NAVAL AIR STATION FORT WORTH,

JOINT RESERVE BASE

July 20, 2021

STATEMENT OF WORK

Paint Department of Defense Commercial Driving Training Course

Project # DDPM 210031

OVERVIEW:

This project removes paint from existing concrete pavements; plots (survey) Department of Defense Commercial Driver’s License (CDL) course; paints new course layout.

SCOPE OF WORK:

GENERAL REQUIREMENTS: The project is located at NAS JRB Fort Worth. See location plan below. The entire CDL course area shall be stripped of existing pavement markings prior to painting the new course. The new course layout provided in figures A thru F shall also be provided in Auto Cad 2020 prior to construction. Contractor shall submit a painting plan for the job, indicating proposed surface preparation, and paint submittals and finishes to be used.

DDPM 21-0031, PAINT DEPARTMENT OF DEFENSE CDL COURSE

Page | 2

Location Plan

Page | 3

The Contractor shall provide all equipment, material, transportation and labor to perform the following:

A. The Contractor shall remove approximately 1700 linear feet of 4 inch existing CDL course (Same layout as new course) traffic lines painted with Sherwin-Williams HOTLINE Fast Dry Waterborne Traffic Marking paint. Dispose of all debris in certified landfill and provide disposal receipts.

B. The Contractor shall survey, install, and paint approximately 70 permanent marking pin units. The units will have less than .25 inch tolerance from the drawings. The marking pin unit shall consist of a PK (Parker- Kalon) type nail installed through a 1.5 inch fender washer that is painted orange, and then surrounded by a black 3 inch painted circle on the pavement. See figures A thru F. The CDL course layout will be provided in ACAD 2020 format for use during construction.

C. The Contractor shall survey and paint approximately 1700 linear feet of 4 inch dashed and solid yellow lines as shown in figure A thru F. All lines shall be within a .25 inch tolerance form the supplied drawings. All paint shall have equal or greater specs then Sherwin-Williams HOTLINE Fast Dry Waterborne Traffic Marking paint.

ACAD 2020 drawing will be supplied by government for this project.

D. The Contractor shall remove approximately 250 square feet of spilled Sherwin- Williams HOTLINE Fast Dry Waterborne Traffic Marking paint from pavement at the corner of Boyington Dr. and A St. See map below for location. Dispose of all debris in certified landfill and provide disposal receipts.

Page | 4

Spilled Paint Location

Spilled Paint Removal Area

Page | 5

Figure A: Overall Course Layout

Page | 6

Figure B:

Not to scale

Page | 7

Figure C:

Not to scale

Page | 8

Figure D:

Not to Scale

Page | 9

Figure E:

Not to Scale

Page | 10

FIGURE F

Page | 11

PART I - GENERAL

REFERENCE PUBLICATIONS: US GOVERNMENT/US AIR FORCE

PUBLICATIONS: US Government/US Air Force publications can be found via internet at http://www.e-publishing.af.mil/. Some suggested publications would include:

1.1. 29 CFR (PART 1910), Occupational Safety and Health Standards

1.2. 29 CFR (PART 1926), Safety and Health Regulations for Construction

1.3. AFI 91-203, Air Force Consolidated Occupational Safety Instructions, Change 1, 26 Oct 2016

PART II - PRODUCTS

2.1 All material selected to accomplish this Statement of Work shall be of good quality and intended for Commercial use. Items shall be of the proper type, size, and material for the use intended.

2.1 Contractor Furnished Materials: The Contractor furnished materials shall include all associated equipment and appurtenances required for performing the work in accordance with the equipment manufacturer’s literature.

PART III – EXECUTION

3.1. WORK REQUIREMENTS:

3.1.1. Scheduling and Coordination: Before commencing work, the Contractor shall ensure that he/she is complying with the approved schedule, that work commences in accordance with the issued Notice to Proceed, and that work is coordinated with the assigned Contracting Officer Representative (COR). The Contractor shall further determine that all required notices have been given and permits obtained.

3.1.2. Scheduling and Sequence of Work: The work shall be performed in such a manner as to minimize interference with the normal daily work of the Government activity. Certain areas of the facility shall be vacated as necessary, in order for the Contractor to perform the required work. Prior to beginning work, the Contractor shall meet with the COR so that the planned sequence of work and/or schedule may be reviewed and approved.

3.1.3. Interruption of Utilities Services: Interruptions shall be kept to a minimum and may only occur at such times and duration as approved by the Contracting Officer (CO). All utility interruptions shall be reviewed and accepted by the COR before approval is provided. Currently NAS JRB Public Works requires fourteen (14) days prior notification for a Utilities (Water, Gas, and Minor Power) Shutdown. Major Power Outages require twenty-one (21) days prior notification.

3.1.4. Material, equipment, tools, and workmen shall be scheduled on site in a timely http://www.e-publishing.af.mil/

Page | 12 manner to avoid delay in work. Items of material shall be inspected to make certain they are in compliance with the specifications and are free from defects and damage.

3.1.5. Measurements: Before paint operations begin, obtain necessary field measurements and verify all field measurements meet design measurements.

3.1.6. Existing Work: The Contractor shall take measures to protect any existing work or property belonging to the government which is to remain in place in the work area.

The Contractor shall be responsible for repairing or replacing any government property that is damaged during the performance of the contracted work. Failure to do so shall result in the government withholding contract funds in order to effect required replacement or repairs.

3.1.7. Facilities: The Contractor shall protect electrical and mechanical services and utilities. Where removal and application of paint is specified or indicated, provide approved barricades, temporary covering of exposed areas, and temporary services or connections for electrical and mechanical utilities.

