This document contains two simplified construction schedules for the Heart Butte Dam Safety of Dams Modification project. The schedules outline the proposed sequence and timing of key construction activities, including jet grouting, filter installation, conduit repairs, and reservoir drawdown, under both a 2-year and 3-year construction timeline.

The schedules were prepared by the Bureau of Reclamation to supplement the Questions for Contractors document released for the Heart Butte Dam Industry Day event. The two timelines present the benefits and drawbacks of each approach, with the 2-year schedule potentially requiring only one reservoir drawdown, but posing increased congestion and schedule risk, while the 3-year schedule spreads out the work over a longer period but necessitates two drawdowns. The Bureau is evaluating the appropriate construction approach based on these factors.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Two (2) Simplified Construction Schedules

On October 3, 2024, the Buerau of Reclamation posted Questions for Contractors at Heart Butte Dam Industry Day document uploaded to SAM.gov. Reclamation prepared the following two simplified construction schedules to supplement the Question 1 and 2 of that document.

The reservoir will be drawn down as much as possible prior to starting work within the outlet works conduit, as the outlet works is the only way to evacuate water from the reservoir. If the work can be constructed in two construction seasons instead of three, Reclamation might be able to avoid a second drawdown of the reservoir in the middle of construction.

2 construction season discussion:

Benefits are that possibly only one reservoir drawdown to dead pool is needed.

Drawbacks:

o A considerable amount of congestion around the outlet works stilling basin is happening all at once, including jet grouting, dewatering, filter trench, filter work in the channel, and access for work inside the conduit. Reclamation is evaluating whether this induces too much construction schedule risk.

3 construction season discussion:

Benefits are that work is spread out over a longer period, resulting in less site congestion.

Drawbacks are that two reservoir drawdowns to dead pool are needed.

ate a 2‐year and 3‐year Construction Schedules Ente Heart Butte SOD Project Disp lay We ek in cell E4 repr

10/8/2024

Ap r‐

M ay ‐2

Ju n‐

Ju l‐2

Au g‐

Se p‐

O ct ‐2

N ov

‐2

De c‐

Ja n‐

Fe b‐

M ar ‐2

Ap r‐

M ay ‐2

Ju n‐

Ju l‐2

Au g‐

Se p‐

O ct ‐2

N ov

‐2

De c‐

Ja n‐

Fe b‐

M ar ‐2

Ap r‐

M ay ‐2

Ju n‐

Ju l‐2

Au g‐

Se p‐ row con

TASK

Cell B8 con

2‐Year Schedule.

Award Oct. 2026

Mob and Site Preparation

Jet Grouting

Void Grouting Below Conduit

Filter Trench

Stilling Basin Filters

Filter Blanket Exavate

Joint Grouting Inside Conduit

Seeding and Cleanup row con

TASK

Cell B8 con

3‐Year Schedule.

Award Oct. 2026

Mob and Site Preparation

Jet Grouting

Void Grouting Below Conduit

Filter Trench

Stilling Basin Filters

Filter Blanket Exavate

Joint Grouting Inside Conduit

Seeding and Cleanup

Construction Complete. Normal Operations

Possible Outlet Works Flow

Jet Grout Outside Conduit & Dewatering Installation

Jet Grout Outside Conduit & Dewatering Installation

Backfill MSE Wall

Unwater and Install Filters

Install Dewatering

Site prep.

Bench install

No Outlet Works Flow No Outlet Works Flow

Jet Grout Interior work

Repair Conduit Interior

Reservoir Drawdown Possible Reservoir

Drawdown

Reservoir Drawdown No Outlet Works Flow Reservoir Drawdown No Outlet Works Flow

Install Dewatering

Site prep.

Bench install

Preparation with Grouting in Nov.

Install Filter Trench

Jet Grout Interior work

Repair Conduit Interior

Install Filter Trench

Preparation with Grouting in Nov.

Unwater and Install Filters

Backfill MSE Wall

Two Simplified Construction Schedules
Heart Butte Dam 2-year and 3-year simplified construction schedules