2025-01 2025 Slurry Seal Project ITB_FINAL.pdf
PDF 1 MB Posted
- Attached to
- 2025 SLURRY SEAL PROJECT
- Solicitation number
- S-KA0010-00012666
- Issued by
- Jackson County, Oregon
About this file
This is an Invitation to Bid (ITB) issued by the City of Ashland, Oregon for the 2025 Slurry Seal Project (Project No. 2025-01). The project involves road construction work including the placement of Type I and Type III Emulsified Asphalt Slurry Seal and installation of permanent pavement markings across multiple street sections in Ashland. The work includes temporary traffic control, erosion control measures, and pavement marking installation. Bids are due by 2:00:00 PM PST on Tuesday, February 18, 2025. The contractor must complete all work within 60 calendar days following receipt of the written Notice to Proceed, with a final completion deadline of June 30, 2025.
The project requires a 10% bid bond or security, and the successful bidder must provide performance and payment bonds each equal to 100% of the contract amount. The contractor must maintain commercial general liability insurance of $2 million per occurrence/$4 million aggregate and commercial automobile liability insurance of $2 million. The work includes slurry seal application across approximately 140,000 square yards total across various city streets and multi-use paths, with a daily installation limit of 20,000 square yards unless pre-approved by the Project Manager. The project is locally funded and requires compliance with Oregon prevailing wage rates. The city reserves the right to reject any and all bids.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2025 Slurry Seal_TCP_flat.pdf | ||
| Beans Pinto.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID
FOR A PUBLIC WORKS CONSTRUCTION PROJECT
CITY OF ASHLAND, OREGON
PROJECT NAME: 2025 SLURRY SEAL PROJECT
PROJECT NUMBER: 2025-01
PROJECT TYPE: Road Construction
BIDS DUE BY: 2:00:00 pm PST, Tuesday, February 18, 2025
DESCRIPTION OF WORK
2025 SLURRY SEAL PROJECT
Project No. 2025-01
Road Construction
TIME AND PLACES OF RECEIVING BIDS (BID CLOSING)
Bid Closing for the work described above will be at 2:00:00 pm on the 18th day of February 2025. Bids will be received by Chuck Schweizer, Street Supervisor at the following time and places:
Before 2:00:00 pm on the day of Bid Closing.
For Bids submitted by mail or parcel delivery service, send to:
City of Ashland c/o Chuck Schweizer, Street Supervisor
20 E. Main Street
Ashland, OR 97520
For Bids submitted by hand delivery, obtain a date stamp on the Bid and submit to:
c/o Chuck Schweizer, Street Supervisor
51 Winburn Way
Ashland, OR 97520
Bids, Bid modifications, and Bid withdrawals will not be accepted at or after 2:00:00 pm on the day of Bid
Closing.
PLACE, TIME, AND DATE OF READING BIDS (BID OPENING)
Bid Opening for the work described above will be in the Siskiyou Room of the Community Development and Engineering Services Building, 51 Winburn Way, Ashland, Oregon, beginning at 2:00:00 pm on the day of Bid Closing.
COMPLETION TIME LIMIT
See Special Provisions Subsection 00180.50(h).
CLASS OF PROJECT
This is a Locally Funded Project.
APPLICABLE SPECIAL PROVISIONS
The Special Provisions booklet applicable to the above-described work, for which Bids will be opened at the place, time, and date stated above, is that which contains the exact information as shown above on this page.
Bidders are cautioned against basing their Bids on a booklet bearing any different description, date(s), Class of Project, or Class of Work.
i | P a g e
Introduction and Table of Contents
All Contract Documents are listed below. Documents are either attached or bound separately and available from the
Project Manager. All Documents bound separately are incorporated into the Contract Documents and have the same force and effect as though set forth in full herein.
PART I – BID & CONTRACT DOCUMENTS
BID AND BID SCHEDULE
FIRST-TIER SUBCONTRACTOR DISCLOSURE FORM
PUBLIC IMPROVEMENT CONTRACT
CONTRACTOR DATA, CERTIFICATION, AND SIGNATURE
CERTIFICATE OF REPRESENTATION
EXHIBIT A - STANDARD TERMS AND CONDITIONS FOR PUBLIC IMPROVEMENT
CONTRACTS
ATTACHMENTS: EXHIBITS B-K
BID BOND
PERFORMANCE BOND
PAYMENT BOND
PART II - SPECIAL PROVISIONS
SECTION 00110 - ORGANIZATION, CONVENTIONS, ABBREVIATIONS AND DEFINITIONS
SECTION 00120 - BIDDING REQUIREMENTS AND PROCEDURES
SECTION 00130 - AWARD AND EXECUTION OF CONTRACT
SECTION 00140 - SCOPE OF WORK
SECTION 00150 - CONTROL OF WORK
SECTION 00170 - LEGAL RELATIONS AND RESPONSIBILITIES
SECTION 00180 - PROSECUTION AND PROGRESS
SECTION 00190 - MEASUREMENT OF PAY QUANTITIES
SECTION 00195 - PAYMENT
SECTION 00196 - PAYMENT FOR EXTRA WORK
SECTION 00197 - PAYMENT FOR FORCE ACCOUNT WORK
SECTION 00199 - DISAGREEMENTS, PROTESTS, AND CLAIMS
TECHNICAL SPECIAL PROVISIONS
SECTION 00210 - MOBILIZATION
SECTION 00220 - ACCOMMODATIONS FOR PUBLIC TRAFFIC
SECTION 00221 - COMMON PROVISIONS FOR WORK ZONE TRAFFIC CONTROL
SECTION 00222 – TEMPORARY TRAFFIC CONTROL SIGNS
SECTION 00290 - ENVIRONMENTAL PROTECTION
SECTION 00706 - EMULSIFIED ASPHALT SLURRY SEAL SURFACING
SECTION 00865 - LONGITUDINAL PAVEMENT MARKINGS - DURABLE
PART III – PROJECT TRAFFIC CONTROL PLANS
ii | P a g e
CHECKLIST FOR BID SUBMITTAL
1. Bid & Bid Schedule
Fill in bidder information on first page
Indicate amount of bid bond on paragraph 17
Indicate bidder status on paragraph 24
Indicate number of addenda received on paragraph 31
Fill in bidder information and sign paragraph 34
Fill in unit prices and amounts for all bid items
Fill in total bid amount
2. First Tier Subcontractor Disclosure Form
Fill in this form and include with bid schedule (or within 2 hours of closing).
