About this file
This document is a solicitation for quotes for a speaker wiring project at the South Shore Charter Public School located in Norwell, Massachusetts. The school is seeking quotes to install new PA speaker wire runs throughout the school building. The contractor must pay prevailing wages and will be required to run new speaker wire (cat 6) to each classroom from the server room, with the ability to daisy chain up to 80 speakers across two separate runs. There are a total of 45 speaker locations, and the contractor will also need to pull 4 CAT wires for camera locations in a separate area of the building. The work can be completed Monday through Friday from 6:30 am to 3:00 pm, and the contractor will be responsible for obtaining any necessary permits. Written quotes are due by July 12, 2023, at 10:00 am and should be submitted to the Procurement Manager, Kerri Doble.
The solicitation specifies that the wire should have a service loop left at the final destination, be separated from all electrical wires to prevent electrical noise, and the work site must be cleaned before the contractor leaves for the day. The school will install the speakers after the wire is run. Interested contractors should direct any questions about the project to the Facilities Director, Wayne Heuer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Prevailing Wage Rates PA Speaker Wiring Project FY24.pdf | ||
| Speaker locations.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
South Shore Charter Public School 100 Longwater Circle Norwell, MA 02061 781-982-4202 www.sscps.org
Quote Solicitation Project 2024-005 : Speaker Wiring Project June 28, 2023
Scope of Work SSCPS is soliciting quotes for new PA speaker wire runs throughout our school building.
● Contractor must pay prevailing wages
● Run new speaker wire (cat 6)to each classroom from our server room.The can be daisy chained up to 80 speakers.Two different runs will be needed.Level IV is a separate area of the building.Connect by a chase
● There are 45 speaker locations in total
● Existing speaker location and map is included
● Wire should have a service loop left at the final destination.20- 30’
● Separate the wire from all electrical wires.This will prevent electrical noise from traveling into the speaker wire
● We will install the speakers after the wire is run
● 4 CAT wires to be pulled for camera locations in LEVEL IV
● Work can be completed M-F 6:30am to 3:00pm
● Permit fees to be included
● All work to be done in Workmanship like manner
● Work site to be cleaned before leaving for the day
Questions about this project should be directed to Wayne Heuer, Facilities Director at wheuer@sscps.org or 781-427-4695
Written Quote Due: July 12, 2023 10:00 am Kerri Doble, Procurement Manager South Shore Charter Public School 100 Longwater Circle, Norwell MA 02061 kdoble@sscps.org http://www.sscps.org mailto:wheuer@sscps.org mailto:kdoble@sscps.org