2018 07 25 Exhaust Bid Spec small.pdf

PDF 10 MB Posted

Attached to
FIRE STATION EMERGENCY VEHICLE EXHAUST SYSTEM
Solicitation number
BD-19-1301-10-10-29736
Issued by
Nantucket County, New Bedford City, Massachusetts

About this file

This document is a bid specification for the removal and relocation of components of an existing vehicle exhaust system at the current Nantucket Fire Station to the new Nantucket Fire Station currently under construction. The Town of Nantucket is seeking sealed bids for this project. The project involves the removal of selected components of the existing Plymovent vehicle exhaust system at the current fire station and the relocation and installation of these components, along with the supply of additional new components, at the new fire station located at 4 Fairgrounds Road.

The bid specification does not provide details on pricing terms, set-asides, incumbents, funding requirements or sources, or contract amounts. It also does not include information on the current environment or any renewal options for the contract.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual and Specifications

Fire Station Emergency Vehicle

Exhaust System System

New Fire Station

Nantucket, MA

Issued for Bid

July 25, 2018

TABLE OF CONTENTS

Section Number

Bidding and Contract Requirements

Invitation to Bid 00020 Instructions to Bidders 00100 Form of General Bid 00300 Certificate of Non-Collusion 00400 Draft Copy of Agreement 00500 Construction Payment Bond 00620 General Conditions C-700 Supplemental Conditions 00800 Excerpts from Applicable State Law 00850

Technical Specifications 233500

Attachment A - Wage Rates

Attachment E - Project Drawings

Drawing A5.01 – New Fire Station Elevations Drawing A10.04 – Apparatus Bay Interior Elevations Drawing A10.05 – Apparatus Bay Interior Elevations Drawing A10.06 – Apparatus Bay Interior Elevations Drawing A13.02 – Apparatus Bay Floor Plan

Section 00020 Emergency Vehicle Exhaust System July 25, 2018

TOWN OF NANTUCKET

INVITATION FOR BIDS

EMERGENCY VEHICLE EXHAUST SYSTEM

The Town of Nantucket, Massachusetts, the Awarding Authority, invites sealed bids for the removal of the existing emergency vehicle exhaust system now in place at the Nantucket Fire Station located at 131 Pleasant Street and relocate the system to the new Nantucket Fire Station at 4 Fairgrounds Road, Nantucket, MA 02554, in accordance with the project drawings and specifications.

General Bidders may obtain complete sets of the Bidding Documents, including Bid Forms, online at http://www.nantucket-ma.gov/199/Procurement , for a downloadable set of the Bidding Documents.

Addenda, if any, will be issued online. Any contract regarding this bid must be approved by the Town of Nantucket and the Town reserves the right to reject any and all proposals if it is in its best interest to do

so. Questions about the above may be directed to Maria Davis, Office Administrator, 508-325-4100 Ext- 5700, Monday – Friday, 8:00 am – 4:00 pm.

Sealed bids will be received up to August 9, 2018 at 2:00 p.m. at the Nantucket Police Department Administrative Office, 2nd Floor, 4 Fairgrounds Road, Nantucket, MA 02554 until the time specified below at which time the bids will be publicly opened and read.

Bids will be opened at the above location, Thursday, August 9, 2018 at 2:00 p.m. Each Bid must be accompanied by a bid security consisting of a BID BOND, CASH, or, CERTIFIED CHECK issued by a responsible bank or trust company in the amount of 5% of the bid price.

All bids for this project are subject to applicable public bidding laws of Massachusetts, including, but not limited to G.L. c.149, §44A(2)(C) and c.30, §39M.

Sealed bids shall be submitted on a form furnished by the Awarding Authority and clearly identified as a bid, endorsed with the name and address of the bidder, and the name of the project, and submitted to:

Maria Davis, Office Administrator Nantucket Police Department 4 Fairgrounds Road, Second Floor Nantucket, Massachusetts 02554 http://www.nantucket-ma.gov/199/Procurement

Section 00100 Emergency Vehicle Exhaust System July 25, 2018

INSTRUCTIONS TO BIDDERS

1. Receipt and Opening of Bids

The Town of Nantucket, Massachusetts, herein called the Owner, will receive sealed Bids for the removal of the existing emergency vehicle exhaust system now in place at the Nantucket Fire

Station located at 131 Pleasant Street and relocate the system to the new Nantucket Fire Station at 4

Fairgrounds Road, Nantucket, MA 02554, This Project is subject to M.G.L. C. 149, §44A-44H and c.30, §39M, the provisions of which are incorporated herein by reference and shall control in the event of any conflict among these provisions and the provisions of the bid documents. It is the responsibility of every bidder and sub-bidder to know the requirements of G.L.c.149 §44A-44H and c.30, §39M, The estimated construction cost for this Project is less than $100,000.

Bids are being solicited for this project. All sealed bids shall be submitted on a form furnished by the Awarding Authority and clearly identified as a bid, endorsed with the name and address of the bidder, and the name of the project and submitted to:

Maria Davis, Office Administrator, Nantucket Police Department, 4 Fairgrounds Road, Second Floor

Nantucket, Massachusetts 02554.

All bidders shall provide with their bids:

1) a Bid Bond, and

2) a signed certificate of non-collusion.

Bids must be endorsed “Bid for Technology Infrastructure – New Nantucket Fire Station” and must be received at the address listed above no later than 2:00 prevailing time, on August 9, 2018, at which time and place said bids will be opened and read aloud.

