2-Specifications-BID.pdf

PDF 510 KB Posted

Attached to
GSPB- SITEWORK PACKAGE
Solicitation number
2026-1204C
Issued by
Baldwin County, Alabama

About this file

Summary

This is a specifications document and bidding package for the Gulf Shores Pedestrian Bridge Plazas project, a construction project by the City of Gulf Shores, Alabama, administered by Construction Manager J.T. Harrison Construction Co., LLC. The project involves construction of pedestrian plaza areas, structural tie-ins, hardscaping, landscaping, and public amenities supporting a pedestrian bridge corridor. The work is divided into three distinct trade contractor packages, with this document covering the Sitework Package (Earthwork, Site Utilities, and Site Amenities). Bidders may submit proposals for single or multiple trade packages. The specifications detail requirements across numerous divisions including site clearing, concrete work, masonry, metals, thermal protection, electrical, plumbing, HVAC, landscaping, and utilities. The contract utilizes a stipulated price method with unit prices available for change orders. Progress schedules, daily reports, and construction photographs are required, with payment processed through applications submitted on a specified interval basis using ASPD Form 6-D. All submittals must be made electronically through an approved submittal exchange service, and a preconstruction meeting must be held after the Notice of Award.

Pricing is structured as a multiple prime contract with stipulated prices as described in the contracting forms. Unit prices are provided for potential modifications during construction, with payment calculated based on actual quantities incorporated into the work and accepted by the Landscape Architect. The Contractor must include the cost of the electronic document submittal service within the Contract Sum and shall provide a Contractor's Quality Control Plan prior to mobilization. Performance bonds are required for erosion and sedimentation control measures equal to 100 percent of that work's cost. The Owner withholds payment equivalent to any fines resulting from non-compliance with erosion and sediment control regulations. Temporary utilities, including electricity and water, are provided by the Owner, though the cost of water used is borne by the Owner while electricity costs are borne by the Contractor. The contract requires compliance with EPA NPDES and Alabama Erosion and Sedimentation Control Manual requirements, and all substitution requests must be submitted within specified timeframes after contract award to remain on the approved project schedule.

View the file

Other files

File Type Posted
3-Plans-BID.pdf PDF
1-GSPB Plaza - Sitework Package.doc DOC document
4-ADVERTISEMENT FOR BIDS INFO.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Gulf Shores Pedestrian Bridge Plazas 000110 - 1 Table of Contents

SECTION 000110

TABLE OF CONTENTS

PROCUREMENT AND CONTRACTING REQUIREMENTS

1.01 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS

A. 000110 - Table of Contents

SPECIFICATIONS

2.01 DIVISION 01 -- GENERAL REQUIREMENTS

A. 011000 - Summary B. 012000 - Price and Payment Procedures C. 012200 - Unit Prices D. 012300 - Alternates E. 012500 - Substitution Procedures F. 013000 - Administrative Requirements G. 013216 - Construction Progress Schedule H. 014000 - Quality Requirements I. 014216 - Definitions J. 015000 - Temporary Facilities and Controls K. 015100 - Temporary Utilities L. 015713 - Temporary Erosion and Sediment Control M. 016000 - Product Requirements N. 017000 - Execution and Closeout Requirements O. 017123 - Field Engineering P. 017419 - Construction Waste Management and Disposal Q. 017800 - Closeout Submittals R. 017900 - Demonstration and Training

