This is a Request for Engineering Service Qualifications issued by the City of St. Peters, Missouri (RFQ No. 26-183) seeking qualified consulting engineering firms to provide professional engineering services for two water infrastructure projects: the design of a 20-inch Water Transmission Main Extension (WM-01) and the design for Old Town South Water Main Replacement. The 20-inch transmission main extension project involves approximately 7,200 linear feet of new main beginning at Jungs Station Road at Winwood Trails Drive and extending to the existing 20-inch transmission main near Hartman Circle and South St. Peters Parkway. The Old Town South Water Main Replacement project encompasses approximately 6,000 linear feet of targeted water main removal and replacement within the Old Town South Subdivision south of I-70, addressing aging infrastructure consisting of cast iron, ductile iron, asbestos cement, and unknown material types ranging from 4-inch to 8-inch diameter. The RFQ was made available on August 3, 2026, with a submission deadline of 2:00 PM local time on August 24, 2026 (non-public opening). Firms must submit one original and one electronic copy of their Technical Qualification sealed envelope clearly marked with the firm name and project number. The tentative project schedule includes interviews the week of September 1, 2026, contract award in October 2026, project startup meeting on November 9, 2026, preliminary submittal in January 2027, 60% design submittal in April 2027, 90% final design submittal in July 2027, and final plans and specifications in August 2027.
The City of St. Peters has allocated $629,400.00 to this project, and the final engineering service agreement will be on a lump-sum basis with a guaranteed maximum limit. Compensation will be determined through contract negotiations following engineer selection and will be invoiced monthly as work progresses, subject to a 5% retention until satisfactory final completion. The selection process will be based on review and evaluation of Technical Qualifications using criteria including understanding of project scope, project approach and schedule, experience performing similar projects, qualifications and experience of the proposed project team, and quality assurance practices. The City reserves the right to evaluate responses, waive irregularities, select candidates for more detailed proposals, accept any submittal or portion thereof, reject any or all firms, or cancel the entire process. Selected engineers must maintain comprehensive insurance coverage including Workers' Compensation (statutory limits with $500,000 employer liability minimum), Comprehensive General Liability ($1,000,000 each occurrence/$2,000,000 aggregate), Business Automobile Liability ($1,000,000 each occurrence), Umbrella/Excess Liability ($1,000,000), and Professional Errors and Omissions Insurance ($2,000,000 per claim/$2,000,000 annual aggregate). All inquiries must be submitted to bids@stpetersmo.net with questions due by noon local time on August 17, 2026. The selected engineer must provide an Affidavit of Compliance with the Federal Work Authorization Program and a copy of their E-Verify Memorandum of Understanding.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
City of St. Peters, Missouri One St. Peters Centre Boulevard P. O. Box 9 St. Peters, Missouri 63376
Request for Engineering Service Qualifications
Purpose: The City of St. Peters is seeking proposals from qualified Consulting Engineering Firms to provide professional engineering services for the design of a 20-inch Water Transmission Main Extension (WM-01) and the design for Old Town South Water Main Replacement. This project work is contained in one (1) project grouping.
RFQ No.
RFQ Available:
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement
August 3, 2026
Deadline for Submissions:
2:00 PM local time August 24, 2026 (Non-Public Opening) Late or faxed Qualifications will be rejected.
Submit Qualification To: Purchasing City of St. Peters One St. Peters Centre Blvd.
P. O. Box 9 St. Peters, MO 63376
Special Instructions: • Clearly mark outside of sealed envelope “26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement” along with the Engineer’s name
• One (1) original and one (1) Electronic Copy of your Technical Qualification
• Affidavit of Compliance with the Federal Work Authorization Program
• Copy of your E-Verify Memorandum of Understanding (MOU)
Direct All Inquiries to: bids@stpetersmo.net with “26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement” in the subject line. The last time for questions is before noon local time, August 17, 2026.
mailto:bids@stpetersmo.net
TABLE OF CONTENTS
DESCRIPTION PAGE
Advertisement for Qualifications 1
General Information 2
Appendix A: Draft Agreement 10
Attachment A: Scope of Services 20
Attachment B: Compensation 21
Attachment C: City’s Responsibilities 22
Attachment D: 20-inch Water Extension Overview 23
Attachment E: Old Town South Water Main Replacement Overview 24
Appendix B: Affidavit Enrollment in Federal Work Authorization Program 25
ADVERTISEMENT FOR QUALIFICATIONS
Sealed requests for qualifications regarding 26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement will be received by the City of St.
Peters, Purchasing Department, City Hall, One St. Peters Centre Boulevard, P.O. Box 9, St. Peters, Missouri 63376 until 2:00 PM local time, August 24, 2026. This will be a Non-Public opening.
The RFQ will be available on August 3, 2026, and may be obtained from the City of St. Peters website www.stpetersmo.net/bids.aspx.
All questions regarding this project shall be submitted to the City of St. Peters Purchasing Department in writing to Bids@stpetersmo.net under the subject line “26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement” before noon local time, August 17, 2026.
The City of St. Peters reserves the right to evaluate the responses submitted; waive any irregularities therein; select candidates for the submittal of more detailed or alternate proposals; accept any submittal or portion of submittal; reject any or all firms submitting responses, should it be deemed in the City of Peters best interest; or cancel the entire process and solicit again at a later date. The City will have final decision in all matters regarding acceptance of proposals and issuance of awards.
