2024_JAC_SOW_3_Stage_Septic_Tanks_-_07-18-2024.pdf
PDF 176 KB Posted
- Attached to
- WY-JACKSON NFH-SEPTIC SYSTEM
- Solicitation number
- 140FC124R0065
About this file
This document is a Statement of Work (SOW) for the procurement of a 2000-gallon, 3-stage concrete septic tank system for the Jackson National Fish Hatchery (NFH) in Jackson, Wyoming. The project requires the contractor to provide, transport, and install the complete septic system, including a concrete distribution box, effluent filter, alarm, and pump station. The work must be completed by September 15, 2024, to support the facility's volunteer operations. The SOW outlines the place of performance, period of performance, scope of work, deliverables, and evaluation and acceptance criteria. The related federal contract opportunity, Solicitation Number 140FC124R0065, is a 100% Small Business Set-Aside with a Lowest Price Technically Acceptable (LPTA) evaluation method. Proposals must be submitted by August 30, 2024, and the contract will be awarded on a Firm Fixed Price basis.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (2024 06 3)
Good
3-Stage Concrete Septic Tank
PR Number: __40668275_____________
1. General:
1.1 Jackson National Fish Hatchery (NFH), 1500 Fish Hatchery Road, Jackson, WY 83001-9805.
2000-gallon, 3-Stage Concrete Septic Tank.
1.2 Purpose is to provide septic service to the Volunteer Complex at the Jackson NFH to include the RV pads and the volunteer bunkhouse.
1.3 The contractor must be appropriately licensed and certified for the construction of the concrete tank.
1.4 The contractor, or sub-contractor, whomever is transporting the concrete tank, must be appropriately licensed and certified to transport in the states that the transport will be conducted.
1.5 The contractor must follow all associated regulations and laws including: Federal, State, County, and municipal.
2. Place of Performance and Period of Performance
2.1 Work is to be performed at Jackson National Fish Hatchery (NFH), 1500 Fish Hatchery Road, Jackson, WY 83001-9805.
2.2 This project needs to be completed as close to September 15, 2024, as possible, for volunteers coming in the fall..
2.3 Normal duty hours Monday thru Friday 8:00 a.m. - 4:30 p.m. In the event of emergencies, Contractor shall provide contact information.
2.4 Non-duty hours include weeknights, weekends, and Government holidays (New Year’s Day, Martin Luther King Jr. Birthday, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day).
3. Scope
3.1 The contractor will provide a 2000-gallon, 3-stage concrete septic tank including concrete distribution box, effluent filter w/ float bracket, alarm, complete low head pump station, risers, etc.
3.2 Contractor or subcontractor will transport septic tank and accessories to Jackson NFH.
3.3 Contractor or subcontractor will excavate location for the septic tank and the drain field to meet Teton County, WY, Septic System Engineering specifications.
3.4 Contractor or subcontractor will off-load and place septic tank at excavated location.
3.5 Contractor or subcontractor will wire/ connect alarm system, pump and any other electrical components required to operate septic system.
4. Deliverables and/or Delivery Schedule: (for extended list a bid schedule and/or use of line-item detail on the PR is recommended)
4.1 The contractor is to provide a 2000-gallon, concrete, top seam, 3-stage septic tank; with all of the materials, penetrations, and equipment to make it legally, fully operational.
4.2 The contractor shall provide all materials and equipment required.
5. Data Management Plan (DMP)
5.1 None.
6. Government-Furnished Equipment (GFE) / Government-Furnished Information
(GFI)
6.1 Jackson NFH will provide restrooms, electricity, and water for the contractor to using while the contracted work is being completed.
6.2 Identify any limitations. N/A
7. Evaluation and Acceptance
7.1 The contractor will be evaluated as detailed herein. Government acceptance is contingent upon: Designated U.S. Fish and Wildlife Service representative(s) determining the work to be acceptable and in good working order.
8. Quality Control/Quality Assurance:
8.1 For commercial supplies reference clauses for inspection and acceptance. Where appropriate, QC will be maintained according to industry standards and made available to the agency with the contractor’s proposal.
8.2 Identify and detail measures for assessing quality control and acceptance; each requirement is unique, and a table format is visually friendly and may be desirable.
9. Technical Coordinator:
9.1 Primary individual responsible for the final product or service.
Sean Henderson Fish Biologist 1500 Fish Hatchery Road Jackson, WY 83001-9805 Office: 307-733-2510 Cell: 307-690-8242 sean_henderson@fws.gov
9.2 Secondary individual responsible for the final product or service.
Kristopher “Kris” Johnson Facility Management Coordinator (FMC) Asset Management Coordinator (AMC) U.S. Fish and Wildlife Service Fish and Aquatic Conservation (FAC) 1380 South 2350 West Vernal, UT 84078 Cell: 435-299-5150 Office: 435-789-0351 ext. 16 kristopher_b_johnson@fws.gov mailto:sean_henderson@fws.gov mailto:kristopher_b_johnson@fws.gov
| STATEMENT OF WORK (2024 06 3) |
| Good |
| 1. General: |
| 2. Place of Performance and Period of Performance |
| 2.1 Work is to be performed at Jackson National Fish Hatchery (NFH), 1500 Fish Hatchery Road, Jackson, WY 83001-9805. |
| 2.2 This project needs to be completed as close to September 15, 2024, as possible, for volunteers coming in the fall.. |
| 2.3 Normal duty hours Monday thru Friday 8:00 a.m. - 4:30 p.m. In the event of emergencies, Contractor shall provide contact information. |
| 2.4 Non-duty hours include weeknights, weekends, and Government holidays (New Year’s Day, Martin Luther King Jr. Birthday, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veteran’s Day, Thanksgiving Day, Christmas Day). |
| 3. Scope |
| 4. Deliverables and/or Delivery Schedule: (for extended list a bid schedule and/or use of line-item detail on the PR is recommended) |