20241219 Industry Day Presentation.pptx

PPTX presentation 23 MB Posted

Attached to
Virtual Industry Day for Oahe and Ft Peck GSU Transformer Supply
Solicitation number
Not on record
Issued by

About this file

This is an Industry Day presentation announcement for a virtual event on December 18, 2024 at 0900 CT regarding Generator Step-Up (GSU) Transformer supply for Oahe and Fort Peck Dams, managed by the US Army Corps of Engineers Omaha District. The project involves designing and manufacturing two new GSU transformers for Fort Peck and ten new GSU transformers for Oahe Dam, including ancillary components, control systems, Factory Acceptance Testing (FAT), delivery, assembly, oil processing, and final acceptance testing at both locations.

Interested contractors must RSVP by December 16, 2024 at 1700 CT to both the Contract Specialist and Contracting Officer. The event includes a government briefing, general Q&A, and optional 30-minute one-on-one sessions between 1230-1630 CT. Draft specifications will be available by December 6, 2024. Questions must be submitted through ProjNet using Bidder Inquiry Key 87GFMC-4S6G7V for solicitation W9128F25R0002. The government will publish attendee lists and Q&A responses on SAM.gov after the event.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

File Name Welcome

Fort peck & Oahe Dam GSU Transformer Supply Industry Day 19 dec 2024

Introductions

Omaha District Office

Ryan BrockmanProject Manager
Nadine CataniaContracting Officer
Brandie MurphyContract Specialist
Marc ProiettoContract Specialist
Lucas KirkpatrickElectrical Engineer

Fort Peck

Dale PughOperations Project Manager
Trevor WaarvikAsst M&O Manager
Jason MolstadTech Branch Chief
Irene WhitmerElectrical Engineer

Oahe

Joseph PintalOperations Project Manager
Jeremy IrvingAsst M&O Manager
Kris ClevelandTech Branch Chief
Jesse RoebuckElectrical Engineer

Hydroelectric Design Center (HDC), Portland

Doug FilerElectrical Engineer(DL)
Cole PobanzElectrical Engineer
Teresa CasperElectrical Engineer

Construction Division

Leeann WimerCOR
Cody NickolasCOR

agenda 19 Dec 2024

0900Industry Check-In
0915 - 1015Presentation by Government
Introductions
Contracting Rules of Engagement
Dam Briefing / General Information
Statement of Work / Project Specs
1030 - 1200Q&A
1200 – 1300Break
1300 – 16001 on 1 Q&A Sessions

USACE, Omaha District Contracting Nadine catania, contracting officer Rules of Engagement Contract officer is the government authority virtual industry day All questions or concerns must be directed to the Contract Specialist No side bars or independent conversations between contractors and government personnel No discussions relating to other Corp acquisitions No corporate denigration or sabotage will be tolerated Hold all questions until the designated question and answer session All questions will be documented and posted in ProjNet.

POTENTIAL Contract information

Contract Information Contract Type: Commercial Supply Solicitation Type: Request for Proposal (RFP) Contract Magnitude: >$7.5M Contract Duration: TBD

Projnet and contact information

ProjNet:

Used for contractor submitted questions Government is not required to respond to feedback Web site: https://www.projnet.org Bidder Inquiry Key: 87GFMC-4S6G7V Contract Specialist Contact Information:

Brandie Murphy Email: Brandie.L.Murphy@usace.army.mil Phone: 402-995-2332

Project schedule

MilestonesNov-24Dec-24Jan-25Feb-25Mar-25Apr-25May-25Jun-25Jul-25Aug-25Sep-25Oct-25
Final Design30-Nov
Industry Day19-Dec
Pre-solicitation20-Dec
Advertise28-Jan28-May
Site Visit23-Apr
Source Selection29-May
Award5-Sep
Notice to Proceed6-Oct

Submittals – Complete120 days after NTP Lead Time – 3 to 5 years Delivery – Oahe will be priority

File Name solicitation Fp/oa GSU transformer supply project Project manager, ryan brockman

Economic price adjustment (epa) Clause 52.216-4

The Economic Price Adjustment (EPA) clause is typically used in contracts to account for changes in costs that could occur over the duration of a project or agreement. These clauses are designed to ensure fairness for both parties by adjusting the contract price based on predefined criteria, such as market fluctuations, inflation, or changes in material costs.