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 1 http://www.stpetersmo.net/bids.aspx mailto:Bids@stpetersmo.net
GENERAL INFORMATION
FOR ENGINEERING SERVICES
26-183 - 20-INCH WATER TRANSMISSION MAIN EXTENSION DESIGN (WM-01)
AND OLD TOWN SOUTH WATER MAIN REPLACEMENT
1.0 GENERAL
The City of St. Peters is soliciting qualifications for Engineering Services for the design of a 20-inch Water Transmission Main Extension, and the design of the Old Town South Water Main Replacement. This project work is contained in one (1) project grouping. The CITY will select one qualified ENGINEER based on submitted Statements of Qualifications and Proposals to perform all tasks as described in this document. Once an ENGINEER is selected a contract will be negotiated based on a mutually agreed upon scope of services. The CITY has allocated $629,400.00 to this project.
In general, the work consists of the following:
• Design of a new 20-inch transmission main extension to connect existing 20-inch water mains to complete the transmission corridor. This water main will begin at the existing 20-inch main on Jungs Station Road at Winwood Trails Drive, in St. Peters, and extend approximately 7,200 LF to the existing 20-inch transmission main near Hartman Circle and South St Peters Parkway. See Attachment D
• Design to remove and replace approximately 6,000 LF of targeted existing water mains in the Old Town South Subdivision. See Attachment E.
• Provide final design plans, related easement documents, permits and final specifications for the construction of the recommended design plans.
All responses, inquiries, or correspondence relating to, or in reference to, this request, and all reports, charts, displays, schedules, exhibits and other documentation by the respondents received by the City shall be public records subject to disclosure pursuant to Chapter 610, RSMo. The City retains the right to use any or all system ideas presented in any response, whether amended or not. Selection or rejection of the respondent does not affect this right.
2.0 INSTRUCTIONS FOR SUBMITTING QUALIFICATIONS
The ENGINEER shall prepare a Technical Qualification with an estimate of total staff hours required each phase of the project as outlined in Section 6 of this Request for Qualification and further described in Appendix A, (Attachment A) Scope of Services. The ENGINEER shall submit one original and one (1) Electronic copy of the technical qualification in a sealed envelope clearly marked with the ENGINEER’s name and 26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement. The qualification must be received by the City of St. Peters Purchasing Department by 2:00 PM local time, August 24, 2026.
2.1 TECHNICAL QUALIFICATION
The Technical Qualification shall include a schedule of tasks and projected work plan for the project. It shall also include discussions of any proposed modifications, or revisions to the scope of services. The Technical Qualification shall consist of the following information, presented in the order that follows.
1. Transmittal Letter
2. Introduction
3. General Business Information:
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 2
a. Identity of ENGINEER and legal status.
b. Name, address, and telephone number of contact person and person legally authorized to enter into a contract on behalf of the ENGINEER.
c. Description of insurance coverage and deductibles (refer to Section 9 for listing of minimum requirements).
4. Project Understanding - include the following:
a. Provide a statement of the ENGINEER’s understanding of the major challenges and opportunities included in the project, as well as the ENGINEER’s basic ideas for addressing these issues.
5. Qualifications of ENGINEER / Professional Registration:
a. Experience of ENGINEER and project team specifically on similar projects; include the names of clients, brief project description and the project team’s involvement in the project.
b. Describe what expertise the ENGINEER, the project team, and any sub-consultants will bring to the project.
6. Project Approach and Schedule –include the following:
a. Include a listing and description of the major phases or tasks to be performed during the project, and indentify key staff (or sub-consultants) that will be assigned to these phases or tasks.
b. Include an estimate of the hours required to complete the project, categorized by the level of Engineer staff performing the work in each phase.
c. Include an organizational chart for the project, indicating key personnel and their primary responsibilities.
d. Include resumes of the key personnel highlighted on the project organizational chart.
e. Provide a proposed schedule for the project, in calendar days, including earliest anticipated start date, estimated time for completion of tasks and project, and suitable review time.
f. Indicate the location of the office(s) where various project services are to be performed. The level of staffing dedicated to the local office shall be clearly identified.
7. Quality Assurance / Quality and Cost Control:
a. Describe the ENGINEER’s quality assurance/quality control policies and procedures and describe how they will relate to the project.
b. Provide comparisons of original engineering proposal to actual final engineering costs for similar projects that have been constructed in the last 5 years. The ENGINEER may provide justification for any discrepancies that may exist with this information.
c. Provide comparisons of engineer’s cost estimate to actual construction costs for similar projects that have been constructed in the last 5 years. The ENGINEER may provide justification for any discrepancies that may exist with this information.
3.0 ENGINEER SELECTION METHOD
The method of final selection of the ENGINEER for the project will be based upon review of the Technical Qualification conducted by the CITY review committee. The CITY reserves the right to reject any or all qualifications for any reason. The selection process used by the CITY will generally consist of the following:
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 3
1. Review and evaluation of the Technical Qualifications using the following criteria:
• Understanding of project scope.
• Project approach and schedule.
• Experience performing similar projects, including information supplied by references.
• Qualifications and experience of the proposed project team.
• Quality Assurance
• The CITY’s previous experience with the ENGINEER and members of the proposed design team, including technical ability, control of costs, quality of work, availability, ability to meet schedules, and responsiveness, will all be considered in the selection of the ENGINEER.
