This Statement of Work (SOW) details a waste wood disposal project for the Blue Grass Army Depot (BGAD) in Richmond, Kentucky. The contractor will be responsible for removing all waste wood accumulated on a concrete hard stand in the Qualified Recycling Program (QRP) yard, using a Backhoe/Loader or similar equipment to load and transport the wood off the depot property. Key requirements include weighing the processed wood on a certified drive-on/drive-off scale, disposing of the material legally, assuming full liability for expenses, and completing the project within 365 days of contract award. Work is restricted to Monday through Thursday, from 06:30 AM to 5:00 PM, with the contractor responsible for maintaining a clean worksite, removing all debris, and cleaning up any equipment-related spills at no additional cost to the government.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
Project Title: Disposal of Waste Wood Project Location: Qualified Recycling Program Building 266, Blue Grass Army Depot, Richmond, Kentucky
Revised: 28 October 2025
1.0 GENERAL
The Contractor shall provide all labor, equipment, fuel, and materials necessary to perform the work as outlined in this Statement of Work (SOW).
During execution of the work, the contractor shall provide adequate professional supervision, quality control, and complete the work on schedule and in a safe manner.
2.0 INTRODUCTION
Waste wood generated by diverse processes on Blue Grass Army Depot (BGAD) accumulates on a concrete hard stand in the QRP yard, the location for this project. The contractor will coordinate all work involved, including the weighing of all processed wood at the certified drive-on/drive-off scale adjacent to Building 266, and the transportation of the waste wood off BGAD property. The contractor shall dispose of the material in a legal and responsible manner of their choosing and shall be responsible for the expenses and/or revenue from any sale of the material. The contractor assumes complete liability for all expenses related to the pickup and transport of material awarded by this agreement. The government assumes no liability for damage caused to the contractor property while working on this project. The equipment brought on to BGAD shall be one Backhoe/Loader or similar equipment to pick up and load trucks for hauling the wood off the depot. No grinding/mulching shall be performed on BGAD property.
3.0 PROJECT SCOPE
All scrap waste wood to be hauled away is contained on the hard stand area in piles. Wood to be hauled away includes all wood in that location.
4.0 CLEANUP
The contractor shall be responsible for maintaining a reasonably tidy worksite. The worksite shall be cleaned of contractor-generated trash and debris daily. The contractor shall be responsible for removing all debris associated with the handling and transport of the waste wood at no additional cost to the Government. The contractor shall be responsible for cleaning up any spills caused during operation of their equipment and for the disposal of spill clean-up materials.
5.0 SCHEDULE
The Contractor shall complete the work within 365 days of contract award.
Working hours at BGAD are from 06:30 AM to 5:00 PM Monday through Thursday only.
***END SCOPE***