Key Elements of an EPA Clause:

Scope of Adjustment: Specifies which costs or factors for materials (i.e. copper, steel, oil) are subject to adjustment.

Adjustment Formula: Often includes a formula or index to calculate price changes. For example, it may rely on a government-published index or market data.

Adjustment Frequency: Defines how often adjustments are made (e.g., monthly, quarterly).

Ceiling or Floor: Sometimes, limits are set on the maximum or minimum adjustment to avoid extreme fluctuations.

Triggering Conditions: Specifies what events or thresholds activate the adjustment (e.g., a percentage change in an index).

Common Uses: Government Contracts: Widely used in long-term contracts where pricing uncertainties exist.

Manufacturing: For supply agreements involving commodities or inputs with fluctuating prices.

Estimated price adjustment (epa) Clause 52.216-4

For this solicitation, the EPA Clause will be limited to the Steel, Plate Steel, Copper, and Transformer Oil Cold Rolled Steel Steel Index - WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics) Standard Plate Steel Plate Steel Index - WPU101704 (Hot rolled steel bars, plates, and structural shapes) Copper Copper Index - WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics) Transformer Oil Transformer Oil Index - WPU057, (Petroleum products, refined - Bureau of Labor Statistics)

Buy American / Trade agreements act

FAR 52.225-1: Buy American Act—Supplies Details requirements for domestic end products in supply contracts.

Key Requirements:

Domestic End Products:

Items must be manufactured in the U.S.

A minimum percentage of the product's components (by cost) must be sourced domestically:

60% currently (2022), rising to 65% in 2024 and 75% by 2029 under recent updates.

Manufacturing Location:

Final assembly or substantial manufacturing must occur in the United States.

Buy American / Trade agreements act

FAR 52.225-5: Trade Agreements The TAA applies to federal contracts over a certain threshold (e.g., $50,000 for supplies and services in 2024), especially when the U.S. has trade agreements like the World Trade Organization’s Government Procurement Agreement (WTO GPA) or other free trade agreements.

Eligible Countries:

Products and services must be from either:

The U.S.

A designated country, such as those part of WTO GPA (e.g., European Union, Japan) Free trade agreements like USMCA (Canada and Mexico)Least developed countries (e.g., Nepal, Bangladesh) Caribbean Basin countries Products from non-designated countries, such as China and Russia, are generally prohibited under the TAA.

Shipping – US - flagged carrier

For government contracts involving shipping supplies, U.S. law mandates the use of U.S.-flagged carriers FAR 52.247-64: Preference for Privately Owned U.S.-Flag Commercial Vessels:

Mandates the use of U.S.-flagged vessels for transporting supplies under government contracts unless a waiver is obtained.

Bid schedule – Clins 0001-0004

Bid schedule – Clins 0005 - 0007

Bid schedule – clins 0008 - 0011

Bid schedule – clins 0012 - 0014

Bid schedule - EPA Cold Rolled Steel:

$__________/lb. Total number of pounds of Steel: __________ lbs. Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics)

Standard Plate Steel:

$__________/lb. Total number of pounds of Steel: __________ lbs. Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:WPU101704 (Hot rolled steel bars, plates, and structural shapes)

Copper:

$__________/lb. Total number of pounds of copper: __________ lbs. Total cost of copper: $__________ Copper Index that shall be used to calculate the EPA:WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics)

Transformer Oil:

$__________/lb. Total number of gallons of transformer oil: __________ gal. Total cost of oil: $__________ Transformer oil that shall be used to calculate the EPA:WPU057 (Petroleum products, refined - Bureau of Labor Statistics)

Evaluation Factors transformer design Hydroelectric design center (HDC) Doug filer, Electrical engineer

QUANTITY: 2

NAMEPLATE DATA

TYPE: CLASS II GSU POWER TRANSFORMER
COOLING CLASS: ONAN/ONAF
KVA RATING: 42,000 / 56,000
VOLTAGE RATINGS: 230,000 GRDY (H) - 13,800 DELTA (X)
BIL LEVELS, KV: 900 (H) / 110 (X) / 150 (H0)
PHASING: THREE-PHASE
FREQUENCY: 60 HZ
IMPEDANCE: 11.0% @ 42,000 KVA (H-X)
SECONDARY WINDING (H) DETC: 5 TAPS; 2 @ +2.5%, 2 @ -2.5% OFNOMINAL 230 KV TAP
TEMPERATURE RISE: 65 ºC
OIL PRESERVATION SYSTEM: CONSTANT OIL PRESSURE SYSTEM(COPS) TANK
MAXIMUM SOUND LEVEL (ONAF): 70 DB
MAXIMUM TOTAL WEIGHT: 230,000 LB
MAXIMUM TOTAL OIL VOLUME: 7,000 GAL