Any bid may be withdrawn prior to the above scheduled time for the opening of bids or authorized postponement thereof. Any bid received after the time and date specified will not be considered. The bidder agrees that this bid shall be good and may not be withdrawn for a period of 30 days, Saturdays, Sundays, and legal holidays excluded, after the opening of bids.

2. Location and Work to be Done

The Work consists of the removal of the selected components of the existing Plymovent vehicle exhaust system at the current Fire Station at 131 Pleasant Street and relocate these components, (and supply additional new components) to the new Nantucket Fire Station which is currently under construction at 4 Fairgrounds Road, as more specifically described in the attached contract drawings and specifications.

The Contractor shall provide all labor, services, materials, equipment, plant, machinery, apparatus, appliances, tools, supplies, and all other things necessary to do all work required for the completion of each item of the Work and as herein specified.

All Electrical Work associated with this Project will be done by Others under separate Contract.

The Work to be done and paid for under any item shall not be limited to the exact extent mentioned or described but shall include all incidental work necessary or customarily done for the completion of that item.

3. Preparation of Bid

Each bid must be submitted on the prescribed form. All blank spaces for bid prices must filled in, in ink or typewritten, in both words and figures.

Each bid must be submitted in a sealed envelope bearing on the outside the name of the bidder, his address, and endorsed with the name of the project as specified in Receipt and Opening of

Bids, above. If forwarded by mail, the sealed envelope containing the bid must be enclosed in another envelope addressed as specified in Receipt and Opening of Bids, above.

4. Bid Opening Procedure

The following list of requirements shall apply to each bid. Bids not meeting all the requirements for timeliness and security will be rejected without opening; bids not meeting signature and addenda requirements will be rejected prior to checking of bid amounts.

Bids shall be filed at the place and before the time specified in Receipt and Opening of Bids, above.

Bid signatures will be checked.

All modifications to the bid documents will be issued electronically on the Town web site via an addendum. All registered plan holders will be electronically notified when addenda are issued.

Hard copies of the addenda will not be forwarded to the plan holders

The total dollar amount of each bid will be read, and the three apparent lowest bids will be selected for further consideration. These three apparent low bids will be read aloud for the benefit of the other bidders and the bid opening procedure will be closed. All those present at the bid opening may examine all bids after the bid opening and after the reading of the three apparent low bids.

5. Bid Modification

Any bidder may withdraw or modify his bid in a signed writing at any time prior to the scheduled closing time for receipt of bids, provided such writing is received by the Owner prior to the bid closing time. Written bid withdrawals and modifications must be sealed and submitted in the same manner as the original bid. Bidders may not withdraw their bid after the bid opening except as may otherwise be expressly provided by law.

6. Ability and Experience of Bidder

No award will be made to any bidder who cannot satisfy the Owner that he has sufficient ability and experience in this class of work and sufficient capital and plant to enable him to prosecute and complete the work successfully within the time named. The Owner's decision or judgment on these matters will be final, conclusive, and binding.

The Owner may make such investigations as he deems necessary, and the bidder shall furnish to the Owner, under oath if so required, all such information and data for this purpose as the Owner may request.

7. Conditions of Work

Each bidder must familiarize themselves fully with the conditions relating to the construction of the project and the employment of labor thereon. Failure to do so will not relieve a successful bidder of his obligation to furnish all material and labor necessary to carry out the provisions of his contract. Insofar as possible the Contractor, in carrying out his work, must employ such methods or means as will not cause any interruption of or interference with the work of any other

Contractor.

8. Addenda and Interpretations

No interpretation of the meaning of the plans, specifications or other pre-bid documents will be made to any bidder orally. All information given to bidders other than by means of the plans, specifications, or by addenda, as described below, is given informally and shall not be used as the basis of a claim against the Owner.

Every request for such interpretation should be via email to the attention of Charles Gibson, at cgibson@police.nantucket-ma.gov to be given consideration must be received at least seven days prior to the date fixed for the opening of bids. Any and all such interpretations and any supplemental instructions will be in the form of written addenda to the specifications which, addenda will be made available online at www.nantucket- ma.gov/199/Procurement, not later than two days prior to the date fixed for the opening of bids. Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder from any obligation under his bid as submitted. Hard copies of the addenda will not be forwarded to the plan holders. The bidder is solely responsible for reviewing all addenda posted online on the Town procurement website. All addenda so issued shall become part of the Contract Documents.

9. Security for Faithful Payment

The Contractor who is selected to perform the Work, will simultaneously with his delivery of the executed Contract, furnish a payment bond in the amount of fifty percent (50%) of the contract amount as security for faithful payment of all persons performing labor and materials under this contract as specified in the herein. The surety on such bond shall be a surety company qualified to do business under the laws of the Commonwealth and satisfactory to the Owner. The bond shall remain in force for one year after final acceptance of the work by the Owner, unless the Owner, in writing, releases the Contractor from the obligation sooner.

10. Power of Attorney

Attorneys-in-fact who sign Contract bonds must file with each bond a certified and effectively dated copy of their power of attorney.

11. Laws and Regulations mailto:cgibson@police.nantucket-ma.gov

The bidder's attention is directed to the fact that all applicable State laws, municipal ordinances or

Bylaws, and the rules and regulations of all authorities having jurisdiction over construction of the project shall apply to the contract throughout, and they will be deemed to be included in the

Contract the same as though herein written out in full.

