This document is an Alaska IIJA Legacy Tracker Contract Projects report from the Alaska Native Tribal Health Consortium, detailing infrastructure improvement projects across Alaska Native communities funded through the Infrastructure Investment and Jobs Act. The tracker lists 57 water, sewer, and solid waste infrastructure projects across various Alaska Native villages and communities, with project values ranging from under $1 million to over $10 million. Projects include comprehensive piped water and sewer systems, water treatment plant repairs and replacements, solid waste site improvements, landfill construction, backup generator installations, and connections to unserved homes. The anticipated project timelines span from FY24 to FY35, with most projects scheduled to begin between FY24 and FY26 and conclude between FY28 and FY34.
Project values are categorized into four tiers: under $1 million (9 projects), under $5 million (16 projects), under $10 million (24 projects), and over $10 million (8 projects). The largest infrastructure investments include comprehensive piped systems for communities like Allakaket, Little Diomede, Shishmaref, Tetlin, and Venetie, each valued at over $10 million with multi-year implementation periods extending into the 2030s. The funding appears to be federal infrastructure investment directed toward addressing critical water, wastewater, and solid waste infrastructure needs in rural Alaska Native communities, representing a significant long-term commitment to improving basic utilities and public health infrastructure in remote areas of Alaska.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-Upcoming Contracts Flyer - AGC 4-2024.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMUNITY PROJECT VALUE ANTICIPATED
START*
ANTICIPATED
END*
Akiak Sewer and Water Reconnection to 6 homes being moved Under $5M FY25 FY30
Allakaket Comprehensive Piped System Over $10M FY24 FY33
Ambler Solid Waste Upgrade Under $1M FY25 FY29
Ambler South Loop Water Replacement Over $10M FY25 FY30
Angoon Water Source Upgrade Under $5M FY25 FY30
Angoon Landfill Improvements Under $1M FY25 FY29
Angoon Water Distribution & Sewer Collection System Replacement Under $10M FY24 FY29
Birch Creek First Service to Five Homes Under $5M FY26 FY31
Brevig Mission Solid Waste Improvements Under $5M FY25 FY29
Chignik Bay Water Source and Transmission Line Under $10M FY25 FY30
Chignik Lagoon Water Distribution Upgrade Under $10M FY25 FY30
Circle First Service to Homes Under $5M FY24 FY28
Eek Water Treatment Plant Foundation Repair Under $5M FY25 FY30
Galena Alexander Loop Water Main Replacement Under $10M FY25 FY30
Galena First Time Water and Sewer Facilities for 16 Homes and Water Main Extension
Under $5M FY25 FY30
Galena Supplemental Ground Water Source Under $5M FY25 FY30
Goodnews Bay Sewer Lagoon Erosion Control Under $1M FY25 FY30
Grayling WTP Backup Generator Under $1M FY25 FY30
Holy Cross WTP Backup Generator Under $1M FY25 FY30
Kiana New Landfill Under $10M FY25 FY29
Kivalina New Solid Waste Site Over $10M FY26 FY30
Koyuk Water and Sewer Connections Under $5M FY24 FY28
Kwethluk Raw Water Intake Under $5M FY25 FY30
Lime Village Solid Waste Improvements Under $1M FY25 FY29
Little Diomede Comprehensive Piped System Over $10M FY26 FY34
Little Diomede Water Storage Tank Replacement and Transmission Line Upgrades Under $10M FY24 FY29
Mertarvik Phase 1 Piped Water & Sewer, Sewage Lagoon, WST, Lift Station, & In-home Plumbing
Over $10M FY24 FY32
Mertarvik Solid Waste Completion Under $1M FY25 FY29
Napaskiak Water Treatment Plant Repair/Replacement Under $10M FY25 FY30
Noorvik Water and Sewer to Two Unserved Homes Under $5M FY26 FY28
Nunam Iqua CUB Backup Generator Under $1M FY25 FY30
Nunam Iqua Water Quantity Under $5M FY25 FY30
Oscarville Water Well & Low Pressure Sewer Under $10M FY25 FY30
ALASKA IIJA LEGACY TRACKER
CONTRACT PROJECTS
Page 1 of 2 *FY stands for Financial Year
COMMUNITY PROJECT VALUE ANTICIPATED
START*
ANTICIPATED
END*
Pilot Station Solid Waste Under $10M FY25 FY29
Port Lions Water Main Replacement Under $10M FY24 FY29
Ruby New Landfill Under $5M FY25 FY29
Russian Mission Solid Waste Site Under $10M FY24 FY28
Selawik New Solid Waste Site Under $5M FY25 FY29
Shishmaref Comprehensive Piped System Over $10M FY26 FY35
South Naknek Water System Backup Generator Under $1M FY25 FY30
St. Mary's Andreafski Loop Water Main Upgrade Under $10M FY24 FY29
St. Mary's St. Marys Distribution Loop Replacement Ph. 2 Under $10M FY25 FY30
St. Michael Raw WST Replacement Under $10M FY24 FY29
Stebbins Honeybucket Lagoon Under $5M FY24 FY29
Stebbins Sewer Lagoon and Force Main Over $10M FY24 FY32
Stebbins Solid Waste Site Improvements Under $1M FY25 FY29
Stebbins Water Distribution and Wastewater Collection Over $10M FY24 FY33
Tanacross Sewer Improvements Under $5M FY24 FY29
Tatitlek Septic Pumper Truck Under $1M FY24 FY27
Tetlin Comprehensive Piped Systems Over $10M FY24 FY32
Togiak East Loop Sewer Facilities Upgrades (Ph. 1) Under $10M FY24 FY29
Togiak East Loop Water Main Upgrades (Ph. 1) Under $10M FY24 FY29
Togiak West Loop #1 W/S Upgrade (Ph.3) Under $10M FY24 FY29
Togiak West Loop #2 W/S Upgrade (Ph. 2) Under $10M FY24 FY29
Tyonek Sludge Lagoon Upgrade Under $5M FY25 FY30
Venetie Comprehensive Piped System Over $10M FY24 FY33
White Mountain New Landfill and Closeout of Old Landfill Under $5M FY25 FY29
ALASKA IIJA LEGACY TRACKER
CONTRACT PROJECTS
Page 2 of 2 *FY stands for Financial Year