Justification and Approval for Sole Source
1. Identification of the agency and contracting activity.
2. Nature and/or description of the action being approved.
3. Description of the supplies or services required to meet the agency’s needs (including the estimated value).
a. Project title.
b. Project description.
• Requirement type. Check the appropriate box:
Research & development (R&D) R & D support services Support services (non-R&D) Supplies/equipment Information technology (IT) Construction Architect-engineer (A & E) services Design-build Other (specify): ____________________
• Type of action. Check the appropriate box:
New requirement Follow-on Other (specify): ______________________
• Proposed contract/order type. Check all that apply:
Firm-fixed-price Other fixed-price (specify, e.g., fixed-price award-fee, fixed-price incentive-fee): __________ Cost-plus-fixed-fee Other cost reimbursement (specify, e.g., cost-plus-award-fee, cost-plus-incentive-fee): ___________ Time and materials Indefinite delivery (specify whether indefinite quantity, definite quantity, or requirements): ___________ Other (specify): ___________ Completion Form Term form
• Contract / Purchase Order number.
c. Total estimated dollar value and performance/delivery period.
d. Demonstration that the proposed contractor(s) unique qualifications or the nature of the acquisition requires use of the authority cited.
4. Identification of the statutory authority permitting other than full and open competition.
This acquisition is conducted under the authority of 41 United States Code (U.S.C.) 3304(a)(__) as set forth in Federal Acquisition Regulation
(FAR) 6.302- __.
This acquisition is conducted under the authority of section 4202 of the
Clinger-Cohen Act of 1996.
This acquisition is conducted under the authority of the Services
Acquisition Reform Act of 2003 (41 U.S.C. 428a).
This acquisition is conducted under the authority of
__________________________________ as set forth in
5. Description of the efforts made to ensure that offers are solicited from as many potential sources as practicable. Indicate whether a FedBizOpps notice was or will be publicized as required by FAR Subpart 5.2 and, if not, which exception under FAR 5.202 applies.
6. Determination by the Contracting Officer that the anticipated cost/price to the Government will be fair and reasonable.
7. Description of the market research conducted (see FAR Part 10) and the results, or a statement of the reasons market research was not conducted.
9. Any other facts supporting the use of other than full and open competition.
10. Listing of sources, if any, that expressed, in writing, an interest in the acquisition.
11. Statement of the actions, if any, the agency may take to remove or overcome any barriers to competition before any subsequent acquisition for the required supplies or services.
12. OPIC office certification.
This is to certify that the portions of this justification that have been developed by the undersigned office personnel, including supporting information and/or data verifying the Government’s minimum needs, schedule requirements and other rationale for other than full and open competition, are accurate and complete.
Official Name & Title Signature Date
Technical Cognizance
Supervisor / Manager
13. Contracting Officer Certification.
This is to certify that the justification for the proposed acquisition has been reviewed and that to the best of my knowledge and belief the information and/or data provided to support the rationale and recommendation for approval is accurate and complete.
Official Name & Title Signature Date
Contracting Officer
14. Managing Director, Office of Acquisition signature(s).
Official Name & Title Signature Date
Managing Director, Office of Acquisition
| Justification and Approval for Sole Source (J&A) (Template) |
| Justification and Approval for Sole Source |
| ADPBC24.tmp |
| Justification and Approval for Sole Source (J&A) (Template) |
| Justification and Approval for Sole Source |
| Please Provide the Federal agency, Sponsoring Organization/Unit: U.S. International Development Finance Corporation (DFC) proposes to enter into s six month extension of services for the maintenance of settlement agreements and judgments already obtained by OPIC. |
| Provide a brief (i: |
| e: |
| , half-page or less) narrative description of the project: Extend the MTIPS Port and Speed connection of 300 Meg services from January 1, 2021 through June 30, 2021. The need for this extension is to allow DFC to migrate to the GSA Enterprise Infrastructure Solutions (EIS) vehicle for services. |
| Enter Project Title: MTIPS Extension of Services |
| Enter Total Dollar Value & Dates of Service: Estimated $108,493.20 at six months. The length of the period of performance is six months. |
| Please Provide the Purpose/Objective and Background: DFC requires the continued services for The Managed Trusted Internet Protocol Service (MTIPS) was developed by the US General Services Administration (GSA) for all US Federal Agencies to physically and logically connect to the public Internet and |
other external connections in compliance with the Office ofManagement and Budget’s (OMB) Trusted Internet Connection (TIC) initiative memorandum M-08-05.
MTIPS will reduce the number of connections, as originally dictated in the TIC Mandate, but will not reduce the connection points to the degree originally quoted. Instead, focus has shifted to the securing of existing connections using the MTIPS architecture.