2.02 DIVISION 02 -- EXISTING CONDITIONS

2.03 DIVISION 03 -- CONCRETE

A. 033000 - Cast-in-Place Concrete

Plazas 000110 - 2 Table of Contents

2.04 DIVISION 04 -- MASONRY

2.05 DIVISION 05 -- METALS

2.06 DIVISION 06 -- WOOD, PLASTICS, AND COMPOSITES

2.07 DIVISION 07 -- THERMAL AND MOISTURE PROTECTION

2.08 DIVISION 08 -- OPENINGS

2.09 DIVISION 09 -- FINISHES

2.10 DIVISION 10 -- SPECIALTIES

2.11 DIVISION 11 -- EQUIPMENT

2.12 DIVISION 12 -- FURNISHINGS

2.13 DIVISION 13 -- SPECIAL CONSTRUCTION

2.14 DIVISION 14 -- CONVEYING EQUIPMENT

2.15 DIVISION 21 -- FIRE SUPPRESSION

2.16 DIVISION 22 -- PLUMBING

2.17 DIVISION 23 -- HEATING, VENTILATING, AND AIR-CONDITIONING (HVAC)

2.18 DIVISION 25 -- INTEGRATED AUTOMATION

2.19 DIVISION 26 -- ELECTRICAL

2.20 DIVISION 27 -- COMMUNICATIONS

2.21 DIVISION 28 -- ELECTRONIC SAFETY AND SECURITY

2.22 DIVISION 31 -- EARTHWORK

A. 312200 - Grading B. 312316 - Excavation C. 312323 - Fill

2.23 DIVISION 32 -- EXTERIOR IMPROVEMENTS

A. 321120 - Subbase and Aggregate Base Courses B. 321313 - Concrete Paving C. 321413 - Precast Concrete Unit Paving D. 328423 - Underground Sprinklers E. 329119 - Landscape Grading F. 329223 - Sodding G. 329300 - Plants

2.24 DIVISION 33 -- UTILITIES

2.25 DIVISION 46 -- WATER AND WASTEWATER EQUIPMENT

END OF SECTION

Plazas 011000 - 1 Summary

SECTION 011000

SUMMARY

PART 1 GENERAL

1.01 PROJECT

A. Project Name: Gulf Shores Pedestrian Bridge Plazas B. Owner's Name: City of Gulf Shores.

C. Landscape Architect's Name: WAS Design, Inc..

D. The Project consists of the construction of plaza/park spaces around the pedestrian bridge towers.

1.02 CONTRACT DESCRIPTION

A. Contract Type: Multiple prime contracts, each based on a Stipulated Price as described in Document 005000 - Contracting Forms and Supplements.

1.03 DESCRIPTION OF ALTERATIONS WORK

A. Scope of demolition and removal work is indicated on drawings and specified in Section

024100.

1.04 OWNER OCCUPANCY

A. Owner intends to occupy the Project upon Substantial Completion.

B. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.

C. Schedule the Work to accommodate Owner occupancy.

This page intentionally left blank

Plazas 012000 - 1 Price and Payment Procedures

SECTION 012000

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedures for preparation and submittal of applications for progress payments.

B. Documentation of changes in Contract Sum and Contract Time.

C. Change procedures.

1.02 RELATED REQUIREMENTS

A. Section 005000 - Contracting Forms and Supplements: Forms to be used.

B. Section 005200 - Agreement Form: Contract Sum, retainages, payment period, monetary values of unit prices.

C. Section 007200 - General Conditions: Additional requirements for progress payments, final payment, changes in the Work.

D. Section 007300 - Supplementary Conditions: Percentage allowances for Contractor's overhead and profit.

E. Section 012100 - Allowances: Payment procedures relating to allowances.

F. Section 012200 - Unit Prices: Monetary values of unit prices; Payment and modification procedures relating to unit prices.

G. Section 017800 - Closeout Submittals: Project record documents.

1.03 SCHEDULE OF VALUES

A. Use Schedule of Values Form: ASPD Form 6-E.

B. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit draft to Landscape Architect for approval.

C. Forms filled out by hand will not be accepted.

1.04 APPLICATIONS FOR PROGRESS PAYMENTS

A. Payment Period: Submit at intervals stipulated in the Agreement.

B. Use Form ASPD Form 6-D.

C. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to Landscape Architect for approval.

D. Forms filled out by hand will not be accepted.

E. Execute certification by signature of authorized officer.

F. Submit an electronic form for each Application for Payment.

G. Include the following with the application:

1. Transmittal letter as specified for submittals in Section 013000.

2. Construction progress schedule, revised and current as specified in Section 013000.

3. Current construction photographs specified in Section 013000.

4. Partial release of liens from major subcontractors and vendors.

H. When Landscape Architect requires substantiating information, submit data justifying dollar amounts in question. Provide one copy of data with cover letter for each copy of submittal.

Show application number and date, and line item by number and description.

1.05 MODIFICATION PROCEDURES

A. For minor changes not involving an adjustment to the Contract Sum or Contract Time, Landscape Architect will issue instructions directly to Contractor.

Plazas 012000 - 2 Price and Payment Procedures

B. For other required changes, Landscape Architect will issue a document signed by Owner instructing Contractor to proceed with the change, for subsequent inclusion in a Change Order.

1. The document will describe the required changes and will designate method of determining any change in Contract Sum or Contract Time.

2. Promptly execute the change.

C. For changes for which advance pricing is desired, Landscape Architect will issue a document that includes a detailed description of a proposed change with supplementary or revised drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required and the period of time during which the requested price will be considered valid. Contractor shall prepare and submit a fixed price quotation within 6 business days.

