This is a Request for Proposals (RFP) issued by the City and County of Denver's Department of Aviation (DEN) for professional design services for the Peña Boulevard Reconstruction project located at Denver International Airport. The RFP seeks a qualified consultant to complete comprehensive design tasks for rehabilitating Peña Boulevard between E-470 and Jackson Gap, covering multiple engineering disciplines including roadway, drainage, structures, traffic, signing, construction phasing, lighting, utility, communication design, survey, geotechnical, and sustainability. The project is estimated to cost $8.5 million, with proposals due on May 9, 2025 by 2:00 PM Denver local time. An optional pre-proposal conference will be held virtually on April 15, 2025, and the contract is anticipated to start in October 2025 with a scheduled duration of five years from the date of execution.
The RFP includes a 12% Minority and Women-Owned Business Enterprise (MWBE) participation requirement, with firms required to be certified or demonstrate sufficient good faith efforts. The project aims to address aging infrastructure and prepare for anticipated airport growth, with DEN expecting to serve 100 million annual passengers as soon as 2027. The consultant will be responsible for developing design deliverables, coordinating with various stakeholders, and supporting DEN's Vision 100 strategic plan, which includes sustainability goals such as pursuing an Envision Silver ISI Certification. The contract will involve multiple design phases, including conceptual, preliminary, and final design submittals, with the ultimate goal of improving safety, system functionality, and infrastructure reliability for the Peña Boulevard corridor.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Exhibit B - Core Staff Labor Rates- v.2.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSALS
PEÑA BOULEVARD RECONSTRUCTION
E-470 to JACKSON GAP DESIGN
RFP No. 202577849
April 11, 2025
Proposal Submittal Requirements
RFP 202577849 Peña Boulevard Reconstruction E-470 to Jacksons Gap April 11, 2025
REQUEST FOR PROPOSALS (RFP)
Airport Office Building (AOB) Denver International Airport (DEN) 8500 Peña Boulevard, Room 8810 Denver, Colorado 80249-6340
Contract Administrator (CA): Rebecca Gloria E-Mail: contract.procurement@flydenver.com
Request for Proposals # 202577849
PROPOSALS MUST BE RECEIVED BY: May 9, 2025, by 2:00 PM Denver Local Time, as noted below
UNDER NO CIRCUMSTANCES WILL E-MAIL OR FACSIMILE RESPONSES BE ACCEPTED.
Schedule of Activities:
This projected schedule is an estimated timeline and is subject to change at the sole discretion of the City.
All times listed in this document are understood to be Denver local time.
Event Date RFP Advertisement April 11, 2025 Optional Pre-Proposal Conference April 15, 2025, at 11:30 AM Denver Local Time Last Date to Submit Written Questions April 25, 2025, by 2:00 PM Denver Local Time Proposal Due Date May 9, 2025, by 2:00 PM Denver Local Time
Pre-Proposal Conference – OPTIONAL An optional Pre-Proposal Conference will be held virtually via a Microsoft Teams Meeting at the date and time listed above in the Schedule of Activities. Please click on the following link to access the meeting.
Pre-Proposal Conference Link
At this conference, DEN representatives will explain the opportunity and answer questions regarding this
RFP.
RFP Questions DEN will not answer any telephone inquiries about this RFP. Written questions are due by the deadline as listed in the Schedule of Activities above and shall be submitted electronically via the Rocky Mountain E-Purchasing System (BidNet) website. DEN requires all questions to be submitted individually on this site.
Note: BidNet limits the characters available to input for DEN to respond to each question. For this reason, multiple questions may not be submitted as a single question, as DEN is unable to respond to multiple questions in the space provided. Because of this limitation, DEN reserves the right to reject groups of questions submitted in a single question box or to select and respond to only one question posed. A multi-part question containing an initial question and a follow-up is the exception to this rule. All questions and answers will be posted on the BidNet website as an addendum to the RFP at the link below following the deadline for submittal of questions:
mailto:contract.procurement@flydenver.com https://teams.microsoft.com/l/meetup-join/19%3ameeting_OGE2ODRmMWItYjZmYy00YmRlLWI1NjEtNThmYTBlNzNmZGY5%40thread.v2/0?context=%7b%22Tid%22%3a%2279c62162-b85e-4b0e-a863-ebe7817ad70d%22%2c%22Oid%22%3a%2249226d1f-d9ba-428a-b52c-fafbcdcccc6c%22%7d https://www.bidnetdirect.com/colorado/cityandcountyofdenverdepartmentofaviation
Proposal Submittal The proposal shall be prepared in accordance with the Preparation of Proposal as described in Section IV of this RFP. Proposers shall submit their proposal and all required forms via the BidNet website at the link below. Proposals are due by the date and time listed in the Schedule of Activities above.
https://www.bidnetdirect.com/colorado/cityandcountyofdenverdepartmentofaviation
Allow ample time for the electronic submission of your proposal. Following are links to a BidNet Electronic Bid Submission (EBS) guide and EBS FAQ site. DEN strongly encourages Proposers to review this information prior to starting your submission in addition to starting the submission process at least one business day prior to the proposal due date. DEN will not extend the submission deadline due to any technical issues or outages you may experience.
EBS FAQs:
http://faq.bidnetdirect.com/electronic-bid-submission/
Minority and Women-Owned Business Enterprise Participation Pursuant to Article III of Chapter 28 of the Denver Revised Municipal Code (D.R.M.C.) the Division of Small Business Opportunity (DSBO) has established the following participation requirement for this project:
12% Minority and Women-Owned Business Enterprise (MWBE)
The requirement must be met with certified firms, §§ 28-62, 28-66, D.R.M.C., or through the demonstration of a sufficient good faith effort. §§ 28-60, 28-64, D.R.M.C. and additional requirements pursuant to the D.R.M.C.
