This Performance Work Statement (PWS) details underground storage tank (UST) inspection requirements for Hanscom Air Force Base located in Massachusetts. The contractor must provide labor, tools, equipment, and personnel to perform comprehensive third-party inspections of UST systems and piping across four buildings (Buildings 1722, 1435, 1201, and 1642), involving a total of six tanks. Specific inspection requirements include performing vacuum tests on tank interstices, testing interstitial sensors, conducting catholic protection system tests, and generating detailed reports documenting leak detection equipment functionality, corrosion protection status, sump and sensor conditions, spill bucket installations, overfill protection, inventory monitoring, and overall system integrity.
The PWS outlines strict compliance requirements, including meeting 310 CMR 80.49 certification standards for third-party inspection reports, adhering to the Hanscom Air Force Base Contractor Environmental Guide, and providing comprehensive documentation. Contractors must perform inspections Monday through Friday between 06:00 a.m. and 4:00 p.m., excluding federal holidays, and must follow extensive environmental protection, safety, and hazardous material handling protocols. The inspection work requires detailed reporting, including a compliance certificate for each tank that passes inspection and a Return to Compliance Plan identifying any necessary corrective actions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK
STATEMENT
FOR
Underground Storage Tank Inspections Buildings
1722,1435,1201and 1642
PREPARED BY:
66 CE/CEOES
17 April 2025
1. DESCRIPTION OF SERVICES:
1.1. Scope: The Contractor shall provide all labor, tools, equipment, hoses, gauges, test equipment, hearing protection, eye protection including prescription safety glasses, materials, supplies and parts, transportation and other incidentals necessary to travel to Hanscom AFB, MA, to perform underground storage tank inspections. The Contractor shall be responsible for ensuring all services provided under this contract are in accordance with the terms and conditions outlined herein and conform to the manufacturers’ equipment specifications and this Performance Work Statement (PWS).
1.2. Requested Service: Perform Underground Storage Tank (UST) Inspections
• Contractor must meet 310 CMR 80.49 certification requirements for providing Third Party Inspection Reports (TPIR).
• Contractor shall perform all tests required to certify each Underground Storage Tank
(UST).
• Contractor must adhere to the Hanscom Air Force Base Contractor Environmental Guide.
• Work will include a third-party inspection in accordance with 310 CMR 80.49(7)(a):
o Performing inspections of Underground Storage Tank (UST) Systems and
Piping at Building 1722 (1 tank), 1435 (1 tank), 1201 (1 tank), 1642 (3 tanks), o Performing a vacuum test on interstices to check for tank tightness and testing interstitial sensors.
o Performing catholic protection system tests.
o Providing all necessary reports and documentation to determine:
Whether leak detection equipment has been installed, tested, maintained and is fully operational.
Whether corrosion protection, if applicable, has been installed, tested, maintained, and is fully operational.
Whether turbine, intermediate and dispenser sumps and sump sensors have been installed, inspected, tested and maintained.
Whether spill buckets have been installed, inspected, tested and maintained
Whether overfill protection has been installed, inspected, tested, maintained, and is fully operational.
Whether inventory monitoring, if applicable, has been performed and recorded.
Whether repairs and replacements have been conducted.
Whether periodic inspections have been conducted and recorded.
Whether the emergency response postings and written procedures are in compliance.
Whether alarms have been responded to and the responses documented.
Whether visual and/or olfactory observations indicate the presence of leakage or release related to the UST system or UST components.
o Providing a compliance certificate for each Underground Storage Tank (UST) that pass inspection.
o Providing a Return to Compliance Plan (RTC) identifying corrective actions, if necessary to certify each tank, including mechanical issues.
• Independent to the third party inspection, perform testing requirements for Spill Buckets and Overfill Prevention Equipment per 310 CMR 80.28 (2)(f).
1.3. Quality Assurance: According to the contract’s inspection clause, the Government will evaluate the Contractor’s performance under this contract. The COR is a representative of the Contracting Officer (CO) and will participate in the administration of this contract. Any matter concerning a change to the scope, prices, terms or conditions of this contract shall be referred to the CO. All services to be performed by the Contractor shall be subject to review by the CO or COR.
