| File | Type | Posted |
|---|---|---|
| 45 BIB WB 0801 Info Book.pdf | ||
| 1- 23Q0101 - RFQ - Barge Overhaul Attachment 1.doc | DOC document | |
| 4 - Site_Walk_List_ID_Proofing_Documents.pdf | ||
| 3 - SECNAV_5512_1 APPROVED PASS ID FORM C350(1).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
THE INTENT OF THIS PROPOSED SCOPE OF WORK IS TO PROVIDE ENGINEERING AND DESIGN SERVICES TO PORTSMOUTH NAVAL SHIPYARD FOR THE DEVELOPMENT OF A REPAIR/MODIFICATION WORK PACKAGE FOR NAVY WORK BOAT WB-0801.
PROVIDE WRITTEN WORK SPECIFICATION ITEMS, FORMATTED IAW NAVSEA JFMM APPENDIX 4E, DESIGNS, MATERIAL LISTS, AND ENGINEERING DRAWINGS TO NAVSEA TECHNICAL SPECIFICATION 9090-600, FOR WB-0801, LOCATED AT PORTSMOUTH NAVAL SHIPYARD, KITTERY, ME.
DRAWINGS SHOULD BE DEVELOPED USING IDEAS TYPE LAYERING STANDARDS USING AUTOCAD RELEASE 13 OR HIGHER.
THE WRITTEN ITEMS, ASSOCIATED DRAWINGS, AND MATERIAL LISTS, WILL BE USED TO EXECUTE A “DEPOT LEVEL” SHIPYARD AVAILABILITY ON WB-0801. A SHIP-CHECK IS REQUIRED, AND WILL BE COORDINATED THROUGH THE PORTSMOUTH NAVAL SHIPYARD PORT OPERATIONS CHIEF ENGINEER.
PROVIDE A CLASS “C” COST ESTIMATE FOR EACH ITEM, IAW NAVSEA JFMM VOL VII, CHAP 5.
THE OFFEROR SHALL HAVE AT LEAST 5 YEARS OF EXPERIENCE WITH THE DESIGN AND ENGINEERING ON US NAVY SERVICE CRAFT INCLUDING THE SIZING, EQUIPMENT SELECTION AND INTERFACE OF EXISTING SYSTEMS ON THE BOATS.
THE OFFEROR SHALL PUBLISH ALL COMPLETED ITEMS TO THE NAVY MAINTENANCE DATABASE RE-PLATFORM (NMDR).
THE VESSEL IS LOCATED AT PORTSMOUTH NAVAL SHIPYARD, KITTERY, ME. THE FOLLOWING IS A LIST OF ITEMS THAT REQUIRE WORK ITEMS, AND/OR DRAWINGS:
1. HAZARDOUS WASTE PRODUCED ON NAVAL VESSELS; CONTROL
2. UNDERWATER HULL; INSPECT AND REPAIR
3. FUEL OIL TANKS; INSPECT AND PRESERVE
4. POTABLE WATER TANK; INSPECT AND PRESERVE
5. MAIN DECK PLATING; INSPECT
6. PROPELLER SHAFTING; REMOVE, INSPECT, AND REINSTALL/ALIGN
7. PROPELLERS; INSPECT AND REPAIR
8. MAIN ENGINE SEAWATER STRAINER AND PIPING; INSPECT AND REPAIR
9. FIRE PUMP DRIVE SYSTEM; FABRICATE GEAR, REPLACE AND ALIGN
10. HYDRAULIC STEERING SYSTEM PIPING/VALVES; RECONFIGURE
11. PORT AND STARBOARD RUDDERS; INSPECT AND REPAIR
12. RUBBER FENDER SYSTEM; INSPECT, REPAIR. ADD FENDER MATERIAL FWD GUNWALE
13. INTERIOR PRESERVATION; ACCOMPLISH
14. UNDERWATER HULL, FREEBOARD AND PILOTHOUSE PRESERVATION; ACCOMPLISH
15. HULL ZINC ANODES; REPLACE
16. EXTERIOR DECK/NON-SKID PRESERVATION; ACCOMPLISH
17. NAVIGATION/COMMUNICATIONS PACKAGE; UPGRADE
