Lakeside Estates Sidewalks Phase 2
Solicitation number
RFB 23-04
Issued by
Williamson County, Hughes Springs City, Texas

About this file

This document is a Contract Time Estimate (CTD) for the Lakeside Estates Sidewalks Phase 2 project for the City of Hutto in Williamson County, Texas. The project involves sidewalk construction and driveway reconstruction across multiple streets including Marjorie Dr, Kaatz Ln, Dana Dr, Cassandra Dr, and Lakemont Dr. The contract time is estimated at 55 days, spanning from September to March, with specific tasks including traffic and erosion control device installation, concrete sidewalk and pedestrian ramp construction, block sod installation, tree and landscape removals, and driveway removal and reinstallation. The project includes detailed scheduling breakdowns for each street segment, with daily work rates and percentage completion tracking.

The contract time estimate provides a comprehensive timeline with granular task-level details, showing daily progress across different project areas. Weather days are included in each month's calculation, and the document notes that the Department will not adjust working days or milestones due to potential scheduling discrepancies. The project appears to be a municipal infrastructure improvement initiative focusing on pedestrian accessibility and street infrastructure enhancement. The schedule suggests a methodical, phased approach to construction with sequential tasks across different street segments, allowing for systematic progress and minimal disruption.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5/5/2023

Rd: Lakeside Estates Sidewalks Phase 2 County:

CSJ: Project:

1 Lakeside Estates Sidewalk Phase 2 0 1 1

2 0 1 1

3 Marjorie Dr 0 1 1

4 0 1 1

5 Install Traffic & Erosion Control Devices 1 DAY 1 1 1 1

6 Install Concrete Sidewalks 578 SY 100 6 5 100 2 7

7 Install Concrete Ped Ramps 10 EA 5 2 6 50 5 6

8 Install Block Sod 730 SY 800 1 6 100 8 8

9 Remove Traffic & Erosion Control Devices 1 DAY 1 1 8 100 9 9

10 0 9 9

11 0 9 9

12 Kaatz Ln 0 9 9

13 0 9 9

14 Install Traffic & Erosion Control Devices 1 DAY 1 1 9 100 10 10

15 Install Concrete Sidewalks 524 SY 100 6 14 100 11 16

16 Install Concrete Ped Ramps 14 EA 5 3 15 50 14 16

17 Install Block Sod 709 SY 800 1 15 100 17 17

18 Remove Traffic & Erosion Control Devices 1 DAY 1 1 17 100 18 18

19 0 18 18

20 0 18 18

21 Dana Dr 0 18 18

22 0 18 18

23 Install Traffic & Erosion Control Devices 1 DAY 1 1 18 100 19 19

24 Tree & Landscape Removals 2 EA 5 1 23 100 20 20

25 Install Concrete Sidewalks 254 SY 100 3 24 100 21 23

26 Concrete Driveways (Remove and Install) 4 EA 1 4 25 50 23 26

27 Install Concrete Ped Ramps 2 EA 5 1 26 100 27 27

28 Install Block Sod 318 SY 800 1 27 100 28 28

29 Remove Traffic & Erosion Control Devices 1 DAY 1 1 28 100 29 29

30 0 29 29

31 0 29 29

32 Cassandra Dr 0 29 29

33 0 29 29

34 Install Traffic & Erosion Control Devices 1 DAY 1 1 29 100 30 30

35 Tree & Landscape Removals 5 EA 5 1 34 100 31 31

36 Install Concrete Sidewalks 479 SY 100 5 35 100 32 36

37 Concrete Driveways (Remove and Install) 9 EA 1 9 36 50 35 43

38 Install Concrete Ped Ramps 2 EA 5 1 37 100 44 44

39 Install Block Sod 535 SY 800 1 38 100 45 45

40 Remove Traffic & Erosion Control Devices 1 DAY 1 1 39 100 46 46

41 0 46 46

42 0 46 46

43 Lakemont Dr 0 46 46

44 0 46 46

45 Install Traffic & Erosion Control Devices 1 DAY 1 1 40 100 47 47

46 Tree & Landscape Removals 2 EA 5 1 45 100 48 48

47 Install Concrete Sidewalks 230 SY 100 3 46 100 49 51

48 Concrete Driveways (Remove and Install) 1 EA 1 1 47 50 51 51

49 Install Concrete Ped Ramps 6 EA 5 2 48 100 52 53

50 Install Block Sod 313 SY 800 1 49 100 54 54

51 Remove Traffic & Erosion Control Devices 1 DAY 1 1 50 100 55 55

52 0 55 55

53 0 55 55

54 0 55 55

55 0 55 55

Provided for informational purposes only. The Department will not adjust the number of working days and milestones, if any, due to differences in opinion regarding any assumptions made in the preparation of the schedule or for errors, omissions, or discrepancies found in the Department’s conceptual time determination schedule.

Weather days are included in each month, do not incorporate weather in the daily rates of each task.

Comp lete

Contract Time Estimate

Comp lete

Start

Day

Finish

Day

Pred

Task

Standard Workweek

Daily Rate

City of Hutto, Williamson

Contract Time

Description Quantity TASK #

Pred

Task

Comp lete

Barricades 4

Unit

Pred

TaskDuration

= # DAYS / CELL

Sep (16)

Oct (16)

Nov (16)

Dec (16)

Jan (16)

Feb (16)

Mar (16)