General Statement of Work This project consists of a competitive Request for Proposal (RFP) to select a qualified professional consultant and Denver International Airport (DEN) to complete Design tasks for rehabilitation improvements to Peña Boulevard between E-470 to Jackson Gap. This Project involves the following design disciplines outlined in the RFP: - Roadway design - Drainage/Water Quality design and analysis - Structures design - Traffic design and analysis - Signing Design - Construction Phasing - Lighting design - Utility design - ITS/Communication design - Survey - Geotechnical and Materials - Sustainability The driving need is rehabilitation of aging infrastructure.
http://faq.bidnetdirect.com/electronic-bid-submission/
PROPOSAL SUBMITTAL REQUIREMENTS
The following is a checklist for reference when compiling the proposal submission. The documents listed below are required:
□ Proposal Narrative:
• Complete responses to the Content Narrative as outlined in Section IV, which includes the required DEN Equity, Diversity, and Inclusion Plan (DEN EDI Plan)
□ Sample Agreement:
• List of all proposed modifications or legal issues regarding terms of the Sample
Agreement as outlined in Section III-2
□ Proposal Forms - all complete and signed
• Proposal Acknowledgement Letter – filled out completely and acknowledged all addenda
• Proposal Data Form
• Disclosure of Legal & Administrative Proceedings & Financial Conditions
□ DSBO Forms
• Commitment to MWBE Participation
• DSBO Program Requirements Handbook - Signature Statement
• MWBE Utilization Plan Form
□ Diversity Survey
• Diversity and Inclusiveness in City Solicitations (online survey – include the completed survey with your proposal submission)
□ Financial Forms (From primes only, financial forms from subs are not required) - to be submitted as separate electronic file from the proposal
• Exhibit B – Core Staff Labor Rates – V2
Table of Contents
REQUEST FOR PROPOSAL
NO. 202577849
PEÑA BOULEVARD RECONSTRUCTION E-470 TO JACKSON GAP DESIGN
REQUEST FOR PROPOSALS (RFP)
I. CITY, AIRPORT AND PROJECT OVERVIEW
II. SCOPE OF WORK
SECTION 1
PROJECT SPECIFIC INFORMATION
A. PROJECT INTRODUCTION
III. ADMINISTRATION INFORMATION
III-1 Issuing Office
III-2 Introduction and Acceptance of RFP Terms
III-3 Means of Communication
III-4 Interpretation of Proposal Documents
III-5 Addenda
III-6 DEN Website
III-7 Withdrawal of Proposal
III-8 Rights of DEN
III-9 Confidentiality of Records
III-10 Proposer Agreements
III-11 Minority and Women-Owned Business Enterprise (MWBE) Participation
III-12 Certification of Independent Price and Work Determination
III-13 Designation of Subcontractors
III-14 Payment
III-15 Disclosure of Legal and Administrative Proceedings and Financial Condition
III-16 Insurance Requirements
III-17 Governmental Immunity
III-18 Security
III-19 Airport Identification (ID) Badge Requirements
III-20 Background Checks
III-21 Vehicles in the Secured Area
III-22 Violations
III-23 Diversity and Inclusivity in City Solicitations
III-24 Wage Ordinances
Table of Contents
III-25 Conflicts of Interest
III-26 Collective Bargaining Agreement
III-27 Title VI Solicitation Notice
III-28 Compliance with Americans with Disabilities Act (“ADA”)
IV. PREPARATION OF PROPOSAL
IV-1 Preparation of Proposal - Proposal Forms
IV-2 Preparation of Proposal - Proposal Narrative
IV-3 Proposal Narrative Contents
V. EVALUATION OF PROPOSALS
V-1 Evaluation of Proposals
V-2 Past Performance
V-3 Shortlisting and Interviews (If Necessary)
V-4 Best and Final Offers
V-5 Evaluation Criteria
VI. ATTACHMENT 1, PROPOSAL FORMS
Attachment 1, Part 1 Proposal Acknowledgement Letter
Attachment 1, Part 2 Proposal Data Form
Attachment 1, Part 3 Disclosure of Legal and Administrative Proceedings and Financial Condition
Attachment 1, Part 4 DSBO Forms
Attachment 1, Part 5 Exhibit B
VII. ATTACHMENT 2, INSURANCE REQUIREMENTS
VIII. ATTACHMENT 3, DIVERSITY AND INCLUSIVENESS IN CITY SOLICITATIONS
IX. ATTACHMENT 4, SAMPLE AGREEMENT
City, Airport and Project Overview
I. CITY, AIRPORT AND PROJECT OVERVIEW
The values of equity, diversity, inclusivity, accessibility, and sustainability are inherent to the City’s strategy to develop and maintain prosperous communities. Accordingly, these values are imbedded into all the City’s procurement processes to ensure competitive procurements that offer equitable opportunities for all potential Bidders, including greater contracted and significant participation for historically underutilized businesses to ensure Denver’s long-term economic, social, and environmental health. Through equitable procurements, the City is committed to working to remove barriers and increase access to City contracting opportunities for all historically underutilized and small businesses including those owned by veterans and individuals living with disabilities as well as those in economically distressed or redlined neighborhoods. It is a primary value to promote economic equity by engaging a more inclusive community of Bidders and contractors, both as prime and sub-contractors to address socioeconomic disparities. Through this promotion of equity and inclusion (EDI), the City strives to improve opportunities that ensure fair and just access to jobs, housing, education, mobility options, and healthier communities. It is the City’s expectation that all successful Bidders demonstrate their commitment to these City values through their procurement responses and post contract and/or lease activities.
