2026-000002 - Addendum 3.pdf
PDF 147 KB Posted
- Solicitation number
- IFB 410 P-2026-000002 4
- Issued by
- Palm Beach County, Florida
About this file
This is an Addendum 3 document issued by the Palm Beach County Board of County Commissioners, Facilities Development and Operations Department, Capital Improvements Division, dated November 12, 2026, for the Supervisory of Elections HVAC Replacement Project (Project Number P-2026-000002). The addendum addresses twelve requests for information submitted by Andrea Construction, Inc., regarding electrical and mechanical specifications outlined in the original bid documents. Key clarifications address breaker and wire sizing for AHU-4.1A circuits, EDH-4.1A heater load confirmation, neutral conductor requirements contingent upon VFD manufacturer selection, confirmation that no demolition of existing equipment is required, 120V power source identification for the DDC control panel with extension of existing circuit PP1C 16 and a manufacturer-sized stand-alone UPS to be provided by the Controls Contractor, duct smoke detector quantities and locations on supply lines only with remote test stations mounted on walls beneath the unit, and VFD furnishing responsibility assigned to the Division 23 unit manufacturer with installation and wiring by Division 26. The addendum also addresses conduit routing requirements including firestopping at mechanical and electrical room penetrations and clarifies that shutdown windows and required notice for breaker installation on the 480V HP1C panel serving multiple loads must be coordinated with the owner. Prospective bidders must acknowledge receipt of this addendum by signing and attaching it to their bid proposal form; failure to do so may result in bidder disqualification.
The addendum contains no pricing information, set-asides, incumbent contractor designation, or contract term details. All responses direct bidders to refer to updated bid documents provided in Addendum One or to coordinate specific details with the owner and equipment manufacturers during project execution. A pre-bid site visit was conducted on September 15, 2026, and as-built drawings are available upon request to support bidder evaluations. Allowable shutdown windows and work hour restrictions, particularly regarding access blackout periods around the November 3 general election and canvass, must be coordinated directly between the contractor and the owner.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BOARD OF COUNTY COMMISSIONERS
PALM BEACH COUNTY, FLORIDA
FACILITIES DEVELOPMENT AND OPERATIONS DEPARTMENT
CAPITAL IMPROVEMENTS DIVISION
PROJECT NAME: Supervisory of Elections HVAC Replacement Project
PROJECT NUMBER: P-2026-000002
ADDENDUM NUMBER: THREE
DATE OF ISSUANCE: 11/12/2026
TO: Prospective Bidders
This addendum forms a part of the contract documents, modifies the original bid documents and shall be as binding as if contained therein. Acknowledge receipt of this addendum in the space provided on the "Bid Proposal Form". Failure to do so may subject the Bidder to disqualification.
This Addendum consists of four (4) pages.
RESPONSES TO REQUESTS FOR INFORMATION:
Andrea Construction, Inc.
Question #1 AHU-4.1A breaker and wire size (E-400, E-600, M-200). The drawings give three different values for the AHU-4.1A circuit (HP1C-19, 21, 23):
• E-400 tags it 3P/60A.
• The E-600 panel schedule shows 30A/3P with 4#10, 1#10G in 3/4"C.
• M-200 lists the AHU at MCA 8.7A / MOCP 15A.
Please confirm the correct breaker size, conductor size and disconnect rating.
Should the 60A disconnect on E-400 Note B be fused at 15A, per the MOCP?
Response: Refer to updated set of Bid Documents (ADDENDUM ONE), sheet E-400
Question #2 EDH-4.1A load in the panel schedule (E-600, M-200) E-600 lists EDH1-4a at
7.2 kVA per phase (21.6 kVA total) on a 15A/3P breaker. M-200 lists EDH-1.4A at 6.0 kW, 480V/3Ph, with MCA/MOCP to “field verify.” Please confirm the heater’s kW and that the 15A/3P breaker with #12 conductors is correct. Please also correct the HP1C load calculation.
Response: Refer to updated set of Bid Documents (ADDENDUM ONE), sheet E-600
Question #3 Neutral conductor (E-600). The panel schedule shows 4 conductors plus ground for both new 480V 3-phase circuits. Neither the AHU/VFD nor the EDH appears to need a neutral. Please confirm whether a neutral is required.
Response: The neutral requirement will be based of the final selection of VFD manufacturer. The note has been modified for the contractor to provide a neutral if required by the equipment manufacturer. Refer to updated set of Bid Documents (ADDENDUM ONE), sheet E-600.
Question #4 Existing equipment and demolition (E-600 Notes 2 and 3). Panel notes mention “replacing old units” and “new CB size as indicated for AHU-2.” No electrical demolition is shown. Please confirm:
• Is any existing unit or circuit in Room 13-13 being removed?
• Does Note 3 apply to this project?
Response: Notes have been removed and/or modified on the electrical panel. Refer to updated set of Bid Documents (ADDENDUM ONE), sheet E-600. NO
DEMOLITION
Question #5 120V power for the DDC control panel (M-900). The control diagram says “120 VAC by EC (provide UPS).” Control Notes 4 and 5 call for Div 26 power from the building UPS or a stand-alone UPS. No 120V circuit, source panel or UPS is shown on the electrical drawings. Please identify:
• The source panel and circuit.
