This is a Pay Item Worksheet for FDOT Project #2019803, a bridge replacement and intersection improvements project involving the State of Florida Department of Transportation (FDOT) and Palm Beach County. The project encompasses CR880 and Sam Senter Road improvements over the South Florida Water Management District (SFWMD) Ocean Canal. The scope of work includes roadway construction items such as clearing and grubbing (9.77 acres), excavation (15,111 cubic yards regular excavation, 6,432 cubic yards canal excavation), embankment work (39,223 cubic yards), asphalt paving operations including milling and Superpave applications totaling approximately 3,893 square yards of milled surface and 1,668.2 tons of asphalt concrete, and installation of various drainage control structures. Structural work includes removal of existing structures (3,989 square feet), installation of Class II and IV structural concrete, reinforcing steel placement, prestressed pile installation (3,959 linear feet), bridge deck finishing operations including grooving and planing, and concrete traffic railing. Contingency items include fencing, flowable fill, bedding stone, and utility protection work totaling 6 line items.
The worksheet presents a comprehensive bid proposal format with itemized pay items organized into three categories: Roadway Items (38 line items), Structural Items (18 line items), and Contingency Items (6 line items). All unit prices in the submitted worksheet are shown as zero dollars, indicating this is a template format awaiting contractor pricing input. The document includes FDOT reference item numbers for each pay item and specifies that unit prices shall include furnishing and installation costs unless otherwise noted. All quantities listed shall govern over the construction plans, and pay item footnotes referenced in the construction plans are incorporated into unit prices. The note indicates that Class 5 Concrete finish costs are incidental to the base concrete cost, and Subsoil Excavation costs are incidental to the Rigid Inclusions pay item.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2019803
| BID PROPOSAL | ||||||
| CR880 AND SAM SENTER ROAD OVER THE SOUTH FLORIDA WATER MANAGEMENT DISTRICT | ||||||
| (SFWMD) OCEAN CANAL INTERSECTION IMPROVEMENTS AND BRIDGE REPLACEMENT | ||||||
| CONTRACT | ||||||
| PBC PROJECT # 2019803 | ||||||
| # | FDOT ITEM NUMBER | ITEM DESCRIPTION | QTY. | UNITS | UNIT PRICE | AMOUNT |
| ROADWAY ITEMS | ||||||
| 1 | 101-1 | Mobilization | 1 | LS | $ - 0 | |
| 2 | 102-1 | Maintenance of Traffic | 1 | LS | $ - 0 | |
| 3 | 104-0 | NPDES Compliance (FDOT Index 101-105) | 1 | LS | $ - 0 | |
| 4 | 110-1-1 | Clearing and Grubbing | 9.77 | AC | $ - 0 | |
| 5 | 120-1 | Regular Excavation | 15,111 | CY | $ - 0 | |
| 6 | 120-5 | Canal Excavation | 6,432 | CY | $ - 0 | |
| 7 | 120-6 | Embankment (Compacted In Place) | 39,223 | CY | $ - 0 | |
| 8 | N/A | Canal Embankment (Compacted In Place) | 107 | CY | $ - 0 | |
| 9 | N/A | Compacted Subgrade (98% T-180) (12") | 3,995.9 | SY | $ - 0 | |
| 10 | 160-4 | Type B Stabilization (LBR 40) (12") | 18,398.9 | SY | $ - 0 | |
| 11 | 285-707 | Optional Base Group 7 | 16,887.7 | SY | $ - 0 | |
| 12 | 285-713 | Optional Base Group 13 | 3,333.1 | SY | $ - 0 | |
| 13 | 327-70-1 | Mill Existing Asphalt Pavement (1") | 3,893.3 | SY | $ - 0 | |
| 14 | 334-1-13 | Superpave Asphalt Concrete (Traffic C) | 1,668.2 | TN | $ - 0 | |
| 15 | 339-1 | Miscellaneous Asphalt Pavement (2" Thick) | 287.3 | TN | $ - 0 | |
| 16 | 334-1-13 | Structural Overbuild Type SP (Traffic C) | 326 | TN | $ - 0 | |
| 17 | 337-7-82 | Asph. Concrete Friction Course (1.0") (Type FC-9.5) | 1,326.3 | TN | $ - 0 | |
| 18 | 337-7-82 | Asph. Concrete Friction Course (1.75") (Type FC-9.5) | 20.4 | TN | $ - 0 | |
| 19 | 400-0-11 | Concrete Class NS (Gravity Wall) | 44.7 | CY | $ - 0 | |
| 20 | 430-175-118 | Pipe Culvert (18") | 36 | LF | $ - 0 | |
| 21 | 425-1-529 | Control Structures (Ditch Bottom Inlet Type C) (Special) | 1 | EA | $ - 0 | |