18. CABIN FANS; REPLACE
19. EXTERIOR/NAVIGATION LIGHTING; UPGRADE
20. ENGINE FLOC SYSTEM; REPAIR
21. ENGINE EXHAUST SYSTEM; INSPECT AND REPAIR
22. HYDRAULIC WINCH/CONTROLS; INSPECT AND REPAIR
23. STEERING SYSTEM; INSPECT AND REPAIR
24. HVAC SYSTEM; INSPECT AND REPAIR
25. MARINE SANITATION/SEWAGE SYSTEM; INSPECT AND REPAIR
26. 12/24V ELECTRICAL SYSTEM; INSPECT AND REPAIR
27. FIRE MONITOR SYSTEM; INSPECT AND REPAIR
28. TEMPORARY SERVICES; PROVIDE
29. CLEANING AND PUMPING; ACCOMPLISH
30. HAUL OUT/LAUNCHING; ACCOMPLISH
31. TOWING OR OVERLAND TRANSPORTATION; ACCOMPLISH
BASIC SCOPE OF SERVICES
TASK 2: DELIVERABLES
1. SHIPCHECK REPORT
2. WORK ITEMS, INCLUDING CLASS “C” COST ESTIMATE
3. 2-KILO PACKAGE
4. GUIDANCE SHIPCHECK SKETCHES/DRAWINGS FOR WORK ITEMS WHERE REQUIRED
5. PUBLISH ALL WORK ITEMS, IN JFFM 4E FORMAT TO NMDR.
TASK 1: SHIPCHECK
CONDUCT A SHIPCHECK OF THE VESSEL AND GATHER INFORMATION FOR THE DEVELOPMENT OF THE OVERHAUL PACKAGE. THE INFORMATION GATHERED SHALL INCLUDE THE FOLLOWING:
1. PERFORM A VISUAL INSPECTION OF THE CRAFT WITH THE SUPERVISOR AND OR CRAFT REPRESENTATIVE. CHECK THE ENTIRE ACCESSIBLE HULL, DECK FITTINGS, DECK PLATING, RAILS, STANCHIONS AND LIFE LINES, FENDERS, DECK COATINGS INCLUDING EXISTING PRESERVATION SYSTEMS, LOOSE COATINGS, AND CONDITION OF DECK PLATING, CHOCKS, BITTS, CLEATS, FOUNDATIONS, BULWARK AND DECK PLATING. NOTE AREAS OF CORROSION, EROSION, EVIDENCE OF STRUCTURAL DEFECTS AND DAMAGE. OBTAIN “AS BUILT” AND OTHER REFERENCE DRAWINGS OR DOCUMENTS TO BE USED DURING PACKAGE DEVELOPMENT. CHECK HULL, MECHANICAL, ELECTRICAL SYSTEMS.
2. CONDUCT A MEETING WITH THE SUPERVISOR OR CRAFT REPRESENTATIVE TO COLLECT DATA AND OBTAIN INFORMATION FOR THE DEVELOPMENT OF TOWING, DRY DOCK, CLEANING AND BLASTING OF HULL, UT INSPECTION, TEMPORARY SERVICES, CLEANING AND PUMPING, CLEAN, PAINT AND PRESERVE AND ZINC REPLACEMENT WORK ITEMS. DISCUSS WITH CRAFT REPRESENTATIVE AMOUNTS OF FRONT LOADS FOR PLATING AND STIFFENER REPLACEMENTS TO PUT IN WORK ITEMS BASED ON HISTORICAL KNOWLEDGE. OBTAIN INFORMATION FOR THE DEVELOPMENT OF HULL, MECHANICAL, AND ELECTRICAL WORK ITEMS. DETERMINE IF 3, 7 OR 12 YEAR SERVICE LIFE PAINT SYSTEM IS WHAT IS APPROPRIATE FOR UNDERWATER HULL.
TASK 2: DELIVERABLES
1. SHIPCHECK REPORT.
2. WORK ITEMS, INCLUDES CLASS “C” COST ESTIMATE.
3. 2-KILO PACKAGE.
4. GUIDANCE SHIPCHECK SKETCHES/DRAWINGS FOR WORK ITEMS WHERE REQUIRED.
5. PUBLISH ALL WORK ITEMS, IN JFFM 4E FORMAT TO NMDR.