- ENGINEER PROCURE CONSTRUCT (EPC) FOR A COMBINED CYCLE PROJECT TO BE LOCATED IN TVA AREA (TVA CC) Federal contract opportunity
- Solicitation number
- 20110119
- Issued by
- Tennessee Valley Authority
About this file
Mandatory Mnimum Qualifications Certification
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MANDATORY MINIMUM QUALIFICATIONS CERTIFICATION
There are certain mandatory minimum qualifications which offerors must meet in order to be invited to submit proposals and be considered for award of the proposed contract. Offerors are required to submit detailed supporting documentation to substantiate meeting all mandatory minimum qualification requirements. Teaming and subcontracting are acceptable. However, offerers that provide only engineering with construction management services but plan to subcontract all the construction work will not be considered for this project. The minimum qualification requirements may collectively be satisfied by combining the qualifications of team members and subcontractors committed to perform in the event of award, however, these team members must collectively have worked together as a team in the past and as a team to satisfy these minimum qualifications. Individual qualification criteria, however, must be satisfied by individual entities. The minimum qualifications are as follows:
CRITERIA
MEETS
CRITERIA?
YES/NO
1. Offerors must have successfully provided engineering, procurement, and construction, including startup and commissioning (full EPC plus startup and commissiong) for a minimum of three (3) Combined Cycle (CC) units of no less than 500 MW capacity. These units must have been a 2X1, 3X1, or 4X1 configurations utilizing “F” class (or higher) technology combustion turbines (GE 7FA’s preferred). These units shall have been successfully operational for at least one (1) year. These 3 CC Projects must also have each met the original (pre-construction start) scheduled in service date and must have been no more than 3% over the original project budget.
2. Offeror must have the resources, capability and experience as an EPC for CC projects (of at least the type and magnitude similar to that described above) and be able to demonstrate the ability for project management of complex CC projects with appropriate proposed structure of the project management team. This shall be demonstrated by the Offeror providing the documentation requested in item 1 above.
3. Offeror must have the financial capacity (creditworthiness) to guarantee the timely performance, obligations, duties and responsibilities under or related to the contract (including performance and warranty issues), for the term of the contract. (Required information shown on following page)
4. Offer must have an established, overall, formalized Total Quality Program (TQP). This TQP must include a detailed SA335, GR.P.91 inspection and installation program, and demonstrate this by providing the table of contents of the TQP and the section(s) related to P91 piping production, fabrication, welding, stress relieving, etc.
5. Offeror must have the demonstrated capability to manage the commissioning and start-up of CC power units. Must be capable of field performance testing of the individual equipment (i.e. CT’s, Steam turbine, HRSG’s, cooling tower, etc.), and the entire CC unit for MW output and efficiency. This shall be demonstrated by the Offeror providing the documentation requested in item 1 above.
6. Offeror must be willing to become signatory to TVA’s project labor agreement (CPA).
7. Offeror must have an acceptable safety program with demonstrated ability to assign on-site safety professionals. The Recordable Injury Rate should be no greater than 1.5 average for the minimum of 3 CC projects described above in Item 1, and a Lost Time Injury Rate of less than .2 average for those same projects. The offeror shall submit the safety records indicating that the Offeror meets the safety criteria above.
Note: Other than the mandatory minimum qualifications required for construction and startup of (3) three CC units, if the offerer believes a valid exception to any of the other mandatory minimum requirements exists, please submit the certification with a detailed explanation of the exception. TVA will review the exception and make a determination of its acceptability. No challenges will be accepted to TVA’s decision.
MANDATORY MINIMUM QUALIFICATIONS CERTIFICATION
| ACTIVITY |
| DATES (Estimated) |
| RFP Issue |
| 2/28/11 |
| Pre-Bid Meeting |
| 3/9/11 |
| Proposal due date |
| 6/2/11 |
| Anticipated Contract Award Date |
| 10/3/11 |
| Mobilize to jobsite and Site Prep Start |
| To be determined |
| Construction Start |
| To be determined |
| CC Plant in service date (Provisional Acceptance) |
| 3/1/15 |
Information required to be submitted in item 3 above regarding financial capacity:
· Audited financial statements for the last three (3) preceding years that include balance sheets, income statements, statements of cash flows and notes to the financial statements, or an annual report on Form 10-K for the last three (3) preceding years.
· Interim financial statements for the most recent fiscal period or quarterly financial statements on Form 10-Q for the most recent fiscal period.
· Bank name, address, phone number and officer contact.
· Credit references from three (3) sources that include name, address, phone number and contact.
· Complete legal name of the company and the State of Incorporation.
· Company ownership schedule if privately held.
Offeror certifies by signing below that it meets all of the mandatory minimum qualification requirements, including, but not limited to, the required in services dates, etc., listed herein. .
Company (Offeror)
Signature of Authorized Representative
Printed Name
Title
Date
Email oleObject2.bin oleObject3.bin image1.wmf oleObject1.bin image2.wmf
File details come from the government source that posted it. Updated .