Each procurement opportunity is to be approached with ethical and honest behavior. The City will solicit, evaluate, and award contracts based upon the Proposer’s alignment with the City’s values as it relates to its approach, proven experience, ability to perform work, costs, and pricing. DEN is looking for Proposers that demonstrate a history of equity, diversity, integrity, stewardship, innovation, and humanity. The City is looking for Proposers that have equity, diversity, and inclusion (EDI) embedded in their policies, procedures, practices, initiatives, and exhibit actionable results and ensures that of those that they partner with.
The City’s values may be demonstrated through but are not limited to: (a) workforce expansion; (b) utilization of and work with the historically underutilized community, separate from required certified goals; (c) environmental sustainability and (d) EDI and Equal Employment Opportunity (EEO) programs for staff.
DEN plays a unique role as a gateway to the world for the region, our passengers, our communities, and our partners. As such, DEN has a generation of operators, concessionaires, designers, builders, planners, and small businesses that are stronger and more successful because of this work. DEN has also helped build new businesses that have flourished and grown into mature industry leaders. As part of its new Vision 100 plan, DEN intends to expand this legacy by looking to the community that has succeeded in the past at DEN to bring the next generation forward.
In its review of this contract opportunity, DEN believes that the scope of work and firms in the industry lends itself to unique partnership opportunities, and therefore, encourages firms that have historically proposed as prime contractors to serve as subcontractors to M/WBE firms in their contract with DEN, or to create Joint Ventures with M/WBE firms. A focus of this partnership should be for the contracting partners to build a meaningful relationship that is not merely transactional to meet a numerical goal. The objective is to afford the M/WBE firm the opportunity to learn from the large contractor, grow its financial capacity, build its generational wealth and its portfolio, and increase its capability to perform new commercially useful functions on future contracts.
In accordance with procedures described herein, you are hereby invited to submit a proposal for the subject project, which is described in the Scope of Work incorporated herein. The work under this Contract is anticipated to start on or about October 2025 and has a scheduled duration of Five (5) Years
City, Airport and Project Overview from Date of Execution (DOE). The proposal must be prepared and submitted in accordance with the requirements and procedures contained in this RFP document and the City’s, including DEN’s, ordinances, rules, policies, and procedures. Compliance with these requirements by the Proposer is mandatory and is a condition of responsiveness. Any failure to satisfy these requirements will be a sufficient basis for the City and County of Denver’s Department of Aviation, also known as Denver International Airport, (DEN or City) to disqualify the Proposer. The City shall not be liable for any of the Proposer’s expenses associated with its preparation of the proposal or DEN’s consideration of it. The Proposer, if selected, shall not include any such expenses as part of its fee for performing the Scope of Work.
Scope of Work
II. SCOPE OF WORK
SECTION 1
PROJECT SPECIFIC INFORMATION
A. PROJECT INTRODUCTION
Denver International Airport (DEN) is a commercial air carrier facility located 23 miles northeast of the metropolitan Denver area. Located near the geographic center of the United States, DEN is the only major hub airport within a 500-mile radius and offers nonstop flights to more than 200 destinations. Therefore, DEN attracts passengers from all over Colorado as well as significant passenger numbers from the Mountain States and Midwest. DEN also has service to approximately 20 Federally subsidized Essential Air Service (EAS) routes across the Western and Midwest U.S. making DEN the only air service option for these rural markets. Transit is currently not a viable option for a significant number of the passengers traveling to DEN, therefore Peña Boulevard remains essential for connecting travelers to the region’s major hub airport.
B. PROJECT BACKGROUND
Peña Boulevard is a four-lane (two lanes each direction) freeway that extends from I-70 to the Jeppesen Terminal at DEN. The roadway widens to three lanes in each direction between the E-470 Tollway (E-470) and the Jeppesen Terminal.
Peña Boulevard was originally constructed almost 30 years ago, as such required maintenance work is extensive, and the cost to maintain the aging facility is substantial. In 2023, DEN served 77.8 million passengers; DEN is expected to serve 100-million annual passengers as soon as 2027. To manage growth, maintain the reliability of the supply-chain and continue to boost the local and regional economy, DEN must rehabilitate Peña Boulevard and address infrastructure deficiencies.
The E470 to Jackson Gap Boulevard stretch is one of the busiest portions of Peña airport traffic as it combines both Peña and E470 traffic. Any emergency pavement failures are crippling to traffic operations and for access to/from the airport.
This stretch of Peña Boulevard originally included a toll plaza for traffic exiting the airport. Peña Boulevard Inbound included a deviation from alignment to allow room for this toll plaza. DEN Facilities has removed the old toll plaza structure. This project will straighten Inbound Peña Boulevard to bring it back on alignment.
This project will also include interchange improvements at the Final Approach development on the north side of Peña Blvd at Gun Club Road. These improvements are anticipation of DEN Real Estate’s continued development in this area. It will include 2 new ramps and other related improvements.
C. PROJECT DESCRIPTION
DEN is seeking a professional consultant to complete the Design Engineering Services for improvements to Peña Boulevard between E-470 and Jackson Gap Boulevard.
This Project involves reconstruction of both Inbound and Outbound Peña Boulevard between E470 and Jackson Gap Boulevard. This includes white topping in most locations, a realignment of inbound Peña Boulevard between E470 and Gun Club, a realignment of the Inbound Gun Club off-ramp.