OVERVIEW of gsu transformer requirements Fort peck dam

UNUSUAL SERVICE CONDITIONS

MAXIMUM AMBIENT AIR TEMPERATURE: 43.3 DEGREES CELSIUS
MAXIMUM AVERAGE AMBIENT AIR TEMPERATURE (24-HOURPERIOD): 33.3 DEGREES CELSIUS

TRANSFORMER COMPONENTS REQURIED BY NAME BRAND

1) COOLING CONTROL MONITOR: SEL MODEL 2414
2) ANNUNCIATOR: SEL MODEL 2533
3) DISSOLVED GAS ANALYZER: MORGAN SCHAFFER CALISTOMODEL R9

FORT PECK GSU TRANSFORMERS

LIMITING DIMENSIONS AND GENERAL ARRANGEMENT

TOP VIEW

FORT PECK GSU TRANSFORMERS

SIDE VIEW – SEGMENT 4

QUANTITY: 9

NAMEPLATE DATA

TYPE: CLASS II GSU POWER TRANSFORMER
COOLING CLASS: OFAF
KVA RATING: 68,667
VOLTAGE RATINGS: 230,000 GRDY / 132,790 (H) - 13,800 DELTA (X)
BIL LEVELS, KV: 900 (H) / 110 (X) / 150 (H0)
PHASING: SINGLE-PHASE
FREQUENCY: 60 HZ
IMPEDANCE: 13.5% @ 68,667 KVA (H-X)
SECONDARY WINDING (H) DETC: 5 TAPS; 2 @ +2.5%, 2 @ -2.5% OFNOMINAL 230 KV TAP
TEMPERATURE RISE: 65 ºC
OIL PRESERVATION SYSTEM: NITROGEN GAS BLANKETED
MAXIMUM SOUND LEVEL (ONAF): 70 DB
MAXIMUM TOTAL WEIGHT: 160,000 LB
MAXIMUM TOTAL OIL VOLUME: 4,700 GAL

OVERVIEW of 230KV gsu transformer requirements OAHE dam

UNUSUAL SERVICE CONDITIONS

TRANSFORMERS ARE TO BE CAPABLE OF FULL LOAD OPERATION
AT AN AMBIENT AIR TEMPERATURE OF 45 DEGREES CELSIUS
MAXIMUM AMBIENT AIR TEMPERATURE: 47.2 DEGREES CELSIUS
MAXIMUM AVERAGE AMBIENT AIR TEMPERATURE (24-HOURPERIOD): 36.4 DEGREES CELSIUS

TRANSFORMER COMPONENTS REQURIED BY NAME BRAND

1) COOLING CONTROL MONITOR: SEL MODEL 2414
2) ANNUNCIATOR: SEL MODEL 2533
3) DISSOLVED GAS ANALYZER: MORGAN SCHAFFER CALISTOMODEL R9

OAHE 230KV GSU TRANSFORMERS

OAHE 230KV GSU TRANSFORMERS

SIDE VIEW – SEGMENT 2

QUANTITY: 1

NAMEPLATE DATA

TYPE: CLASS II GSU POWER TRANSFORMER
COOLING CLASS: OFAF
KVA RATING: 103,000
VOLTAGE RATINGS: 115,000 GRDY (H) - 13,800 DELTA (X)
BIL LEVELS, KV: 550 (H) / 110 (X) / 150 (H0)
PHASING: THREE-PHASE
FREQUENCY: 60 HZ
IMPEDANCE: 10.5% @ 103,000 KVA (H-X)
SECONDARY WINDING (H) DETC: 5 TAPS; 2 @ +2.5%, 2 @ -2.5% OFNOMINAL 115 KV TAP
TEMPERATURE RISE: 65 ºC
OIL PRESERVATION SYSTEM: NITROGEN GAS BLANKETED
MAXIMUM SOUND LEVEL (ONAF): 70 DB
MAXIMUM TOTAL WEIGHT: 212,000 LB
MAXIMUM TOTAL OIL VOLUME: 4,400 GAL