1.4. Continuation of Essential Services during Crisis: This requirement has been determined not to be essential and does not require continued support during a crisis as defined in DFARS Clause 252.237-7023.
1.5. Hours of Operation: The Contractor shall perform work Monday through Friday under this contract during the following hours: 06:00 a.m. until 4:00 p.m., excluding Federal Holidays. Work required to be performed outside of these hours shall only be done after approval from the Contracting Officer.
1.5.1 Federal Holidays:
New Year’s Day - 1 January Martin Luther King Day - 3rd Monday in January Washington’s Birthday - 3rd Monday in February Memorial Day - last Monday in May Juneteenth – 19 June Independence Day - 4 July Labor Day - 1st Monday in September Columbus Day - 2nd Monday in October Veteran’s Day - 11 November Thanksgiving Day - 4th Thursday in November Christmas Day - 25 December
If these holidays fall on Saturday, the preceding Friday shall be observed. If these holidays fall on Sunday, the following Monday shall be observed. If a holiday falls on a scheduled service day, the Contractor shall be responsible for rescheduling services for the first day following the holiday observance.
1.6. Contractor Personnel: The Contractor shall not employ persons on this contract if such employee is identified to the Contractor as a potential threat to the health, safety, security and general well-being or operational mission of the installation and its population. The Contractor shall not employ any person who is an employee of the United States Government if the employment of that person would create a conflict of interest, nor shall the Contractor employ any person who is an employee of the Department of the Air Force, either military or civilian, unless such person seeks and receives approval according to the DoD 5500.7-R Joint Ethics Regulations (JER). In addition, the Contractor shall not employ any person who is an employee of the Department of the Air Force if such employment would be contrary to the policies contained in AFI 64-106, Air Force Industrial Labor Relations Activities. The Contractor shall be prohibited from employing off-duty COR’s who are surveilling any contracts/subcontracts awarded to the Contractor. All contract employees depending on particular condition, occasion or place, or job assignment shall require professional, suitable attire. All Contractor employees shall conduct themselves in a professional, courteous manner. The selection, assignment, reassignment, transfer, supervision, management, and control of Contractor employees in performance of this PWS shall be the responsibility and prerogative of the contractor; however, the Contractor shall comply with the requirements set forth in this PWS and Hanscom AFB regulations concerning conduct of employees as referenced herein. The Contractor shall employ and maintain a technically trained and experienced work force.
1.7. Environmental Protection and Safety: The contractor shall be knowledgeable of and comply with all applicable federal, state and local laws, regulations and requirements regarding environmental protection and occupational safety and health. The contractor shall comply with any laws or regulation changes during the term of this contract. The contractor shall follow manufacturer’s guidelines and professional recommendations for control of humidity, temperature, cleanliness and materials handling (including hazardous materials).
1.8. Hazardous Material (HAZMAT): The Contractor shall not store chemicals/HAZMAT on Hanscom AFB. All chemicals/HAZMAT shall be approved prior to being transported on base for use by any contractor. The Contractor shall prepare and submit to the COR, ten (10) calendar days after contract award date, one (1) each, Chemical/Hazardous Material Request Authorization Form (Air Force Form 3952) and Safety Data Sheets (SDS) for each chemical, material and substance proposed to be used in performance of this PWS. The COR will forward the completed AF Form 3952(s) and SDS to 66 ABW/CEIE for approval. The Contractor shall not transport or use any chemical, material or substance on Hanscom AFB before written approval is provided by 66 ABW/CEIE. Contractor shall maintain copies of SDS(s) for all chemicals. The SDS(s) shall correspond with the manufacturers of the chemicals on hand.