The following improvements have been identified for the work:
1. Either existing pavement and rubblization and PCCP white toping or full reconstruction of Peña Boulevard.
2. Increase inside shoulder width from 6 feet to 12 feet.
3. Realignment of Inbound Peña Boulevard from E470 to Gun Club Road.
4. Realignment of Inbound Peña Boulevard off-ramp to Gun Club Road.
5. Bridge rehabilitation (3).
6. Removal of old toll plaza pavement in the median.
7. Repurposing of old Inbound Peña Boulevard Gun Club off-ramp to two-way local road.
8. Multi-use trail east from E470 High Plains Trail to 78th/77th intersection.
9. Turning the Inbound Peña Boulevard Jackson Gap single lane off-ramp into a two-lane off-ramp (off and optional).
10. Construction of two outbound off-ramps at Gun Club Road. (West Approach Improvements)
11. Existing ramp tie-ins will need to be modified to meet the new Peña elevation (4).
12. Widening of the Outbound Peña Boulevard bridge over Piccadilly and both Gun Club bridges to accommodate phasing and for future use identified by the Peña Blvd NEPA study.
13. Replacement of all sign bridges and addition of exit ramp overhead signing. One impacted sign includes dynamic parking information and will need communication design.
14. Lighting modifications/upgrades at the old toll plaza location.
15. Phasing plan that allows for 3 lanes of traffic in both directions at all times.
16. Intersection/Signal modifications at the ramp intersection and 75th intersection
D. DESIGN TASKS
1. Conceptual Design The Consultant shall prepare a conceptual (10-20%) design that incorporates the following elements (see attached overall exhibit - Overall conceptual Exhibit – E470 to Jackson Gap):
a. Reconstruction Limits – Limits of reconstruction to be defined by design team analysis that will include a field visit to determine the general pavement condition. The approximate project limit starts at about 200 feet west of the eastern E470 ramp gores and continues along Peña Boulevard to the western edge of the Jackson Gap approach slabs. A separate, early action, “Peña Blvd outbound Low Point” Reconstruction and Drainage Improvement from Picadilly to Gun Club Road Project is not included in this scope. Plans and CAD files for that project will be supplied to the Consultant.
b. White topping vs full reconstruction limits – Any existing concrete pavement panel that is equal to or greater than 10 feet in width and within the proposed pavement limits shall be rubblized and add an 11-inch PCCP white-topping (amount of ABC to be determined). Full reconstruction shall occur on the approaches to approach slabs, the Inbound straightening, areas where geotechnical investigation determines the subgrade is inadequate and at tie-in points. Final design plans are to include a standard detail for the vertical transition from white-topping to full reconstruction.
c. Widened Gun Club Road bridges to accommodate phasing – The existing bridges over Gun Club include an 8-foot and a 6-foot shoulder, giving a total bridge width of 50 feet. In order to accomplish the phasing requirement of 3 lanes open at all times, a bridge width of 78 feet would be required across the bridge.
d. Widened Outbound Piccadilly Bridge by 12-15 feet – The existing outbound Piccadilly bridge needs to be widened in order to maintain 3 lanes at all times during construction.
e. Trail alignment (2-3 options) – DEN is in the process of studying a trail that connects the High Plains Trail to points east within Airport property. DEN is currently considering an option that runs parallel to the A line bridge and another option that sticks closer to Peña Boulevard. The goal is to minimize grading and structures required to pass over Third Creek.
f. Continuous accel/decel lane between inbound Gun Club On-ramp and Jackson Gap off-ramp – This will require some reconstruction along the existing ramp at Jackson Gap. The Consultant shall devise a design that minimizes reconstruction to and minimizes limited operations for the existing off ramp. The new configuration will include an off and a shared lane.
g. Inbound Gun Club off-ramp, including modified entrances to Development south of the new ramp.
h. Modified 75th/old Inbound Gun Club Road off-ramp to a 2-way surface street, including modified accesses to the development to the north.
i. Prepare conceptual designs and evaluate/analyze intersection types (signal, roundabout, other) for Gun Club Road/75th Avenue and Gun Club Road/New Inbound Off-ramp
2. West Approach Improvements (See Gun Club Ramps Conceptual Exhibit attached)
a. New Outbound off-ramps at Gun Club Road – Design two new outbound off-ramps at Gun Club Road. The first ramp is a standard Outbound Peña Boulevard off-ramp that ties into the eastern edge of Gun Club Road. The second Outbound off-ramp will tie into 78th Avenue west of Gun Club and shall create a new eastbound lane. These improvements will also require modifications to both Gun Club Road and 78th Avenue, as well as analysis at the new intersections and 2 new traffic signals.
The conceptual design will be analyzed by the project team and will be used to determine if all or some of the options will be carried forward. This conceptual design will also be used to start stakeholder coordination. The Consultant shall create a high-resolution pdf long plot (digital and hard copies) for this purpose.
3. Preliminary and Final Design The Consultant shall complete 30%, 60%, 90%, 100%, IFB and IFC submittals per DEN requirements.
As part of the preliminary design, the Consultant shall create a design criteria table that includes each roadway by name and all related design criteria. The table shall be submitted for review and approval.
The consultant shall perform all design criteria related calculations/analysis and submit them with the 60% design for review and approval. This includes but it not limited to vertical clearance, line of sight, turning templates and superelevation calculations.
4. Constructability Review DEN will conduct an industry constructability review based on corrected 30% plans. Anticipate pdf plan deliverable and attendance at industry review meetings. DEN will coordinate contractor meetings.
E. COST ESTIMATES AND FINANCIAL ANALYSIS
1. Preliminary Construction Cost Estimates The Consultant will prepare preliminary construction cost estimates based on the conceptual design.
2. Cost Estimates
All submittals will include Engineer’s Cost Estimates.