DFC currently has a contract through the GSA Networx Universal vehicle with AT&T (7131117F0013), is ending December 31, 2020. An additional six months is needed until the EIS contract is awarded and implementation is completed. GSA contract number for AT&T Networx Universal: GS00T07NSD0007, has been extended until May 31, 2023.
| Provide Additional Information: |
| Indefinite Quantity, Defined Quantity or Requirements: |
| Fee: |
| Federal Acquisition Regulation: |
| What Was Done to Find Other Sources: A sole source notice will be publicized on BetaSam. The new solicitation for EIS is being publicized on GSA-eBuy. |
| Describe the market research that was conducted or Contact with acquisition or program offices or Industry or Vendors: DFC has conducted market research for the new EIS solicitation that is being pursued. However, in the interim the Networx services will need to be continued against GSA contract GS00T07NSD0007 until the new contract is awarded and implementation is completed. |
| Additional Information to support the justification: GSA has issued their own extensions for the GSA Networx contracts and included the determination and findings for each contract extension. GSA contract GS00T07NSD0007 has been extended until GSA on November 25, 2019, which proposes to add pricing in order to extend the Networx contract by an additional period of up to thirty-eight months: (one (1), two (2) month base extension period with three (3) one year extension option periods) from the current contract end date of March 28, 2020 to May 31, 2023 as follows: |
Base Period: March 29, 2020 – May 31, 2020 Option Period 1: June 1, 2020 – May 31, 2021 Option Period 2: June 1, 2021 – May 31, 2022 Option Period 3: June 1, 2022 – May 31, 2023
| Any interested vendors or firms?: No other sources have expressed an interest, in writing, in the proposed acquisition | |
| Explain How to Aviod Sole Source in the Future: DFC is a currently pursuing a replacement contract for EIS services through GSA. The solicitation is set to close on December 21, 2020. | |
| Name & Title: Marie Mulloy, IT Specialist | |
| 2020-12-22T10:19:48-0500 | |
| MARK REIN |
| Date: 12/22/2020 | |
| 2020-12-22T10:27:12-0500 | |
| ANTIONETTE COLLINS |
| 2020-12-22T11:23:21-0500 | |
| KERON WHITE |
| Please Specify: |
| Comp: Off |
| Unknown: Off |
| IDIQ: Off |
| T&A: Off |
| OCR: Off |
| CPFF: Off |
| OFFP: Off |
| FFP: Yes |
| Term: Off |
| New: Off |
| MOD: Yes |
| Oth: Off |
| R&D: Off |
| R&D Support: Off |
| Services: Off |
| Supplies: Off |
| IT: Yes |
| Construction: Off |
| A&E: Off |
| Other: Off |
| DB: Off |
| CCA: Off |
| 41 USC: Yes |
| USC: Off |
| USC Code: 1 |
| FAR 6: |
| 302: 1 |
| SARA: Off |
| USC Code Reference: |
| Text5: The Managing Director, Office of Acquisition, if applicable, shall indicate review of, and concurrence with, any J & A over $25,000 by providing the information required below and signing in the applicable block. |
| Please Provide the Purpose/Objective and Background 2: DFC currently has a contract through the GSA Networx Universal vehicle with AT&T (7131117F0013), is ending December 31, 2020. An additional six months is needed until the EIS contract is awarded and implementation is completed. |
To incorporate proposal AU6437.02e, received by GSA on November 25, 2019, which proposes to add pricing in order to extend the Networx contract by an additional period of up to thirty-eight months: (one (1), two (2) month base extension period with three (3) one year extension option periods) from the current contract end date of March 28, 2020 to May 31, 2023 as follows:
Base Period: March 29, 2020 – May 31, 2020 Option Period 1: June 1, 2020 – May 31, 2021 Option Period 2: June 1, 2021 – May 31, 2022 Option Period 3: June 1, 2022 – May 31, 2023
The sole source is in the best interest because the extension will allow DFC to have additional time needed to modernize their IT infrastructures, enabling improved cybersecurity and increased savings. Failure to issue the extension will result in either a break in service with disruption to Government operations, or revision to higher tarriff rates, significantly increasing the Government's costs.
DFC at this time cannot compete the requirement to leave Networx/EIS in order to get a third party solution. in the interim. GSA has extended the Networx/EIS as a part of the GSA implementation process. DFC cannot receive services from another provider without requesting a waiver through our agency head by pursuing a openly competitive requirement. DFC does not have the time to pursue a waiver process, nor is it guaranteed that it would be granted and this could result in a disruption of services.
The estimated total value of the services is $108,493.20
| Name & Title2: Mark Rein, CIO | |
| Name & Title3: Antionette Collins | |
| Name & Title4: Keron White | |
| Please Provide PO Number: REQ-821-21-0007, 71311117F0013 | |
| Provide a statement Price: The prices offered are based on GSA contract and have been determined fair and reasonable. The pricing offered is the current rate for the expiring contract and will be the same during the extension period. | |
| Date54: 12/22/2020 | |
| 2020-12-22T10:04:47-0500 | |