• Whether to connect to the existing building UPS or provide a stand-alone UPS, and at what size.
• Which contractor furnishes the UPS.
• The control panel location.
Response: Plans have been updated to denote extension of existing PP1C 16 serving adjacent control panel to new DDC control panel. A stand-alone UPS, sized by the manufacturer, shall be provided by the Controls Contractor. Refer to updated set of Bid Documents (ADDENDUM ONE), electrical and mechanical plans for the location of the control panel in Mechanical Room 13-14.
Question #6 Duct smoke detectors: quantity and location (M-200, M-500 Note B, E-400 Note D). M-200 lists duct smoke detectors at “Supply” only. M-500 Note B calls for a detector in the return duct. Please confirm the quantity and locations.
Are remote test stations required? Where should they be mounted?
Response: Duct smoke detectors shall be installed on the supply of the unit. Refer to updated set of Bid Documents (ADDENDUM ONE), sheet M-500. Duct smoke detectors shall be connected to the existing building Fire Alarm system, a remote test station shall be provided on the wall, under the unit.
Question #7 Existing fire alarm system (E-400 Note D, M-900 Note 12). Please provide the existing fire alarm panel’s make, model and servicing vendor. Please also confirm:
• Whether the system and loop have capacity for the new devices.
• Whether the owner’s fire alarm vendor must do the programming.
• Who furnishes the duct detectors and who installs the sampling tubes.
Response: As per Gartek’s original site visit, the existing system has room for the additional smoke detector. Contractor shall confirm with owner’s fire alarm vendor and shall review the existing system capacity. Yes, the owner's fire alarm vendor is responsible for programming. Mechanical Installer shall provide and install detector, tubes, and accessories. Electrical and Fire Alarm contractor shall wire, connect, and program into existing building Fire Alarm system.
Question #8 AHU shutdown interlock (M-900 Sequence of Operation). Please confirm the contractor responsible for wiring the smoke detector and fire alarm shutdown to the AHU and VFD: Div 26, Div 28 or the controls contractor (Wisch & Jackson).
Response: Refer to response to Question 7 above.
Question #9 VFD: furnish and install responsibility (M-500 Note C, E-400, M-200). M-500 Note C says “provide new variable frequency drive,” and E-400 shows a wall-mounted VFD next to the disconnect. Please confirm:
• The VFD with bypass is furnished by Div 23 and installed and wired by Div 26.
• Mounting location and whether a backboard or rack is required.
Response: Refer to updated set of Bid Documents(ADDENDUM ONE). VFD shall be provided by unit manufacturer under Div 23, installation and wiring by Div 26.
Mounting location shall be coordinated in field with unit manufacturer and Mechanical Contractor.
Question #10 Breaker type and panel spaces in HP1C (E-600). Please confirm the existing HP1C manufacturer and breaker type, and that spaces 19–24 are open and can take new breakers. Are as-built drawings or a panel photo available?
Response: A Pre-Bid site visit was performed on 09-15-2026 to confirm this item. As-Built are available upon request. This should be confirmed on site by the electrical contractor.
Question #11 Conduit routing (E-400). No home-run route is shown from Electrical Room 13-15 to Room 13-13. Please confirm:
• Whether exposed EMT is acceptable in the corridor, or conduit must be concealed above the ceiling.
• Ceiling heights and type along the route.
• Whether any rated walls are crossed, for firestopping.
Response: Refer to updated set of Bid Documents (ADDENDUM ONE) for new unit location. Firestopping is required at all Mechanical and Electrical room penetrations
Question #12 Shutdowns and work hours Breaker installation requires de-energizing HP1C (480V), which also serves AHU1.3, EDH1-3 and AC-1. Please confirm allowable shutdown windows and required notice. Please also confirm any restricted access or blackout periods around the November 3 general election and canvass.
Response: Allowable shutdown windows and required notice shall be coordinated between contractor and the owner.
PLEASE ACKNOWLEDGE RECEIPT OF THIS ADDENDUM NO. THREE BY
SIGNING BELOW AND ATTACHING THIS ADDENDUM TO YOUR BID FORM.
THIS ADDENDUM MUST BE SIGNED BY AN AUTHORIZED AGENT AND
ATTACHED TO YOUR BID FORM, AND RECEIPT OF THIS ADDENDUM MUST BE
ACKNOWLEDGED ON THE “BID PROPOSAL FORM”. FAILURE TO DO THIS
MAY RESULT IN BIDDER’S DISQUALIFICATION.
ACKNOWLEDGMENT OF RECEIPT: _____________________________________
END OF ADDENDUM - 3
| BOARD OF COUNTY COMMISSIONERS |
| PALM BEACH COUNTY, FLORIDA |
| ADDENDUM NUMBER: THREE |
| TO: Prospective Bidders |
| PLEASE ACKNOWLEDGE RECEIPT OF THIS ADDENDUM NO. THREE BY SIGNING BELOW AND ATTACHING THIS ADDENDUM TO YOUR BID FORM. THIS ADDENDUM MUST BE SIGNED BY AN AUTHORIZED AGENT AND ATTACHED TO YOUR BID FORM, AND RECEIPT OF THIS ADDENDUM MUST BE ACKNOWLEDGED ... |