3. Bid Bond
Provide 10% bid bond on form included on page 45.
iii | P a g e
CHECKLIST FOR CONTRACT SUBMITTAL
1. Standard Public Improvement Contract
Fill in contractor data and certification on page 2 and 3 of the contract form.
Sign on page 3 of the contract form
2. Certifications of Representation
Check all items that apply and sign
3. IRS Form W-9
4. Insurance certifications as required by Exhibit C (page 42)
5. Exhibit D – Certification Statement for Corporation as Independent Contractor
6. Performance Bond
Provide on form provided on page 46 (or approved surety form)
7. Payment Bond
Provide on form provided on page 48 (or approved surety form)
1 | P a g e
PART I – BID & CONTRACT DOCUMENTS
2 | P a g e
BID AND BID SCHEDULE
TO FURNISH ALL PERMITS, LABOR, TOOLS, MACHINERY, MATERIALS,
TRANSPORTATION, EQUIPMENT AND SERVICES OF ALL KINDS REQUIRED FOR THE
CONSTRUCTION OF THIS PROJECT FOR THE CITY OF ASHLAND, JACKSON COUNTY,
OREGON, AS STATED IN THE COMPLETED BID SCHEDULE, ALL IN ACCORDANCE WITH
THE CONTRACT DOCUMENTS, PLANS, SPECIFICATIONS, AND DRAWINGS WHICH ARE
ON FILE AT THE CITY OF ASHLAND, CITY HALL, 20 EAST MAIN STREET, ASHLAND,
OREGON 97520.
NAME OF BIDDER ____________________________________
CONTACT ___________________________________________
ADDRESS ____________________________________________
CITY _____________________ STATE __________ZIP_______
TELEPHONE NO.______________________________________
FAX NO. _____________________________________________
EMAIL ADDRESS _____________________________________
To the Honorable Mayor and City Council
City Hall
City of Ashland
20 East Main Street
Ashland, Oregon 97520
In response to the City of Ashland’s Invitation to Bid, this Bid is submitted as an offer by the undersigned to enter into a contract with the City of Ashland for furnishing all permits, labor, tools, machinery, materials, transportation, equipment and services of all kinds required for, necessary for, or reasonable incidental to, the construction of the 2025 SLURRY SEAL PROJECT No. 2025-01
(hereinafter “Project”) for the City of Ashland, Oregon, as shown in the contract documents on file at City
Community Development Building, which are a condition of this Bid as though they were attached. This offer is subject to the following declarations as to the acts, intentions and understandings of the undersigned and the agreement of the City of Ashland to the terms and prices herein submitted.
1. The undersigned has familiarized itself with the nature and extent of the Contract Documents, the project work, the site, the locality, the general nature of work to be performed by the City or others at
3 | P a g e the site that relates to the project work required by the Contract Documents, local conditions, and federal, state, and local Laws and Regulations that in any manner may affect cost, progress, performance, or furnishing of the project work.
2. The undersigned has obtained and carefully studied (or assumes responsibility for obtaining and carefully studying) examinations, investigation, exploration, tests, and studies which pertain to the conditions (subsurface or physical) at or contiguous to the site or otherwise and which may affect the cost, progress, performance, or furnishing of the project work as Contractor deems necessary for the performance and furnishing of the project work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract Documents; and no additional or supplementary examinations, investigations, explorations, tests, reports, or similar information or data are or will be required by Contractor for such purposes.
3. It is understood that the City shall investigate and determine the qualifications of the apparent low responsive bidder prior to awarding the contract. The City shall reject any bid by a nonqualified or disqualified bidder. The City of Ashland reserves the right to reject for any good cause any or all bids, waive formalities, or to accept any bid which appears to serve the best interests of the City. The
City reserves the right to reject any bid not in compliance with all prescribed public bidding procedures and requirements and may reject all bids for good cause upon a finding that it is in the public interest to do so. Evaluation of bids will be based on minimum requirements established by the specifications and compliance with conditions of the Notice to Contractors and Invitation to Bid, and compliance with City public contracting rules. Additional evaluation criteria are as follows: None.
4. The deadline to file a written protest or request, pursuant to the Instructions to Bidders to change contract terms, conditions or specifications is not less than ten (10) calendar days prior to bid opening. Bid closing may be extended by the City to consider a protest or request.
5. All of the contract documents, including all plans, specifications, and drawings have been examined and an examination of the site of the proposed work, together with such investigations as are necessary to determine the conditions to be encountered have been made by the undersigned and the terms and conditions of the contract and solicitation documents are hereby accepted, and that if this
Offer is accepted, the undersigned will contract with the City of Ashland, Oregon, in a form substantially similar to that attached Agreement and agree to be bound to the terms and conditions of said contract and solicitation documents.
6. It is understood that the contract drawings may be supplemented by additional drawings and specifications in explanation and elaboration thereof and, if they are not in conflict with those referred to in paragraph 1 above, they shall have the same force and effect as though they were attached, and they shall be accepted as part of the contract when issued.
7. The undersigned agrees that upon written acceptance of this bid s/he will, within ten working days, of receipt of such notice, execute a formal contract agreement with the City. The undersigned further agrees that s/he will provide the following in order to execute the contract:
Performance Bond and Corporate Surety Payment Bond, both in the amount equal to 100% of the awarded contract;
Certificates of Insurance for Liability and property damage coverage;
Certificates of Coverage for Workman Compensation and unemployment insurance;
All other bonds, permits, licenses, etc. as required in the contract documents.
