2025-013A UpFit_Addendum #1.pdf
PDF 211 KB Posted
- Solicitation number
- 2025-013A
- Issued by
- Cherokee County, Georgia
About this file
This document is Addendum #1 for Solicitation Number 2025-013A issued by the Cherokee County Board of Commissioners Purchasing Department on March 4, 2025, related to the Cherokee Sheriff's Office Real Time Intelligence Center (RTIC) "Upfit" project. The addendum addresses three specific questions from potential bidders regarding the solicitation, providing clarifications about floor plans, contractor licensing requirements, and submittal instructions. The addendum indicates that "As Built" plans in .pdf format are available in an attached file named "Shaw Woodard Building Scans 10Dec2024.pdf", and confirms that neither Appendix G nor a General Contractor's License is required for this project.
The addendum does not provide detailed pricing, funding sources, or comprehensive project specifications, but serves as a clarifying document to assist potential bidders in understanding the submission requirements. By releasing this addendum, the Cherokee County Board of Commissioners is ensuring that all bidders have access to consistent and accurate information about the RTIC project's technical and administrative requirements, which helps to promote fair and competitive bidding practices.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CHEROKEE COUNTY BOARD OF COMMISSIONERS
Purchasing Department 1130 Bluffs Pkwy, Canton, GA 30114
Ph: 678-493-6000 | Fax: 678-493-6035
ADDENDUM # 1
Solicitation Number: 2025-013A Solicitation Name: CHEROKEE SHERIFF’S OFFICE (RTIC) REAL TIME INTELLIGENCE
CENTER “UPFIT”
Addendum Release Date: March 4, 2025
Prime Bidders/Proposers acknowledge the receipt of this Addendum by inserting the number and date in the appropriate position on the Proposal Form. Failure to do so may subject the Bidder/Proposer to disqualification. This Addendum is a part of the Contract Documents. It modifies them as follows:
Question: Can floor plans for the space be provided, preferably in AutoCAD or PDF format?
Answer: Only the “As Built” plans are available and are in .pdf format. See attached file
“Shaw Woodard Building Scans 10Dec2024.pdf”.
Question: Under Submittal Instructions, what kind of contractor’s license is required for
Appendix G if no construction work is being performed by the selected vendor?
Answer: Appendix G is not required.
Question: Under Submittal Instructions, the box for General Contractor’s License is marked off. Is this accurate since there is no construction work being requested in the Statement of Work?
Answer: General Contractor’s License is not required.
**END**