D. Computation of Change in Contract Amount: As specified in the Agreement and Conditions of the Contract.

E. Execution of Change Orders: Landscape Architect will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

Plazas 012200 - 1 Unit Prices

SECTION 012200

UNIT PRICES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Measurement and payment criteria applicable to Work performed under a unit price payment method.

1.02 RELATED REQUIREMENTS

A. Document 004322 - Unit Prices Form: List of Unit Prices as supplement to Bid Form B. Section 012000 - Price and Payment Procedures: Additional payment and modification procedures.

1.03 COSTS INCLUDED

A. Unit Prices included on the Bid Form shall include full compensation for all required labor, products, tools, equipment, plant, transportation, services and incidentals; erection, application or installation of an item of the Work; overhead and profit.

1.04 UNIT QUANTITIES SPECIFIED

A. Quantities indicated in the Bid Form are for bidding and contract purposes only and will not be used as a typical method of payment. Quantities will be used to evaluate the validity of the bid and for change purposes that occur during the course of the work.

B. Order of Magnitude: Unit prices in 004322 - UNIT PRICE FORM shall be based on the cost of one (1) unit when considering an adjustment to the Total Quantity required for the overall job.

1.05 MEASUREMENT OF QUANTITIES

A. Measurement methods delineated in the individual specification sections complement the criteria of this section. In the event of conflict, the requirements of the individual specification section govern.

B. Assist by providing necessary equipment, workers, and survey personnel as required.

1.06 PAYMENT

A. When changes occur that can be resolved by use of provided Unit Prices, payment for changed work governed by unit prices will be made on the basis of the actual measurements and quantities of Work that is incorporated in or made necessary by the Work and accepted by the Landscape Architect, multiplied by the unit price.

B. Where change-related work is to be paid by Unit Price, payment will occur on the basis of a Change Order process.

C. Payment will not be made for any of the following:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products not completely unloaded from the transporting vehicle.

4. Products placed beyond the lines and levels of the required Work.

5. Products remaining on hand after completion of the Work.

6. Loading, hauling, and disposing of rejected Products.

1.07 DEFECT ASSESSMENT

A. Replace Work, or portions of the Work, not complying with specified requirements.

B. If, in the opinion of Landscape Architect, it is not practical to remove and replace the Work, Landscape Architect will direct one of the following remedies:

1. The defective Work may remain, but the unit price will be adjusted to a new unit price at the discretion of Landscape Architect.

Plazas 012200 - 2 Unit Prices

2. The defective Work will be partially repaired to the instructions of the Landscape Architect, and the unit price will be adjusted to a new unit price at the discretion of Landscape Architect.

C. If, in the opinion of Owner, it is not practical to remove and replace the Work, Owner will direct one of the following remedies:

1. The defective Work may remain, but the unit price will be adjusted to a new unit price at the discretion of Owner.

2. The defective Work will be partially repaired to the instructions of the Owner, and the unit price will be adjusted to a new unit price at the discretion of Owner.

D. The authority of Landscape Architect to assess the defect and identify payment adjustment is final.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

Plazas 012300 - 1 Alternates

SECTION 012300

ALTERNATES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Description of Alternates.

B. Procedures for pricing Alternates.

C. Documentation of changes to Contract Price and Contract Time.

1.02 RELATED REQUIREMENTS

A. Document 002113 - Instructions to Bidders: Instructions for preparation of pricing for

Alternates.

1.03 ACCEPTANCE OF ALTERNATES

A. Alternates quoted on Bid Forms will be reviewed and accepted or rejected by Owner. Accepted Alternates will be identified in the Owner-Contractor Agreement.

B. Coordinate related work and modify surrounding work to integrate the Work of each Alternate.

1.04 SCHEDULE OF ALTERNATES

A. Alternate No. 1 - Bollards:

1. Alternate Item: Drawing number LH500.

PART 2 PRODUCTS - NOT USED

Plazas 012500 - 1 Substitution Procedures

SECTION 012500

SUBSTITUTION PROCEDURES

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Procedural requirements for proposed substitutions.

1.02 RELATED REQUIREMENTS

A. Section 002113 - Instructions to Bidders: Restrictions on timing of substitution requests.

B. Section 012100 - Allowances, for cash allowances affecting this section.

C. Section 012200 - Unit Prices, for additional unit price requirements.

D. Section 012300 - Alternates, for product alternatives affecting this section.

E. Section 013000 - Administrative Requirements: Submittal procedures, coordination.

F. Section 016000 - Product Requirements: Fundamental product requirements, product options, delivery, storage, and handling.

1.03 DEFINITIONS

A. Substitutions: Changes from Contract Documents requirements proposed by Contractor to materials, products, assemblies, and equipment.