F. Water Quality
1. City of Denver MS4 Permit requirements WILL apply to this project. The Consultant will determine the requirements of the Municipal Separate Storm Sewer System (MS4), Colorado Discharge Permit System (CDPS), and design and permitting issues per the DEN PWQ Master Plan. It is anticipated that the total impervious area will be less than existing with the removal of the Toll Plaza pavement.
2. The Consultant will recommend and design appropriate Water Quality mitigation measures as necessary. Water Quality design shall be included starting with the 60% design and included through IFC.
3. The Consultant shall analyze the existing pond north of Peña Blvd at the Outbound Jackson Gap on-ramp tie in. Determine if the pond capacity is sufficient for the current and proposed impervious area and redesign the pond as needed.
G. Hydrology/Hydraulic Engineering
a. Data Collection and Hydrology
i. Establish drainage basin data: delineate and determine size, waterway geometrics, vegetation cover, and land use.
ii. Collect historical data: research flood history and previous designs in the project proximity;
obtain data from other sources (e.g., MHFD, CWCB, DEN Maintenance, and local residents).
iii. Complete a project site visit to evaluate channel/overbank roughness coefficients, channel stability, vegetation, condition/adequacy of existing structures, Ordinary High Water, allowable high water, etc. Document the site visit with photos.
iv. Select a design storm frequency based on the established criteria.
v. Complete a hydrological analysis using existing studies or approved methods.
vi. Perform a risk analysis.
b. Hydraulics
i. Complete design of minor drainage structures:
a) Determine locations, sizes, and alignment based on preliminary hydraulic design. Identify locations by highway station or coordinates, as appropriate.
b) Determine the allowable headwater.
c) Assess the degree of sediment and debris problems to be encountered.
ii. Complete design of major drainage structures:
a) Complete hydraulic analysis and water surface profiles.
b) Determine required hydraulic size/skew of major structures/channels.
c) Determine minimum low chord elevation per CDOT criteria.
d) Determine design storm and 500-year water surface elevations.
e) Determine scour for design storm, the 500-year event, incipient overtopping condition, and maximum scour-inducing storm (if applicable).
f) Assess channel erosion protection for structures.
c. Prepare plans that include:
i. Drainage Plan Sheets
ii. Drainage Detail Sheets as needed
iii. Water quality ponds (if necessary)
iv. Hydraulic Information Sheets as needed
d. Prepare a Drainage Report in accordance with the CDOT Drainage Design Manual
H. Floodplains Assessment
a. Comply with the latest FEMA Federal Flood Risk Management Standard or equivalent in relation to Second Creek.
b. Identify any planned changes to the floodplain from the proposed design.
c. Analyze impacts and develop possible design actions to mitigate for the adverse impacts, coordinate with roadway and structural designer and proposed options to minimize or eliminate floodplain impacts.
I. Wetlands and Waters of the U.S. (WUS) All wetland related work will be the responsibility of DEN with support from the Consultant for exhibits related to design impacts. Wetland delineation mapping will be provided to the consultant for use.
J. Utilities and RTD A-Line Utility coordination will be a joint effort between DEN staff and the consultant but the coordination effort will be led by DEN.
1. Collect utility location key maps for all existing and planned utilities in the area in coordination with the DEN. Conduct all field utility locates. The potential impacts on or from utilities in the project area will be analyzed as well as any appropriate mitigation measures and shall be included in the design.
2. The project also crosses the RTD A Line. All design elements must take the A Line bridge into account and minimize/eliminate any impacts. The Consultant must analyze and adhere to the current agreement between DEN and RTD. RTD coordination shall be led by DEN staff with assistance from the Consultant. Provide a structural integrity determination with RTD submittal.
3. There is an adjacent waterline design project that is about 6 months ahead of this project.
The project is installing a waterline down the center of Peña Blvd. The engineer will need to coordinate design with that project.
K. Survey Arrange project Field Survey and/or Aerial Survey. Coordinate with DEN/PM and DEN Survey for project control and survey requirements. Follow DEN Survey request protocols and make all Survey related submittals that must occur before Survey can begin. DEN Survey Control shall be used. The Consultant shall plan for the full survey of the project area at Notice to Proceed after coordinating the limits with DEN. The Consultant shall plan for Supplemental Survey after 30% design is complete to insure full coverage.
,.mThe consultant shall receive survey information from the Peña Boulevard Outbound Low Point project to supplement their own. The Low Point survey information shall be verified and supplemented as needed.
L. Traffic Design Final signing, striping and signal design is required.
Striping/restriping of the entire project limits shall be included in the 30% plans for approval before moving forward. Gun Club Road shall be restriped accordingly to accommodate the new configuration.
The signing shall follow MUTCD design standards and CDOT design criteria. Impacted wayfinding shall be replaced as necessary. At a minimum, this will include a Parking DMS sign bridge between 470 and Gun Club along Peña Blvd and two static sign bridges between Gun Club and Jackson Gap, both inbound. Wayfinding shall be designed in accordance with the DEN Peña Boulevard corridor signing concept. The DMS design will require IT elements and coordination with DEN technologies and DEN Parking. The Consultant shall The two southern Gun Club Signals shall be re-designed to meet the new configuration. The engineer shall attempt to use existing infrastructure before placing any portion of the signal.
The Consultant shall obtain all traffic volumes necessary to complete their design.
M. Traffic Control / Phasing The Peña Boulevard phasing plan shall maintain 3 lanes in each direction at all times. Determine phasing alternatives including preparation of several conceptual layout options with high level costs for consideration. Phasing plans shall be included, started in the concept submittal as a long plot for each phase and will be in sheet format after that. DEN allows lane closures overnight on an as needed basis.
