2025 Bid Schedule.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
2025 Helical Pier Retrofit - Noise Wall Rehabilitation Project
Solicitation number
94005-2025-1
Issued by
Arapahoe County, Colorado

About this file

The 2025 Bid Schedule.xlsx is a detailed bidding document for the City of Colorado's Helical Pier Retrofit - Noise Wall Rehabilitation Project, covering six distinct wall locations: Cherry Creek Village North, DTC Roundtree, Greenwood Gardens, Orchard Farms, Sundance Valley, and Union. The project involves installing helical piers and providing traffic control, with a total of 163 piers to be installed across the six sites. Each wall section has a standardized bid structure featuring two line items: "Install New Helical Pier" (measured in individual piers) and "Traffic Control" (as a lump sum), though the current document shows placeholder zero-dollar amounts where actual pricing will be inserted.

The bid schedule provides a comprehensive breakdown of quantities, with pier installation volumes ranging from 11 piers (Greenwood Gardens) to 62 piers (Cherry Creek Village North), totaling 163 piers for the entire project. While specific pricing details are not populated in this document, the structured format suggests a competitive bidding process where contractors will submit unit pricing for pier installation and traffic control. The project appears to be a systematic noise wall rehabilitation effort focused on structural reinforcement through helical pier installation, indicating potential infrastructure maintenance or resilience improvement across multiple municipal locations in Colorado.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Wall #8 - Cherry Creek Village North (CCVN)
Bid ItemUnitQtyUnit CostTotal
1Install New Helical PierEA62$ - 0
2Traffic ControlLS1$ - 0
Totals$ - 0
Wall #12 - DTC Roundtree
Bid ItemUnitQtyUnit CostTotal
1Install New Helical PierEA17$ - 0
2Traffic ControlLS1$ - 0
Totals$ - 0
Wall #15 - Greenwood Gardens
Bid ItemUnitQtyUnit CostTotal
1Install New Helical PierEA11$ - 0
2Traffic ControlLS1$ - 0
Totals$ - 0
Wall #20 - Orchard Farms
Bid ItemUnitQtyUnit CostTotal
1Install New Helical PierEA13$ - 0
2Traffic ControlLS1$ - 0
Totals$ - 0
Wall #24 - Sundance Valley
Bid ItemUnitQtyUnit CostTotal
1Install New Helical PierEA40$ - 0
2Traffic ControlLS1$ - 0
Totals$ - 0
Wall #26 - Union
Bid ItemUnitQtyUnit CostTotal
1Install New Helical PierEA20$ - 0
2Traffic ControlLS1$ - 0
Totals$ - 0
Totals for the Project
Total Piers163$ - 0
Project Cost$ - 0