8. It is understood that all the work will be performed under a lump sum or unit price basis and that for the lump sum or unit price all services, materials, labor, equipment, and all work necessary to complete the project in accordance with the plans and specifications shall be furnished for the said lump sum or unit price named. It is understood that the quantities stated in connection with the price schedule for the contract are approximate only and payment shall be made at the unit prices named
4 | P a g e for the actual quantities incorporated in the completed work. If there shall be an increase in the amount of work covered by the lump sum price, it shall be computed on a basis of “extra work” for which an increase in payment will have been earned and if there be a decrease in the lump sum payment, it shall be made only as a result of negotiation between the undersigned and the Owner.
Furthermore, it is understood that any estimate with respect to time, materials, equipment, or service which may appear on the plans or in the specifications is for the sole purpose of assisting the undersigned in checking the undersigned’s own independent calculations and that at no time shall the undersigned attempt to hold the Owner, the Engineer, or any other person, firm or corporation responsible for any errors or omissions that may appear in any estimate.
9. The undersigned submits the unit prices as those at which he will perform the work involved. The extensions of the column headed "ITEM TOTAL" are made for the sole purpose of facilitating bid comparisons and if there are any discrepancies between the unit prices and the total amount shown, the unit prices shall govern.
10. The undersigned agrees to furnish labor, tools, machinery, materials, transportations, equipment and services of all kinds required for, necessary for, or reasonably incidental to, construction of this
Project with all appurtenant work as required by the plans and specifications of this Offer for the unit or lump sum prices in the "BID SCHEDULE".
11. In stating prices, it is understood that the prices include all materials and work required to complete the project in accordance with the Contract Documents, the plans and the specifications. If any material, item, or service required by the plans and specifications has not been mentioned specifically in the "BID SCHEDULE," the same shall be furnished and placed with the understanding that the full cost to the City has been merged with the several prices stated in the "BID SCHEDULE."
12. The City reserves the right to cancel this solicitation or to reject any and all bids in whole or in part when the cancellation or rejection is in the best interests of the City as determined by the City in accordance with ORS 279B.100
13. The foregoing prices shall include all labor, materials, equipment, overhead, profit, insurance, and all other incidental expenses to cover the finished work of the several kinds called for. Unit prices are to be shown in both words and figures. In case of any discrepancy, the amounts shown in words shall govern.
14. Upon receipt of written notice of the acceptance of its bid, Bidder shall execute a formal contract with the City within ten (10) days, deliver surety bond or bonds as required, and deliver required proof of insurance. The bid security attached in the sum of five percent (5%) of the total price for the bid or combination of bids is to become the property of the Owner in the event the contract and bond are not executed within the time above set forth as liquidated damages for the delay and additional expense to the Owner caused thereby.
15. If the proposed bid price will exceed $50,000.00 the undersigned, as bidder, acknowledges that provisions of ORS 279C.800 to 279C.870 relating to workers on public works to be paid not less than prevailing rate of wage shall be included in the contract, or in the alternative, if the project is to be funded with federal funds and is subject to the Davis-Bacon Act (40 U.S.C. §276a) bidder agrees to comply with the Davis- Bacon Act requirements. “Prevailing Wage Rates for Public Works
Contracts in Oregon,” which are incorporated herein by reference, and can be accessed at:
https://www.oregon.gov/boli/WHD/PWR/Pages/pwr_state.aspx
16. The undersigned shall furnish bonds required by the specifications and comply with the laws of the
Federal Government, State of Oregon and the City of Ashland which are pertinent to construction contracts of this nature even though such laws may not have been quoted or referred to in the specifications.
17. Accompanying this Offer is a certified check, cashier's check or a bid bond, for the sum of
_____________________, payable to the City of Ashland, Oregon, this being an amount for ten https://www.oregon.gov/boli/WHD/PWR/Pages/pwr_state.aspx
5 | P a g e percent (10%) of the total bid based upon the estimate of quantities at the above price according to the conditions of the advertisement. If this Offer is accepted by the City and the undersigned fails to execute a satisfactory contract and bonds as stated in the Advertisement within ten (10) working days from the date of notification, then the City may, at its option, determine that the undersigned has abandoned the contract and there upon this Offer shall be considered null and void, and the bid security accompanying this Offer shall be forfeited to and become the property of the City of
Ashland. If the bid is not accepted, the bid security accompanying this Offer shall be returned to the undersigned.
18. The undersigned agrees to comply with the provisions of ORS 279C.800 to 279C.870, the Oregon
Prevailing Wage law. The undersigned, as bidder, acknowledges that provisions of ORS 279C.800 to 279C.870 relating to workers on public works to be paid not less than prevailing rate of wage shall be included in the contract, or in the alternative, if the project is to be funded with federal funds and is subject to the Davis-Bacon Act (40 U.S.C. §276a), bidder agrees to comply with the Davis-
Bacon Act requirements. The undersigned Contractor agrees to be bound by and will comply with the provisions of ORS 279C.838, 279C.840 or 40 U.S.C. 3141 to 3148. [OAR 137-049-
0200(1)(a)(J)].
19. The undersigned certifies that the undersigned Contractor is not ineligible to receive a contract for a public work pursuant to ORS 279C.860. Bidder further agrees, if awarded a contract, that every subcontractor will be eligible to receive a contract for a public work pursuant to ORS 279C.860.
20. The undersigned certifies that the undersigned Contractor has not discriminated against minority, women or emerging small businesses enterprises in obtaining any required subcontracts. The bidder understands and acknowledges that it may be disqualified from bidding on this public improvement project as set forth in OAR 137-049-0370, including but not limited to City discovery a misrepresentation or sham regarding a subcontract or that the Bidder has violated any requirement of
ORS 279A.110 or the administrative rules implementing the Statute.