N. Major Structural Design
For each proposed Bridge Widening and Bridge Rehabilitation conduct an investigation of Accelerated Bridge Construction (ABC) opportunities and coordinate with DEN regarding benefit and feasibility.
Maintaining three lanes of traffic is a critical goal of the project to reduce user impacts.
a. Structural Data Collection
i. Obtain the structure site data. The following data, as applicable, shall be collected: (Typical roadway section, roadway plan and profile sheets showing all alignment data, topography, utilities, preliminary design plan) Property/Right-of-Way restrictions, preliminary hydraulics and geology information, environmental constraints, lighting requirements, guardrail types, recommendations for structure type, and architectural recommendations.
ii. Obtain data on existing structures. When applicable, collect items such as existing plans, inspection reports, structure ratings, foundation information, and shop drawings. A field investigation of existing structures will be made with notification to the DEN/PM. This includes the 3-cell drainage feature running beneath Pena Boulevard withing the project limits.
b. Structure Selection and Layout
i. Review the structure site data to determine the requirements that will control the structure size, layout, type, and rehabilitation alternatives. On a continuing basis, provide support data and recommendations as necessary to finalize the structure site data. This includes taking the “A Line” bridge structure into account.
ii. Determine the structure layout alternatives. For bridges, determine the structure length, width, and span configurations that satisfy all horizontal and vertical clearance criteria. For walls, determine the necessary top and bottom of wall profiles.
iii. Determine the structure type alternatives. For bridges, consider precast and cast-in-place concrete and steel superstructures and determine the spans and depths for each. For walls, determine the feasible wall types.
iv. Determine the foundation alternatives. Consider piles, drilled caissons, spread footings, and mechanically stabilized earth foundations based on geology information from existing structures and early estimates from the project geologist. To obtain supporting information, initiate the foundation investigation as early as possible during the preliminary design phase.
v. Determine the rehabilitation alternatives. Continued use of all or parts of existing structures shall be considered as applicable. The condition of existing structures shall be investigated and reported. Determine the modifications and rehabilitation necessary to use all or parts of existing structures and the associated costs.
vi. Develop the staged construction phasing plan, as necessary for traffic control and detours, in conjunction with the parties performing the roadway design and traffic control plan. The impact of staged construction on the structure alternatives shall be considered and reported on.
vii. Compute preliminary quantities and preliminary cost estimates as necessary to evaluate and compare the structure layout, type, and rehabilitation alternatives.
viii. Evaluate the structure alternatives. Establish the criteria for evaluating and comparing the structure alternatives that, in addition to cost, encompass all aspects of the project’s objectives.
Based on these criteria, select the optimum structure layout, type, and rehabilitation alternative, as applicable, for recommendation to DEN.
ix. Prepare preliminary general layout for the recommended structure. Prepare structure layouts in accordance with current standards. Special detail drawings and a detailed preliminary cost estimate shall accompany the general layout. The special detail drawings shall include the architectural treatment. Perform an independent design and detail check of the general layout.
e. Structure Selection Report
Prepare a structure selection report to document, for submittal with the 30% design, and obtain approval for, the structure preliminary design. By means of the structure general layout, with supporting drawings, tables, and discussion, provide for the following:
i. Summarize the structure site data used to select and layout the structures. Include the following:
a) Existing structure data, including sufficiency rating and whether or not the structure is on the “select list”.
b) Project site plan
c) Roadway vertical and horizontal alignments and cross sections at the structure
d) Construction phasing
e) Utilities on, below, and adjacent to the structure
f) Hydraulics:
Channel size and skew, design year frequency, minimum low girder elevation, design year and 500-year high water elevations, estimated design year and 500 year scour profiles, and channel erosion protection
g) Preliminary geology information for structure foundation
h) Architectural requirements (matching existing) i.) Include analysis and recommendations to rehabilitate existing 3 cell drainage structure.
ii. Report on the structure selection and layout process. Include the following:
a) Discuss the structure layout, type, and rehabilitation alternatives considered
b) Define the criteria used to evaluate the structure alternatives and how the recommended structure was selected
c) Provide a detailed preliminary cost estimate and general layout of the recommended structure
iii. Obtain acceptance by DEN on the recommended structure and its layout. Allow approximately two weeks for review of the structure selection report. The associated general layout, with the revisions required by the DEN review, will be included in the FIR plans. The structure selection report, with the associated general layout, must be accepted in writing by DEN prior to the commencement of further design activities.
f. Foundation Investigation Request
Initiate the foundation investigation as early in the preliminary design phase as is practical. On plan sheets showing the project control line, its stations and coordinates, utilities, identify the test holes needed and submit them to the project geologist. The available general layout information for the new structure shall be included in the investigation request.
O. Bridge Widening
a. Existing bridge condition investigation (4)
Determine condition of existing bridge deck, superstructure and substructure material as required.
b. Foundation Investigation Report (4)
i. Prepare a Foundation Investigation Request showing requested test hole locations.
ii. Formulate drilling pattern, perform the necessary subsurface investigation and collect samples as required.
iii. Perform the appropriate laboratory tests and analyze the data. Determine strength, allowable bearing capacity and corrosiveness of foundation material.
iv. Perform lateral analyses (deformation, moment, and shear) for the caissons and/or piles which are subjected to lateral loadings. This may be a computer analysis which will consider the group effect and selection of the soil parameters.
v. If appropriate, a pile driving analysis using a wave equation will be accomplished.
vi. Submit the Foundation Investigation Report to the DEN/PM for approval.
Prepare engineering geology plan sheet and copies of the Foundation Investigation Report foundation report with recommendations for type, size, and tip (bottom) elevation of the required foundation.
Specify if pre-drilling, pile tip, casing, dewatering, etc., are needed for foundation construction.