1. Substitutions for Cause: Proposed due to changed Project circumstances beyond

Contractor's control.

a. Unavailability.

b. Regulatory changes.

1.04 REFERENCE STANDARDS

A. CSI/CSC Form 1.5C - Substitution Request (During the Bidding/Negotiating Stage); Current

Edition.

B. CSI/CSC Form 13.1A - Substitution Request (After the Bidding/Negotiating Phase); Current

Edition.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 GENERAL REQUIREMENTS

A. A Substitution Request for products, assemblies, materials, and equipment constitutes a representation that the submitter:

1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product, equipment, assembly, or system.

2. Agrees to provide the same warranty for the substitution as for the specified product.

3. Agrees to provide same or equivalent maintenance service and source of replacement parts, as applicable.

4. Agrees to coordinate installation and make changes to other work that may be required for the work to be complete, with no additional cost to Owner.

5. Waives claims for additional costs or time extension that may subsequently become apparent.

6. Agrees to reimburse Owner and Landscape Architect for review or redesign services associated with re-approval by authorities.

B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents. Burden of proof is on proposer.

1. Note explicitly any non-compliant characteristics.

C. Content: Include information necessary for tracking the status of each Substitution Request, and information necessary to provide an actionable response.

Plazas 012500 - 2 Substitution Procedures

1. No specific form is required. Contractor's Substitution Request documentation must include the following:

a. Project Information:

1) Official project name and number, and any additional required identifiers established in Contract Documents.

2) Owner's, Landscape Architect's, and Contractor's names.

b. Substitution Request Information:

1) Discrete and consecutive Substitution Request number, and descriptive subject/title.

2) Indication of whether the substitution is for cause or convenience.

3) Issue date.

4) Reference to particular Contract Document(s) specification section number, title, and article/paragraph(s).

5) Description of Substitution.

6) Reason why the specified item cannot be provided.

7) Differences between proposed substitution and specified item.

8) Description of how proposed substitution affects other parts of work.

c. Attached Comparative Data: Provide point-by-point, side-by-side comparison addressing essential attributes specified, as appropriate and relevant for the item:

1) Physical characteristics.

2) In-service performance.

3) Expected durability.

4) Visual effect.

5) Sustainable design features.

6) Warranties.

7) Other salient features and requirements.

8) Include, as appropriate or requested, the following types of documentation:

(a) Product Data:

(b) Samples.

(c) Certificates, test, reports or similar qualification data.

(d) Drawings, when required to show impact on adjacent construction elements.

d. Impact of Substitution:

1) Savings to Owner for accepting substitution.

2) Change to Contract Time due to accepting substitution.

D. Limit each request to a single proposed substitution item.

1. Submit an electronic document, combining the request form with supporting data into single document.

3.02 SUBSTITUTION PROCEDURES DURING PROCUREMENT

A. Submittal Time Restrictions:

B. Submittal Form (before award of contract):

1. Submit substitution requests by completing CSI/CSC Form 1.5C - Substitution Request.

See this form for additional information and instructions. Use only this form; other forms of submission are unacceptable.

3.03 SUBSTITUTION PROCEDURES DURING CONSTRUCTION

A. Submittal Form (after award of contract):

1. Submit substitution requests by completing CSI/CSC Form 13.1A - Substitution Request (After Bidding/Negotiating). See this form for additional information and instructions. Use only this form; other forms of submission are unacceptable.

B. Landscape Architect will consider requests for substitutions only within 30 days after date of Agreement.

Plazas 012500 - 3 Substitution Procedures

C. Submit request for Substitution for Cause immedately upon discovery of need for substitution, but not later than 14 days prior to time required for review and approval by Landscape Architect, in order to stay on approved project schedule.

D. Submit request for Substitution for Convenience immediately upon discovery of its potential advantage to the project, but not later than 21 days prior to time required for review and approval by Landscape Architect, in order to stay on approved project schedule.

1. In addition to meeting general documentation requirements, document how the requested substitution benefits the Owner through cost savings, time savings, greater energy conservation, or in other specific ways.

2. Document means of coordinating of substitution item with other portions of the work, including work by affected subcontractors.

3. Bear the costs engendered by proposed substitution of:

a. Owner's compensation to the Landscape Architect for any required redesign, time spent processing and evaluating the request.

b. Other construction by Owner.

c. Other unanticipated project considerations.

E. Substitutions will not be considered under one or more of the following circumstances:

1. When they are indicated or implied on shop drawing or product data submittals, without having received prior approval.