12. Liquidated Damages for Failure to Enter into Contract

Subject to, and except as otherwise may be provided by G.L.c.149. §§ 44B and 44E. the successful bidder, upon his failure or refusal to execute and deliver the Contract and bonds required within five (5) days (Saturdays, Sundays and legal holidays excluded) after he/she has received notice of the acceptance of his/her bid, shall forfeit to the Owner, as liquidated damages for such failure or refusal, a portion of security deposited with his/her bid, but the amount forfeited shall not exceed the difference between his/her bid price and the bid price of the next lowest responsible and eligible bidder.

13. Obligation of Bidder

At the time of the opening of bids each bidder will be presumed to have inspected the site and to have read and to be thoroughly familiar with the Contract Documents (including all addenda). The failure or omission of any bidder to examine any form, instrument, or document shall in no way relieve any bidder from any obligation in respect of his bid.

14. Information Not Guaranteed

All information given in the Contract Documents relating to subsurface and other conditions, natural phenomena, existing pipes, and other structures is from the best sources at present available to the Owner. All such information is furnished only for the information and convenience of bidders and is not guaranteed.

It is agreed and understood that the Owner does not warrant or guarantee that the subsurface or other conditions, natural phenomena, existing pipes, or other structures encountered during construction will be the same as those indicated in the Contract Documents.

It is further agreed and understood that no bidder or Contractor shall use or be entitled to use any of the information made available to him or obtained in any examination made by him in any manner as a basis of or ground for any claim or demand against the Owner or the Architect, arising from or by reason of any variance which may exist between the information made available and the actual subsurface or other structures actually encountered during the construction work, except as may otherwise be expressly provided for in the Contract Documents.

15. Bid Security

As stated in G.L.c.149. § 44A, each bid must be accompanied by a bid bond of 5% of their bid in the form of a certified check, treasurer's or cashier's check, payable to Town of Nantucket, or a Bid

Bond from a surety company in the amount stated in their Bid. Such checks will be returned to all except the three lowest responsible and eligible bidders within five days, Saturdays, Sundays, and legal holidays excluded, after the opening of bids, and the remaining checks will be returned promptly after the Owner and the accepted bidder have executed the Contract, or if no notice of intent to award has been presented to the selected contractor within 30 days, Saturdays, Sundays and holidays excluded, after the date of the opening of bids, upon demand of the bidder at any time thereafter.

16. Right to Reject Bid

The Owner reserves the right to waive any informalities in the bids, and to reject any and all bids, should the Owner deem it to be in the public interest to do so, and for any other reason as may be allowed by law.

The Owner may also reject bids which in its sole judgment are either incomplete, conditional, obscure or not responsive or which contain additions not called for, erasures not properly initialed, alterations, or similar irregularities, or the Owner may waive such omissions, conditions or irregularities.

17. Time for Completion

The successful Contractor shall commence work within ten (10) calendar days of the date of the

Notice to Proceed or, in the absence of such a notice, of the date of execution of a contract with the Town, and to fully complete the project within the time limit stated in the Contract

Documents.

18. Comparison of Bids

Bids will be compared on the basis of the price for the Work set forth in the submission of the

FORM OF GENERAL BID.

In the event that there is a discrepancy in FORM OF GENERAL BID between the lump sum or unit prices written in words and figures, the prices written in words will govern.

The Owner agrees to examine and consider each FORM OF GENERAL BID submitted in consideration of the qualifications of the bidder and the bidder's agreements, as hereinabove set forth and as set forth in FORM OF GENERAL BID.

19. Award of Contract

The Contract will be awarded to "the lowest responsible and eligible bidder" pursuant to General

Laws Chapter 149, Section 44A(2), as amended. Such a bidder shall possess the skill, ability and integrity necessary for the faithful performance of the work, shall be able to furnish labor that can work in harmony with all other elements of labor employed, or to be employed, in the work, and shall otherwise comply with all applicable provisions of law, including satisfaction of the OSHA requirements as stated in the Form of General Bid included herein and prescribed by G.L.c.149.§

44E.

20. Statutes Regulating Competitive Bidding

Any bid which does not comply with the provisions of Massachusetts General Laws Chapter 149, Sections 44A through 44H, as amended, need not be accepted and the Owner may reject every such bid.

21. Certificate of Eligibility and Update Statement

A certificate of eligibility issued by the Division of Capital Asset Management is not required.

22. Wage Rates

Prevailing Wage Rates as determined by the Commissioner of Department of Labor and

Industries under the provision of the Massachusetts General Laws, Chapter 149, Section 26 to

27G, as amended, apply to this project.

State schedules of Prevailing wage rates are included in the Supplemental General Conditions section of the contract documents.

23. Contractor Records

The Contractor shall comply with the provisions of Massachusetts General Laws, Chapter 30, Section 39R and Chapter 149, Section 27B concerning Contractor records.

24. Insurance

The Contractor shall carry and continuously maintain until completion of the Contract, insurance as specified in the Contract Documents.

Section 00300-1 Emergency Vehicle Exhaust System July 25, 2018

SECTION 00300

FORM OF GENERAL BID

Bid of _________________________________________ (hereinafter called "Bidder")* a corporation, organized and existing under the laws of the state of: ________________________________________ a partnership a joint venture an individual doing business as

To the Town of Nantucket, Massachusetts (hereinafter called "Owner").