The Consultant shall create a conceptual design for bridge widenings after the approved concept phase and include an interim submittal for approval.
P. Materials Engineering A soil investigation shall be conducted.
a. Determine test hole locations (horizontal and vertical) and coordinate with the DEN/PM.
b. Collect soil samples and test for:
i. Classification
ii. Moisture – Density Relationship
iii. Resistance Value
iv. Corrosiveness – Note locations of high corrosiveness with recommendations; see CDOT pipe material selection policy.
v. Bearing Capacity
c. Prepare and submit a soils investigation report for approval.
Q. Pavement
a. New Pavement Structure
The feasible PCCP alternatives of new pavement structure shall be designed utilizing procedures accepted by the DEN/PM. New pavement designs for widening shall be compatible with adjacent pavements. This also includes a temporary asphalt section for detoured Peña traffic.
b. Pavement Justification
i. Basic factors:
a) Desired life expectancy (obtain design life from DEN).
b) Required maintenance activities intervals.
c) Basis for performance life.
ii. Analyze life cycle cost of the selected alternatives:
a) Perform analysis with unit and maintenance costs from DEN. Determine present worth and annual costs in accordance with the procedures in the CDOT Pavement Design Guide.
b) Compare alternatives over the same life span.
c) Recommend the pavement structure and provide the basis for the recommendations.
c. Pavement Design Report Include all the above tests, investigations, analyses, and calculations performed. Submit to the DEN/PM for acceptance after the Conceptual Submittal.
R. Roadside Development and Landscaping Previous recent projects have constructed curb and gutter with cable rail for storm drainage runoff and erosion control protection. This project will analyze the options for roadside curb & cable rail versus hardscape/rock treatments and other lower cost/lower maintenance solutions. Maintenance, erosion, seeding, and safety will all be considerations. The design consultant in consult with DEN approval will determine the preferred design to be advanced. Roadside options will be included with the 30% design for review and approval.
Prepare and provide final roadway design plans incorporating all input from applicable DEN specialties and outside entities.
a. Roadside design
b. Landscaping
c. Determine the most economical landscape establishment alternative, finalize concept, and complete the plan.
S. Lighting plans Street lighting infrastructure includes mid-mast poles and high mast light poles (around previous toll plaza west of Gun Club Road). Complete a concept layout of both options and conduct an analysis of high mast lighting versus traditional roadside light poles for the entirety of the project limits.
Coordinate with DEN for comparison, costs, metrics and opportunities. Relocations of existing would be completed by Xcel under the DEN franchise agreement.
i. Provide a foundation investigation for each proposed/relocated high mast light location.
ii. After approval of the lighting concept and locations of the lights, the lighting design will be completed with the following information shown on the plan sheets:
a) Circuit type and voltage of power source
b) Location of power source (coordinated with the utility engineer)
c) Luminaire type and lumens
d) Light standard type and mounting height
e) Bracket arm type and length
f) Foundation details
g) Size and location of electrical conduit
h) Locations of power sources(s)/lighting control center(s) (if appropriate)
i) Location of direct burial cable
j) Size of wiring and/or direct burial cable
iii. Coordinate with DEN and Xcel for executed work orders.
T. PROJECT GOALS
This project is intended to produce the following improvements:
• Safety o Improve the safety of all travelers in the corridor, fully supporting the City’s Vision Zero goal.
• System Functionality o Produce a project that is consistent with the DEN’s vision and commitments and is consistent with surrounding planning and studies.
o Deliver a project that is consistent with and building upon DEN Vision 100 including:
sustainability & resiliency; equity, diversity, inclusion & accessibility; continuous stakeholder input/feedback; and enhancing the customer experience.
The Peña Boulevard improvements between E-470 and Jackson Gap Boulevard are intended to improve failing infrastructure, enhance safety, and address congestion.
U. ENVIRONMENTAL SUSTAINABILITY
DEN is committed to the construction, operation and maintenance of environmentally sustainable infrastructure. Figure 1 outlines the four guiding principles of Vision 100 and Operation 2045 which includes sustainability and resiliency and specifically the goal for DEN to becoming the greenest airport in the world. Vision 100 and Operation 2045 are two phases of DEN’s strategic plan. Vision 100 is phase one and is focused on preparing the airport to serve 100 million annual passengers as soon as 2027. Operation 2045 is phase two and is focused on preparing the airport for its 50th Anniversary in 2045 and for an expected 120 million-plus annual passengers. Both phases combined serve as a blueprint to align decision-making and accountability.
Figure 1 Vision 100 and Operation 2045 Strategic Guiding Principles
As part of Vision 100, DEN has made the following sustainability and resiliency commitments:
• Develop initiatives to help reduce the environmental impact of airport operations
• Expand solar energy program
• Implement deep energy and water retrofits across the airport
• Design and build LEED certified Gold Facilities and Envision certified facilities
• Plan for the transition to electric vehicles (EV) and install additional charging stations
• Improve recycling and composting infrastructure
• Increase Climate Resilience
As part of this effort, the Consultant shall work with DEN to reach an Envision Silver ISI Certification on this project. The ISI Certification will be lead by DEN with support from the Consultant. The Consultant shall include Envision discussion in all work products. The early envision assessment completed by DEN must be taken into consideration during Conceptual design.
V. PROJECT LIMITS
The Peña Boulevard E470 to Jackson Gap Boulevard Design is in Denver County and goes from the E- 470 Interchange to the Jackson Gap Interchange.
Project Location Map
W. WORK DURATION
The time period for the work described in this scope is estimated to begin in Q3 2025 and issue for bid documents completed in Q3 2027. The consultant will perform design services during construction through construction closeout in Q1 2030.