OVERVIEW of 115KV gsu transformer requirements OAHE dam

UNUSUAL SERVICE CONDITIONS

TRANSFORMERS ARE TO BE CAPABLE OF FULL LOAD OPERATION
AT AN AMBIENT AIR TEMPERATURE OF 45 DEGREES CELSIUS
MAXIMUM AMBIENT AIR TEMPERATURE: 47.2 DEGREES CELSIUS
MAXIMUM AVERAGE AMBIENT AIR TEMPERATURE (24-HOURPERIOD): 36.4 DEGREES CELSIUS

TRANSFORMER COMPONENTS REQURIED BY NAME BRAND

1) COOLING CONTROL MONITOR: SEL MODEL 2414
2) ANNUNCIATOR: SEL MODEL 2533
3) DISSOLVED GAS ANALYZER: MORGAN SCHAFFER CALISTOMODEL R9

OAHE 115KV GSU TRANSFORMER

OAHE 115KV GSU TRANSFORMER

SIDE VIEW – SEGMENT 2

On-site overview Oahe project Kris cleveland, Electrical engineer

Oahe – Temp Storage and Staging Locations

Oahe Project – Access to Tailrace

Oahe Project – Current GSU Transformers

Oahe Project – Ancillary Connections

Oahe Project -

Oahe Project -

Oahe Project

On-site overview Fort pECK project Irene whitmer, Electrical engineer

FORT PECK – SITE OVERVIEW

Fort Peck Powerhouses Site Overview Gate Transformer Storage & Staging Area Transformers Access Road

Main facility gate located on southeast corner of site.

Transformer located in Switchyard 2, on the north side of Powerhouse 2.

Transformer Temporary storage and staging area located northwest corner of Switchyard 2

FORT PECK Project – Access

Highway 24 runs across top of dam, Yager Rd runs North from Hwy 24 to bottom of hill where it turns into Lower Yellowstone Rd.

Facility gate located at the bottom of hill.

FORT PECK Project – TEMPORARY STORAGE & STAGING AREA

- Temporary storage & staging area located adjacent to northwest corner of Switchyard 2.

FORT PECK Project – Access to SWITCHYARD 2

Switchyard 2 access for Unit 4 & 5 Transformers located on west side of switchyard.

Not sure if we need to add this slide since this is the supply contract and KTR will deliver and assemble transformers in temp. storage/staging area. Transformers will not relocate to switchyard 2 until installation contract.

FORT PECK Project – Current GSU Transformers

Questions?

1 on 1 discussion schedule (19 Dec)

1300 - 1330Virginia Transformers
1400 – 1430PAF Electrical, Inc.
1500 – 1530Koontz Electric

image9.jpeg image10.jpeg image11.jpeg

Microsoft_Excel_Worksheet.xlsx FP_OA GSU XFMR Supply (Word)

FP / OA GSU Transformer Supply

OA00106

SECTION 00 10 00

Pricing Schedule

CLIN Description Quantity Unit Measure Unit Price Amount Basis

BASE ITEMS

0001 (OA) Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF, three-phase GSU power transformer. 1 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

0002 (OA)Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. 9 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

0003 (OA)Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $_______ $_______ None

0004 (OA)Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 9 EA $_______ $_______ None

0005 (OA)Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $_______ $_______ None

0006 (OA)Offload the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 9 EA $_______ $_______ None

0007 (OA)Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 1 EA $_______ $_______ None

0008 (OA)Move the 68,667 kVA, 230/132.79 kV single-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 9 EA $_______ $_______ None

00009 (OA)Furnish spare parts (See Section 48 19 23.05 26) 1 LOT $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

00010 (FP)Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformer. 2 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

00011 (FP)Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories from the manufacturing facility complete to the Fort Peck Dam power plant. 2 EA $_______ $_______ None

00012 (FP)Offload the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 2 EA $_______ $_______ None

00013 (FP)Move the 42,000/56,000 kVA, 230 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 2 EA $_______ $_______ None

00014 (FP)Furnish spare parts (See Section 48 19 23.04 26) 1 LOT $_______ $_______

The following CLIN/PRICE ITEMS is a LOT pricing item to be used for Economic Price Adjustment purposes. This CLIN will be administered in accordance with the Economic Price Adjustment Clause 52.216-2

Economic Price Adjustment (EPA) FFP 1 LOT XXX

PROJECT NO.: ______________ FOB: DESTINATION PURCHASE REQUEST NUMBER: ______________

The Government will make an Economic Price Adjustment (EPA) limited to the Steel, Copper, and Transformer Oil listed below, as FAR clause 52.216-4. In accordance with FAR 52.216-4(a), supporting data shall include, but is not limited to, material invoices.