2. From this review, the CITY will rank each Technical Qualification in order to determine the most qualified ENGINEERS. From this group, the CITY will select the ENGINEER it considers the best qualified for the project and begin negotiations for an engineering services agreement for the project.
3. If the CITY is unable to negotiate a satisfactory contract with the ENGINEER selected for the project, negotiations with that firm shall be terminated. The CITY will then undertake negotiations with the second ranked ENGINEER for the project.
4. If the CITY is unable to negotiate a contract with any of the selected ENGINEERS, the CITY shall reevaluate the necessary services, including the scope and reasonable fee requirements, and again compile a list of qualified ENGINEERS.
5. The final engineering service agreement for the project will be on a “lump sum” basis with a guaranteed maximum limit for all services indicated in the qualification for that project.
4.0 BACKGROUND
20-inch Water Transmission Main Extension Design (WM-01)
The City’s Water Distribution Study Master Plan, completed in 2021, provided recommendations to meet future water resource needs, and identified the extension of an existing 20-inch water transmission main to meet level of service goals. The project includes alignment determination and design of approximately 7,200LF of 20-inch water transmission main, with the goal to use existing right-of-way and easements where possible. The existing 20-inch main located at Jungs Station provides supply from our Joint Venture Booster Pump Station and this new main extension will complete this transmission corridor.
A permanent utility easement has been acquired across the frontage of the Townhomes at Lienemann Park subdivision, located on the south side of Highway 364/South St. Peters Parkway, east of Cinnamon Hills. City crews have installed 27LF of 20-inch PVC under the driveway access (Cinnamon Spice Drive) to be incorporated into the alignment, and to prevent disruption to the access during future construction of the project. See Attachment D
The Consultant shall provide final construction plans and specifications for this extension and should consider items such as valve locations to maximize operational flexibility, temporary water service needs during tie-ins, and other improvements that could improve the system as part of this work.
Old Town South Water Main Replacement
This project area is south of I-70 in the Old Town South Subdivision and is generally including mains along Henry Street to the north, McMenamy to the south, Rainbow Drive and South Gatty Drive. See attachment E. The water mains within this project area were installed starting in 1959, and consist of cast Iron, ductile iron, asbestos cement and unknown material types and sizes ranging from 4-inch to 8-inch diameter. This area of the water distribution system has experienced several water main breaks/failures and the City intends to replace the aging water mains to improve system reliability and reduce future service disruptions.
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 4
The Consultant shall provide final construction plans and specifications for a cost-effective, constructible design with strategies for maintaining water service during construction to minimize disruption to residents. Consultant should consider opportunities to improve the distribution system, to include where appropriate, upsizing, replacing obsolete valves and hydrants, etc.
5.0 CITY OF ST. PETERS RESPONSIBILITIES
The CITY shall provide the following services to assist the ENGINEER:
1. Provide information as to the requirements of the project.
2. Assist the Engineer by providing existing CITY information, records, and reports pertinent to the project.
3. Furnish the Engineer, as required for performance of the services, data prepared by others, which the Engineer may use at their discretion subject to their verification, provided that such data is specifically required to be provided by the CITY.
4. Provide access to and make provisions for the Engineer to enter upon City and other public and private properties required to perform the services. The ENGINEER shall notify the CITY with sufficient advance notice in writing of any request to enter private property so that the CITY may obtain or confirm the existence of appropriate rights of entry.
5. Provide suitable rooms in CITY facilities to the Engineer to conduct progress meetings and workshops.
6. Review all studies, reports, sketches, drawings, specifications, proposals, and other documents presented by the Engineer and render in writing decisions pertaining thereto within reasonable time so as not to delay the service of the Engineer.
7. Endeavor to give notice to the Engineer whenever the City observes or otherwise becomes aware of a defect in the project or changed circumstances; provided however, that the failure of the CITY to provide such notice to the Engineer shall in no way affect the ENGINEER’s obligations under this Agreement, nor shall such failure relieve the ENGINEER from any liability for its failure to discover and correct any such fault, defect, error, omission, or inconsistency.
6.0 ENGINEER’S RESPONSIBILITIES
The ENGINEER shall perform a complete design of a 20-inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacements and provide all necessary information to construct the design plans and shall include the following items as a minimum.
• One set of plans to include all detail sheets with the project areas separated
• Split bid proposal by project
6.1 DESIGN MEMORANDUM
The ENGINEER shall attend a pre-design meeting with CITY staff to discuss in detail the scope of the project.
• After the pre-design meeting, the ENGINEER shall electronically deliver a design memorandum discussing the project. Included within the memorandum shall be budgetary estimates of each component of the design and construction schedules.
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 5
6.2 REVIEW AND CONFIRM EXISTING DATA
The ENGINEER shall review available data and provide a memorandum to CITY outlining the sustainability of the existing data to support the project goals, additional data needs and next steps and anticipated results
6.3 EXISTING CONDITIONS SURVEY
The CONSULTANT shall perform topographic and design surveys as required for the preparation of the design plans and easement plans. Such field surveys shall include, but not be limited to:
• Establish horizontal and vertical control points, suitable for construction of the project.
Tie vertical control to both GPS Monuments and Flood Insurance Study benchmarks.
• Locate all property lines, easements, visible public utilities and contact all utility companies within the project.