Gentlemen:

A) The undersigned Bidder, in compliance with your invitation for bids for the project known as, Emergency Vehicle Exhaust System, having examined the plans and specifications and related documents and the site of the proposed work, and being familiar with all of the conditions surrounding the construction of the proposed project including the availability of materials and labor, hereby proposes to furnish all labor, materials, and supplies, and to construct the project in accordance with the contract documents and the plans and specifications within the time set forth below, and at the prices stated below.

These prices are to cover all expenses incurred in performing the work required under the contract documents, of which this bid is a part.

The Bidder hereby agrees to commence work on or before the date to be specified in written "Notice to Proceed" of the Owner, and to fully complete the project by January 30, 2019.

*Specify corporation, partnership or individual as applicable.

Section 00300-2 Emergency Vehicle Exhaust System July 25, 2018

B) Bidder acknowledges receipt of and this bid includes the following addenda:

Number:________ Dated:______________

C) The Bidder agrees to perform the bid work described in the specifications and shown on the plans for the following contract price:

_____________________________________________________________Dollars

(insert words and numbers. In cases of conflict between words and numbers, words shall control)

Section 00300-3 Emergency Vehicle Exhaust System July 25, 2018

The Bidder understands that all bids for this project are subject to the applicable bidding laws of the Commonwealth of Massachusetts, including General Laws Chapter 149 and Chapter 30, Section 39M, as amended.

The Bidder understands that the Owner reserves the right to reject any or all bids and to waive any informalities in the bidding.

The Bidder agrees that this bid shall be good and may not be withdrawn for a period of 30 days, Saturdays, Sundays and legal holidays excluded, after the opening of bids.

Within 10 days of receipt of the written notice of acceptance of this bid, the Bidder will execute the formal Agreement set forth in a draft copy in Section 00500 AGREEMENT.

Bid security is attached in the sum of five percent (5%) of the total bid in accordance with the conditions of Section 00100 INSTRUCTIONS TO BIDDERS. The bid security may become the property of the Owner in the event the contract and bond are not executed within the time set forth above.

The selected Contractor shall furnish a payment bond in an amount at least equal to fifty percent

(50%) of the contract price in accordance with Section 00620 PAYMENT BOND, and as stipulated in the contract.

The undersigned offers the following information as evidence of his qualifications to perform the work as bid upon according to all the requirements of the plans and specifications.

1. Have been in business under present name for _____ years.

2. The names and addresses of all persons interested in the bid (if made by a partnership or corporation) as principals, are as follows:

(attach supplementary list if necessary)

Section 00300-4 Emergency Vehicle Exhaust System July 25, 2018

3. The bidder is requested to state below what work of a similar character to that included in the proposed contract he has done, and give references that will enable the Owner to judge his experience, skill and business standing (add supplementary page if necessary).

a. Completion Date: Project Name:

Contract Amount: Design Engineer:

Reference Name: Telephone Nbr:

b. Completion Date: Project Name:

c. Completion Date: Project Name:

d. Completion Date: Project Name:

Bank reference:

(Name)

(Bank)

(Address)

(Telephone No.)

Section 00300-5 Emergency Vehicle Exhaust System July 25, 2018

Pursuant to G.L. c.62C, §49A, I certify hereby in writing, under penalties of perjury, that the within named Bidder/Contractor has complied with all laws of the commonwealth relating to taxes, reporting of employees and contractors, and withholding and remitting of child support.

The undersigned Bidder hereby certifies under penalties of perjury, as follows: (1) that he/she is able to furnish labor that can work in harmony with all other elements of labor employed or to be employed in the work; (2) that all employees to be employed at the worksite will have successfully completed a course in construction safety and health approved by the United States Occupational Safety and Health Administration that is at least 10 hours in duration at the time the employee begins work and who shall furnish documentation of successful completion of said course with the first certified payroll report for each employee; and (3) that all employees to be employed in the work subject to this bid have successfully completed a course in construction safety and health approved by the United States Occupational Safety and Health Administration that is at least 10 hours in duration.

The undersigned certifies under penalties of perjury that this bid is in all respects bona fide, fair and made without collusion or fraud with any other person. As used in this paragraph the word “person” shall mean any natural person, joint venture, partnership, corporation or other business or legal entity.

The undersigned bidder hereby certifies, under pains and penalties of perjury, that the foregoing bid is based upon the payment to laborers to be employed on the project of wages in an amount no less that the applicable prevailing wage rates established for the project by the Massachusetts Department of Labor and Workforce Development. The undersigned bidder agrees to indemnify the awarding authority for, from and against any loss, expense, damages, actions or claims, including any expense incurred in connection with any delay or stoppage of the project work arising out of or as a result of (1) the failure of the said bid to be based upon the payment of the said applicable prevailing wage rates or (2) the failure of the bidder, if selected as the contractor, to pay laborers employed on the project the said applicable prevailing wage rates.

Section 00300-6 Emergency Vehicle Exhaust System July 25, 2018

Respectfully submitted:

Date: By:

Signature

Type Name of Bidder

Title

Business Address

City, State, Zip

Telephone Number

PAGES 0300-1 thru 0300-6 MUST BE SUBMITTED WITH YOUR BID

Section 00400-1 Emergency Vehicle Exhaust System July 25, 2018

SECTION 00400

CERTIFICATE OF NON_COLLUSION

The undersigned certifies under penalties of perjury that this bid or proposal has been made and submitted in good faith and without collusion or fraud with any person. As used in this certification, the word "person" shall mean any natural person, business, partnership, corporation, union, committee, club, or other organization, entity, or group of individuals.

