About this file
This document is an Invitation to Bid for the City of Thomson 2023 CDBG Project No. 23b-x-094-2-6333, Sanitary Sewer and Storm Drainage Improvements. The work consists of installing approximately 2,040 LF of 8-inch gravity sewer line, 1,300 LF of various size storm drain pipe, and 16,000 SY of 1.5" asphalt milling and inlay in the Thomson Housing Authority area. Sealed bids will be received until 10:00 AM on Monday, August 26th, 2024 at the Thomson-McDuffie Government Center. The project must be completed within 180 calendar days. This project is subject to the requirements of Section 3 of the HUD Act of 1968 and the Build America, Buy America Act (BABAA) under the Infrastructure Investment and Jobs Act.
The project is funded through a Community Development Block Grant (CDBG) administered by the Georgia Department of Community Affairs. Bidders must provide a bid bond or certified cashier's check in an amount not less than 10% of the base bid, and the successful bidder will be required to provide 100% performance and payment bonds. Bidders must also be registered with and use the E-Verify program, and possess a valid Georgia Utility Contractor license.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID
PART 1. GENERAL
1.1 SEALED BIDS
Sealed bids for construction of the City of Thomson 2023 CDBG Project No. 23b-x-094-2- 6333, Sanitary Sewer and Storm Drainage Improvements, will be received until 10:00 AM on Monday August 26th, 2024_ at the Thomson-McDuffie Government Center, 210 Railroad Street, 2nd Floor, Thomson, Georgia 30824, at which time and place they will be publicly opened and read aloud. Any proposal received after said time and date will not be considered by the Owner. No bid may be withdrawn after the closing time for the receipt of bids for a period of sixty (60) days.
1.2 SCOPE OF WORK
The work shall consist of, but not be limited to, furnishing all products and performing all labor necessary to perform the following construction work in the Thomson Housing Authority area:
Installation of approximately 2,040 L.F. of 8-inch gravity sewer line, including manholes and services. Installation of approximately 1,300’ of various size storm drain pipe including structures. Approximately 16,000 s.y of 1.5” asphalt milling and inlay. Also included, but not limited to, in this project are all associated items such as: traffic control, clearing, earthwork, bypass pumping, grassing, soil erosion and sediment controls, and any associated appurtenances.
This project is covered under the requirements of Section 3 of the HUD Act of 1968.
Time allotted for completion of work is one hundred eighty (180) calendar days. All Work shall be completed in accordance with the plans and specifications. The Work will be awarded in one (1) Contract.
1.3 PLANS, SPECIFICATIONS AND CONTRACT DOCUMENTS
Plans, Specifications and Contract Documents are on file at Civil Design Solutions, L.L.C. in Warrenton, Georgia. Copies may be obtained from Civil Design Solutions, L.L.C., 371 Main Street, Warrenton, Georgia 30828, Phone: (706) 465-0900, Fax: (706) 465-0909, upon payment of $100 for each full-size set (non-refundable).
1.4 CONTRACTOR AFFIDAVIT REQUIREMENT
All bidders who will be engaged in the physical performance of services on behalf of The City of Thomson must be registered with, authorized by, and use the federal work authorization program commonly known as E-Verify, or any subsequent replacement program, in accordance with the applicable provisions and deadlines established in O.C.G.A. § 13-10-91. Furthermore, the contractor will be required to continue to use the federal work authorization program throughout the contract period and the contractor will contract for the physical performance of services in satisfaction of such contract only with subcontractors who present an affidavit to the contractor with the information required by O.C.G.A. § 13-10-91(b).
1.5 CONTRACTOR LICENSE
The Scope of Work as described herein is defined as “utility contracting” in accordance with O.C.G.A 43-14-2(17) so the Contractor performing the work must provide proof of a valid license by the State of Georgia as a “Utility Contractor” and must also employ a “Utility Manager” certification holder who will have oversight of all the work. Therefore, the Contractor submitting a bid must list the license number of the Contractor(s) performing the utility contracting on the Bid Form and provide proof of a valid license and the license number shall also be written on the face of the bid envelope. See Instruction to Bidders for additional bidding requirements.
1.6 BONDS
Bids shall be accompanied by a bid bond or certified cashier’s check in an amount not less than 10% of the base bid. All bonds shall be by a surety company licensed in Georgia with an “A” minimum rating of performance and a financial strength of at least five (5) times the contract price as listed in the most current publication of “Best’s Key Rating Guide Property Liability”. Performance and Payment Bonds, each in an amount equal to 100% of the contract price shall be required of the successful bidder if contract is awarded. Each Bond shall be accompanied by a “Power of Attorney” authorizing the attorney-in-fact to bind the surety and certified to include the date of the bond.