• Locate all other pertinent features, as appropriate, to include trees 8” diameter and larger, fences, sheds, etc., within the proposed project corridor.
6.4 PRELIMINARY EVALUATION REPORT AND PRELIMINARY PLAN (30% DESIGN
PLANS)
The CONSULTANT shall submit a project design memorandum that demonstrates the CONSULTANTS’ understanding of the proposed scope of work and preliminary design plans. The plans should be drawn to a horizontal scale of 1” =20’ and a vertical scale of 1” =5’ on 22” x 34” plan sheets. The plans shall include, but not be limited to the following list of items:
• Plan sheets of existing conditions, property lines, and proposed conceptual improvements for the priorities.
• Location of all utilities, existing easements and property lines. Include names of property owners, parcel addresses, and the Book/Page numbers on which their deed is recorded.
• The CONSULTANT shall perform a design to include, but not limited to, conceptual alignment, route selection, any major utility conflicts identified, conceptual hydraulic analysis, approximate limits of construction and identification of necessary easements, and opinion of probable construction costs.
• CONSULTANT shall assist CITY with coordination with any regulatory agencies.
6.5 60% DESIGN PLANS AND EASEMENT PLANS
After approval of the preliminary plans by the CITY, the CONSULTANT shall proceed with 60% design plans to include temporary and permanent easement plans which shall accurately describe all necessary easements for the project. The CONSULTANT shall submit for review and comment; submittal shall include updated construction cost estimate.
The plans shall include, but not be limited to:
• Plan sheets of existing conditions, property lines, utilities, construction limits, existing easements, proposed temporary and permanent easements, and proposed water main alignments, components, and improvements required for this project. Include names of property owners, parcel addresses, and the Book/Page numbers on which their deed is recorded.
• Developing 60% Design Specifications
• Metes and bounds descriptions and exhibits of all proposed temporary and permanent easements (electronically submitted to CITY).
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 6
• CONSULTANT shall submit all drawings, specifications and permit application to the Missouri Department of Natural Resources as required for any permit approvals.
6.6 90% FINAL PLANS AND SPECIFICATIONS
Based on the approved preliminary plans and easement plans, the CONSULTANT shall prepare 90% Final Plans and Specifications. This submittal shall include, at a minimum:
• Full set of construction drawings, including summary of quantities, plan sheets, standard details, cross-sections, restoration details, and easement sheets.
• Final Construction Cost Estimate.
• Complete set of technical specifications and bid documents, using the City’s standard construction document page.
6.7 FINAL ISSUE FOR CONSTRUCTION PLANS, SPECIFICATIONS, AND BID
DOCUMENTS
After approval of the 90% Final plans, the ENGINEER shall prepare one set of 22”x34” paper final construction plans, and electronic copies of all plan sheet files, all legal descriptions, exhibits, specifications, manuals, and bid documents.
6.8 BID PHASE SERVICES
The ENGINEER shall include hours in the scope of work to assist the CITY during the bid phase of the project. Scope to include but not be limited to the following services as needed: response to contractor bid questions and bid alternative submittal analysis.
7.0 TENTATIVE SCHEDULE
The following is a tentative design schedule for this project, any variance from this schedule shall be discussed in the ENGINEER’s Project Approach.
Issue Request for Proposals August 3, 2026 Receive Proposals August 24, 2026 Interviews (if necessary) Week of September 1, 2026 Award Contract October 2026 Project Startup Meeting November 9, 2026 Preliminary Submittal January 2027 60% Submittal Apri 2027 90% Submittal July 2027 Final Plans and Specifications August 2027
8.0 INVOICING
The ENGINEER shall present an invoice to the CITY’s Accounts Payable Department with each required submittal for services rendered and expenses resulting there from. The invoice shall include the following information:
1. Submittal record.
2. Description of services provided to date.
3. Description of services pending.
4. Amount of basic services fee.
5. Amount of optional services fee.
6. Total Amount.
Additional invoicing and payment information can be found in the Sample Agreement
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 7
9.0 INSURANCE REQUIREMENTS
ENGINEER shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property, which may arise from or in connection with the performance of the work hereunder by the ENGINEER, his agents, representatives, employees or subcontractors, including those insurance coverages set forth below. All such insurance policies shall name the CITY as an additional insured with the exception of the Workers’ Compensation/Employer’s Liability Policy and Professional Errors and Omissions Insurance, with a subrogation waiver on all policies except Professional Liability. Each insurance policy required by this clause shall be endorsed to state that coverage shall not be suspended, voided, cancelled by either party, except after thirty (30) days prior written notice by certified mail, return receipt requested, or by such other method approved by the CITY, has been given to the CITY. The cost of such insurance shall be included in the ENGINEER’S proposal.
9.1 MINIMUM LIMITS OF INSURANCE
ENGINEER shall maintain limits no less than:
1. Workers’ Compensation for statutory limits and Employer’s Liability minimum $500,000 limit.
2. Comprehensive General Liability to cover claims which may arise from operations under this contract. The policy shall include, but not be limited to, protection for the following hazards:
a. Premises and Operations-Bodily Injury and Property Damage Liability
b. Independent Contractors Coverage
c. Products & Completed Operations liability coverage
d. Personal Injury/Advertising Injury Liability
e. Broad Form Property Damage
f. Contractual Liability
g. Explosion, collapse and underground damage, if applicable
The above policy shall be written with limits of at least $1,000,000 each occurrence and $2,000,000 aggregate.