2. Without a separate written request.

3. When acceptance will require revisions to Contract Documents.

3.04 RESOLUTION

A. Landscape Architect may request additional information and documentation prior to rendering a decision. Provide this data in an expeditious manner.

B. Landscape Architect will notify Contractor in writing of decision to accept or reject request.

1. Landscape Architect's decision following review of proposed substitution will be noted on the submitted form.

3.05 ACCEPTANCE

A. Accepted substitutions change the work of the Project. They will be documented and incorporated into work of the project by Change Order, Construction Change Directive, Architectural Supplementary Instructions, or similar instruments provided for in the Conditions of the Contract.

3.06 CLOSEOUT ACTIVITIES

A. See Section 017800 - Closeout Submittals, for closeout submittals.

B. Include completed Substitution Request Forms as part of the Project record. Include both approved and rejected Requests.

3.07 ATTACHMENTS

A. A facsimile of the Substitution Request Form (During Construction) required to be used on the Project is included after this section.

Plazas 013000 - 1 Administrative Requirements

SECTION 013000

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. General administrative requirements.

B. Electronic document submittal service.

C. Preconstruction meeting.

D. Site mobilization meeting.

E. Progress meetings.

F. Construction progress schedule.

G. Contractor's daily reports.

H. Progress photographs.

I. Coordination drawings.

J. Submittals for review, information, and project closeout.

K. Number of copies of submittals.

L. Requests for Interpretation (RFI) procedures.

M. Submittal procedures.

1.02 RELATED REQUIREMENTS

A. Section 013216 - Construction Progress Schedule: Form, content, and administration of schedules.

B. Section 016000 - Product Requirements: General product requirements.

C. Section 017000 - Execution and Closeout Requirements: Additional coordination requirements.

D. Section 017800 - Closeout Submittals: Project record documents; operation and maintenance data; warranties and bonds.

1.03 REFERENCE STANDARDS

A. AIA G716 - Request for Information; 2004.

B. AIA G810 - Transmittal Letter; 2001.

1.04 PROJECT COORDINATOR

A. Project Coordinator: Construction Manager.

B. Cooperate with the Project Coordinator in allocation of mobilization areas of site; for field offices and sheds, for ________ access, traffic, and parking facilities.

C. During construction, coordinate use of site and facilities through the Project Coordinator.

D. Comply with Project Coordinator's procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts.

E. Comply with instructions of the Project Coordinator for use of temporary utilities and construction facilities. Responsibility for providing temporary utilities and construction facilities is identified in Section 011000 - Summary.

F. Coordinate field engineering and layout work under instructions of the Project Coordinator.

G. Make the following types of submittals to Landscape Architect through the Project Coordinator:

1. Requests for Interpretation.

2. Requests for substitution.

3. Shop drawings, product data, and samples.

4. Test and inspection reports.

Plazas 013000 - 2 Administrative Requirements

5. Design data.

6. Manufacturer's instructions and field reports.

7. Applications for payment and change order requests.

8. Progress schedules.

9. Coordination drawings.

10. Correction Punch List and Final Correction Punch List for Substantial Completion.

11. Closeout submittals.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 ELECTRONIC DOCUMENT SUBMITTAL SERVICE

A. All documents transmitted for purposes of administration of the contract are to be in electronic (PDF, MS Word, or MS Excel) format, as appropriate to the document, and transmitted via an Internet-based submittal service that receives, logs and stores documents, provides electronic stamping and signatures, and notifies addressees via email.

1. Besides submittals for review, information, and closeout, this procedure applies to

Requests for Interpretation (RFIs), progress documentation, contract modification documents (e.g. supplementary instructions, change proposals, change orders), applications for payment, field reports and meeting minutes, Contractor's correction punchlist, and any other document any participant wishes to make part of the project record.

2. Contractor and Landscape Architect are required to use this service.

3. It is Contractor's responsibility to submit documents in allowable format.

4. Subcontractors, suppliers, and Landscape Architect's consultants are to be permitted to use the service at no extra charge.

5. Users of the service need an email address, internet access, and PDF review software that includes ability to mark up and apply electronic stamps (such as Adobe Acrobat, www.adobe.com, or Bluebeam PDF Revu, www.bluebeam.com), unless such software capability is provided by the service provider.

6. Paper document transmittals will not be reviewed; emailed electronic documents will not be reviewed.

7. All other specified submittal and document transmission procedures apply, except that electronic document requirements do not apply to samples or color selection charts.