21. The undersigned agrees that the time of completion shall be defined in the specifications, and further, the undersigned agrees to initiate and complete this Project by the date stated below.
• The work shall be commenced within ten (10) business days after receipt of the written Notice to Proceed.
• The work shall be completed in all respects within 60 calendar days from Notice to Proceed.
• The undersigned agrees that the “Time of Completion” shall be as defined in the specifications and that the bidder will complete the work within the number of consecutive calendar days stated for each schedule after “Notice to Proceed” has been issued by the Owner. Bidder furthermore agrees to pay as liquidated damages, for each calendar day thereafter, the amounts shown in Standard Conditions, for each day the project remains incomplete.
22. The undersigned bidder is registered with the Oregon Construction Contractors Board (CCB), the registration is current and valid, and the bidder's registration number is stated below. [OAR 137-049-
0230(1)] Bidder understands that failure to have a current CCB license shall result in rejection of this bid.
23. The undersigned bidder is licensed by the State Landscape Contractors Board, if applicable, the license is current and valid, and the bidder’s registration number is stated below. [OAR 137-049-
0200(1)(a)(K)] Bidder understands that failure to have a current LCB license shall result in rejection of this bid.
24. In determining the lowest responsible bidder, City shall, for the purpose of awarding the contract, add a percent increase on the bid of a non-resident bidder equal to the percent, if any, of the preference given to that bidder in the state in which the bidder resides. "Resident bidder" of Oregon means a bidder that has paid unemployment taxes or income taxes in this state during the 12 calendar months immediately preceding submission of the bid, has a business address in this state and has stated in the
6 | P a g e bid that the bidder is a "resident bidder" of the State of Oregon. The undersigned represents him/her self in this bid to be either a Resident or a Nonresident bidder by completing the appropriate blank below.
• The Bidder is ________ or is not _______ a Resident Bidder as defined in ORS 279A.120.
25. The undersigned hereby represents that no Councilor, Commissioner, officer, agency or employee of the City of Ashland is personally interested directly or indirectly in this Contract or the compensation to be paid hereunder and that no representation, statement or statements, oral or in writing, of the
City, its Councilors, Commissioners, officers, agents or employees had induced him/her to enter into this Contract, and the papers made a part of its terms;
26. The undersigned has not directly or indirectly induced or solicited any person to submit a false or sham bid or refrain from bidding. The undersigned certifies that this bid has been arrived at independently and submitted without connection with any person, firm or corporation making a bid for the same material and is, in all respects, fair and without collusion or fraud.
27. The undersigned confirms that this firm has a Qualified Drug Testing Program for employees in place and will demonstrate this prior to award of contract. [OAR 137-049-0200(1)(c)(B)]
28. The undersigned confirms that if this contract involves asbestos abatement or removal, the bidder is licensed under ORS 468A.710 for asbestos removal. Asbestos abatement is not implicated in this contract.
29. The City of Ashland may waive minor informalities, reject any bid not in compliance with all prescribed public bidding procedures and requirements, and may reject for good cause any or all bids upon a finding that it is in the public interest to do so.
30. The undersigned confirms that this offer is not contingent upon City’s acceptance of any terms and conditions other than those contained in this Solicitation and the Contract Documents.
31. The bidder understands that the City reserves the right to make changes to the Notice to Contractors /
Invitation to Bid and the resulting contract by written addenda, prior to the closing time and date.
The City will transmit addenda to registered plan holders but shall publish notice of any addenda on
City’s website (www.ashland.or.us) at the Public Works page. The addenda may be downloaded or picked up at the Department of Public Works, 51 Winburn Way, Ashland, Oregon. The bidder must check the website and Public Works bulletin board frequently until closing.
The bidder acknowledges that the Addendum(s) listed below have been reviewed online or a copy obtained and considered as part of the submittal of this Offer and Bid Schedule.
ADDENDUM NUMBER ____ THROUGH ____ HAVE BEEN REVIEWED
32. The bidder understands that the City will be awarding the contract to the Responsible Bidder with the lowest Responsive Bid. OAR 137-049-0200(1)(b)(C). Whether a bidder is responsible will be determined by ORS 279C.375 and the City’s completion of the attached Bidder Responsibility
Determination Form.
33. Instructions for First-Tier Subcontractors Disclosure.
Bidders are required to disclose information about certain first-tier subcontractors (those subcontractors contracting directly with the bidder) when the contract price exceeds $100,000 (see
ORS 279C.370). Specifically, when the contract amount of a first-tier subcontractor is greater than or equal to: (i) 5% of the project bid, but at least $15,000, or (ii) $350,000 regardless of the percentage, you must disclose the following information about that subcontract within two working hours of bid closing:
• The subcontractor’s name and address;
7 | P a g e
• The subcontractor’s Construction Contractor Board registration number, if one is required, and;
• The subcontract dollar value.
If you will not be using any subcontractors that are subject to the above disclosure requirements, you are required to indicate “NONE” on the form. Failure to submit this form by the disclosure deadline will result in a non-responsive bid. A non-responsive bid will not be considered for award.
THE CITY MAY REJECT A BID IF THE BIDDER FAILS TO SUBMIT THE DISCLOSURE
FORM WITH THIS INFORMATION WITHIN TWO HOURS OF BID CLOSING.
THIS DOCUMENT SHALL NOT BE FAXED. IT IS THE RESPONSIBILITY OF BIDDERS
TO SUBMIT THIS DISCLOSURE FORM AND ANY ADDITIONAL SHEETS BY THE
DEADLINE. SEE INSTRUCTIONS TO BIDDERS.
The disclosure should be submitted on the First-Tier Subcontractor Disclosure Form attached to this Invitation to Bid.
34. Bidder Information and Signature
Firm Name of Bidder Signature of Bidder
Printed Name of Bidder
Official Title
State of Incorporation CCB Number
Dated this day of 20___.
Name of Bidder
Address
Telephone No.
8 | P a g e
BID SCHEDULE
Project No. 2025-01
Spec.
No.
Item
No. Item Bid
Unit Quantity Unit Price Total Price
TEMPORARY FEATURES AND APPURTENANCES
00210 10 MOBILIZATION LS 1 $ $
00221 20
TEMPORARY WORK ZONE TRAFFIC CONTROL,
COMPLETE
LS 1 $ $
00223 30 FLAGGERS HR 750 $ $
00280 40 EROSION CONTROL LS 1 $ $
00290 50 POLLUTION CONTROL PLAN LS 1 $ $
WEARING SURFACES
EMULSIFIED ASPHALT SLURRY SEAL SURFACING (TYPE III)
00706 60 TOLMAN CREEK RD - HWY 66 TO SISKIYOU BLVD SQYD
13,724 $ $
00706 70
JEFFERSON AVE - NORTHERLY INTERSECTION w/
WASHINGTON ST TO SOUTHERLY INTERSECTION w/
WASHINGTON ST
SQYD 6,261 $ $
00706 80 FREMONT ST - NORMAL AVE TO PARK ST SQYD 2,039 $ $
00706 90
E. MAIN ST - LITHIA WAY TO 725' EAST OF WALKER
AVE
SQYD 22,767 $ $
00706 100 SCENIC DR - WIMER ST TO NUTLEY ST SQYD 10,414 $ $
00706 110 GUTHRIE ST - HOLLY ST TO ASHLAND ST SQYD 4,113 $ $
00706 120 ASHLAND ST - GUTHRIE ST TO UNIVERSITY WAY SQYD 11,326 $ $
00706 130 S. MOUNTAIN AVE - E. MAIN ST TO ASHLAND ST SQYD 11,008 $ $
00706 140 WALKER AVE - SISKIYOU BLVD TO PINECREST TERR SQYD 8,551 $ $
00706 150 PEACHEY RD - WALKER AVE TO HILLVIEW DR SQYD 2,774 $ $
00706 160 PARADISE LN - PEACHEY RD TO END OF PAVEMENT SQYD 1,118 $ $
00706 170 GLENVIEW DR - FORK ST TO GRANITE ST SQYD 14,642 $ $
00706 180 ORANGE AVE - N. LAUREL ST TO HELMAN ST SQYD 1,382 $ $
00706 190 CAMPUS WAY - E. MAIN ST TO END OF ROAD SQYD 1,517 $ $
00706 200 FIELDER ST - INDIANA ST TO END OF ROAD SQYD 760 $ $
00706 210 MOHAWK ST - PARK ST TO MARY JANE AVE SQYD 3,518 $ $
00706 220
CRESTVIEW DR - WESTERLY END OF ROAD TO
EASTERLY END OF ROAD
SQYD 7,137 $ $
00706 230 LINDA AVE - NEZLA ST TO CRESTVIEW DR SQYD 4,312 $ $
00706 240 WRIGHTS CREEK DR - WIMER ST TO GRANDVIEW DR SQYD 3,621 $ $
00706 250 IVY LN - END OF ROAD TO S. MOUNTAIN AVE SQYD 2,381 $ $
00706 260 ALMOND ST - MANZANITA ST TO PINE ST SQYD 3,049 $ $
EMULSIFIED ASPHALT SLURRY SEAL SURFACING (TYPE I & III)
00706 270 SECT 3 - MULTI USE PATH SQYD 2,712 $ $
00706 280 SECT 4 - MULTI USE PATH SQYD 577 $ $
00706 290 SECT 5 - MULTI USE PATH SQYD 767 $ $
00706 300 SECT 6 - MULTI USE PATH SQYD 1,494 $ $
9 | P a g e
PERMANENT TRAFFIC SAFETY AND GUIDANCE DEVICES
00865 310
THERMOPLASTIC, EXTRUDED, SURFACE, NON-
PROFILED, BROKEN LINE, YELLOW
FT 4,272 $ $
00865 320
THERMOPLASTIC, EXTRUDED, SURFACE, NON-
PROFILED, DOUBLE SOLID LINE, YELLOW
FT 2,650 $ $
00865 330
THERMOPLASTIC, EXTRUDED, SURFACE, NON-
PROFILED, SOLID LINE, WHITE
FT 24,256 $ $
00865 340
THERMOPLASTIC, EXTRUDED, SURFACE, NON-
PROFILED, SOLID LINE, YELLOW
FT 3,581 $ $
BID TOTAL
Name of Authorized Representative Total Written in Dollars
Authorized Representative Signature Date
10 | P a g e
FIRST-TIER SUBCONTRACTOR DISCLOSURE FORM
INSTRUCTIONS
Instructions for Submitting Form
Submit the First-Tier Subcontractor Disclosure form in any of the following manners:
• Not later than two working hours after the time set for opening Bids. (For example, before 11:00 a.m. after a 9:00 a.m. Bid Opening.) Submit according to one of the following methods:
• Print the form from the Bid Booklet, fill it in, and either:
o Deliver to the following address where it can be time and date stamped
Community Development and Engineering Services Building
51 Winburn Way
Ashland, OR 97520, or o FAX it to (541) 488-6006.
The Agency is not responsible for partial, failed, illegible, or partially legible FAX transmissions or electronic submissions.
Instructions for First-Tier Subcontractor Disclosure
Without regard to the amount of a Bidder's Bid, if the Agency's cost range for a public improvement project in the "Notice to Contractors", or in other advertisement or solicitation documents is greater than
$100,000, bidders are required to disclose information about first-tier subcontractors that will furnish labor or labor and materials (See ORS 279C.370). Specifically, when the contract amount of a first-tier subcontractor is greater than or equal to: (1) 5% of the total project Bid, but at least $15,000, or (2)
$350,000 regardless of the percentage of the total project Bid, you must disclose the following information about that subcontractor not later than two working hours after the time set for opening Bids:
• The name of the subcontractor
• The category of work that the subcontractor will be performing
• The dollar amount of the subcontract
If the Agency's cost range is greater than $100,000 and you will not be using any first-tier subcontractors, you are still required to submit the form, with the appropriate box checked or enter "NONE" on the first line.
If the Agency's cost range is greater than $100,000 and you are not subject to the above disclosure requirements, you are still required to submit the form, with the appropriate box checked or enter
"NONE" on the first line.
THE AGENCY MUST REJECT BIDS if the Bidder fails to submit the disclosure form with this information by the stated deadline.
To determine disclosure requirements, the Agency recommends that you disclose subcontract information for any subcontractor as follows:
1) Determine the lowest possible prime contract price. That will be the base Bid amount less all alternate deductive Bid amounts (exclusive of any options that can only be exercised after Bid award).
11 | P a g e
2) Provide the required disclosure information for any first-tier subcontractor whose potential contract services are greater than or equal to: (1) 5% of the lowest contract price, but at least $15,000, or (2)
$350,000 regardless of the percentage. Total all possible work for each subcontractor in making this determination, (for example, if a subcontractor will provide $15,000 worth of services on the base Bid and
$40,000 on an additive alternate, then the potential amount of the subcontractor’s services is $55,000.
Assuming that $55,000 exceeds 5% of the lowest contract price, provide the disclosure for both the
$15,000 services and the $40,000 services).
12 | P a g e
FIRST-TIER SUBCONTRACTOR DISCLOSURE FORM
Project Name
Project Number
Bid Opening Date
Name of Bidding Contractor
☐ CHECK THIS BOX IF YOU WILL NOT BE USING ANY FIRST-TIER SUBCONTRACTORS OR IF
YOU ARE NOT SUBJECT TO THE DISCLOSURE REQUIREMENTS (SEE INSTRUCTIONS)
Firm Name Dollar Amount
Category of Work
(Attach additional sheets as necessary)
13 | P a g e
PUBLIC IMPROVEMENT CONTRACT
FOR
PROJECT NO. 2025-01
This Public Improvement Contract (hereinafter “Contract”) is entered into by and between the CITY
OF ASHLAND, an Oregon municipal corporation (hereinafter “City”), and
(hereinafter “Contractor”).
NOW THEREFORE, for good and valuable consideration, the sufficiency of which is hereby acknowledged, the parties mutually covenant and agree as follows:
1. PROJECT MANAGER:
The City’s Project Manager for this Contract is:
Chuck Schweizer, Street Supervisor, City of Ashland Public Works/Street Department
2. WORK:
1. The Work under this Contract is for the 2025 SLURRY SEAL PROJECT, Project No.
2025-01 as more fully described in the Contract Documents listed in Section 5 of
EXHIBIT A, STANDARD TERMS AND CONDITIONS FOR PUBLIC
IMPROVEMENT CONTRACTS. Contractor shall complete all Work as specified in the
Contract Documents. The Work is generally described as follows: The placement of
Type I and Type III Emulsified Asphalt Slurry Seal and the installation of permanent pavement markings. The Statement of Work, including the delivery schedule for the
Work, is contained in the Contract Documents.
2.1. Contractor shall, at its own risk and expense, perform the Work described in the Contract
Documents and furnish all permits, labor, tools, machinery, materials, transportation, equipment and services of all kinds required for, necessary for, or reasonable incidental to, performance of the Work, that is, the construction of the 2025 SLURRY SEAL PROJECT, Project No. 2025-01. Contractor shall secure all municipal, County, State, or Federal
Permits or licenses including payment of permit fees, license fees, and royalties necessary
14 | P a g e for or incidental to the performance of the Work. The risk of loss for such Work shall not shift to the City until written acceptance of the Work by the City.
3. EFFECTIVE DATE AND DURATION:
This Contract is effective as of the date of execution by the City (the “Effective Date”). All
Work under this Contract shall, unless otherwise terminated or extended, be completed on or before 60 calendar days following Contractor’s receipt of the written Notice to Proceed.
4. CONSIDERATION
4.1. City agrees to pay Contractor, at the times and in the manner provided in the Contract
Documents, the sum of ________________________________ for performing the Work required by this Contract, including allowable expenses. This sum cannot be modified except by Change Order approved in writing by the City. Any progress payments to
Contractor shall be made only in accordance with the schedule and the requirements as set forth in the Standard Terms and Conditions.
4.2. City certifies that sufficient funds have been appropriated to make payments required by this
Contract during the current fiscal year. Contractor understands and agrees that City’s payment of amounts under this Contract attributable to Work performed after the last day of the current fiscal year is contingent upon City appropriations, or other expenditure authority sufficient to allow City in the exercise of its reasonable discretion, to continue to make payments under this Contract. In the event City has insufficient appropriations, limitations or other expenditure authority, City may terminate this Contract without penalty or liability to City, effective upon the delivery of written notice to Contractor, with no further liability to Contractor.
5. CONTRACTOR’S REPRESENTATIONS
In order to induce City to enter into this Contract, Contractor makes the following representations:
5.1. Contractor has examined and carefully studied the contract documents, and any data and reference items identified in the contract documents.
5.2. Contractor has visited the Site, conducted a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
5.3. Contractor is familiar with and is satisfied as to all laws and regulations that may affect cost, progress, and performance of the Work.
5.4. Contractor has carefully studied all drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified or provided in the project bid documents especially with respect to technical data in such reports and drawings, and reports and drawings relating to hazardous environmental conditions, if any, at or adjacent to the Site that have been identified in the project bid documents, especially with respect to Technical Data in such reports and drawings.
5.5. Contractor has considered the information known to Contractor itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the contract documents; and the Site-related
15 | P a g e reports and drawings identified in the contract documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the
Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor; and (3) Contractor’s safety precautions and programs.
5.6. Based on the information and observations referred to in the preceding paragraph, Contractor agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract
Times, and in accordance with the other terms and conditions of the Contract.
5.7. Contractor is aware of the general nature of work to be performed by City and others at the
Site that relates to the Work as indicated in the contract documents.
5.8. Contractor has given City written notice of all conflicts, errors, ambiguities, or discrepancies that Contractor has discovered in the contract documents, and the written resolution thereof by City is acceptable to Contractor.
5.9. The contract documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
6. GOVERNING LAW
The provisions of this Contract shall be construed in accordance with the laws of the State of
Oregon. Any action or suits involving any question arising under this contract must be brought in the appropriate court in Jackson County, Oregon. If the claim must be brought in a federal forum, then it shall be brought and conducted in the United States District Court for the District of Oregon. Contractor, by the signature herein of its authorized representative, hereby consents to the in persopnam jurisdiction of said courts. In no event shall this section be construed as a waiver of the City of any form of defense or immunity.
16 | P a g e page left intentionally blank
17 | P a g e
CONTRACTOR DATA, CERTIFICATION, AND SIGNATURE
Business Name (please print):
Contact Name: Phone: Fax:
Address
Do Not Write Federal and State Tax ID Numbers on this Agreement: One copy of W-9 is to be submitted with the signed contract to be kept on file in the City of Ashland Finance Department.
Ashland Business License # Construction Contractors Board #
Citizenship: Nonresident alien ______ Yes _____ No
Business Designation (check one): _____ Individual ____ Sole Proprietorship ____
Partnership _____ Corporation ____ Government/Nonprofit
The above information must be provided prior to contract approval. Payment information will be reported to the Internal Revenue Service (IRS) under the name and taxpayer I.D. number provided above. (See IRS 1099 for additional instructions regarding taxpayer ID numbers.) Information not matching IRS records could subject you to 31 percent backup withholding.
I, the undersigned, understand that the Standard Terms and Conditions For Public Improvement
Contracts (Exhibit A) together with Exhibits B through J together with all other Contract
Documents as described in Standard Terms and Conditions Section 5 below, and the separately bound Oregon 2024 Standard Specifications for Construction, as amended by the City of
Ashland’s most recent Addenda to the 2024 Standard Specifications are an integral part of this contract and agree to perform the work described above, in accordance with the terms and conditions of this contract. I further understand the City is prohibited from entering into a contract when the contractor has neglected or refused to file any return, pay any tax, or properly contest a tax, pursuant to ORS 305.385; I hereby certify, under penalty of perjury and false swearing, that
I/my business am/is not in violation of any Oregon tax laws; I further certify that the certification and representations in Standard Term and Condition # 16 [CCB Registration Requirements] are true and correct, and further I certify that I am an independent contractor as defined in ORS
670.600.
18 | P a g e
CONTRACTOR:
Signature/Title
Printed name
Date
NOTICE TO CONTRACTOR: This contract does not bind the City of Ashland unless and until it has been executed by the Public Contracting Officer or designee.
CITY OF ASHLAND SIGNATURE
CITY:
City Manager, City of Ashland
Date
ATTACHMENTS: Certificate of Representation
Standard Terms & Conditions
Bid Schedule
Insurance Requirements
19 | P a g e
CERTIFICATE OF REPRESENTATION
Contractor, under penalty of perjury, certifies that:
(a) The number shown on this form is its correct taxpayer ID (or is waiting for the number to be issued to it; and
(b) Contractor is not subject to backup withholding because
(i) it is exempt from backup withholding or
(ii) it has not been notified by the Internal Revenue Service (IRS) that it is subject to backup withholding as a result of a failure to report all interest or dividends, or
(iii) the IRS has notified it that it is no longer subject to backup withholding. Contractor further represents and warrants to City that
(a) it has the power and authority to enter into and perform the work,
(b) the Contract, when executed and delivered, shall be a valid and binding obligation of
Contractor enforceable in accordance with its terms, and
(c) The work under the Contract shall be performed in accordance with the highest professional standards, and
(d) Contractor is qualified, professionally competent and duly licensed to perform the work. Contractor also certifies under penalty of perjury that its business is not in violation of any Oregon tax laws, and it is a corporation authorized to act on behalf of the entity designated above and authorized to do business in Oregon or is an independent contractor as defined in the contract documents, and has checked four or more of the following criteria:
________ (1) I carry out the labor or services at a location separate from my residence or is in a specific portion of my residence, set aside as the location of the business.
________ (2) Commercial advertising or business cards or a trade association membership are purchased for the business.
________ (3) Telephone listing is used for the business separate from the personal residence listing.
________ (4) Labor or services are performed only pursuant to written contracts.
________ (5) Labor or services are performed for two or more different persons within a period of one year.
________ (6) I assume financial responsibility for defective workmanship or for service not provided as evidenced by the ownership of performance bonds, warranties, errors and omission insurance or liability insurance relating to the labor or services to be provided.
Contractor Date
20 | P a g e
EXHIBIT A - STANDARD TERMS AND CONDITIONS FOR PUBLIC
IMPROVEMENT CONTRACTS
1. Contractor is Independent Contractor
a. Contractor shall perform the work required by this Contract as an independent contractor.
b. The Contractor represents and warrants that Contractor (i) is not currently an employee of the federal government or the State of Oregon, and (ii) meets the specific independent contractor standards of ORS 670.600, as certified on the Independent Contractor Certification Statement attached as Exhibit D.
c. Contractor will be responsible for any federal or state taxes applicable to any compensation or payment paid to Contractor under this contract.
d. Contractor is not eligible for any federal Social Security, unemployment insurance, state
Public Employees’ Retirement System, or workers’ compensation benefits from compensation or payments to Contractor under this contract.