3. Business Automobile Policy (Comprehensive Automobile Liability Insurance) provides coverage for all owned, non-owned and hired vehicles. Minimum limits should be at least $1,000,000 Each Occurrence Bodily Injury Liability and Property Damage Liability.
4. Umbrella/Excess Liability – Limit of $1,000,000 which will be excess f the primary limits for General Liability, Auto Liability and Employer Liability.
5. Professional Errors and Omissions Insurance: If CONSULTANT is an architect, engineer, surveyor, ENGINEER agrees to obtain Professional Errors and Omissions Insurance. ENGINEER shall also require all professional subcontractors to obtain and maintain similar insurance with similar limits in connection with subcontracted work. Limit of Liability should be no less than $2,000,000 Per Claim/$2,000,000 Annual Aggregate.
9.2 DEDUCTIBLES AND SELF-INSURED RETENTIONS
Any deductibles or self-insured retentions must be declared to and approved by the CITY. At the option of the CITY, either; the insurer shall reduce or eliminate such deductibles or self-insured retentions as respects the City, its officers, officials and employees; or the ENGINEER shall procure a bond guaranteeing payment of losses and related investigations, claim administrative and defense expense.
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 8
9.3 OTHER INSURANCE PROVISIONS
The ENGINEER shall also obtain and pay for insurance policies that contain, or are endorsed to contain, the following provisions:
1. ENGINEER'S Contingent or Protective Liability and Property Damage to protect the ENGINEER from any and all claims arising from the operations of subconsultant employed by the ENGINEER.
2. The coverage shall be for a minimum of $2,000,000 unless otherwise stated in the Contract Documents, and shall contain no special limitations on the scope of protection afforded to the CITY, its officers, officials, employees or volunteers.
3. The ENGINEER’s insurance coverage SHALL BE PRIMARY INSURANCE as respects the CITY, its officers, officials, employees and volunteers. Any insurance or self-insurance maintained by the CITY, its officers, officials, employees or volunteers shall be excess of the ENGINEER’s insurance and shall not contribute with it.
4. Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the CITY, its officers, officials, employees or volunteers.
5. The ENGINEER's insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the limits of the insurer's liability.
9.4 ACCEPTABILITY OF INSURERS
Insurance is to be placed with insurers with a Bests' rating of no less than A:VI.
9.5 VERIFICATION OF COVERAGE
ENGINEER shall furnish the CITY with certificates of insurance. The certificates for each insurance policy are to be signed by a person authorized by that insurer to bind coverage on its behalf, and are to be received and approved by the CITY before work commences. The CITY reserves the right to require complete, certified copies of all required insurance policies, at any time.
9.6 SUBCONSULTANTS
ENGINEER shall include all subconsultants as insureds under its policies or shall furnish separate certificates of each subconsultant. All coverages for subconsultants shall be subject to all of the requirements stated herein.
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 9
APPENDIX A
AGREEMENT FOR ENGINEERING SERVICES
26-183 - 20-INCH WATER TRANSMISSION MAIN EXTENSION DESIGN (WM-01) AND OLD
TOWN SOUTH WATER MAIN REPLACEMENT
This Agreement, entered into in the City of St. Peters, County of St. Charles, State of Missouri this day of _________, is by and between the City of St. Peters, Missouri, a Missouri municipal corporation, hereinafter referred to as CITY, and INSERT NAME., a Missouri corporation, hereinafter referred to as ENGINEER.
WITNESSETH:
WHEREAS, the CITY is seeking professional and technical services to complete 26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement (the PROJECT); and
WHEREAS, the ENGINEER has submitted a proposal to provide professional and technical services, and
WHEREAS, the CITY and the ENGINEER have held subsequent meetings after the submittal of the proposal to define the terms and conditions of such professional and technical services, which terms and conditions are specified herein.
NOW THEREFORE, in consideration of the foregoing recitals and the terms and conditions of such professional and technical services, which terms and conditions are specified herein.
ARTICLE 1 – GENERAL
The ENGINEER shall serve as the CITY’S professional and technical representative in providing professional engineering services for the PROJECT and shall also provide consultation and advice to the CITY during the performance of these services.
ARTICLE 2 – DEFINITIONS
The meaning and intent of the following terms in this Agreement shall be as follows:
2.1 COST: Includes direct labor expense, plus a percentage of direct labor expense for total indirect costs, plus other direct costs at actual out-of-pocket expense.
2.2 DIRECT LABOR EXPENSE: Includes the direct compensation payable to employees for time specifically chargeable to the PROJECT, with the average hourly labor rate being the annual direct compensation divided by 2,080.
2.3 FIXED FEE: A dollar amount to compensate the ENGINEER for contingencies, interest on invested capital, professional expertise, readiness to serve, risk management, other non-reimbursable costs, and profit. The amount varies with the complexity and size of a given project and the scope of the engineering services required. The fee shall be calculated as a percentage of the total initial contractual sum of direct labor expenses, other direct costs and total indirect costs chargeable to the PROJECT.
2.4 OTHER DIRECT COSTS: Includes such items as subcontract expenses, computer run time and CADD charges, special equipment rental, special material purchases, reproduction costs, mileage, traveling expenses, and living costs for personnel on assignment away from their home office, and other incidental expenses directly chargeable to the PROJECT, charged at actual cost to the ENGINEER.