B. Cost: The cost of the service is to be paid by Contractor; include the cost of the service in the Contract Sum.

C. Submittal Service: The selected service is:

1. Submittal Exchange (tel: 1-800-714-0024): www.submittalexchange.com/#sle.

2. EADOC LLC (tel: 1-877-305-3844): www.eadocsoftware.com/#sle.

3. Newforma ConstructEx: www.newforma.com/our-solutions/constructex/#sle.

D. Training: One, one-hour, web-based training session will be arranged for all participants, with representatives of Landscape Architect and Contractor participating; further training is the responsibility of the user of the service.

E. Project Closeout: Landscape Architect will determine when to terminate the service for the project and is responsible for obtaining archive copies of files for Owner.

3.02 PRECONSTRUCTION MEETING

A. Project Coordinator will schedule a meeting after Notice of Award.

B. Attendance Required. All participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work:

1. Owner or authorized representatives.

2. Landscape Architect and their consultants.

3. Contractor and its superintendent

Plazas 013000 - 3 Administrative Requirements

4. Major subcontractors

5. Suppliers.

C. Agenda: Discuss items of significance that could affect progress, including the following:

1. Execution of Owner-Contractor Agreement.

2. Submission of executed bonds and insurance certificates.

3. Distribution of Contract Documents.

4. Submission of list of subcontractors, list of products, schedule of values, and progress schedule.

5. Tentative construction schedule.

6. Phasing.

7. Critical work sequencing and long lead times.

8. Submission of initial Submittal schedule.

9. Designation of personnel representing the parties to Contract and their duties.

10. Lines of communication.

11. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures.

12. Procedures for testing and inspecting.

13. Distribution of Contract Documents.

14. Use of premises and existing building.

15. Work restrictions.

16. Working hours.

17. Owner's occupancy requirements.

18. Responsibility for temporary facilities and controls.

19. Procedures for disruptions and shutdowns.

20. Construction waste management and recycling.

21. Parking availability.

22. Office, work and storage areas.

23. Equipment delieveries and priorities.

24. First aid.

25. Security.

26. Progress Cleaning.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Landscape Architect, Owner, participants, and those affected by decisions made.

3.03 SITE MOBILIZATION MEETING

A. Project Coordinator will schedule meeting at the Project site prior to Contractor occupancy.

B. Attendance Required:

1. Contractor.

2. Owner.

3. Landscape Architect.

4. Special consultants.

5. Contractor's superintendent.

6. Major subcontractors.

C. Agenda:

1. Use of premises by Owner and Contractor.

2. Owner's requirements.

3. Construction facilities and controls provided by Owner.

4. Temporary utilities provided by Owner.

5. Survey and building layout.

6. Security and housekeeping procedures.

7. Schedules.

8. Application for payment procedures.

Plazas 013000 - 4 Administrative Requirements

9. Procedures for testing.

10. Procedures for maintaining record documents.

11. Requirements for start-up of equipment.

12. Inspection and acceptance of equipment put into service during construction period.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Landscape Architect, Owner, participants, and those affected by decisions made.

3.04 PROGRESS MEETINGS

A. Project Coordinator will make arrangements for meetings, prepare agenda with copies for participants, preside at meetings.

B. Attendance Required:

1. Contractor.

2. Owner.

3. Landscape Architect.

4. Contractor's superintendent.

5. Major subcontractors.

C. Agenda:

1. Review minutes of previous meetings.

2. Review of work progress.

3. Field observations, problems, and decisions.

4. Identification of problems that impede, or will impede, planned progress.

5. Review of submittals schedule and status of submittals.

6. Review of RFIs log and status of responses.

7. Maintenance of progress schedule.

8. Corrective measures to regain projected schedules.

9. Planned progress during succeeding work period.

10. Maintenance of quality and work standards.

11. Effect of proposed changes on progress schedule and coordination.

12. Other business relating to work.

D. Record minutes and distribute copies within two days after meeting to participants, with two copies to Landscape Architect, Owner, participants, and those affected by decisions made.

3.05 CONSTRUCTION PROGRESS SCHEDULE - SEE SECTION 013216

A. Within 10 days after date of the Agreement, submit preliminary schedule defining planned operations for the first 60 days of work, with a general outline for remainder of work.

