Department of Energy Western Area Power Administration
Rocky Mountain Customer Service Region
P.O. Box 3700
Loveland, CO 80539-3003
23 December 2021 Two-Step Sealed Bid Solicitation:
Estes-Pole Hill-Flatiron 115-kV Double Circuit Rebuild Step One: Request for Technical Proposals (RFTP)
Government Furnished Cover Sheet for Each Submitted Project
Project Title: ___________________________________________________________
Project Completion Date: _________________________________________________
Project Submission meets the following Step one evaluation criteria technical factors (check below):
______ Factor 1 – Provide evidence of the installation of a minimum of thirty, 115-kV or above, multi-section, steel monopole transmission line structures. For example, provide two (2) successfully completed projects to include the following for each project, 1) project specifications and plan and profile drawings (showing >30 115-kV or above monopole structures) and 2) structure drawings (showing multi-section steel monopoles).
Evidence of satisfying Factor 1 provided in the form of (list type of evidence and page location within proposal submission):
_______Factor 2 – Provide evidence of the installation (prime contractor or subcontractor) of a minimum of thirty concrete foundations (drilled foundations greater than five feet in diameter or micropile foundations) using drilling methods in rock (including slightly weathered or slightly fractured rock up to strong/very strong rock, in accordance with definitions in RFTP). For example, provide data for two (2) successfully completed projects to include the following for each project, 1) construction documents (showing >30 foundations), 2) correlating foundation drawings (showing >5ft diameter), 3) respective geotechnical surveys (showing rock), and any other information to correlate the foundation location with the survey information provided.
Evidence of satisfying Factor 2 provided in the form of (list type of evidence and page location within proposal submission):
_______Factor 3 – Provide evidence of the installation of transmission line conductor (115-kV or above) with a minimum elevation change of 2,000 feet on a single line section not to exceed 15 miles. For example, provide data for two (2) successfully completed projects to include the following for each project 1) plan and profile drawings and project specifications to show stringing of a transmission line from 5,000 to 7,000 ft elevation over 15 (or fewer) miles.
Evidence of satisfying Factor 3 provided in the form of (list type of evidence and page location within proposal submission):