Cold Rolled Steel: $__________/lb.

Total number of pounds of Steel: __________ lbs.

Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:

WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics)

Standard Plate Steel: $__________/lb.

Total number of pounds of Steel: __________ lbs.

Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:

WPU101704 (Hot rolled steel bars, plates, and structural shapes)

Copper: $__________/lb.

Total number of pounds of copper: __________ lbs.

Total cost of copper: $__________ Copper Index that shall be used to calculate the EPA:

WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics)

Transformer OIL: $__________/lb.

Total number of gallons of transformer oil: __________ gal.

Total cost of transformer oil: $__________ Transformer Oil that shall be used to calculate the EPA:

WPU057, (Petroleum products, refined - Bureau of Labor Statistics) Not Separately Priced

TOTAL BASE (Items 0001 thru 0014) $_______

NOTES:

1 Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump sum) prices and the total amount, the lump sum prices will be considered the price submitted.

2 A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item Nos. 0001 thru 0014.

FP_OA GSU XFMR Supply 00 10 00

FP / OA GSU Transformer Supply

OA00106

SECTION 00 10 00

Pricing Schedule

CLIN Description Quantity Unit Measure Unit Price Amount

Oahe GSU Transformer Supply, SD

BASE ITEMS

0001 Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF, three-phase GSU power transformer. 1 EA $______________ $______________

0002 Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. 9 EA $______________ $______________

0003 Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $______________ $______________

0004 Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 9 EA $______________ $______________

0005 Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $______________ $______________

0006 Offload the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 9 EA $______________ $______________

0007 Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 1 EA $______________ $______________

0008 Move the 68,667 kVA, 230/132.79 kV single-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 9 EA $______________ $______________

The following CLIN/PRICE ITEMS is a LOT pricing item to be used for Economic Price Adjustment purposes. This CLIN will be administered in accordance with the Economic Price Adjustment Clause 52.216-2

0009 Economic Price Adjustment (EPA) FFP 1 LOT XXX Not Separately Priced

PROJECT NO.: ______________ FOB: DESIINATION PURCHASE REQUEST NUMBER: ______________

The Government will make an Economic Price Adjustment (EPA) limited to the Steel, Copper, and Transformer Oil listed below, as FAR clause 52.216-4. In accordance with FAR 52.216-4(a), supporting data shall include, but is not limited to, material invoices.

Steel: $__________/lb.

Total number of pounds of Steel: __________ lbs.

Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:

WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics)

Copper: $__________/lb.

Total number of pounds of copper: __________ lbs.

Total cost of copper: $__________ Copper Index that shall be used to calculate the EPA:

WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics)

TRANSFORMER OIL: $__________/lb.

Total number of gallons of transformer oil: __________ gal.

Total cost of transformer oil: $__________

WPU057, (Petroleum products, refined - Bureau of Labor Statistics)

0010 Furhish spare parts (See Section 48 19 23.05 26) 1 LOT $______________ $______________

SUB-TOTAL BASE (Items 0001 thru 0009) $______________

OPTIONAL ITEMS

0010 Manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. (SPARE) 1 EA $______________ $______________

0011 Deliver the spare 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $______________ $______________

0012 Offload the spare 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant spare storage location, perform inspections, perform cleaning, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $______________ $______________

SUB-TOTAL OPTIONS (Items 0010 thru 0012) $______________

TOTAL BASE + OPTIONS (Items 0001 thru 0012) $______________

Ft Peck T4/T5 GSU Transformer Supply, MT

BASE ITEMS

0013 Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformer. 2 EA $______________ $______________

0014 Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories from the manufacturing facility complete to the Fort Peck Dam power plant. 2 EA $______________ $______________

0015 Offload the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 2 EA $______________ $______________

0016 Move the 42,000/56,000 kVA, 230 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 2 EA $______________ $______________

0017 Furhish spare parts (See Section 48 19 23.04 26) 1 LOT $______________ $______________

TOTAL BASE (Items 0013 thru 0017) $______________

NOTES:

1 See SECTION 00 21 00, INSTRUCTIONS, CONDITIONS, & NOTICES TO BIDDERS for evaluation of options.

The Government may exercise an option by written notice to the Contractor commencing from the date of contract award thru the date the contract is closed, unless otherwise specified herein.