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 10
2.5 TOTAL INDIRECT COSTS: Includes labor overhead and general and administration overhead costs. Overhead expenses shall also include costs of all required insurance, including professional liability coverage for the project. Labor overhead includes allowances for sick leave, vacation and holiday, plus unemployment, excise and other payroll taxes; and statutory and usual contributions for Social Security; Worker's Compensation Insurance, retirement benefits, and medical and other insurance benefits. General and administrative overhead costs shall include costs of preparing proposals for the PROJECT and also consist of costs not directly identifiable with any specific project and include allowable general corporate overhead such as office rent, accounting and insurances. The provisional rate for total indirect costs indicated in the attached proposal is for use during the performance of this contract. The provisional rate may be revised by mutual consent of the parties if such a rate varies significantly from the actual rate experienced during the period of performance under this Agreement.
ARTICLE 3 - SERVICES TO BE PERFORMED BY ENGINEER
ENGINEER shall perform the Services described in Attachment A, Scope of Services. ENGINEER shall have no liability for defects in the Services attributable to ENGINEER'S reliance upon or use of data, design criteria, drawings, specifications, or other information that the City is required to furnish under this Agreement; provided that such reliance is reasonable and not a breach of any contractual obligation, warranty or standard of care under this Agreement.
ARTICLE 4 - COMPENSATION
CITY shall pay ENGINEER the amounts stated in Attachment B, Compensation, subject to a 5% retention until satisfactory final completion of the Services. Prices quoted are firm for the duration of the Project. CITY shall not be liable for any taxes assessed against the ENGINEER’s income.
Requests for progress payments for services rendered will be made by the ENGINEER monthly as the work progresses by the ENGINEER submitting a correctly detailed invoice for work performed prior to the request for payment, along with all other required submittals, all in accordance with the terms of this Agreement.
All invoices, payroll records, supporting documentation, and payment certifications shall be submitted to the Accounts Payable Department, City Hall, One St. Peters Centre Blvd., P O Box 9, St. Peters, Missouri 63376 who will forward to the Project Manager (the CITY staff official in charge of the Project). For purposes of payment, the ENGINEER’s invoices and requests for payment shall be deemed to be duly delivered to the CITY ten days after the CITY’s Project Manager certifies to the CITY Accounts Payable Department that the invoice is for a correct amount, was properly submitted in accordance with the contract documents, and that all required and necessary supporting documents required by the contract or requested by the CITY have been submitted by the ENGINEER to support the invoice.
The CITY’s Project Manager shall act on the ENGINEER’s payment request by either:
a. Approving the request for payment as submitted
b. Approving a lesser amount that the Project Manager determines is due the
ENGINEER, informing the ENGINEER in writing of his reasons for approving the amended amount.
c. Rejecting the request for payment, informing the ENGINEER in writing of his reasons for rejecting it.
If there are errors in the invoice, it is not for a proper amount, additional supporting information is required by the CITY, or there are other defects in the invoice, the CITY’s Project Manager shall return the invoice to the ENGINEER with a request to correct the errors. The invoice will not be deemed to be duly delivered until the errors are corrected, additional requested information is supplied, and the City staff official in charge of the Project certifies to the CITY Accounts Payable Department that the invoice is for a correct amount, was properly submitted in accordance with the
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 11 contract documents, and that all required and necessary supporting documents required by the contract or requested by the CITY have been submitted by the ENGINEER to support the invoice.
Within thirty (30) calendar days from the date that the ENGINEER’s invoice or amended invoice is duly delivered to the CITY, the CITY shall either:
a. Pay the request for payment as certified by the CITY’s Project Manager.
b. Pay such other amount as the CITY determines is actually due the ENGINEER, informing the ENGINEER and the Project Manager in writing of his reasons for paying the amended amount.
c. Reject the invoice and inform the ENGINEER and the Project Manager in writing of the reasons for rejecting the invoice.
The City may withhold payment in whole or in part on a request for payment or invoice because of, but not limited to, the following reasons, even if such reasons are discovered subsequent to approval of a request for payment by the CITY’s Project Manager or the CITY.
a. Defective work or material not remedied.
b. Evidence indicating the probable filing of claims by other parties against the
ENGINEER or against the CITY because of the ENGINEER’s work.
c. Failure of the ENGINEER to make payments to subcontractors, consultants, material suppliers, or labor.
d. Damage to the CITY’s or another’s property or work.
e. Unsatisfactory job progress;
f. Disputed work;
g. Failure to comply with any material provision of the contract;
h. Reasonable evidence that a subcontractor, consultant, or material supplier cannot be fully compensated under its contract with the ENGINEER for the unpaid balance of the contract sum;
i. Citation by the enforcing authority for acts of the ENGINEER or its consultants or subcontractors that do not comply with any material provision of the contract or that result in a violation of any federal, state or local law, regulation or ordinance applicable to that Project causing additional costs, delays, or damages to the CITY;
j. Funds from a State grant are not timely received by the CITY;
k. Failure to fulfill any condition precedent to payment;
l. Failure to provide all appropriate, requested, or required documentation and certifications in complete and acceptable form; or
m. Any other cause or reason permitted by law.
Only properly submitted invoices for valid charges will become due and payable.