3.1.8. Dust and Debris Control: The Contractor shall prevent the spread of dust and debris to the surrounding buildings and avoid the creation of a nuisance or hazard in the surrounding area. Non-hazardous and hazardous debris resulting from the work being performed shall be cleaned up and properly disposed of daily.

3.2. PERFORMANCE:

3.2.1. Workmanship: Skilled personnel shall execute in a careful, neat, and proficient manner and in compliance with accepted trade practices and prevailing industry standards. All work, including any required design, shall be executed in accordance with OSHA standards, and specifically 29 CFR 1910 and 29 CFR 1926. All work on this contract shall comply with all Local, State, and Federal Environmental Laws.

3.2.2. As used herein, “replace” means provide new materials to replace existing or missing materials.

3.2.3. Minor Materials and Work: Minor materials and work not specifically mentioned herein but necessary for the proper completion of the specified work shall be furnished without additional cost to the Government.

3.2.4. Unforeseen Major Repairs: Should deteriorated materials of a major nature be uncovered in the course of the work, it shall be brought to the attention of the CO and COR. Repairs shall be made as directed by the CO, in writing, and an adjustment will be made in contract price in accordance with the terms of the modifications.

3.2.5. Existing Work: Where existing work is changed or removed, or where new work adjoins, connects to, or abuts existing work, the existing work shall be altered as necessary and connected in a substantial and workmanlike manner. All new work shall match, as nearly as practicable, existing, adjoining, and/or adjacent similar work.

Operations affecting existing work shall be conducted with care not to damage work in place, and all existing work damaged by such operations shall be rectified or

Page | 13 replaced without additional expense to the Government.

3.3. REQUIRED FINAL SUBMITTALS: The contractor shall return to the government all CDL course layout CAD files (paper and electronic) provided by the government and all survey data created during the course layout and construction.

PART IV: OTHER REQUIREMENTS

4.1. SCHEDULE:

The Contractor shall provide a Construction Schedule for CO approval not to exceed 30 days. Work will be accomplished during normal Base operating hours, approximately 0730-1630 hours, Monday-Friday. No work will be scheduled on weekends without prior written approval by the CO, and concurrence of the COR.

4.2. IDENTIFICATION OF EMPLOYEES:

The Contractor shall be responsible for furnishing to each employee, and for requiring each employee engaged on the Work to display, identification as approved and directed by the CO. Prescribed identification shall immediately be delivered to the CO upon release of any employee. All Contractor and Sub-Contractor personnel shall wear identifying markings on hard hats clearly identifying the Company for whom the employee works.

4.3. JOB SITE TOOLS AND EQUIPMENT:

All hand tools and equipment shall be maintained in good working order and properly stored when not in use. Construction attire shall be in accordance with applicable OSHA regulations.

4.4. SANITATION:

Government toilet facilities shall not be available to Contractor personnel. The contractor shall provide portable toilets at the job site for Contractor personnel.

4.5. CLEANUP:

At the end of each Working day, the Contractor shall clean up the Work Site by the removal of all construction debris, waste materials, packaging material, and the like.

All construction waste shall be stored in appropriate size dumpsters, and covered in order to keep contents inside. Cleanup of the Work Site shall include the construction site and any other adjacent areas that have been affected. Any dirt or mud which is tracked on to any Base street, parking area, sidewalk, patio, or driveway shall be cleaned away daily.

Page | 14

4.6. OCCUPATIONAL SAFETY:

The Contractor shall be subject to No Notice Inspections under Occupational Safety and Health Act (OSHA) Program by Inspectors of the Department of Labor.

4.7. GENERATED REFUSE:

The Contractor shall take positive action to prevent Work generated refuse from entering the sewer system. The Contractor shall use contractor provided approved waste containers. All refuse and waste material shall be hauled in trucks with tight fitting beds and covers to prevent spillage on roadways. The Construction Site shall be kept neat, orderly, and safe for Workmen at all times.

4.8. RECYCLABLE MATERIAL:

The Contractor shall recycle any material removed from the Aircraft Parking Ramps at either the NAS JRB Fort Worth, Texas recycling center or an off-base recycling center.

The amount of recyclable material and solid waste from demolition operations shall be documented on a Waste Tracker Form and submitted to the CO at the conclusion of the project.

4.9. SCHEDULE OF SUBMITTALS:

Contractor Furnished Materials. The Contractor shall submit to the CO for approval a detailed list of the Manufacturer’s data on the Contractor furnished materials. The CO may request Drawings and Descriptions indicating the quality and fitness for the intended application.

4.10. SITE VISITATION:

Prior to submitting proposals, it is highly recommended that prospective contractors visit the site in order to satisfy themselves as to the nature of the project site, details, character, and amount of work to be accomplished. The Contractor is responsible for the verification of all statement of work details, critical measurements, drawing specification and dimensions, etc., prior to preparation of their proposal, ordering of materials, and execution of work. Failure to attend a site visit shall not relieve the contractor of responsibility for being knowledgeable of those conditions that can only be readily observed by attending a site visit.

Site visitation may be arranged by the CO.

4.11. TIME OF COMPLETION:

The Contractor shall submit a planned performance period not to exceed 30 days for review and acceptance by the Government.

4.9. SCHEDULE OF SUBMITTALS:
Contractor Furnished Materials. The Contractor shall submit to the CO for approval a detailed list of the Manufacturer’s data on the Contractor furnished materials. The CO may request Drawings and Descriptions indicating the quality and fitness for th...