CONTRACTOR NAME:

SIGNATURE:

PRINTED NAME:

DATE:

THIS PAGE, 400-1 MUST BE SUBMITTED WITH YOUR BID

Section 00500-1 Emergency Vehicle Exhaust System July 25, 2018

SECTION 00500

DRAFT CONTRACT

Section 00500-1 Emergency Vehicle Exhaust System July 25, 2018

Section 00500-2 Emergency Vehicle Exhaust System July 25, 2018

Section 00500-3 Emergency Vehicle Exhaust System July 25, 2018

Section 00500-4 Emergency Vehicle Exhaust System July 25, 2018

Section 00500-5 Emergency Vehicle Exhaust System July 25, 2018

Section 00500-6 Emergency Vehicle Exhaust System July 25, 2018

Section 00500-7 Emergency Vehicle Exhaust System July 25, 2018

Section 00500-8 Emergency Vehicle Exhaust System July 25, 2018

Section 00500-9 Emergency Vehicle Exhaust System July 25, 2018

Section 00500-10 Emergency Vehicle Exhaust System July 25, 2018

Section 00500-11 Emergency Vehicle Exhaust System July 25, 2018

Section 00500-12 Emergency Vehicle Exhaust System July 25, 2018

Section 00500-13 Emergency Vehicle Exhaust System July 25, 2018

Section 00620-1 Emergency Vehicle Exhaust System July 25, 2018

SECTION 00620

CONSTRUCTION PAYMENT BOND

KNOW ALL MEN BY THESE PRESENTS: That we ___________________________________________

______________________________ a ________________________________________________________

(Name of Contractor) (Corporation, Partnership, Joint Venture or Individual) hereinafter called "Principal" and ________________________________ of __________________________, (Surety) State of ______________________________ hereafter called the “Surety” and licensed by the State

(City and State) Division of Insurance to do business under the laws of the Commonwealth of Massachusetts, are held and firmly bound to the Town of Nantucket, Massachusetts hereinafter called "Owner", in the penal sum of

______________________________ Dollars ($_______________) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION is such that Whereas, the Principal entered into a certain contract with the Owner, dated the __________________ day of ______________________, 2018 for the construction described as follows:

NOW, THEREFORE, if the Principal shall promptly make payment to all persons, firms, subcontractors, and corporations furnishing materials for or performing labor in the prosecution of the work provided for in such contract, and any authorized extension or modification thereof, including all amounts due for materials, lubricants, oil, gasoline, coal and coke, repairs on machinery, equipment and tools, consumed or used in connection with the construction of such work, and all insurance premiums on said work, and for all labor, performed in such work whether by subcontractor or otherwise, then this obligation shall be void; otherwise to remain in full force and effect.

PROVIDED, FURTHER, that the said Surety, for value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the work to be performed thereunder or the specifications accompanying the same shall in any way affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of this contract or to the work or to the specifications.

Section 00620-2 Emergency Vehicle Exhaust System July 25, 2018

PROVIDED, FURTHER, that no final settlement between the Owner and the Contractor shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied.

IN WITNESS WHEREOF, this instrument is executed in ______( ) counterparts, each one of which shall be deemed an original, this the _________ day of ____________________, 20_____.

ATTEST: ____________________________________________

Surety

________________________________________ By: _________________________________________

(Attorney-in-Fact)

(Address, City, State, Zip)

________________________________________(SEAL)

Witness as to Surety

(Address, City, State, Zip)

NOTE: Date of Bond must not be prior to date of Contract. If Contractor is a Partnership, all partners should execute Bond.

Section C700-3 Emergency Vehicle Exhaust System July 25, 2018

SECTION C-700

STANDARD GENERAL CONDITIONS OF THE

CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1 – Definitions and Terminology

1.01 Defined Terms

1.02 Terminology

Article 2 – Preliminary Matters

2.01 Delivery of Bonds and Evidence of Insurance

2.02 Copies of Documents

2.03 Commencement of Contract Times; Notice to Proceed

2.04 Starting the Work

2.05 Before Starting Construction

2.06 Preconstruction Conference; Designation of Authorized Representatives

2.07 Initial Acceptance of Schedules

Article 3 – Contract Documents: Intent, Amending, Reuse

3.01 Intent

3.02 Reference Standards

3.03 Reporting and Resolving Discrepancies

3.04 Amending and Supplementing Contract Documents

3.05 Reuse of Documents

3.06 Electronic Data

Article 4 – Availability of Lands; Subsurface and Physical Conditions; Hazardous Environmental

