2024-18PC Addendum 1.pdf
PDF 192 KB Posted
- Attached to
- LAKE EMILY WELL DRILLING & INSTALLATION
- Solicitation number
- 2024-18PC
- Issued by
- Portage County, Wisconsin
About this file
This is Addendum 1 to RFB #2024-18PC for the County of Portage, Wisconsin, issued on June 18, 2024, regarding the drilling and installation of a drinking well for Lake Emily County Park. The addendum clarifies specifications and addresses bidder inquiries regarding well testing and equipment requirements. Key revisions include a modification to Section 10.9 to specify the installation of two 2 HP STA-Right submersible pumps at 20 GPM constant capacity, replacing the originally specified 1 HP pump. The addendum confirms that three separate nitrate level tests are required, with testing to be conducted at the contractor's discretion. Additionally, the specifications require the installation of a 1 1/4-inch pit-less shut-off valve as part of the project deliverables.
No pricing information, set-asides, incumbents, funding sources, or contract term details are contained within this addendum document. The addendum serves solely to provide technical clarifications and revisions to the original bid specifications in response to bidder questions regarding pump horsepower, testing frequency, and valve requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2024-18PC Bid Document.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFB #2024-18PC
Lake Emily Well Drilling and Installation
ADDENDUM 1
Date=06/18/2024 The following changes are hereby added to and made part of Bid #2024-18PC.
Questions, Answers, Clarifications and Revisions:
Revisions to Bid Document:
Page 5 sec 10.9 Install 2 1 HP STA-Right Submersible Pump 20GPM Constant…
Question Responses:
Q1 How many times are we required to test extra nitrate levels? And when should we collect samples to test for Nitrate levels?
A. We need 3 tests in total. Testing should be done at your discretion.
Q2 We feel the pump should be 2hp. Should we bid on a 1 hp pump or a 2 hp pump?
A. Bid on a 2 hp pump. See revision above.
Q3 Do you need a pit-less shut off value?
A. Yes, use a 1 1/4 “pit-less.
*******End of Addendum 1********