The document is a Notice to Bidders/Invitation to Bid from Whiting-Turner Contracting Company for Trade Bid Package 1A for Frederick County Public Schools (FCPS) for Elementary School #41, located at 5680 Mussetter Road, New Market, MD. The bid package covers site work activities including mass grading, import/export, sediment and erosion control, temporary perimeter fencing, contractor staging areas, and temporary water services. Key dates include a project bid advertisement on April 14th, 2025, a pre-bid conference and site visit on April 21st, 2025, a pre-bid RFI deadline on April 23rd, 2025, and a project bid due date of May 5th, 2025, with a planned project start in June 2025 and expected completion in November 2025.
The project has an overall Minority Business Enterprise (MBE) goal of 15% with no sub-goals, and MBE participation will be evaluated as part of the award. Prevailing wage rates will apply to all bidders, and only 31A and/or 33A divisions of work are anticipated for this trade bid package. Bidders must complete Whiting-Turner's prequalification program prior to submitting a bid, and failure to comply could result in the bid being deemed non-responsive. Bid documents can be obtained electronically through Whiting-Turner's Building Connected website, and interested parties must contact Ryan Fox or Greg Kile to receive project access.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
I N T E G R I T Y E X C E L L E N C E E X P E R I E N C E L E A D E R S H I P
W H I T I N G -T U R N E R C O N T R A C T I N G C O M P A N Y
DESCRIPTION Trade Bid Package 1A - Site work activities to include, but are not necessarily limited to Mass
Grading, import/export, Sediment and Erosion control, Temporary perimeter fencing, Contractor
Staging Areas, temporary water, etc as required to complete this scope of work.
MDOT Certified Minority Business Enterprises are encouraged to respond to this solicitation notice. The project has an overall MBE Goal of 15% with no sub-goals. MBE participation will be evaluated as part of the award.
Prevailing Wage Rates Will Apply for ALL BIDDERS
SCHEDULE TR A DE B I D PA CK A G E 1 A – M A S S GR A D I N G
Project Bid Advertisement – April 14th, 2025
Pre-bid Conference and Site Visit – April 21st, 2025 @ 11:00am
Pre-bid RFI Deadline – April 23rd, 2025 @ 2:30pm
Project Bid Due Date – On or Before May 5th, 2025 @ 11:00am
Project Start – June of 2025
CO N TR A CT A W A R DS C O N S TR UC TI O N S TA R T E XP E C TE D C O M PL E TI O N
May/June, 2025 June, 2025 (Site Package) November, 2025
CONTACTS Ryan Fox
Cell: 443-802-0794
Email: ryan.fox@whiting-turner.com
Greg Kile
Cell: 443-201-6657
Email: greg.kile@whiting-turner.com
PACKAGES
BIDDING
REQUIREMENTS
Only 31A and/or 33A Divisions of work are anticipated for Trade Bid Package 1A.
Bid Documents may be obtained electronically from the Construction Manager, The Whiting-Turner
Contracting Company through Whiting-Turners Elementary School #41 Building Connected website.
Please contact Ryan Fox or Greg Kile to receive access to this project.
All Bidders shall complete Whiting-Turner’s prequalification program prior to submitting a bid. Failure to comply with Whiting-Turner’s pre-qualification process could result in the bid being determined as non-responsive.
Pre-bid Conference and Site Visit – The Construction Manager and FCPS will review the scope of Trade
Bid Package 1A and answer questions about the bidding documents. Attendance is strongly recommended and will assist the Owner in evaluating bids to determine if the bid can be considered responsive and/or responsible.
Proposals must be submitted on provided BID FORM with Bid Bond electronically through Building
Connected and/or Email. All BIDS/PROPOSALS must be SEALED.
The bidder or offeror acknowledges the MBE Participation requirements and will submit their completed bid forms and MBE participation forms accordingly. Proposals that do not acknowledge the
MBE goals along with the required documentation for the project may not be considered responsive.
The Conditions contained in this Notice to Bidders – Invitation to bid, are a part of the Bid Documents.
The Owner and Construction Manager reserve the right to waive any informality in, or to reject any or all bids.
Scope review meetings will be held immediately following the bid due date. Please plan to be available for a descope at the Whiting-Turner main office. May 6th – May 9th.
The Apparent Qualified Bidder shall be requested to submit other Minority Business Enterprise materials and supporting data within five (5) working days after notification that the firm is the apparent Qualified bidder.
NOTICE TO BIDDERS/INVITATION TO BID
TRA DE BI D PA CK A G E 1A - E L E ME NT A RY SC H O O L #41
5680 Mussetter Road, New Market, MD 21774
I N T E G R I T Y E X C E L L E N C E E X P E R I E N C E L E A D E R S H I P
W H I T I N G -T U R N E R C O N T R A C T I N G C O M P A N Y
File details come from the government source that posted it. Updated .