B. If preliminary schedule requires revision after review, submit revised schedule within 5days.

C. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

1. Include written certification that major Subcontractors have reviewed and accepted proposed schedule.

D. Within 10 days after joint review, submit complete schedule.

E. Submit updated schedule with each Application for Payment.

3.06 DAILY CONSTRUCTION REPORTS

A. Include only factual information. Do not include personal remarks or opinions regarding operations and/or personnel.

1. Submit using required form, to be furnished by the Construction Manager.

B. Prepare a daily construction report recording the following information concerning events at Project site and project progress:

1. Date.

2. High and low temperatures, and general weather conditions.

3. List of subcontractors at Project site.

Plazas 013000 - 5 Administrative Requirements

4. List of separate contractors at Project site.

5. Approximate count of personnel at Project site.

a. Include a breakdown for supervisors, laborers, journeymen, equipment operators, and helpers.

6. Major equipment at Project site.

7. Material deliveries.

8. Safety, environmental, or industrial relations incidents.

9. Meetings and significant decisions.

10. Unusual events (submit a separate special report).

11. Stoppages, delays, shortages, and losses. Include comparison between scheduled work activities (in Contractor's most recently updated and published schedule) and actual activities. Explain differences, if any. Note days or periods when no work was in progress and explain the reasons why.

12. Meter readings and similar recordings.

13. Emergency procedures.

14. Directives and requests of authority having jurisdiction (AHJ).

15. Change Orders received and implemented.

16. Testing and/or inspections performed.

17. List of verbal instruction given by Owner and/or Landscape Architect.

18. Signature of Contractor's authorized representative.

3.07 PROGRESS PHOTOGRAPHS

A. Submit photographs with each application for payment, taken not more than 3 days prior to submission of application for payment.

B. Photography Type: Digital; electronic files.

C. Provide photographs of site and construction throughout progress of work produced by an experienced photographer, acceptable to Landscape Architect.

D. In addition to periodic, recurring views, take photographs of each of the following events:

1. Completion of site clearing.

2. Completion of subgrade prep.

3. Completion of subbase.

4. Completion of separation fabric.

5. Completion of layout.

6. Completion of fence bases, posts and light bases.

7. Completion of bituminous binder layer.

8. Completion of tack coat.

9. Completion of bituminous wearing surface.

10. Completion of fencing and lighting.

11. Excavations in progress.

12. Foundations in progress and upon completion.

13. Structural framing in progress and upon completion.

14. Final completion, minimum of ten (10) photos.

E. Take photographs as evidence of existing project conditions as follows:

F. Views:

1. Provide aerial photographs from four cardinal views at each specified time, until structure is enclosed.

2. Provide non-aerial photographs from four cardinal views at each specified time, until date of Substantial Completion.

3. Consult with Landscape Architect for instructions on views required.

4. Provide factual presentation.

5. Provide correct exposure and focus, high resolution and sharpness, maximum depth of field, and minimum distortion.

Plazas 013000 - 6 Administrative Requirements

G. Digital Photographs: 24 bit color, minimum resolution of 1600 by 1200 ("2 megapixel") or better, in JPG format; provide files unaltered by photo editing software.

1. Delivery Medium: via Project Management software.

2. File Naming: Include project identification, date and time of view, and view identification.

3. PDF File: Assemble all photos into printable pages in PDF format, with 2 to 3 photos per page, each photo labeled with file name; one PDF file per submittal.

4. Hard Copy: Printed hardcopy (grayscale) of PDF file and point of view sketch.

3.08 COORDINATION DRAWINGS

A. Provide information required by Project Coordinator for preparation of coordination drawings.

B. Review drawings prior to submission to Landscape Architect.

3.09 REQUESTS FOR INTERPRETATION (RFI)

A. Definition: A request seeking one of the following:

1. An interpretation, amplification, or clarification of some requirement of Contract Documents arising from inability to determine from them the exact material, process, or system to be installed; or when the elements of construction are required to occupy the same space (interference); or when an item of work is described differently at more than one place in Contract Documents.

2. A resolution to an issue which has arisen due to field conditions and affects design intent.

B. Whenever possible, request clarifications at the next appropriate project progress meeting, with response entered into meeting minutes, rendering unnecessary the issuance of a formal RFI.

C. Preparation: Prepare an RFI immediately upon discovery of a need for interpretation of

Contract Documents. Failure to submit a RFI in a timely manner is not a legitimate cause for claiming additional costs or delays in execution of the work.

1. Prepare a separate RFI for each specific item.

a. Review, coordinate, and comment on requests originating with subcontractors and/or materials suppliers.

b. Do not forward requests which solely require internal coordination between subcontractors.

2. Prepare in a format and with content acceptable to the Landscape Architect.

a. Use AIA G716 - Request for Information .

3. Prepare using an electronic version of the form appended to this section.

4. Prepare using software provided by the Electronic Document Submittal Service.

5. Combine RFI and its attachments into a single electronic file. PDF format is preferred.

D. Reason for the RFI: Prior to initiation of an RFI, carefully study all Contract Documents to confirm that information sufficient for their interpretation is definitely not included.