Manufacturer, material, and SDS shall match. NOTE: SDS refers to manufacturer SDS. Once material is approved for use, contractor shall contact base Environmental Management (EM) (66 ABW/CEIE) and provide a list of all material. 66 ABW/CEIE shall determine any additional material requirements based on the hazard code of the material. Compliance required in accordance with Hanscom Air Force Base Hazardous Operation Plan (HMOP) Change 15, April 2023.
1.9. Hazardous Waste: Contractor shall dispose of any spent/processed chemical solutions and used rags in waste drums located in the shop/area where the work is being performed.
1.10. Discharges: Any discharges into industrial waste treatment plant (IWTP) or sanitary sewer shall be done in accordance with Hanscom Industrial Wastewater Discharge Permit as instructed by 66 ABW/CEIE. The Contractor shall maintain records of written authorization issued by 66 ABW/CEIE for discharges into IWTP and sanitary sewer.
1.11. The subject tanks are used in industrial applications with non-potable water and varying levels of heavy metals. For discharges outside of Hanscom AFB, the Contractor shall ensure wastewater discharges, that may contain RCRA regulated metals resulting from any contracted service, go to a state/federal permitted treatment facility such as a municipal Publicly Owned Treatment Works (POTW).
1.12. Spills: Upon occurrence of any spills that could enter the storm system or cause any harmful environment effects, the Contractor shall immediately call 911 to report the incident.
When possible, the contractor shall use a base telephone to receive help from Hanscom AFB
911. If using a cell phone, Contractor shall request Hanscom AFB 911. The Contractor shall report all environmental violations to the COR. The Contractor shall submit a typed or written report about the incident within four (4) clock hours of the occurrence of said incident. The Contractor shall provide five (5) copies of the written report. The Contractor shall provide one copy to the CO, two copies to the COR, a copy for the Unit Environment Coordinator (UEC) and a copy for record. The format of the report shall be left up to the Contractor, but the report shall contain the following information.
1.) Name and contact number of person reporting the spill 2.) Date and time of incident 3.) Location and source of spill 4.) Substance or pollutant spilled 5.) Amount spilled and the rate of discharge 6.) Any damages or injuries involved 7.) Extent of the area impacted 8.) Potential hazards 9.) Action taken 10.) Organizations contacted 11.) Remarks Section - that addresses the cause of the spill (e.g. human error, equipment) and whether 911 was called and which agencies responded.
1.13. Environmental and Safety Training: The Contractor personnel shall have Resource Conservation Recovery Act (RCRA) environmental and safety training required by the state and federal government. The training shall be IAW the following regulations: Resource Conservation Recovery Act (RCRA) 40 Code of Federal Regulation (CFR) 265.16 “Personal Training”, Occupational Safety and Health Administration (OSHA) Hazardous Waste Operations and Emergency Response Standard Title 29, CFR Part 1910.120 “Hazardous Waste Operations and Emergency Reponses”, Hazardous Waste Management Instruction, Section 13, and Air Force Instruction (AFI) 32-7042, “Solid and Hazardous Waste Compliance”, Section 2.The Contractor shall provide the environmental and safety training certificate for all employees to the CO and COR, after contract award date.
1.14. Housekeeping: The Contractor shall keep the work areas clean and neat in accordance with Industry Standards, Occupational, Safety and Health Administration (OSHA), fire and safety standards and this PWS.
1.15. Privately Owned Motor Vehicles (POV): Contractor personnel shall comply with the directives pertaining to operation of POVs on Hanscom AFB per AFI 31-204 (in its entirety), Motor Vehicle Traffic supervision.
1.16. Visitor Pass: The Contractor shall comply with requirement and procedures IAW FAR 5353.242-9000, Contractor Access to Air Force Installations. Prior to coming to Hanscom AFB to perform any work, Contractor shall contact the Civil Engineering Government Representative to coordinate access to the base as well as to the building (s) where the work shall be performed. A list of the names of the workers shall be required to gain access, and passes shall be distributed at the visitor’s building at Vandenberg Gate. Workers shall have a REAL ID-compliant driver’s license, Real ID-compliant state identification card or valid passport. If bringing a vehicle on base, the Contractor will need proof of registration and insurance of that vehicle. Contractor employees must have identification that readily identifies them as contractors. During the contract, certain areas/sites may be restricted or closed to Contractor personnel. The Contractor shall comply with all requirements for entry. In addition, unscheduled gate closures may occur at any time and personnel entering or exiting the installation may experience delays.