| 22 | 425-1-549 | Control Structures (Ditch Bottom Inlet Type D) (Special) | 1 | EA | $ - 0 | |
| 23 | 425-1-589 | Control Structures (Ditch Bottom Inlet Type H) (Special) | 1 | EA | $ - 0 | |
| 24 | 430-982-125 | Mitered End Section 18" (2:1) | 3 | EA | $ - 0 | |
| 25 | N/A | Rigid Inclusions | 148,642 | SF | $ - 0 | |
| 26 | 145-71 | Geotextile Geogrid Reinforcement Type R-2 | 33,031.6 | SY | $ - 0 | |
| 27 | 521-72-40 | Shoulder Concrete Barrier | 77 | LF | $ - 0 | |
| 28 | 521-8-7 | Concrete Barrier with Junction Slab | 103 | LF | $ - 0 | |
| 29 | 536-1-1 | Roadway Guardrail | 7,462.5 | LF | $ - 0 | |
| 30 | 536-73 | Guardrail Removal | 4,550 | LF | $ - 0 | |
| 31 | 536-7-1 | Special Guardrail Post | 676 | EA | $ - 0 | |
| 32 | 536-8-112 | Guardrail Attachment to Barrier - Approach Trans to Rigid Barrier | 3 | EA | $ - 0 | |
| 33 | 536-85-24 | Guardrail End Treatment - Parallel Approach Terminal | 3 | EA | $ - 0 | |
| 34 | 536-85-20 | Guardrail End Treatment - Trailing Anchorage | 5 | EA | $ - 0 | |
| 35 | N/A | Sfwmd 20' Width Vehicle Barrier Gate | 1 | EA | $ - 0 | |
| 36 | 530-3-3 | Rip-Rap (Rubble) | 3,030.1 | TN | $ - 0 | |
| 37 | 570-1-2 | Sodding | 24,926.4 | SY | $ - 0 | |
| 38 | 571-1-11 | Plastic Erosion Mat, Turf Reinforced, Type 1 | 3,328.7 | SY | $ - 0 | |
| SUBTOTAL (ROADWAY) | $ - 0 | |||||
| STRUCTURAL ITEMS | ||||||
| 39 | 110-3 | Removal of Existing Structure | 3,989 | SF | $ - 0 | |
| 40 | 400-2-4 | Class II Structural Concrete (Flat Slab) | 297 | CY | $ - 0 | |
| 41 | 400-4-5 | Class IV Structural Concrete (Substructure) | 236 | CY | $ - 0 | |
| 42 | 400-2-10 | Class II Structural Concrete (Approach Slab) | 123 | CY | $ - 0 | |
| 43 | 400-2-47 | Concrete Class II Topping (Overlay) | 83 | CY | $ - 0 | |
| 44 | 400-7-1 | Bridge Deck Grooving | 827 | SY | $ - 0 | |
| 45 | 400-9-1 | Bridge Deck Planing | 827 | SY | $ - 0 | |
| 46 | 415-1-4 | Reinforcing Steel (Superstructure) | 85,303 | LB | $ - 0 | |
| 47 | 415-1-5 | Reinforcing Steel (Substructure) | 20,444 | LB | $ - 0 | |
| 48 | 415-1-9 | Reinforcing Steel (Approach Slab) | 13,153 | LB | $ - 0 | |
| 49 | 400-148 | Plain Neoprene Bearing Pads | 35 | CF | $ - 0 | |
| 50 | 450-8-11 | Florida Slab Beam New/Widening (50" x 12") | 424 | LF | $ - 0 | |
| 51 | 450-8-13 | Florida Slab Beam New/Widening (55" x 12") | 229 | LF | $ - 0 | |
| 52 | 455-34-3 | Structural Concrete (18" Prestressed Piles) | 3,959 | LF | $ - 0 | |
| 53 | 455-143-3 | Test Piles (18" Prestressed Piles) | 551 | LF | $ - 0 | |
| 54 | 458-1-11 | Bridge Deck Expansion Joints | 331 | LF | $ - 0 | |
| 55 | 521-5-13 | Concrete Traffic Railing Bridge (36" Single-Sloped) | 347 | LF | $ - 0 | |
| 56 | 400-72 | 8" Precast Concrete Panels | 3,326 | SF | $ - 0 | |
| SUBTOTAL (STRUCTURAL) | $ - 0 | |||||
| CONTINGENCY ITEMS | ||||||
| 57 | 530-74 | Bedding Stone (Sect. 530) | 804.3 | TN | $ - 0 | |
| 58 | 121-70 | Flowable Fill | 30 | CY | $ - 0 | |
| 59 | 550-10-212 | Type B Fence (4' Hight) (w/Top Rail) (Green Vinyl Clad) | 1,465 | LF | $ - 0 | |
| 60 | 550-10-218 | Remove And Reset Silt Fence, Type B | 1,000 | LF | $ - 0 | |
| 61 | 550-10-210 | Temporary Fencing | 2,500 | LF | $ - 0 | |
| 62 | 1050-115 | Support & Protect Existing Utility & Appurtences (>12") | 500 | LF | $ - 0 | |
| SUBTOTAL (CONTINGENCY) | $ - 0 | |||||
| TOTAL BID | $ - 0 |
| THE COUNTY DOES NOT GUARANTEE THE ACCURACY OF THE FORMULAS AND EXTENSIONS USED IN THIS SPREADSHEET. | ||
| THE ITEMS AND QUANTITIES ABOVE, SHALL GOVERN OVER THE PLANS. | ||
| PAY ITEM FOOTNOTES IN CONSTRUCTION PLANS SHALL ALSO BE INCLUDED IN ITEM UNIT PRICE. | ||
| Note # | FDOT Item # | PAY ITEM FOOTNOTES |
| 1 | All | All items shall include cost to furnish and install unless otherwise noted. |
| 2 | All | FDOT Item numbers are for reference only. |
| 3 | All | The cost of Class 5 Concrete finish is incidental to the cost of the concrete in which the finish is being applied to. See sheet B-4 for Conctrete Surface Finish notes. |
| 4 | 120-4 | Subsoil Excavation (Inclusion Piles Spoils Disposal) shall be incidental to the Rigid Inclusions pay item. |