2 Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump sum) prices and the total amount, the lump sum prices will be considered the price submitted.

3 A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item Nos. 0001 thru 0017.

4 See SECTION 00 21 00, INSTRUCTIONS, CONDITIONS, & NOTICES TO BIDDERS for evaluation of options.

The Government may exercise an option by written notice to the Contractor commencing from the date of contract award thru the date the contract is closed, unless otherwise specified herein.

FP_OA GSU XFMR Supply (EPA)

FP / OA GSU Transformer Supply

OA00106

SECTION 00 10 00

Pricing Schedule

CLIN Description Quantity Unit Measure Unit Price Amount Basis

BASE ITEMS

0001 (OA) Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF, three-phase GSU power transformer. 1 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

0002 (OA)Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. 9 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

0003 (OA)Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $_______ $_______ None

0004 (OA)Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 9 EA $_______ $_______ None

0005 (OA)Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $_______ $_______ None

0006 (OA)Offload the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 9 EA $_______ $_______ None

0007 (OA)Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 1 EA $_______ $_______ None

0008 (OA)Move the 68,667 kVA, 230/132.79 kV single-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 9 EA $_______ $_______ None

0009 (OA)Furnish spare parts (See Section 48 19 23.05 26) 1 LOT $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

0010 (FP)Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformer. 2 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

0011 (FP)Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories from the manufacturing facility complete to the Fort Peck Dam power plant. 2 EA $_______ $_______ None

0012 (FP)Offload the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 2 EA $_______ $_______ None

0013 (FP)Move the 42,000/56,000 kVA, 230 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 2 EA $_______ $_______ None

0014 (FP)Furnish spare parts (See Section 48 19 23.04 26) 1 LOT $_______ $_______

The following CLIN/PRICE ITEMS is a LOT pricing item to be used for Economic Price Adjustment purposes. This CLIN will be administered in accordance with the Economic Price Adjustment Clause 52.216-2

Economic Price Adjustment (EPA) FFP 1 LOT XXX

PROJECT NO.: ______________ FOB: DESTINATION PURCHASE REQUEST NUMBER: ______________

The Government will make an Economic Price Adjustment (EPA) limited to the Steel, Copper, and Transformer Oil listed below, as FAR clause 52.216-4. In accordance with FAR 52.216-4(a), supporting data shall include, but is not limited to, material invoices.

Total number of pounds of Steel: __________ lbs.

Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:

WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics)

Standard Plate Steel: $__________/lb.

Total number of pounds of Steel: __________ lbs.

Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:

WPU101704 (Hot rolled steel bars, plates, and structural shapes)

Copper: $__________/lb.

Total number of pounds of copper: __________ lbs.

Total cost of copper: $__________ Copper Index that shall be used to calculate the EPA:

WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics)

Transformer OIL: $__________/lb.

Total number of gallons of transformer oil: __________ gal.

Total cost of transformer oil: $__________

WPU057, (Petroleum products, refined - Bureau of Labor Statistics) Not Separately Priced

TOTAL BASE (Items 0001 thru 0014) $_______

NOTES:

1 Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump sum) prices and the total amount, the lump sum prices will be considered the price submitted.

2 A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item Nos. 0001 thru 0014.

Sheet1 image12.emf

Microsoft_Excel_Worksheet1.xlsx

FP / OA GSU Transformer Supply

OA00106

SECTION 00 10 00

Pricing Schedule

CLIN Description Quantity Unit Measure Unit Price Amount Basis

BASE ITEMS

0001 (OA) Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF, three-phase GSU power transformer. 1 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

0002 (OA)Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. 9 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

0003 (OA)Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $_______ $_______ None

0004 (OA)Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 9 EA $_______ $_______ None

0005 (OA)Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $_______ $_______ None

0006 (OA)Offload the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 9 EA $_______ $_______ None

0007 (OA)Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 1 EA $_______ $_______ None

0008 (OA)Move the 68,667 kVA, 230/132.79 kV single-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 9 EA $_______ $_______ None

00009 (OA)Furnish spare parts (See Section 48 19 23.05 26) 1 LOT $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

00010 (FP)Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformer. 2 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

