About this file

This is a Special Provision document issued by the Georgia Department of Transportation for the Gulfstream Road at Gulfstream Drive Intersection Improvements project located in Chatham County, Georgia. The project involves construction of intersection improvements and signalization at the intersection of Gulfstream Road and Gulfstream Drive between RB Miller Road and Savannah International Airport. The special provisions establish restrictive work hour requirements and traffic control conditions to manage impacts on the surrounding roadways during construction.

The contractor is prohibited from installing lane closures, pacing traffic, or moving equipment that interferes with traffic on Gulfstream Road between 7:00 am to 9:00 am and 4:00 pm to 7:00 pm, Monday through Friday, and on Gulfstream Drive between 7:00 am to 7:00 pm, Monday through Friday. All work must cease between 10:00 pm and 7:00 am per Chatham County noise ordinance requirements. Milled surfaces must be covered with asphaltic concrete mix within 48 hours before opening to traffic. Non-compliance with these provisions will result in liquidated damages assessed at $638.00 per hour or portion thereof for failure to reopen travel lanes during restrictive hours, $638.00 per calendar day for failure to reopen travel lanes during specified periods, and $638.00 per calendar day for failure to cover milled surfaces as required.

View the file

Other files

File Type Posted
20260316_Gulfstream Intersection Improvements.pdf PDF
Gulfstream ITB.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF TRANSPORTATION

STATE OF GEORGIA

SPECIAL PROVISION

GULFSTREAM ROAD AT GULFSTREAM DRIVE

INTERSECTION IMPROVEMENTS

CHATHAM COUNTY, GEORGIA

SECTION 108 - PROSECUTION AND PROGRESS

Retain Sub-Section 108.08 as written and add the following:

108.08. Failure or Delay in Completing Work on Time

C. Restrictive Work Hours

1. Failure to re-open travel lanes as specified in Special Provision Section 150.6.A will result in the assessment of liquidated damages in the amount of $638.00 per hour or portion thereof.

2. Failure to re-open travel lanes as specified in Special Provision Section 150.6.B will result in the assessment of liquidated damages in the amount of $638.00 per calendar day.

D. Milled Surfaces

Failure to cover milled surfaces as specified in Special Provision Section 150.6 will result in the assessment of liquidated damages in the amount of $638.00 per calendar day.

DEPARTMENT OF TRANSPORTATION

STATE OF GEORGIA

SPECIAL PROVISION

GULFSTREAM ROAD AT GULFSTREAM DRIVE

INTERSECTION IMPROVEMENTS

CHATHAM COUNTY, GEORGIA

SECTION 150 – TRAFFIC CONTROL

Add the following:

150.6 Special Conditions:

A. The Contractor shall not install lane closures, pace traffic, or move equipment or materials that interferes with traffic on Gulfstream Road between the hours of 7:00 am to 9:00 am and from 4:00 pm to 7:00 pm, Monday through Friday.

B. The Contractor shall not install lane closures, pace traffic, or move equipment or materials that interferes with traffic on Gulfstream Drive between the hours of 7:00 am to 7:00 pm, Monday through Friday.

C. The Contractor shall adhere to the Chatham County noise ordinance; no work will be allowed from 10:00 pm to 7:00 am.

D. Miscellaneous

1. Milled Surfaces:

All milled surfaces shall be covered within 48 hours before they are opened to traffic. Failure to cover milled surfaces with asphaltic concrete mix as required by the applicable typical section shall be considered a failure to comply with the requirements of Section 150 Traffic Control and shall result in the assessment of non-refundable deductions as specified in Special Provision Section

150.7.01 Enforcement and Adjustments.