2020_POW_Maintenance_Worklist.docx

DOCX document 16 KB Posted

Attached to
Prince of Wales Island Road Maintenance
Solicitation number
12010920Q0033
Issued by

View the file

Other files

File Type Posted
Relevant Experience Evaluation Form.pdf PDF
12010920Q0033 Solicitation.pdf PDF
156_Public Traffic.docx DOCX document
POW RD MTCE vicinity map.pdf PDF
Construction Wage Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2020 POW Road Maintenance and Culvert Replacement Worklist

Road Number
Milepost
Description of Work

3018 000

8.65
Slide removal - sidecast approximately 200CY of debris from road

3023 500

0.93
Remove slide debris (approximately 100 CY)from road surface, haul to helicopter landing 150ft before slide, reconstruct catch basin and lead-in ditch to 36" CPP, excavate channel and re-establish ditchline
1.96
Remove slide debris (approximately 300 CY) from road surface, end haul debris to turnout at MP 0.94, re-establish upslope ditch(approx. 300FT), repair road surface

3000 000

18.36
Install new 24"x40' CPP
20.92
Install new 18"x30' CPP/ 200ft of ditching
21.17
Remove 18" CMP and replace with 24"x40' CPP/ 500ft of ditching as staked
23.23
Remove earthen berms from underneath approach rails so water may drain off of the road prism. Install 4 object markers with posts
23.3
Install new 36"x40' CPP
23.52
200ft of ditching as staked- remove woody debris from ditch as well as reconstruct short section of ditch
23.56
Remove 18" CMP and replace with 24"x40' CPP
23.61
Remove 18" CMP and replace with 24"x35' CPP
23.95
Remove earthen berms from underneath approach rails so water may drain off of the road prism. Install 4 object markers with posts
24.29
Remove 18" CMP and replace with 24"x40' CPP
24.34
Remove 18" CMP and replace with 24"x30' CPP
24.46
Remove 24"CMP and replace with 24"x30' CPP
24.52
Remove 18" CMP and replace with 24"x30' CPP
24.67
Remove 24"CMP and replace with 24"x30' CPP
24.77
Remove 24" CMP and replace with 24"x40' CPP
24.821
Remove earthen berms from underneath approach rails so water may drain off of the road prism.
33.49
Remove earthen berms from underneath approach rails so water may drain off of the road prism. Install 4 object markers with posts
37.75
Remove earthen berms from underneath approach rails so water may drain off of the road prism. Install 4 object markers with posts
37.88
Remove earthen berms from underneath approach rails so water may drain off of the road prism.
38.37
Remove 18" CMP and replace with 24"x30' CPP
38.37-38.41
Ditch
38.37-38.41
Haul and place 20CY crushed rock to repair road surface
38.41
Remove 18" CMP and replace with 24"x30' CPP
38.41-38.455
Ditching
38.455
Install new 24"x30' CPP with ditchblock- ditch 50ft to 38.47
40.35
Remove 18" CMP and replace with 18"x30' CPP - 150ft of ditching
40.4
Remove 18" CMP and replace with 18"x35' CPP - 150ft ditching
40.47
Remove 24" CMP replace with 24"x30' CPP
40.5
Remove 18" CMP replace with24"x35' CPP
40.56
Remove 18" CMP replace with 18"x35' CPP
40.64
Remove 18" CMP replace with 24"x30' CPP
40.74
Remove 18" CMP replace with 24"x35' CPP
40.82
Remove 18" CMP replace with 24"x30' CPP
41.11
Remove 18" CMP replace with 24"x35' CPP with ditchblock
41.15
Remove 18" CMP replace with 24"x35' CPP
41.2
Remove 18" CMP replace with 24" x30' CPP
41.3
Remove 18" CMP replace with 18"x30' CPP
41.51
Remove 18" CMP replace with 18"x30' CPP
41.62
Remove 18" CMP replace with 18"x30' CPP
41.84
Haul and place 80CY of riprap (class 3-5)to repair slump below road