00011 (FP)Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories from the manufacturing facility complete to the Fort Peck Dam power plant. 2 EA $_______ $_______ None

00012 (FP)Offload the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 2 EA $_______ $_______ None

00013 (FP)Move the 42,000/56,000 kVA, 230 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 2 EA $_______ $_______ None

00014 (FP)Furnish spare parts (See Section 48 19 23.04 26) 1 LOT $_______ $_______

The following CLIN/PRICE ITEMS is a LOT pricing item to be used for Economic Price Adjustment purposes. This CLIN will be administered in accordance with the Economic Price Adjustment Clause 52.216-2

Economic Price Adjustment (EPA) FFP 1 LOT XXX

PROJECT NO.: ______________ FOB: DESTINATION PURCHASE REQUEST NUMBER: ______________

The Government will make an Economic Price Adjustment (EPA) limited to the Steel, Copper, and Transformer Oil listed below, as FAR clause 52.216-4. In accordance with FAR 52.216-4(a), supporting data shall include, but is not limited to, material invoices.

Total number of pounds of Steel: __________ lbs.

Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:

WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics)

Standard Plate Steel: $__________/lb.

Total number of pounds of Steel: __________ lbs.

Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:

WPU101704 (Hot rolled steel bars, plates, and structural shapes)

Copper: $__________/lb.

Total number of pounds of copper: __________ lbs.

Total cost of copper: $__________ Copper Index that shall be used to calculate the EPA:

WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics)

Transformer OIL: $__________/lb.

Total number of gallons of transformer oil: __________ gal.

Total cost of transformer oil: $__________

WPU057, (Petroleum products, refined - Bureau of Labor Statistics) Not Separately Priced

TOTAL BASE (Items 0001 thru 0014) $_______

NOTES:

1 Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump sum) prices and the total amount, the lump sum prices will be considered the price submitted.

2 A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item Nos. 0001 thru 0014.

FP / OA GSU Transformer Supply

OA00106

SECTION 00 10 00

Pricing Schedule

CLIN Description Quantity Unit Measure Unit Price Amount

Oahe GSU Transformer Supply, SD

BASE ITEMS

0001 Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF, three-phase GSU power transformer. 1 EA $______________ $______________

0002 Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. 9 EA $______________ $______________

0003 Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $______________ $______________

0004 Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 9 EA $______________ $______________

0005 Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $______________ $______________

0006 Offload the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 9 EA $______________ $______________

0007 Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 1 EA $______________ $______________

0008 Move the 68,667 kVA, 230/132.79 kV single-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 9 EA $______________ $______________

The following CLIN/PRICE ITEMS is a LOT pricing item to be used for Economic Price Adjustment purposes. This CLIN will be administered in accordance with the Economic Price Adjustment Clause 52.216-2

0009 Economic Price Adjustment (EPA) FFP 1 LOT XXX Not Separately Priced

PROJECT NO.: ______________ FOB: DESIINATION PURCHASE REQUEST NUMBER: ______________

The Government will make an Economic Price Adjustment (EPA) limited to the Steel, Copper, and Transformer Oil listed below, as FAR clause 52.216-4. In accordance with FAR 52.216-4(a), supporting data shall include, but is not limited to, material invoices.

Total number of pounds of Steel: __________ lbs.

Total cost of Steel: $__________ Steel Index that shall be used to calculate the EPA for Steel:

WPU101707 (Cold Rolled Steel Sheet and Strip - Bureau of Labor Statistics)

Copper: $__________/lb.

Total number of pounds of copper: __________ lbs.

Total cost of copper: $__________ Copper Index that shall be used to calculate the EPA:

WPU102403 (Secondary copper, Alloyed and Unalloyed - Bureau of Labor Statistics)

TRANSFORMER OIL: $__________/lb.

Total number of gallons of transformer oil: __________ gal.