The ENGINEER may submit an invoice at substantial completion of the Services requesting that the CITY pay ninety-eight percent of the retainage, less any offsets or deductions authorized in this Agreement or otherwise authorized by law. “Substantial Completion” means that point where all of the Services have been performed and accepted by the CITY except for the delivery of the completed final product. If the CITY determines the work is not substantially completed and accepted, then the CITY shall provide a written explanation of why the work is not considered substantially completed and accepted within fourteen calendar days of the date that the substantial completion invoice is duly delivered to the CITY. If there are any remaining minor items to be completed at substantial completion, an amount equal to one hundred fifty percent (150%) of the value of each item as determined by the CITY shall be withheld until such items are fully and finally completed.
The ENGINEER may submit a final invoice upon the satisfactory completion of all the Services required by this Agreement. The CITY shall make final payment of all moneys owed to the ENGINEER, including any retainage withheld under this Agreement, less any offsets or deductions
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 12 authorized in the contract or otherwise authorized by law, within thirty days of the due date. The final payment due date shall be the date of the earliest of the following events:
a. Completion of the Project and filing with the CITY of all required documentation and certifications, in complete and acceptable form, in accordance with the terms and conditions of the contract;
b. The Project is certified by the CITY as having been completed, including the filing of all documentation and certifications required by the contract, in complete and acceptable form.
As part of the documentation and certifications required for final payment, the ENGINEER must also provide to the CITY the following:
a. Written certification and verification by the ENGINEER and any consultants and subcontractors that the ENGINEER has made all payments to any subconsultants or subcontractors used to complete the Project and there are no outstanding claims by or against them;
b. Certification from the CITY’s Project Manager that the Project is fully and finally complete with no other work remaining to be performed, and no claims arising from or related to the ENGINEER’s Services are outstanding;
c. Certification from the CITY’s Project Manager that the final invoice is for the proper amount; and
d. All funds from state or federal sources for the Project have been received by the
CITY.
No additional services or overtime services shall be payable by the CITY unless the CITY has approved them in writing as an Amendment as additional services for an additional fee before those services are provided. Any adjustments to the rates and amounts of ENGINEER's compensation shall be negotiated in good faith. CITY agrees to pay for such additional services or extra work only if the Engineer specifies it as extra work to be performed for an extra fee in advance of the work being formed. No request for payment for extra work shall be valid unless it has been accepted in compliance with RSMo. §432.070. The CITY shall not be obligated to pay any sums beyond the stated not-to-exceed price unless the CITY agrees to do so after the execution of this Agreement in compliance with RSMo. §432.070.
ARTICLE 5 - CITY'S RESPONSIBILITIES
CITY shall be responsible for all matters described in Attachment C, City's Responsibilities. CITY shall not be responsible for discovering deficiencies in the technical accuracy of Engineer's services. Engineer shall correct deficiencies in its Services without compensation, unless such corrective action is directly attributable to deficiencies in CITY-furnished information.
ARTICLE 6 – INSURANCE REQUIREMENTS
ENGINEER shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to property, which may arise from or in connection with the performance of the work hereunder by the ENGINEER, his agents, representatives, employees or subcontractors, including those insurance coverages set forth below. All such insurance policies shall name the CITY as an additional insured with the exception of the Workers’ Compensation/Employer’s Liability Policy and Professional Errors and Omissions Insurance, with a subrogation waiver on all policies except Professional Liability. Each insurance policy required by this clause shall be endorsed to state that coverage shall not be suspended, voided, cancelled by either party, except after thirty (30) days prior written notice by certified mail, return receipt requested, or by such other method approved by the CITY, has been given to the CITY. The cost of such insurance shall be included in the ENGINEER’S proposal.
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 13
6.1 MINIMUM LIMITS OF INSURANCE
ENGINEER shall maintain limits no less than:
1. Workers’ Compensation for statutory limits and Employer’s Liability minimum $500,000 limit.
2. Comprehensive General Liability to cover claims which may arise from operations under this contract. The policy shall include, but not be limited to, protection for the following hazards:
a. Premises and Operations-Bodily Injury and Property Damage Liability
b. Independent Contractors Coverage
c. Products & Completed Operations liability coverage
d. Personal Injury/Advertising Injury Liability
e. Broad Form Property Damage
f. Contractual Liability
g. Explosion, collapse and underground damage, if applicable
The above policy shall be written with limits of at least $1,000,000 each occurrence and $2,000,000 aggregate.
3. Business Automobile Policy (Comprehensive Automobile Liability Insurance) provides coverage for all owned, non-owned and hired vehicles. Minimum limits should be at least $1,000,000 Each Occurrence Bodily Injury Liability and Property Damage Liability.
4. Umbrella/Excess Liability – Limit of $1,000,000 which will be excess f the primary limits for General Liability, Auto Liability and Employer Liability.
5. Professional Errors and Omissions Insurance: If ENGINEER is an architect, engineer, surveyor, or consultant, ENGINEER agrees to obtain Professional Errors and Omissions Insurance. ENGINEER shall also require all professional subcontractors to obtain and maintain similar insurance with similar limits in connection with subcontracted work. Limit of Liability should be no less than $2,000,000 Per Claim/$2,000,000 Annual Aggregate.
6.2 DEDUCTIBLES AND SELF-INSURED RETENTIONS
Any deductibles or self-insured retentions must be declared to and approved by the CITY. At the option of the CITY, either; the insurer shall reduce or eliminate such deductibles or self-insured retentions as respects the City, its officers, officials and employees; or the ENGINEER shall procure a bond guaranteeing payment of losses and related investigations, claim administrative and defense expense.
