Lumber Mount by others), stand to include two (2) 4’ x 4” PT legs and three (3) ¾” x 5” PT decking boards. Backfill all excavated areas with soils/fill dirt. Topsoil seed and straw all excavations.

image1.png

File details come from the government source that posted it. Updated .