Conditions; Reference Points

4.01 Availability of Lands

4.02 Subsurface and Physical Conditions

4.03 Differing Subsurface or Physical Conditions

4.04 Underground Facilities

4.05 Reference Points

4.06 Hazardous Environmental Condition at Site

Article 5 – Bonds and Insurance

5.01 Performance, Payment, and Other Bonds

5.02 Licensed Sureties and Insurers

5.03 Certificates of Insurance

5.04 Contractor’s Insurance

5.05 Owner’s Liability Insurance

5.06 Property Insurance

5.07 Waiver of Rights

5.08 Receipt and Application of Insurance Proceeds

Section C700-4 Emergency Vehicle Exhaust System July 25, 2018

5.09 Acceptance of Bonds and Insurance; Option to Replace

5.10 Partial Utilization, Acknowledgment of Property Insurer

Article 6 – Contractor’s Responsibilities

6.01 Supervision and Superintendence

6.02 Labor; Working Hours

6.03 Services, Materials, and Equipment

6.04 Progress Schedule

6.05 Substitutes and “Or-Equals”

6.06 Concerning Subcontractors, Suppliers, and Others

6.07 Patent Fees and Royalties

6.08 Permits

6.09 Laws and Regulations

6.10 Taxes

6.11 Use of Site and Other Areas

6.12 Record Documents

6.13 Safety and Protection

6.14 Safety Representative

6.15 Hazard Communication Programs

6.16 Emergencies

6.17 Shop Drawings and Samples

6.18 Continuing the Work

6.19 Contractor’s General Warranty and Guarantee

6.20 Indemnification

6.21 Delegation of Professional Design Services

Article 7 – Other Work at the Site

7.01 Related Work at Site

7.02 Coordination

7.03 Legal Relationships

Article 8 – Owner’s Responsibilities

8.01 Communications to Contractor

8.02 Replacement of Engineer

8.03 Furnish Data

8.04 Pay When Due

8.05 Lands and Easements; Reports and Tests

8.06 Insurance

8.07 Change Orders

8.08 Inspections, Tests, and Approvals

8.09 Limitations on Owner’s Responsibilities

8.10 Undisclosed Hazardous Environmental Condition

8.11 Evidence of Financial Arrangements

8.12 Compliance with Safety Program

Article 9 – Engineer’s Status During Construction

9.01 Owner’s Representative

9.02 Visits to Site

Section C700-5 Emergency Vehicle Exhaust System July 25, 2018

9.03 Project Representative

9.04 Authorized Variations in Work

9.05 Rejecting Defective Work

9.06 Shop Drawings, Change Orders and Payments

9.07 Determinations for Unit Price Work

9.08 Decisions on Requirements of Contract Documents and Acceptability of Work

9.09 Limitations on Engineer’s Authority and Responsibilities

9.10 Compliance with Safety Program

Article 10 – Changes in the Work; Claims

10.01 Authorized Changes in the Work

10.02 Unauthorized Changes in the Work

10.03 Execution of Change Orders

10.04 Notification to Surety

10.05 Claims

Article 11 – Cost of the Work; Allowances; Unit Price Work

11.01 Cost of the Work

11.02 Allowances

11.03 Unit Price Work

Article 12 – Change of Contract Price; Change of Contract Times

12.01 Change of Contract Price

12.02 Change of Contract Times

12.03 Delays

Article 13 – Tests and Inspections; Correction, Removal or Acceptance of Defective Work

13.01 Notice of Defects

13.02 Access to Work

13.03 Tests and Inspections

13.04 Uncovering Work

13.05 Owner May Stop the Work

13.06 Correction or Removal of Defective Work

13.07 Correction Period

13.08 Acceptance of Defective Work

13.09 Owner May Correct Defective Work

Article 14 – Payments to Contractor and Completion

14.01 Schedule of Values

14.02 Progress Payments

14.03 Contractor’s Warranty of Title

14.04 Substantial Completion

14.05 Partial Utilization

14.06 Final Inspection

14.07 Final Payment

14.08 Final Completion Delayed

14.09 Waiver of Claims

Section C700-6 Emergency Vehicle Exhaust System July 25, 2018

Article 15 – Suspension of Work and Termination

15.01 Owner May Suspend Work

15.02 Owner May Terminate for Cause

15.03 Owner May Terminate For Convenience

15.04 Contractor May Stop Work or Terminate

Article 16 – Dispute Resolution

16.01 Methods and Procedures

Article 17 – Miscellaneous

17.01 Giving Notice

17.02 Computation of Times

17.03 Cumulative Remedies

17.04 Survival of Obligations

17.05 Controlling Law

17.06 Headings

Section C700-7 Emergency Vehicle Exhaust System July 25, 2018

ARTICLE 1 – DEFINITIONS AND TERMINOLOGY

1.01 Defined Terms

A. Wherever used in the Bidding Requirements or Contract Documents and printed with initial capital letters, the terms listed below will have the meanings indicated which are applicable to both the singular and plural thereoF. In addition to terms specifically defined, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms.

1. Addenda—Written or graphic instruments issued prior to the opening of Bids which clarify, correct, or change the Bidding Requirements or the proposed Contract Documents.

2. Agreement—The written instrument which is evidence of the agreement between Owner and

Contractor covering the Work.

3. Application for Payment—The form acceptable to the Owner which is to be used by Contractor during the course of the Work in requesting progress or final payments and which is to be accompanied by such supporting documentation as is required by the Contract Documents.

4. Asbestos—Any material that contains more than one percent asbestos and is friable or is releasing asbestos fibers into the air above current action levels established by the United States

Occupational Safety and Health Administration.

5. Bid—The offer or proposal of a Bidder submitted on the prescribed form setting forth the prices for the Work to be performed.

6. Bidder—The individual or entity who submits a Bid directly to Owner.

7. Bidding Documents—The Bidding Requirements and the proposed Contract Documents

(including all Addenda).

8. Bidding Requirements—The advertisement or invitation to bid, Instructions to Bidders, Bid security of acceptable form, if any, and the Bid Form with any supplements.