6.3 OTHER INSURANCE PROVISIONS
The ENGINEER shall also obtain and pay for insurance policies that contain, or are endorsed to contain, the following provisions:
1. ENGINEER'S Contingent or Protective Liability and Property Damage to protect the ENGINEER from any and all claims arising from the operations of subconsultant employed by the ENGINEER.
2. The coverage shall be for a minimum of $2,000,000 unless otherwise stated in the Contract Documents, and shall contain no special limitations on the scope of protection afforded to the CITY, its officers, officials, employees or volunteers.
3. The ENGINEER’s insurance coverage SHALL BE PRIMARY INSURANCE as respects the CITY, its officers, officials, employees and volunteers. Any insurance or
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 14 self-insurance maintained by the CITY, its officers, officials, employees or volunteers shall be excess of the ENGINEER’s insurance and shall not contribute with it.
4. Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the CITY, its officers, officials, employees or volunteers.
5. The ENGINEER's insurance shall apply separately to each insured against whom claim is made or suit is brought, except with respect to the limits of the insurer's liability.
6.4 ACCEPTABILITY OF INSURERS
Insurance is to be placed with insurers with a Bests' rating of no less than A:VI.
6.5 VERIFICATION OF COVERAGE
ENGINEER shall furnish the CITY with certificates of insurance. The certificates for each insurance policy are to be signed by a person authorized by that insurer to bind coverage on its behalf, and are to be received and approved by the CITY before work commences. The CITY reserves the right to require complete, certified copies of all required insurance policies, at any time.
6.6 SUBCONSULTANTS
ENGINEER shall include all subconsultants as insureds under its policies or shall furnish separate certificates of each subconsultant. All coverages for subconsultants shall be subject to all of the requirements stated herein.
ARTICLE 7 – COVENANT AGAINST CONTINGENT FEES
The ENGINEER warrants that they have not employed or retained any company or person, other than a bonafide employee working for their company, to solicit or secure this contract, and that they have not paid or agreed to pay any company or person, other than a bonafide employee, any fee, commission, percentage, brokerage fee, gift, or any other consideration, contingent upon or resulting from the award or making of this contract. For breach or violation of this warranty, the CITY shall have the right to rescind this contract without liability.
ARTICLE 8 – INTELLECTUAL PROPERTY -- OWNERSHIP OF DOCUMENTS -- REUSE OF
DOCUMENTS
All original documents, studies, drawings, maps and plans prepared by the ENGINEER for the project , and all right, title and interest, including all rights under federal and state copyright and intellectual property laws in the drawings, specifications, reports, plans, analyses, and other documents prepared by the ENGINEER for this Project (collectively, "Instruments of Service") and the electronic methods of reproducing such documents are hereby conveyed, assigned and transferred by ENGINEER and its consultants to CITY and shall be deemed to be the property of the CITY. CITY shall retain legal title to such Instruments of Service, whether or not the Project for which they may be made is completed. No further compensation shall be due to ENGINEER for CITY's use of the Instruments of Service, whether during performance of this Agreement or after is termination or completion. All Instruments of Service, including services in electronic form, shall be furnished to CITY in a format requested by CITY, including electronic format.
Any reuse without prior written verification or adaptation by ENGINEER for the specific purpose intended will be at CITY's sole risk and without liability or legal exposure to Engineer.
Because of the potential degradation of electronic medium over time, in the event of a conflict between the sealed original drawings/hard copies and the electronic files, the sealed drawings/hard copies will govern.
26-183 - 20-Inch Water Transmission Main Extension Design (WM-01) and Old Town South Water Main Replacement 15
If ENGINEER will be preparing, drafting, displaying, reproducing, or otherwise using, in any manner or form, any information, document, or material that is subject to a copyright, trademark, patent, or other property or privacy right, then ENGINEER must: Obtain all necessary licenses, authorizations, and approvals related to its use; include the CITY in any approval, authorization, or license related to its use; and indemnify and hold harmless the CITY related to ENGINEER’s alleged infringing or otherwise improper or unauthorized use. Accordingly, the ENGINEER must protect, indemnify, and hold harmless the CITY from and against all liabilities, actions, damages, claims, demands, judgments, losses, costs, expenses, suits, or actions, and attorneys’ fees and the costs of the defense of the CITY, in any suit, including appeals, based upon or arising out of any allegation of infringement, violation, unauthorized use, or conversion of any patent, copyright, trademark or trade name, license, proprietary right, or other related property or privacy interest in connection with, or as a result of, this contract or the performance by the ENGINEER of any of its activities or obligations under this Agreement.
ARTICLE 9 – INDEMNIFICATION
ENGINEER shall indemnify, defend, and save and hold harmless the CITY, its officers, agents and employees from any and all liability, claims, suits, demands, actions, damages and expenses (including reasonable attorney fees) of whatsoever kind and by whomsoever brought against the CITY, it officers, agents and employees, arising from, relating to, or in connection with any breach of this Agreement, any willful or negligent act, or error or omission of ENGINEER or ENGINEER’s employees, consultants, subcontractors, or agents in the performance of this Agreement. This requirement shall be included in all of the ENGINEER’s subcontract and consultant agreements.
Notwithstanding any other provisions of this Agreement, the CITY reserves…