X. WORK PRODUCT
The work in the scope of services for this project will include the followings services:
1. Coordination of all Environmental and Design Work efforts and documentation with ISI Envision sustainability framework.
2. Project Coordination
3. Schedule Management
4. Risk Assessment and Mitigation Planning
5. Meeting Minutes, Monthly project update reports
6. Reports, Design plans, specifications and engineer’s estimate.
7. Coordination and submittals for CCD related permitting.
Requirements are further described in the sections that follow.
SECTION 2
PROJECT MANAGEMENT AND COORDINATION
A. PROJECT COORDINATION
Coordination will be required with the following at a minimum:
1. Cities: City & County of Denver
2. Counties: City & County of Denver
3. Regional Transportation District (RTD)
4. Utilities
5. Colorado Department of Public Health and Environment (CDPHE)
The consultant should anticipate that a design which affects another agency will have to be accepted by that agency prior to its acceptance by DEN. Submittals to affected agencies will be coordinated with DEN.
B. NOTICE TO PROCEED
Work shall not commence until the written Notice-to-Proceed is issued by DEN.
C. PROJECT COMMUNICATION
Routine Working Contact shall be between the DEN/PM and the Consultant Project Manager (C/PM). Each Project Manager shall provide the others with a written synopsis or copy of their respective contacts by telephone and in person with others and copies of pertinent written communications.
D. PERSONNEL QUALIFICATIONS
1. The C/PM must be approved by the DEN/PM. Certain tasks must be done by Licensed Professional
Engineers (PE) or Professional Land Surveyors (PLS) who are registered with the Colorado State Board of Registration for Professional Engineers and Land Surveyors. National Institute for Certification in Engineering Technology (NICET) or other certifications may be required for project inspectors and testers.
2. All tasks assigned to the Consultant must be conducted by a person on the Consultant team that is qualified and has specific expertise in that task. The qualified person is a professional with the necessary education, certifications (including registrations and licenses), skills, experience, qualities, or attributes to complete a particular task. Design of any special project features must be directed, completed, and overseen by a professional engineer with significant experience in design of those special project features.
3. This contract requires that the prime firm or any member of its team, be pre-qualified in the following disciplines for the entire length of the contract:
• BR – Bridge Design
• CE - Civil Engineering,
• EL -Electrical Engineering,
• EN - Environmental Engineering,
• GE - Geotechnical Engineering,
• HD - Highway & Street Design,
• HY - Hydrology and Hydraulics (including PWQ),
• LA – Landscape Architecture
• MA - Management (Contract Admin),
• MT – Materials Testing
• SE -Structural Engineering,
• SU – Surveying and ROW
• TP - Transportation Engineering
• TR - Traffic Engineering
4. It is the intent of DEN that all key personnel be engaged to perform their specialty for all services required by this contract, and that the Consultant’s key personnel be retained for the life of this contract to the extent practicable and to the extent that such services maximize the quality of work.
If the Consultant or a subconsultant decides to replace any of its key personnel, the Consultant shall notify the DEN/PM in writing of the desired change. No such changes shall be made until at least two qualified replacement candidates are recommended by the Consultant and a replacement is approved in writing by the DEN/PM. The DEN/PM’s approval shall not be unreasonably withheld.
5. Failure of the Consultant to comply with the requirements of this provision may be the basis for DEN’s termination of this contract. The DEN/PM shall respond to the Consultant’s written notice regarding replacement of key personnel within fifteen working days after the DEN/PM receives the list of proposed changes. If the DEN/PM or its designated representative does not respond within that time, the listed changes shall be deemed to be approved. If during the term of the contract the DEN/PM determines that the performance of approved key personnel is not acceptable, he shall notify the Consultant and give the Consultant the time which the DEN/PM considers reasonable to correct such performance. Thereafter he may require the Consultant to reassign or replace such key personnel. If the DEN/PM notifies the Consultant that certain of their key personnel or the key personnel of a subconsultant should be replaced, the Consultant shall use its best efforts to replace such key personnel within a reasonable time, not to exceed thirty calendar days from the date of the DEN/PM’s notice.
E. REPORTING AND BILLING
The Consultant shall provide the following on a routine basis:
• Coordination: Coordination of all contract activities by the C/PM
• Periodic Reports and Billings: The periodic reports and billings required by DEN, including monthly drawdown schedules.
• General Reports and Submittals: In general, all reports and submittals must be approved by DEN prior to their content being utilized in follow-up work effort.
F. ELECTRONIC SUBMITTALS
AUTOCAD Civil 3D is the official electronic archive for DEN projects. Project submittals and all relevant documents shall be uploaded to the DEN BIM project folder by the consultant. The data format for submitting design computer files shall be compatible with the latest version of the adopted DEN software.
The Consultant shall immediately notify the DEN/PM if the firm is unable to produce the desired format for any reason and cease work until the problem is resolved.
G. PROJECT DESIGN DATA AND STANDARDS
The consultant is responsible for obtaining and ensuring compliance with the most recent DEN versions of the standards and specifications, manuals, and software or as directed by the DEN/PM. Conflicts in criteria shall be resolved by the DEN/PM.
H. SCOPE OF WORK ORGANIZATION
This draft scope of work contained herein reflects a plan of approach based on the known goals. One factor determining the selection of a consultant is the ability of that consultant to analyze the project goals, evaluate the work elements, and formulate a work plan. This process may produce new approaches or modification to the project work elements. Because of that, all consultants shall be aware that the Final Scope of Work for a project will be produced with input from the selected consultant.
The following sections are intended for preliminary information only. DEN has staff and contract consultants that may contribute and/or collaborate on the Project.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .