This is an Industry Day presentation announcement for a virtual event on December 18, 2024 at 0900 CT regarding Generator Step-Up (GSU) Transformer supply for Oahe and Fort Peck Dams, managed by the US Army Corps of Engineers Omaha District. The project involves designing and manufacturing two new GSU transformers for Fort Peck and ten new GSU transformers for Oahe Dam, including ancillary components, control systems, Factory Acceptance Testing (FAT), delivery, assembly, oil processing, and final acceptance testing at both locations.
Interested contractors must RSVP by December 16, 2024 at 1700 CT to both the Contract Specialist and Contracting Officer. The event includes a government briefing, general Q&A, and optional 30-minute one-on-one sessions between 1230-1630 CT. Draft specifications will be available by December 6, 2024. Questions must be submitted through ProjNet using Bidder Inquiry Key 87GFMC-4S6G7V for solicitation W9128F25R0002. The government will publish attendee lists and Q&A responses on SAM.gov after the event.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
File Name Welcome
Fort peck & Oahe Dam GSU Transformer Supply Industry Day 19 dec 2024
Introductions
Omaha District Office
| Ryan Brockman | Project Manager |
| Nadine Catania | Contracting Officer |
| Brandie Murphy | Contract Specialist |
| Marc Proietto | Contract Specialist |
| Lucas Kirkpatrick | Electrical Engineer |
Fort Peck
| Dale Pugh | Operations Project Manager | |
| Trevor Waarvik | Asst M&O Manager | |
| Jason Molstad | Tech Branch Chief | |
| Irene Whitmer | Electrical Engineer |
Oahe
| Joseph Pintal | Operations Project Manager |
| Jeremy Irving | Asst M&O Manager |
| Kris Cleveland | Tech Branch Chief |
| Jesse Roebuck | Electrical Engineer |
Hydroelectric Design Center (HDC), Portland
| Doug Filer | Electrical Engineer(DL) | |
| Cole Pobanz | Electrical Engineer | |
| Teresa Casper | Electrical Engineer |
Construction Division
| Leeann Wimer | COR |
| Cody Nickolas | COR |
agenda 19 Dec 2024
| 0900 | Industry Check-In | |
| 0915 - 1015 | Presentation by Government | |
| Introductions | ||
| Contracting Rules of Engagement | ||
| Dam Briefing / General Information | ||
| Statement of Work / Project Specs | ||
| 1030 - 1200 | Q&A | |
| 1200 – 1300 | Break | |
| 1300 – 1600 | 1 on 1 Q&A Sessions |
USACE, Omaha District Contracting Nadine catania, contracting officer Rules of Engagement Contract officer is the government authority virtual industry day All questions or concerns must be directed to the Contract Specialist No side bars or independent conversations between contractors and government personnel No discussions relating to other Corp acquisitions No corporate denigration or sabotage will be tolerated Hold all questions until the designated question and answer session All questions will be documented and posted in ProjNet.
POTENTIAL Contract information
Contract Information Contract Type: Commercial Supply Solicitation Type: Request for Proposal (RFP) Contract Magnitude: >$7.5M Contract Duration: TBD
Projnet and contact information
ProjNet:
Used for contractor submitted questions Government is not required to respond to feedback Web site: https://www.projnet.org Bidder Inquiry Key: 87GFMC-4S6G7V Contract Specialist Contact Information:
Brandie Murphy Email: Brandie.L.Murphy@usace.army.mil Phone: 402-995-2332
Project schedule
| Milestones | Nov-24 | Dec-24 | Jan-25 | Feb-25 | Mar-25 | Apr-25 | May-25 | Jun-25 | Jul-25 | Aug-25 | Sep-25 | Oct-25 |
| Final Design | 30-Nov | |||||||||||
| Industry Day | 19-Dec | |||||||||||
| Pre-solicitation | 20-Dec | |||||||||||
| Advertise | 28-Jan | 28-May | ||||||||||
| Site Visit | 23-Apr | |||||||||||
| Source Selection | 29-May | |||||||||||
| Award | 5-Sep | |||||||||||
| Notice to Proceed | 6-Oct |
Submittals – Complete120 days after NTP Lead Time – 3 to 5 years Delivery – Oahe will be priority
File Name solicitation Fp/oa GSU transformer supply project Project manager, ryan brockman
Economic price adjustment (epa) Clause 52.216-4
The Economic Price Adjustment (EPA) clause is typically used in contracts to account for changes in costs that could occur over the duration of a project or agreement. These clauses are designed to ensure fairness for both parties by adjusting the contract price based on predefined criteria, such as market fluctuations, inflation, or changes in material costs.
Key Elements of an EPA Clause:
Scope of Adjustment: Specifies which costs or factors for materials (i.e. copper, steel, oil) are subject to adjustment.
Adjustment Formula: Often includes a formula or index to calculate price changes. For example, it may rely on a government-published index or market data.
Adjustment Frequency: Defines how often adjustments are made (e.g., monthly, quarterly).
Ceiling or Floor: Sometimes, limits are set on the maximum or minimum adjustment to avoid extreme fluctuations.
Triggering Conditions: Specifies what events or thresholds activate the adjustment (e.g., a percentage change in an index).
Common Uses: Government Contracts: Widely used in long-term contracts where pricing uncertainties exist.
Manufacturing: For supply agreements involving commodities or inputs with fluctuating prices.
Estimated price adjustment (epa) Clause 52.216-4
For this solicitation, the EPA Clause will be limited to the Steel, Plate Steel, Copper, and Transformer Oil Cold Rolled Steel Steel Index - WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics) Standard Plate Steel Plate Steel Index - WPU101704 (Hot rolled steel bars, plates, and structural shapes) Copper Copper Index - WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics) Transformer Oil Transformer Oil Index - WPU057, (Petroleum products, refined - Bureau of Labor Statistics)
Buy American / Trade agreements act
FAR 52.225-1: Buy American Act—Supplies Details requirements for domestic end products in supply contracts.
Key Requirements:
Domestic End Products:
Items must be manufactured in the U.S.
A minimum percentage of the product's components (by cost) must be sourced domestically:
60% currently (2022), rising to 65% in 2024 and 75% by 2029 under recent updates.
Manufacturing Location:
Final assembly or substantial manufacturing must occur in the United States.
Buy American / Trade agreements act
FAR 52.225-5: Trade Agreements The TAA applies to federal contracts over a certain threshold (e.g., $50,000 for supplies and services in 2024), especially when the U.S. has trade agreements like the World Trade Organization’s Government Procurement Agreement (WTO GPA) or other free trade agreements.
Eligible Countries:
Products and services must be from either:
The U.S.
A designated country, such as those part of WTO GPA (e.g., European Union, Japan) Free trade agreements like USMCA (Canada and Mexico)Least developed countries (e.g., Nepal, Bangladesh) Caribbean Basin countries Products from non-designated countries, such as China and Russia, are generally prohibited under the TAA.
Shipping – US - flagged carrier
For government contracts involving shipping supplies, U.S. law mandates the use of U.S.-flagged carriers FAR 52.247-64: Preference for Privately Owned U.S.-Flag Commercial Vessels:
Mandates the use of U.S.-flagged vessels for transporting supplies under government contracts unless a waiver is obtained.
Bid schedule – Clins 0001-0004
Bid schedule – Clins 0005 - 0007
Bid schedule – clins 0008 - 0011
Bid schedule – clins 0012 - 0014
Bid schedule - EPA Cold Rolled Steel:
$__________/lb. Total number of pounds of Steel: __________ lbs. Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics)
Standard Plate Steel:
$__________/lb. Total number of pounds of Steel: __________ lbs. Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:WPU101704 (Hot rolled steel bars, plates, and structural shapes)
Copper:
$__________/lb. Total number of pounds of copper: __________ lbs. Total cost of copper: $__________ Copper Index that shall be used to calculate the EPA:WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics)
Transformer Oil:
$__________/lb. Total number of gallons of transformer oil: __________ gal. Total cost of oil: $__________ Transformer oil that shall be used to calculate the EPA:WPU057 (Petroleum products, refined - Bureau of Labor Statistics)
Evaluation Factors transformer design Hydroelectric design center (HDC) Doug filer, Electrical engineer
QUANTITY: 2
NAMEPLATE DATA
| TYPE: CLASS II GSU POWER TRANSFORMER | |
| COOLING CLASS: ONAN/ONAF | |
| KVA RATING: 42,000 / 56,000 | |
| VOLTAGE RATINGS: 230,000 GRDY (H) - 13,800 DELTA (X) | |
| BIL LEVELS, KV: 900 (H) / 110 (X) / 150 (H0) | |
| PHASING: THREE-PHASE | |
| FREQUENCY: 60 HZ | |
| IMPEDANCE: 11.0% @ 42,000 KVA (H-X) | |
| SECONDARY WINDING (H) DETC: 5 TAPS; 2 @ +2.5%, 2 @ -2.5% OF | NOMINAL 230 KV TAP |
| TEMPERATURE RISE: 65 ºC | |
| OIL PRESERVATION SYSTEM: CONSTANT OIL PRESSURE SYSTEM | (COPS) TANK |
| MAXIMUM SOUND LEVEL (ONAF): 70 DB | |
| MAXIMUM TOTAL WEIGHT: 230,000 LB | |
| MAXIMUM TOTAL OIL VOLUME: 7,000 GAL |
OVERVIEW of gsu transformer requirements Fort peck dam
UNUSUAL SERVICE CONDITIONS
| MAXIMUM AMBIENT AIR TEMPERATURE: 43.3 DEGREES CELSIUS | |
| MAXIMUM AVERAGE AMBIENT AIR TEMPERATURE (24-HOUR | PERIOD): 33.3 DEGREES CELSIUS |
TRANSFORMER COMPONENTS REQURIED BY NAME BRAND
| 1) COOLING CONTROL MONITOR: SEL MODEL 2414 | |
| 2) ANNUNCIATOR: SEL MODEL 2533 | |
| 3) DISSOLVED GAS ANALYZER: MORGAN SCHAFFER CALISTO | MODEL R9 |
FORT PECK GSU TRANSFORMERS
LIMITING DIMENSIONS AND GENERAL ARRANGEMENT
TOP VIEW
FORT PECK GSU TRANSFORMERS
SIDE VIEW – SEGMENT 4
QUANTITY: 9
NAMEPLATE DATA
| TYPE: CLASS II GSU POWER TRANSFORMER | |
| COOLING CLASS: OFAF | |
| KVA RATING: 68,667 | |
| VOLTAGE RATINGS: 230,000 GRDY / 132,790 (H) - 13,800 DELTA (X) | |
| BIL LEVELS, KV: 900 (H) / 110 (X) / 150 (H0) | |
| PHASING: SINGLE-PHASE | |
| FREQUENCY: 60 HZ | |
| IMPEDANCE: 13.5% @ 68,667 KVA (H-X) | |
| SECONDARY WINDING (H) DETC: 5 TAPS; 2 @ +2.5%, 2 @ -2.5% OF | NOMINAL 230 KV TAP |
| TEMPERATURE RISE: 65 ºC | |
| OIL PRESERVATION SYSTEM: NITROGEN GAS BLANKETED | |
| MAXIMUM SOUND LEVEL (ONAF): 70 DB | |
| MAXIMUM TOTAL WEIGHT: 160,000 LB | |
| MAXIMUM TOTAL OIL VOLUME: 4,700 GAL |
OVERVIEW of 230KV gsu transformer requirements OAHE dam
UNUSUAL SERVICE CONDITIONS
| TRANSFORMERS ARE TO BE CAPABLE OF FULL LOAD OPERATION | |
| AT AN AMBIENT AIR TEMPERATURE OF 45 DEGREES CELSIUS | |
| MAXIMUM AMBIENT AIR TEMPERATURE: 47.2 DEGREES CELSIUS | |
| MAXIMUM AVERAGE AMBIENT AIR TEMPERATURE (24-HOUR | PERIOD): 36.4 DEGREES CELSIUS |
TRANSFORMER COMPONENTS REQURIED BY NAME BRAND
| 1) COOLING CONTROL MONITOR: SEL MODEL 2414 | |
| 2) ANNUNCIATOR: SEL MODEL 2533 | |
| 3) DISSOLVED GAS ANALYZER: MORGAN SCHAFFER CALISTO | MODEL R9 |
OAHE 230KV GSU TRANSFORMERS
OAHE 230KV GSU TRANSFORMERS
SIDE VIEW – SEGMENT 2
QUANTITY: 1
NAMEPLATE DATA
| TYPE: CLASS II GSU POWER TRANSFORMER | |
| COOLING CLASS: OFAF | |
| KVA RATING: 103,000 | |
| VOLTAGE RATINGS: 115,000 GRDY (H) - 13,800 DELTA (X) | |
| BIL LEVELS, KV: 550 (H) / 110 (X) / 150 (H0) | |
| PHASING: THREE-PHASE | |
| FREQUENCY: 60 HZ | |
| IMPEDANCE: 10.5% @ 103,000 KVA (H-X) | |
| SECONDARY WINDING (H) DETC: 5 TAPS; 2 @ +2.5%, 2 @ -2.5% OF | NOMINAL 115 KV TAP |
| TEMPERATURE RISE: 65 ºC | |
| OIL PRESERVATION SYSTEM: NITROGEN GAS BLANKETED | |
| MAXIMUM SOUND LEVEL (ONAF): 70 DB | |
| MAXIMUM TOTAL WEIGHT: 212,000 LB | |
| MAXIMUM TOTAL OIL VOLUME: 4,400 GAL |
OVERVIEW of 115KV gsu transformer requirements OAHE dam
UNUSUAL SERVICE CONDITIONS
| TRANSFORMERS ARE TO BE CAPABLE OF FULL LOAD OPERATION | |
| AT AN AMBIENT AIR TEMPERATURE OF 45 DEGREES CELSIUS | |
| MAXIMUM AMBIENT AIR TEMPERATURE: 47.2 DEGREES CELSIUS | |
| MAXIMUM AVERAGE AMBIENT AIR TEMPERATURE (24-HOUR | PERIOD): 36.4 DEGREES CELSIUS |
TRANSFORMER COMPONENTS REQURIED BY NAME BRAND
| 1) COOLING CONTROL MONITOR: SEL MODEL 2414 | |
| 2) ANNUNCIATOR: SEL MODEL 2533 | |
| 3) DISSOLVED GAS ANALYZER: MORGAN SCHAFFER CALISTO | MODEL R9 |
OAHE 115KV GSU TRANSFORMER
OAHE 115KV GSU TRANSFORMER
SIDE VIEW – SEGMENT 2
On-site overview Oahe project Kris cleveland, Electrical engineer
Oahe – Temp Storage and Staging Locations
Oahe Project – Access to Tailrace
Oahe Project – Current GSU Transformers
Oahe Project – Ancillary Connections
Oahe Project -
Oahe Project -
Oahe Project
On-site overview Fort pECK project Irene whitmer, Electrical engineer
FORT PECK – SITE OVERVIEW
Fort Peck Powerhouses Site Overview Gate Transformer Storage & Staging Area Transformers Access Road
Main facility gate located on southeast corner of site.
Transformer located in Switchyard 2, on the north side of Powerhouse 2.
Transformer Temporary storage and staging area located northwest corner of Switchyard 2
FORT PECK Project – Access
Highway 24 runs across top of dam, Yager Rd runs North from Hwy 24 to bottom of hill where it turns into Lower Yellowstone Rd.
Facility gate located at the bottom of hill.
FORT PECK Project – TEMPORARY STORAGE & STAGING AREA
- Temporary storage & staging area located adjacent to northwest corner of Switchyard 2.
FORT PECK Project – Access to SWITCHYARD 2
Switchyard 2 access for Unit 4 & 5 Transformers located on west side of switchyard.
Not sure if we need to add this slide since this is the supply contract and KTR will deliver and assemble transformers in temp. storage/staging area. Transformers will not relocate to switchyard 2 until installation contract.
FORT PECK Project – Current GSU Transformers
Questions?
1 on 1 discussion schedule (19 Dec)
| 1300 - 1330 | Virginia Transformers |
| 1400 – 1430 | PAF Electrical, Inc. |
| 1500 – 1530 | Koontz Electric |
image9.jpeg image10.jpeg image11.jpeg
Microsoft_Excel_Worksheet.xlsx FP_OA GSU XFMR Supply (Word)
FP / OA GSU Transformer Supply
OA00106
SECTION 00 10 00
Pricing Schedule
CLIN Description Quantity Unit Measure Unit Price Amount Basis
BASE ITEMS
0001 (OA) Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF, three-phase GSU power transformer. 1 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
0002 (OA)Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. 9 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
0003 (OA)Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $_______ $_______ None
0004 (OA)Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 9 EA $_______ $_______ None
0005 (OA)Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $_______ $_______ None
0006 (OA)Offload the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 9 EA $_______ $_______ None
0007 (OA)Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 1 EA $_______ $_______ None
0008 (OA)Move the 68,667 kVA, 230/132.79 kV single-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 9 EA $_______ $_______ None
00009 (OA)Furnish spare parts (See Section 48 19 23.05 26) 1 LOT $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
00010 (FP)Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformer. 2 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
00011 (FP)Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories from the manufacturing facility complete to the Fort Peck Dam power plant. 2 EA $_______ $_______ None
00012 (FP)Offload the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 2 EA $_______ $_______ None
00013 (FP)Move the 42,000/56,000 kVA, 230 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 2 EA $_______ $_______ None
00014 (FP)Furnish spare parts (See Section 48 19 23.04 26) 1 LOT $_______ $_______
The following CLIN/PRICE ITEMS is a LOT pricing item to be used for Economic Price Adjustment purposes. This CLIN will be administered in accordance with the Economic Price Adjustment Clause 52.216-2
Economic Price Adjustment (EPA) FFP 1 LOT XXX
PROJECT NO.: ______________ FOB: DESTINATION PURCHASE REQUEST NUMBER: ______________
The Government will make an Economic Price Adjustment (EPA) limited to the Steel, Copper, and Transformer Oil listed below, as FAR clause 52.216-4. In accordance with FAR 52.216-4(a), supporting data shall include, but is not limited to, material invoices.
Cold Rolled Steel: $__________/lb.
Total number of pounds of Steel: __________ lbs.
Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:
WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics)
Standard Plate Steel: $__________/lb.
Total number of pounds of Steel: __________ lbs.
Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:
WPU101704 (Hot rolled steel bars, plates, and structural shapes)
Copper: $__________/lb.
Total number of pounds of copper: __________ lbs.
Total cost of copper: $__________ Copper Index that shall be used to calculate the EPA:
WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics)
Transformer OIL: $__________/lb.
Total number of gallons of transformer oil: __________ gal.
Total cost of transformer oil: $__________ Transformer Oil that shall be used to calculate the EPA:
WPU057, (Petroleum products, refined - Bureau of Labor Statistics) Not Separately Priced
TOTAL BASE (Items 0001 thru 0014) $_______
NOTES:
1 Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump sum) prices and the total amount, the lump sum prices will be considered the price submitted.
2 A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item Nos. 0001 thru 0014.
FP_OA GSU XFMR Supply 00 10 00
FP / OA GSU Transformer Supply
OA00106
SECTION 00 10 00
Pricing Schedule
CLIN Description Quantity Unit Measure Unit Price Amount
Oahe GSU Transformer Supply, SD
BASE ITEMS
0001 Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF, three-phase GSU power transformer. 1 EA $______________ $______________
0002 Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. 9 EA $______________ $______________
0003 Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $______________ $______________
0004 Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 9 EA $______________ $______________
0005 Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $______________ $______________
0006 Offload the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 9 EA $______________ $______________
0007 Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 1 EA $______________ $______________
0008 Move the 68,667 kVA, 230/132.79 kV single-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 9 EA $______________ $______________
The following CLIN/PRICE ITEMS is a LOT pricing item to be used for Economic Price Adjustment purposes. This CLIN will be administered in accordance with the Economic Price Adjustment Clause 52.216-2
0009 Economic Price Adjustment (EPA) FFP 1 LOT XXX Not Separately Priced
PROJECT NO.: ______________ FOB: DESIINATION PURCHASE REQUEST NUMBER: ______________
The Government will make an Economic Price Adjustment (EPA) limited to the Steel, Copper, and Transformer Oil listed below, as FAR clause 52.216-4. In accordance with FAR 52.216-4(a), supporting data shall include, but is not limited to, material invoices.
Steel: $__________/lb.
Total number of pounds of Steel: __________ lbs.
Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:
WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics)
Copper: $__________/lb.
Total number of pounds of copper: __________ lbs.
Total cost of copper: $__________ Copper Index that shall be used to calculate the EPA:
WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics)
TRANSFORMER OIL: $__________/lb.
Total number of gallons of transformer oil: __________ gal.
Total cost of transformer oil: $__________
WPU057, (Petroleum products, refined - Bureau of Labor Statistics)
0010 Furhish spare parts (See Section 48 19 23.05 26) 1 LOT $______________ $______________
SUB-TOTAL BASE (Items 0001 thru 0009) $______________
OPTIONAL ITEMS
0010 Manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. (SPARE) 1 EA $______________ $______________
0011 Deliver the spare 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $______________ $______________
0012 Offload the spare 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant spare storage location, perform inspections, perform cleaning, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $______________ $______________
SUB-TOTAL OPTIONS (Items 0010 thru 0012) $______________
TOTAL BASE + OPTIONS (Items 0001 thru 0012) $______________
Ft Peck T4/T5 GSU Transformer Supply, MT
BASE ITEMS
0013 Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformer. 2 EA $______________ $______________
0014 Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories from the manufacturing facility complete to the Fort Peck Dam power plant. 2 EA $______________ $______________
0015 Offload the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 2 EA $______________ $______________
0016 Move the 42,000/56,000 kVA, 230 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 2 EA $______________ $______________
0017 Furhish spare parts (See Section 48 19 23.04 26) 1 LOT $______________ $______________
TOTAL BASE (Items 0013 thru 0017) $______________
NOTES:
1 See SECTION 00 21 00, INSTRUCTIONS, CONDITIONS, & NOTICES TO BIDDERS for evaluation of options.
The Government may exercise an option by written notice to the Contractor commencing from the date of contract award thru the date the contract is closed, unless otherwise specified herein.
2 Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump sum) prices and the total amount, the lump sum prices will be considered the price submitted.
3 A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item Nos. 0001 thru 0017.
4 See SECTION 00 21 00, INSTRUCTIONS, CONDITIONS, & NOTICES TO BIDDERS for evaluation of options.
The Government may exercise an option by written notice to the Contractor commencing from the date of contract award thru the date the contract is closed, unless otherwise specified herein.
FP_OA GSU XFMR Supply (EPA)
FP / OA GSU Transformer Supply
OA00106
SECTION 00 10 00
Pricing Schedule
CLIN Description Quantity Unit Measure Unit Price Amount Basis
BASE ITEMS
0001 (OA) Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF, three-phase GSU power transformer. 1 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
0002 (OA)Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. 9 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
0003 (OA)Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $_______ $_______ None
0004 (OA)Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 9 EA $_______ $_______ None
0005 (OA)Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $_______ $_______ None
0006 (OA)Offload the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 9 EA $_______ $_______ None
0007 (OA)Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 1 EA $_______ $_______ None
0008 (OA)Move the 68,667 kVA, 230/132.79 kV single-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 9 EA $_______ $_______ None
0009 (OA)Furnish spare parts (See Section 48 19 23.05 26) 1 LOT $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
0010 (FP)Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformer. 2 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
0011 (FP)Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories from the manufacturing facility complete to the Fort Peck Dam power plant. 2 EA $_______ $_______ None
0012 (FP)Offload the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 2 EA $_______ $_______ None
0013 (FP)Move the 42,000/56,000 kVA, 230 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 2 EA $_______ $_______ None
0014 (FP)Furnish spare parts (See Section 48 19 23.04 26) 1 LOT $_______ $_______
The following CLIN/PRICE ITEMS is a LOT pricing item to be used for Economic Price Adjustment purposes. This CLIN will be administered in accordance with the Economic Price Adjustment Clause 52.216-2
Economic Price Adjustment (EPA) FFP 1 LOT XXX
PROJECT NO.: ______________ FOB: DESTINATION PURCHASE REQUEST NUMBER: ______________
The Government will make an Economic Price Adjustment (EPA) limited to the Steel, Copper, and Transformer Oil listed below, as FAR clause 52.216-4. In accordance with FAR 52.216-4(a), supporting data shall include, but is not limited to, material invoices.
Total number of pounds of Steel: __________ lbs.
Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:
WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics)
Standard Plate Steel: $__________/lb.
Total number of pounds of Steel: __________ lbs.
Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:
WPU101704 (Hot rolled steel bars, plates, and structural shapes)
Copper: $__________/lb.
Total number of pounds of copper: __________ lbs.
Total cost of copper: $__________ Copper Index that shall be used to calculate the EPA:
WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics)
Transformer OIL: $__________/lb.
Total number of gallons of transformer oil: __________ gal.
Total cost of transformer oil: $__________
WPU057, (Petroleum products, refined - Bureau of Labor Statistics) Not Separately Priced
TOTAL BASE (Items 0001 thru 0014) $_______
NOTES:
1 Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump sum) prices and the total amount, the lump sum prices will be considered the price submitted.
2 A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item Nos. 0001 thru 0014.
Sheet1 image12.emf
Microsoft_Excel_Worksheet1.xlsx
FP / OA GSU Transformer Supply
OA00106
SECTION 00 10 00
Pricing Schedule
CLIN Description Quantity Unit Measure Unit Price Amount Basis
BASE ITEMS
0001 (OA) Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF, three-phase GSU power transformer. 1 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
0002 (OA)Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. 9 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
0003 (OA)Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $_______ $_______ None
0004 (OA)Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 9 EA $_______ $_______ None
0005 (OA)Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $_______ $_______ None
0006 (OA)Offload the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 9 EA $_______ $_______ None
0007 (OA)Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 1 EA $_______ $_______ None
0008 (OA)Move the 68,667 kVA, 230/132.79 kV single-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 9 EA $_______ $_______ None
00009 (OA)Furnish spare parts (See Section 48 19 23.05 26) 1 LOT $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
00010 (FP)Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformer. 2 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
00011 (FP)Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories from the manufacturing facility complete to the Fort Peck Dam power plant. 2 EA $_______ $_______ None
00012 (FP)Offload the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 2 EA $_______ $_______ None
00013 (FP)Move the 42,000/56,000 kVA, 230 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 2 EA $_______ $_______ None
00014 (FP)Furnish spare parts (See Section 48 19 23.04 26) 1 LOT $_______ $_______
The following CLIN/PRICE ITEMS is a LOT pricing item to be used for Economic Price Adjustment purposes. This CLIN will be administered in accordance with the Economic Price Adjustment Clause 52.216-2
Economic Price Adjustment (EPA) FFP 1 LOT XXX
PROJECT NO.: ______________ FOB: DESTINATION PURCHASE REQUEST NUMBER: ______________
The Government will make an Economic Price Adjustment (EPA) limited to the Steel, Copper, and Transformer Oil listed below, as FAR clause 52.216-4. In accordance with FAR 52.216-4(a), supporting data shall include, but is not limited to, material invoices.
Total number of pounds of Steel: __________ lbs.
Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:
WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics)
Standard Plate Steel: $__________/lb.
Total number of pounds of Steel: __________ lbs.
Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:
WPU101704 (Hot rolled steel bars, plates, and structural shapes)
Copper: $__________/lb.
Total number of pounds of copper: __________ lbs.
Total cost of copper: $__________ Copper Index that shall be used to calculate the EPA:
WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics)
Transformer OIL: $__________/lb.
Total number of gallons of transformer oil: __________ gal.
Total cost of transformer oil: $__________
WPU057, (Petroleum products, refined - Bureau of Labor Statistics) Not Separately Priced
TOTAL BASE (Items 0001 thru 0014) $_______
NOTES:
1 Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump sum) prices and the total amount, the lump sum prices will be considered the price submitted.
2 A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item Nos. 0001 thru 0014.
FP / OA GSU Transformer Supply
OA00106
SECTION 00 10 00
Pricing Schedule
CLIN Description Quantity Unit Measure Unit Price Amount
Oahe GSU Transformer Supply, SD
BASE ITEMS
0001 Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF, three-phase GSU power transformer. 1 EA $______________ $______________
0002 Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. 9 EA $______________ $______________
0003 Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $______________ $______________
0004 Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 9 EA $______________ $______________
0005 Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $______________ $______________
0006 Offload the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 9 EA $______________ $______________
0007 Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 1 EA $______________ $______________
0008 Move the 68,667 kVA, 230/132.79 kV single-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 9 EA $______________ $______________
The following CLIN/PRICE ITEMS is a LOT pricing item to be used for Economic Price Adjustment purposes. This CLIN will be administered in accordance with the Economic Price Adjustment Clause 52.216-2
0009 Economic Price Adjustment (EPA) FFP 1 LOT XXX Not Separately Priced
PROJECT NO.: ______________ FOB: DESIINATION PURCHASE REQUEST NUMBER: ______________
The Government will make an Economic Price Adjustment (EPA) limited to the Steel, Copper, and Transformer Oil listed below, as FAR clause 52.216-4. In accordance with FAR 52.216-4(a), supporting data shall include, but is not limited to, material invoices.
Total number of pounds of Steel: __________ lbs.
Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:
WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics)
Copper: $__________/lb.
Total number of pounds of copper: __________ lbs.
Total cost of copper: $__________ Copper Index that shall be used to calculate the EPA:
WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics)
TRANSFORMER OIL: $__________/lb.
Total number of gallons of transformer oil: __________ gal.
Total cost of transformer oil: $__________
0010 Furhish spare parts (See Section 48 19 23.05 26) 1 LOT $______________ $______________
SUB-TOTAL BASE (Items 0001 thru 0009) $______________
OPTIONAL ITEMS
0010 Manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. (SPARE) 1 EA $______________ $______________
0011 Deliver the spare 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $______________ $______________
0012 Offload the spare 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant spare storage location, perform inspections, perform cleaning, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $______________ $______________
SUB-TOTAL OPTIONS (Items 0010 thru 0012) $______________
TOTAL BASE + OPTIONS (Items 0001 thru 0012) $______________
Ft Peck T4/T5 GSU Transformer Supply, MT
BASE ITEMS
0013 Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformer. 2 EA $______________ $______________
0014 Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories from the manufacturing facility complete to the Fort Peck Dam power plant. 2 EA $______________ $______________
0015 Offload the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 2 EA $______________ $______________
0016 Move the 42,000/56,000 kVA, 230 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 2 EA $______________ $______________
0017 Furhish spare parts (See Section 48 19 23.04 26) 1 LOT $______________ $______________
TOTAL BASE (Items 0013 thru 0017) $______________
NOTES:
1 See SECTION 00 21 00, INSTRUCTIONS, CONDITIONS, & NOTICES TO BIDDERS for evaluation of options.
The Government may exercise an option by written notice to the Contractor commencing from the date of contract award thru the date the contract is closed, unless otherwise specified herein.
2 Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump sum) prices and the total amount, the lump sum prices will be considered the price submitted.
3 A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item Nos. 0001 thru 0017.
4 See SECTION 00 21 00, INSTRUCTIONS, CONDITIONS, & NOTICES TO BIDDERS for evaluation of options.
The Government may exercise an option by written notice to the Contractor commencing from the date of contract award thru the date the contract is closed, unless otherwise specified herein.
FP / OA GSU Transformer Supply
OA00106
SECTION 00 10 00
Pricing Schedule
CLIN Description Quantity Unit Measure Unit Price Amount Basis
BASE ITEMS
0001 (OA) Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF, three-phase GSU power transformer. 1 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
0002 (OA)Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. 9 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
0003 (OA)Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $_______ $_______ None
0004 (OA)Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 9 EA $_______ $_______ None
0005 (OA)Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $_______ $_______ None
0006 (OA)Offload the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the services an Erecting Engineer. 9 EA $_______ $_______ None
0007 (OA)Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the services of an Erecting Engineer and Commissioning Agent. 1 EA $_______ $_______ None
0008 (OA)Move the 68,667 kVA, 230/132.79 kV single-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 9 EA $_______ $_______ None
0009 (OA)Furnish spare parts (See Section 48 19 23.05 26) 1 LOT $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
0010 (FP)Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformer. 2 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal
0011 (FP)Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories from the manufacturing facility complete to the Fort Peck Dam power plant. 2 EA $_______ $_______ None
0012 (FP)Offload the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the services of an Erecting Engineer. 2 EA $_______ $_______ None
0013 (FP)Move the 42,000/56,000 kVA, 230 kV three-phase…