Total cost of transformer oil: $__________

0010 Furhish spare parts (See Section 48 19 23.05 26) 1 LOT $______________ $______________

SUB-TOTAL BASE (Items 0001 thru 0009) $______________

OPTIONAL ITEMS

0010 Manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. (SPARE) 1 EA $______________ $______________

0011 Deliver the spare 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $______________ $______________

0012 Offload the spare 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant spare storage location, perform inspections, perform cleaning, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $______________ $______________

SUB-TOTAL OPTIONS (Items 0010 thru 0012) $______________

TOTAL BASE + OPTIONS (Items 0001 thru 0012) $______________

Ft Peck T4/T5 GSU Transformer Supply, MT

BASE ITEMS

0013 Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformer. 2 EA $______________ $______________

0014 Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories from the manufacturing facility complete to the Fort Peck Dam power plant. 2 EA $______________ $______________

0015 Offload the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 2 EA $______________ $______________

0016 Move the 42,000/56,000 kVA, 230 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 2 EA $______________ $______________

0017 Furhish spare parts (See Section 48 19 23.04 26) 1 LOT $______________ $______________

TOTAL BASE (Items 0013 thru 0017) $______________

NOTES:

1 See SECTION 00 21 00, INSTRUCTIONS, CONDITIONS, & NOTICES TO BIDDERS for evaluation of options.

The Government may exercise an option by written notice to the Contractor commencing from the date of contract award thru the date the contract is closed, unless otherwise specified herein.

2 Prices must be entered for all items of the schedule. Total amounts submitted without prices being entered on individual items will be rejected. Additions will be subject to verification by the Government. In case of variation between the Job (lump sum) prices and the total amount, the lump sum prices will be considered the price submitted.

3 A modification to a proposal which provides for a single adjustment to the total amount submitted, should state the application of the adjustment to each respective lump sum price affected. If the modification is not so apportioned, the single adjustment will be applied to Item Nos. 0001 thru 0017.

4 See SECTION 00 21 00, INSTRUCTIONS, CONDITIONS, & NOTICES TO BIDDERS for evaluation of options.

The Government may exercise an option by written notice to the Contractor commencing from the date of contract award thru the date the contract is closed, unless otherwise specified herein.

FP / OA GSU Transformer Supply

OA00106

SECTION 00 10 00

Pricing Schedule

CLIN Description Quantity Unit Measure Unit Price Amount Basis

BASE ITEMS

0001 (OA) Design, manufacture and factory test 103,000 kVA, 115 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class OFAF, three-phase GSU power transformer. 1 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

0002 (OA)Design, manufacture and factory test 68,667 kVA, 230/132.79 kV high-voltage, 13.8 kV low-voltage, cooling class OFAF, single-phase GSU power transformer. 9 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

0003 (OA)Deliver the 103,000 kVA, 115 kV three-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 1 EA $_______ $_______ None

0004 (OA)Deliver the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories from the manufacturing facility complete to the Oahe Dam power plant. 9 EA $_______ $_______ None

0005 (OA)Offload the 103,000 kVA, 115 kV three-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the of services of an Erecting Engineer. 1 EA $_______ $_______ None

0006 (OA)Offload the 68,667 kVA, 230/132.79 kV single-phase power transformer and accessories at the Oahe Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the services an Erecting Engineer. 9 EA $_______ $_______ None

0007 (OA)Move the 103,000 kVA, 115 kV three-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the services of an Erecting Engineer and Commissioning Agent. 1 EA $_______ $_______ None

0008 (OA)Move the 68,667 kVA, 230/132.79 kV single-phase power transformer from the temporary storage location to the permanent operating location, perform testing, perform inspections, perform cleaning, perform touch-up painting, and provide the of services of an Erecting Engineer and Commissioning Agent. 9 EA $_______ $_______ None

0009 (OA)Furnish spare parts (See Section 48 19 23.05 26) 1 LOT $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

0010 (FP)Design, manufacture and factory test 42,000/56,000 kVA, 230 kV Grd. Y high-voltage, 13.8 kV delta low-voltage, cooling class ONAN/ONAF, three-phase GSU power transformer. 2 EA $_______ $_______ ___lbs of Core Steel @ $____/lbs ___lbs of Plate Steel @ $___/lbs ___lbs of Copper @ $____/lbs ___gal of Transformer Oil @ $___/gal

0011 (FP)Deliver the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories from the manufacturing facility complete to the Fort Peck Dam power plant. 2 EA $_______ $_______ None

0012 (FP)Offload the 42,000/56,000 kVA, 230 kV three-phase power transformer and accessories at the Fort Peck Dam power plant temporary storage location, perform inspections, perform cleaning, provide temporary storage materials, perform transformer reassembly, furnish oil and perform oil-filling and processing, perform field tests, and provide the services of an Erecting Engineer. 2 EA $_______ $_______ None

0013 (FP)Move the 42,000/56,000 kVA, 230 kV three-phase…