1.7 PERMITS
The status of Federal, State and /or local permits for this project are as follows:
Permits Status A. Land Disturbing Permit Submitted – Not Approved B. NPDES GAR 100002 (Stormwater) Not Required (< 1 acre) C. Stream Buffer Variance Not Required D. GA DOT Utility Facility Encroachment Not Required E. Building Permit Not Required
1.8 RIGHTS-OF-WAY AND EASEMENTS
All portions of this project are located on publicly owned property. No easements will be required for this project.
1.9 RESERVATION OF RIGHTS
Owner reserves the right to reject any or all Bids, including without limitation, the rights to reject any or all nonconforming, non-responsive, unbalanced or conditional Bids and to reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the
Project to make an award to that Bidder, whether because the Bid is not responsive or the Bidder is unqualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by the Owner.
1.10 BUILD AMERICA, BUY AMERICA (BABA)
This agreement is for services related to a project that is subject to the Build America, Buy America Act (BABAA) requirements under Title IX of the Infrastructure Investment and Jobs Act (“IIJA”), Pub. L. 177-58. Absent an approved waiver, all iron, steel, manufactured products, and construction materials used in this project must be produced in the United States, as further outlined by the Office of Management and Budget’s Memorandum M-22- 11, Initial Implementation Guidance on Application of Buy America Preference in Federal Financial Assistance Programs for Infrastructure, April 18,2022.
1.11 FUNDING SOURCES
Funding shall be provided through a Community Development Block Grant (CDBG) as administered by the Georgia Department of Community Affairs.
CITY OF THOMSON
OWNER
END OF SECTION
| PART 1. GENERAL |
| 1.1 SEALED BIDS |
| Sealed bids for construction of the City of Thomson 2023 CDBG Project No. 23b-x-094-2-6333, Sanitary Sewer and Storm Drainage Improvements, will be received until 10:00 AM on Monday August 26th, 2024_ at the Thomson-McDuffie Government Center, 210 Rai... |
| 1.2 SCOPE OF WORK |
| The work shall consist of, but not be limited to, furnishing all products and performing all labor necessary to perform the following construction work in the Thomson Housing Authority area: |
| Installation of approximately 2,040 L.F. of 8-inch gravity sewer line, including manholes and services. Installation of approximately 1,300’ of various size storm drain pipe including structures. Approximately 16,000 s.y of 1.5” asphalt milling and ... |
| This project is covered under the requirements of Section 3 of the HUD Act of 1968. |
| Time allotted for completion of work is one hundred eighty (180) calendar days. All Work shall be completed in accordance with the plans and specifications. The Work will be awarded in one (1) Contract. |
| 1.3 PLANS, SPECIFICATIONS AND CONTRACT DOCUMENTS |
| Plans, Specifications and Contract Documents are on file at Civil Design Solutions, L.L.C. in Warrenton, Georgia. Copies may be obtained from Civil Design Solutions, L.L.C., 371 Main Street, Warrenton, Georgia 30828, Phone: (706) 465-0900, Fax: (706)... |
| 1.4 CONTRACTOR AFFIDAVIT REQUIREMENT |
| All bidders who will be engaged in the physical performance of services on behalf of The City of Thomson must be registered with, authorized by, and use the federal work authorization program commonly known as E-Verify, or any subsequent replacement p... |
| 1.5 CONTRACTOR LICENSE |
| The Scope of Work as described herein is defined as “utility contracting” in accordance with O.C.G.A 43-14-2(17) so the Contractor performing the work must provide proof of a valid license by the State of Georgia as a “Utility Contractor” and must als... |
| 1.6 BONDS |
| Bids shall be accompanied by a bid bond or certified cashier’s check in an amount not less than 10% of the base bid. All bonds shall be by a surety company licensed in Georgia with an “A” minimum rating of performance and a financial strength of at l... |
| 1.7 PERMITS |
| The status of Federal, State and /or local permits for this project are as follows: |
| 1.8 RIGHTS-OF-WAY AND EASEMENTS |
| All portions of this project are located on publicly owned property. No easements will be required for this project. |
| 1.9 RESERVATION OF RIGHTS |
| Owner reserves the right to reject any or all Bids, including without limitation, the rights to reject any or all nonconforming, non-responsive, unbalanced or conditional Bids and to reject the Bid of any Bidder if Owner believes that it would not be ... |
| 1.10 BUILD AMERICA, BUY AMERICA (BABA) |
| This agreement is for services related to a project that is subject to the Build America, Buy |
| America Act (BABAA) requirements under Title IX of the Infrastructure Investment and |
| Jobs Act (“IIJA”), Pub. L. 177-58. Absent an approved waiver, all iron, steel, manufactured |
| products, and construction materials used in this project must be produced in the United |
| States, as further outlined by the Office of Management and Budget’s Memorandum M-22- |
| 11, Initial Implementation Guidance on Application of Buy America Preference in Federal |
| Financial Assistance Programs for Infrastructure, April 18,2022. |
| 1.11 FUNDING SOURCES |
| Funding shall be provided through a Community Development Block Grant (CDBG) as administered by the Georgia Department of Community Affairs. |