To maintain accountability once gaining access onto Hanscom AFB, Contractor shall immediately sign the logs at Building 1810, indicating time and date of arrival. Before departure, Contractor shall again sign the logs indicating the departure time, as well as the work performed, and the buildings worked in. A copy of a signed work receipt on Contractor’s letterhead detailing work performed shall also be given to the Civil Engineering Government Representative or left in the logbook prior to departure
1.17. Foreign National(s): The Contractor shall notify the COR before sending a Foreign National representative to perform services. Special rules apply for foreign national(s) visiting a US Government facility.
1.18. Health and Safety on Government Installation: In performing work under this contract on a Government installation, the Contractor shall comply with federal, state and local regulations regarding occupational safety and health and the specific health and safety requirements established by this contract. The Contractor shall notify the COR of any injuries that occur to Contractor personnel while on the installation. The Contractor shall notify the COR of damage to Government property or equipment during the execution of the contract.
1.19. Emergency Procedures: Contractor employees shall follow the direction of Government employees regarding emergency evacuation procedures, i.e. fire, tornado, active shooter and bomb threats. It is the Contractors’ responsibility to account for their employees following an emergency evacuation. Contractor personnel shall participate with government personnel in all fire and tornado drills, and at no additional cost to the government.
SECTION 2
Performance Assessment
The Contractor shall be aware that the absence of any contract requirement from the Service Summary does not detract from its enforceability nor limit the rights or remedies of the Government under any other provision of the contract. The Contractor shall ensure the following service summary requirements are accomplished.
2.1.
Performance
Objective
PWS
Para.
Performance
Threshold
Method of Assessment
SS 1: Clean and maintain boilers in accordance with the established schedule
1.2 100% Compliance Visual inspection
SECTION 3
GOVERNMENT-FURNISHED PROPERTY AND SERVICES
3.1. Government Furnished Property (GFP): Government Furnished Property is not applicable to the in the performance of this contract.
3.2. Reserved.
3.3. Government Furnished Services: Government Furnished Services are applicable during the performance of this contract.
3.3.1. Security Police: The Government will provide general on-base Security Forces service.
The Security Forces’ telephone number is 911 for emergencies, for crime in progress 781-225- 5613 and 781-225-5613 for non-emergency calls.
3.3.2. Fire and Emergency Services: The Government will provide general on-base fire protection services. The Contractor shall comply with fire prevention rules and regulations enforced by the Hanscom AFB Fire Prevention Branch. Call 911 for emergencies. For routine fire prevention matters and/or calls to dispatch, call 781-225-3330.
Note: Calling 911 from a cell phone will be received by off base emergency 911 systems, causing a delay in response time by emergency personnel. When possible, use a base telephone to receive on base help.
3.3.3. Utilities: The Government will furnish utility services. These utilities include natural gas, electricity, water and sewer for the sole purpose of accomplishing this contract. If the Contractor requires additional utility services, it shall be the Contractor’s responsibility to provide such services. Contractor shall use due care and diligence in efforts to conserve utilities in order to reduce utility costs.
3.3.4. Refuse Collection: The Government will provide refuse collection services limited to the extent provided in the Base Refuse Collection Contract for Government provided facilities.
The Government will only allow non-hazardous refuse to be emptied into the nearest authorized refuse dumpster for trash collection. Government dumpsters shall not be used for collection of Contractor debris.
3.3.5. Workspace: The Government will provide adequate workspace around the equipment area.
| 1.7. Environmental Protection and Safety: The contractor shall be knowledgeable of and comply with all applicable federal, state and local laws, regulations and requirements regarding environmental protection and occupational safety and health. The... |
| Method of Assessment |