2. Subcontracts and Assignment
Contractor shall not subcontract any of the work required by this contract, or assign, sell, dispose of, or transfer any of its interest in this contract, nor delegate duties under the contract, either in whole or in part, without the prior written consent of the City. Such consent if provided shall not relieve the
Contractor of any of the obligations under the contract. Any assignee or transferee shall be considered the agent of the contractor and be bound to abide by all provisions of the contract. If the City consents in writing to an assignment, sale, disposal or transfer of the Contractor’s rights or delegation of Contractor’s duties, the Contractor and its Surety, if any, shall remain liable to the City for complete performance of the Contract as if no such assignment, sale, disposal, transfer or delegation had occurred unless the City otherwise agrees in writing. [OAR 137-049-0200(2)]
Use of Subcontractors, material suppliers or equipment suppliers shall in no way release Contractor from any obligations of contract with City. Contractor will provide in all subcontract agreements that the Subcontractor, material supplier and equipment supplier will be bound by the terms and conditions of this Contract to the extent that they relate to the Subcontractor's work, material or equipment. All Subcontracts are assignable to the City at City's option, in the event this agreement is terminated for default of Contractor.
Contractor covenants and agrees to bind any and all subcontractors for performance of work under this Contract in the same manner Contractor is bound to City. Contractor further agrees that if subcontractors are employed in the performance of this contract, the Contractor and its subcontractors are subject to the requirements and sanction of ORS Chapter 656, Workers’ Compensation.
3. No Third-Party Beneficiaries
City and Contractor are the only parties to this Contract and are the only parties entitled to enforce its terms. Nothing in this Contract gives or provides any benefit or right, whether directly, indirectly, or otherwise, to third persons unless such third persons are individually identified by name herein and expressly described as intended beneficiaries of the terms of this Contract.
4. Successors in Interest
21 | P a g e
The provisions of this Contract shall be binding upon and shall inure to the benefit of the parties hereto, and their respective successors and approved assigns, if any.
5. Contract Documents
The Contract Documents, which comprise the entire Contract between the City and Contractor, include all sections or parts of the bid package however denominated, including all documents and plans attached or referenced therein, the Notice to Contractors - Invitation to Bid, Offer, First-Tier
Subcontractors Disclosure Form, Surety Bond, Public Improvement Contract, Contract Standard
Terms and Conditions and Exhibits thereto, Performance Bond, Payment Bond, Special Provisions, Plans, Construction Drawings, Standard Drawings, and Contract Addendums, all attached hereto, and incorporated herein by this reference, together with the Prevailing Wage (BOLI) if applicable AND any other separately bound reference, Oregon 2024 Standard Specifications for Construction, and
City of Ashland Addenda, incorporated herein by this reference. All exhibits, schedules and lists attached to the Contract Documents, or delivered pursuant to the Contract Documents, or otherwise available from the City, shall be deemed a part of the Contract Documents and incorporated herein, where applicable, as if fully set forth herein.
6. Contractor’s Representations
By executing this contract, the Contractor hereby certifies that the representations made by the
Contractor in the Contract Documents, including specifically the Offer, are true and correct and are incorporated herein by this reference. Contractor further certifies that Contractor has given the City written notice of conflicts, errors, ambiguities, or discrepancies that it has discovered in the Contract
Documents, and the written resolution thereof by the City is acceptable to the Contractor, and the
Contract Documents are generally sufficient to indicate and convey understanding of terms and conditions for performing and furnishing the project work.
7. Drug Testing [ORS 279C.505(2)]
a. Contractor shall certify to the City that it has a drug-testing program in place for all its employees that includes, at a minimum, the following:
i. A written employee drug-testing policy,
ii. Required drug testing for all new Subject Employees or alternatively, required testing of all Subject Employees every 12 months on a random selection basis, and
iii. Required testing of a Subject Employee when the Contractor has reasonable cause to believe the Subject Employee is under the influence of drugs.
b. A drug-testing program that meets the above requirements will be deemed a “Qualifying
Employee Drug-testing Program.” For the purposes of this section, an employee is a “Subject
Employee” only if that employee will be working on the Public Improvement project job site.
c. By executing and returning this contract the Contractor certifies, represents and warrants to the City that a Qualifying Employee Drug-testing Program is in place at the time of execution, will continue in full force and effect for the duration of this contract, and that
Contractor will comply with the provisions of subsection (d) below. Further, the City’s performance obligation (which includes, without limitation, the City’s obligation to make payment) is contingent on Contractors compliance with this representation and warranty.
22 | P a g e
d. Contractor will require each subcontractor providing labor for the project to:
i. Demonstrate to the Contractor that it has a Qualifying Employee Drug-testing Program for the subcontractor's Subject Employees, and represent and warrant to the Contractor that the Qualifying Employee Drug-testing Program is in place at the time of subcontract execution and will continue in full force and effect for the duration of the subcontract; or
ii. Require that the subcontractor's Subject Employees participate in the Contractor's
Qualifying Employee Drug-testing Program for the duration of the subcontract.
8. Notice to Proceed
Written Notice to Proceed will be given by the City after the Contract has been executed and the
Performance Bond, Payment Bond, and all required insurance documents approved. Notice To
Proceed shall not be unreasonably delayed and shall generally occur within thirty (30) days of the contract date. Reasonable delay may be occasioned by the need to obtain necessary permits or easements or utility relocation. The Contractor shall commence the project work within ten (10) days of the date of the written Notice To Proceed. Contractor is not to commence work under the Contract prior to such written notice.
9. Suspension of the Work
The City, and its authorized representatives, may suspend portions or all of the project work due to causes including, but not limited to:
a. Failure of the Contractor to correct unsafe conditions;
b. Failure of the Contractor to carry out any provision of the Contract;
c. Failure of the Contractor to carry out orders;
d. Conditions, in the opinion of the City, which are unsuitable for performing the project work;
e. Allowance of time required to investigate differing site conditions;
f. Any…
This is the start of the file's text. The full file is on GovTribe.