9. Change Order—A document recommended by Engineer which is signed by Contractor and

Owner and authorizes an addition, deletion, or revision in the Work or an adjustment in the

Contract Price or the Contract Times, issued on or after the Effective Date of the Agreement.

10. Claim—A demand or assertion by Owner or Contractor seeking an adjustment of Contract

Price or Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Claim.

11. Contract—The entire and integrated written agreement between the Owner and Contractor concerning the Work. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral.

Section C700-8 Emergency Vehicle Exhaust System July 25, 2018

12. Contract Documents—Those items so designated in the Agreement. Only printed or hard copies of the items listed in the Agreement are Contract Documents. Approved Shop

Drawings, other Contractor submittals, and the reports and drawings of subsurface and physical conditions are not Contract Documents.

13. Contract Price—The moneys payable by Owner to Contractor for completion of the Work in accordance with the Contract Documents as stated in the Agreement (subject to the provisions of Paragraph 11.03 in the case of Unit Price Work).

14. Contract Times—The number of days or the dates stated in the Agreement to: (i) achieve

Milestones, if any; (ii) achieve Substantial Completion; and (iii) complete the Work so that it is ready for final payment as evidenced by Engineer’s written recommendation of final payment.

15. Contractor—The individual or entity with whom Owner has entered into the Agreement.

16. Cost of the Work—See Paragraph 11.01 for definition.

17. Drawings—That part of the Contract Documents prepared or approved by Engineer which graphically shows the scope, extent, and character of the Work to be performed by Contractor.

Shop Drawings and other Contractor submittals are not Drawings as so defined.

18. Effective Date of the Agreement—The date indicated in the Agreement on which it becomes effective, but if no such date is indicated, it means the date on which the Agreement is signed and delivered by the last of the two parties to sign and deliver.

19. Engineer—The individual or entity named as such in the Agreement. If no Engineer is listed, then the Owner.

20. Field Order—A written order issued by Engineer which requires minor changes in the Work but which does not involve a change in the Contract Price or the Contract Times.

21. General Requirements—Sections of Division 1 of the Specifications.

22. Hazardous Environmental Condition—The presence at the Site of Asbestos, PCBs, Petroleum, Hazardous Waste, or Radioactive Material in such quantities or circumstances that may present a substantial danger to persons or property exposed thereto.

23. Hazardous Waste—The term Hazardous Waste shall have the meaning provided in Section

1004 of the Solid Waste Disposal Act (42 USC Section 6903) as amended from time to time.

24. Laws and Regulations; Laws or Regulations—Any and all applicable laws, rules, regulations, ordinances, codes, and orders of any and all governmental bodies, agencies, authorities, and courts having jurisdiction.

25. Liens—Charges, security interests, or encumbrances upon Project funds, real property, or personal property.

26. Milestone—A principal event specified in the Contract Documents relating to an intermediate completion date or time prior to Substantial Completion of all the Work.

Section C700-9 Emergency Vehicle Exhaust System July 25, 2018

27. Notice of Award—The written notice by Owner to the Successful Bidder stating that upon timely compliance by the Successful Bidder with the conditions precedent listed therein, Owner will sign and deliver the Agreement.

28. Notice to Proceed—A written notice given by Owner to Contractor fixing the date on which the Contract Times will commence to run and on which Contractor shall start to perform the

Work under the Contract Documents.

29. Owner—The individual or entity with whom Contractor has entered into the Agreement and for whom the Work is to be performed.

30. PCBs—Polychlorinated biphenyls.

31. Petroleum—Petroleum, including crude oil or any fraction thereof which is liquid at standard conditions of temperature and pressure (60 degrees Fahrenheit and 14.7 pounds per square inch absolute), such as oil, petroleum, fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil mixed with other non-Hazardous Waste and crude oils.

32. Progress Schedule—A schedule, prepared and maintained by Contractor, describing the sequence and duration of the activities comprising the Contractor’s plan to accomplish the

Work within the Contract Times.

33. Project—The total construction of which the Work to be performed under the Contract

Documents may be the whole, or a part.

34. Project Manual—The documentary information prepared for bidding and constructing the

Work. A listing of the contents of the Project Manual, which may be bound in one or more volumes, is contained in the table(s) of contents.

35. Radioactive Material—Source, special nuclear, or byproduct material as defined by the

Atomic Energy Act of 1954 (42 USC Section 2011 et seq.) as amended from time to time.

36. Resident Project Representative—The authorized representative of Engineer who may be assigned to the Site or any part thereof.

37. Samples—Physical examples of materials, equipment, or workmanship that are representative of some portion of the Work and which establish the standards by which such portion of the

Work will be judged.

38. Schedule of Submittals—A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to support scheduled performance of related construction activities.

39. Schedule of Values—A schedule, prepared and maintained by Contractor, allocating portions of the Contract Price to various portions of the Work and used as the basis for reviewing

Contractor’s Applications for Payment.

Section C700-10 Emergency Vehicle Exhaust System July 25, 2018

40. Shop Drawings—All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work.

41. Site—Lands or areas indicated in the Contract Documents as being furnished by Owner upon which the Work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by Owner which are designated for the use of

Contractor.

42. Specifications—That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto.

43. Subcontractor—An individual or entity having a direct contract with Contractor or with any other Subcontractor for the performance of a part of the Work at the Site.

