About this file
This Addendum No. 1 is issued by the City of Owosso for the 2025 Sewer Lining Project, with bids due on April 22, 2025 at 3pm. The addendum modifies the previously issued bidding documents and adds a "2025 Sewer Lining Project Questions" section to the contract documents. The document provides clarification on staging areas for the cleaning contractor, specifically that the Owosso Department of Public Works (DPW) yard can be used for storing roll-off boxes and equipment between 7:30am and 3pm, Monday through Friday.
The addendum addresses two key questions from potential bidders: availability of staging areas for roll-off boxes and equipment storage. The city specifies that all roll-off boxes must comply with the Owosso Code of Ordinances, not emit any odors, and any vehicles or containers brought to the site must be marked with the owner's contact information. No specific pricing, funding sources, or contract value details are provided in this addendum, which appears to be a supplementary document to provide additional operational guidance for bidders on the sewer lining project.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM
Addendum No. 1
Owner: City of Owosso Project: 2025 Sewer Lining Project Engineer: City of Owosso
NOTICE TO ALL PROSPECTIVE BIDDERS
BIDS DUE: April 22, 2025 at 3pm
This Addendum is a part of the Contract Documents and modifies the previously issued Bidding Documents. Acknowledge receipt of this Addendum in the space provided on the “Signature Page and Legal Status” section of the Bid Proposal. Failure to do so may result in rejection of the Bid.
ITEM NO. 1:
Add “2025 Sewer Lining Project Questions” to the Contract Documents.
END OF ITEM NO. 1
END OF ADDENDUM NO. 1
2025 Sewer Lining Project Questions
Q: Will the city provide a staging area for the cleaning contractor to store roll off boxes?
A: The city of Owosso DPW yard can be used for the storage of roll off boxes. The DPW yard is open from 7:30am to 3pm, Monday through Friday. All roll off boxes shall meet the requirement of the city of Owosso Code of Ordinances and shall not emit any odor.
Q: Will the city provide a staging area for the cleaning contractor to store equipment?
A: The city of Owosso DPW yard can be used for the storage of equipment. The DPW yard is open from 7:30am to 3pm, Monday through Friday. Any vehicles or containers brought onsite shall be marked with the owner’s contact information.
| 2025 Sewer Lining Project Addendum 1 |
| 2025 Sewer Lining Project Questions |
File details come from the government source that posted it. Updated .