44. Substantial Completion—The time at which the Work (or a specified part thereof) has progressed to the point where, in the opinion of Engineer, the Work (or a specified part thereof) is sufficiently complete, in accordance with the Contract Documents, so that the Work (or a specified part thereof) can be utilized for the purposes for which it is intendeD. The terms

“substantially complete” and “substantially completed” as applied to all or part of the Work refer to Substantial Completion thereof.

45. Successful Bidder—The Bidder submitting a responsive Bid to whom Owner makes an award.

46. Supplementary Conditions—That part of the Contract Documents which amends or supplements these General Conditions.

47. Supplier—A manufacturer, fabricator, supplier, distributor, materialman, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment to be incorporated in the Work by Contractor or Subcontractor.

48. Underground Facilities—All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.

49. Unit Price Work—Work to be paid for on the basis of unit prices.

50. Work—The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents.

51. Work Change Directive—A written statement to Contractor issued on or after the Effective

Date of the Agreement and signed by Owner and recommended by Engineer ordering an

Section C700-11 Emergency Vehicle Exhaust System July 25, 2018 addition, deletion, or revision in the Work, or responding to differing or unforeseen subsurface or physical conditions under which the Work is to be performed or to emergencies. A Work

Change Directive will not change the Contract Price or the Contract Times but is evidence that the parties expect that the change ordered or documented by a Work Change Directive will be incorporated in a subsequently issued Change Order following negotiations by the parties as to its effect, if any, on the Contract Price or Contract Times.

1.02 Terminology

A. The words and terms discussed in Paragraph 1.02.B through F are not defined but, when used in the Bidding Requirements or Contract Documents, have the indicated meaning.

B. Intent of Certain Terms or Adjectives:

1. The Contract Documents include the terms “as allowed,” “as approved,” “as ordered,” “as directed” or terms of like effect or import to authorize an exercise of professional judgment by Engineer. In addition, the adjectives “reasonable,” “suitable,” “acceptable,” “proper,”

“satisfactory,” or adjectives of like effect or import are used to describe an action or determination of Engineer as to the Work. It is intended that such exercise of professional judgment, action, or determination will be solely to evaluate, in general, the Work for compliance with the information in the Contract Documents and with the design concept of the Project as a functioning whole as shown or indicated in the Contract Documents (unless there is a specific statement indicating otherwise). The use of any such term or adjective is not intended to and shall not be effective to assign to Engineer any duty or authority to supervise or direct the performance of the Work, or any duty or authority to undertake responsibility contrary to the provisions of Paragraph 9.09 or any other provision of the Contract Documents.

C. Day:

1. The word “day” means a calendar day of 24 hours measured from midnight to the next midnight.

D. Defective:

1. The word “defective,” when modifying the word “Work,” refers to Work that is unsatisfactory, faulty, or deficient in that it:

A. does not conform to the Contract Documents;

or

B. does not meet the requirements of any applicable inspection, reference standard, test, or approval referred to in the Contract Documents; or

C. has been damaged prior to Engineer’s recommendation of final payment (unless responsibility for the protection thereof has been assumed by Owner at Substantial

Completion in accordance with Paragraph 14.04 or 14.05).

E. Furnish, Install, Perform, Provide:

Section C700-12 Emergency Vehicle Exhaust System July 25, 2018

1. The word “furnish,” when used in connection with services, materials, or equipment, shall mean to supply and deliver said services, materials, or equipment to the Site (or some other specified location) ready for use or installation and in usable or operable condition.

2. The word “install,” when used in connection with services, materials, or equipment, shall mean to put into use or place in final position said services, materials, or equipment complete and ready for intended use.

3. The words “perform” or “provide,” when used in connection with services, materials, or equipment, shall mean to furnish and install said services, materials, or equipment complete and ready for intended use.

4. When “furnish,” “install,” “perform,” or “provide” is not used in connection with services, materials, or equipment in a context clearly requiring an obligation of Contractor, “provide” is implied.

F. Unless stated otherwise in the Contract Documents, words or phrases that have a well-known technical or construction industry or trade meaning are used in the Contract Documents in accordance with such recognized meaning.

ARTICLE 2 – PRELIMINARY MATTERS

2.01 Delivery of Bonds and Evidence of Insurance

A. When Contractor delivers the executed counterparts of the Agreement to Owner, Contractor shall also deliver to Owner such bonds as Contractor may be required to furnish.

B. Evidence of Insurance: Before any Work at the Site is started, CONTRACTOR shall deliver to

OWNER, with copies to each additional insured identified in the Supplementary Conditions, certificates of insurance (and other evidence of insurance which OWNER or any additional insured may reasonably request) which CONTRACTOR is required to purchase and maintain in accordance with Article 5.

2.02 Copies of Documents

A. Owner shall furnish to Contractor up to ten printed or hard copies of the Drawings and Project

Manual. Additional copies will be furnished upon request at the cost of reproduction.

2.03 Commencement of Contract Times; Notice to Proceed

A. The Contract Times will commence to run on the thirtieth day after the Effective Date of the

Agreement or, if a Notice to Proceed is given, on the day indicated in the Notice to ProceeD. A

Notice to Proceed may be given at any time within 30 days after the Effective Date of the

Agreement.

Section C700-13 Emergency Vehicle Exhaust System July 25, 2018

2.04 Starting the Work

A. Contractor shall start to perform the Work on the date when the Contract Times commence to run. No Work shall be done at the Site prior to the date on which the Contract Times commence to run.

2.05 Before Starting…

This is the start of the file's text. The full file is on GovTribe.