1. Unacceptable Uses for RFIs: Do not use RFIs to request the following::

a. Approval of submittals (use procedures specified elsewhere in this section).

b. Approval of substitutions (see Section - 016000 - Product Requirements)

c. Changes that entail change in Contract Time and Contract Sum (comply with provisions of the Conditions of the Contract).

d. Different methods of performing work than those indicated in the Contract Drawings and Specifications (comply with provisions of the Conditions of the Contract).

2. Improper RFIs: Requests not prepared in compliance with requirements of this section, and/or missing key information required to render an actionable response. They will be returned without a response, with an explanatory notation.

3. Frivolous RFIs: Requests regarding information that is clearly indicated on, or reasonably inferable from, Contract Documents, with no additional input required to clarify the question. They will be returned without a response, with an explanatory notation.

a. The Owner reserves the right to assess the Contractor for the costs (on time-and-materials basis) incurred by the Landscape Architect, and any of its consultants, due to processing of such RFIs.

Plazas 013000 - 7 Administrative Requirements

E. Content: Include identifiers necessary for tracking the status of each RFI, and information necessary to provide an actionable response.

1. Official Project name and number, and any additional required identifiers established in

Contract Documents.

2. Owner's, Landscape Architect's, and Contractor's names.

3. Discrete and consecutive RFI number, and descriptive subject/title.

4. Issue date, and requested reply date.

5. Reference to particular Contract Document(s) requiring additional information/interpretation. Identify pertinent drawing and detail number and/or specification section number, title, and paragraph(s).

6. Annotations: Field dimensions and/or description of conditions which have engendered the request.

7. Contractor's suggested resolution: A written and/or a graphic solution, to scale, is required in cases where clarification of coordination issues is involved, for example;

routing, clearances, and/or specific locations of work shown diagrammatically in Contract Documents. If applicable, state the likely impact of the suggested resolution on Contract Time or the Contract Sum.

F. Attachments: Include sketches, coordination drawings, descriptions, photos, submittals, and other information necessary to substantiate the reason for the request.

G. RFI Log: Prepare and maintain a tabular log of RFIs for the duration of the project.

1. Indicate current status of every RFI. Update log promptly and on a regular basis.

2. Note dates of when each request is made, and when a response is received.

3. Highlight items requiring priority or expedited response.

4. Highlight items for which a timely response has not been received to date.

5. Identify and include improper or frivolous RFIs.

H. Review Time: Landscape Architect will respond and return RFIs to Contractor within seven calendar days of receipt. For the purpose of establishing the start of the mandated response period, RFIs received after 12:00 noon will be considered as having been received on the following regular working day.

1. Response period may be shortened or lengthened for specific items, subject to mutual agreement, and recorded in a timely manner in progress meeting minutes.

I. Responses: Content of answered RFIs will not constitute in any manner a directive or authorization to perform extra work or delay the project. If in Contractor's belief it is likely to lead to a change to Contract Price or Contract Time, promptly issue a notice to this effect, and follow up with an appropriate Change Order request to Owner.

1. Response may include a request for additional information, in which case the original RFI will be deemed as having been answered, and an amended one is to be issued forthwith.

Identify the amended RFI with an R suffix to the original number.

2. Do not extend applicability of a response to specific item to encompass other similar conditions, unless specifically so noted in the response.

3. Upon receipt of a response, promptly review and distribute it to all affected parties, and update the RFI Log.

4. Notify Landscape Architect within seven calendar days if an additional or corrected response is required by submitting an amended version of the original RFI, identified as specified above.

3.10 SUBMITTAL SCHEDULE

A. Submit to Landscape Architect for review a schedule for submittals in tabular format.

1. Coordinate with Contractor's construction schedule and schedule of values.

2. Format schedule to allow tracking of status of submittals throughout duration of construction.

3. Arrange information to include specification number and title and description of item of work covered.

Plazas 013000 - 8 Administrative Requirements

4. Account for time required for preparation, review, manufacturing, fabrication and delivery when establishing submittal delivery and review deadline dates.

a. For assemblies, equipment, systems comprised of multiple components and/or requiring detailed coordination with other work, allow for additional time to make corrections or revisions to initial submittals, and time for their review.

3.11 SUBMITTALS FOR REVIEW

A. When the following are specified in individual sections, submit them for review:

1. Product data.

2. Shop drawings.

3. Samples for selection.

4. Samples for verification.

B. Submit to Landscape Architect for review for the limited purpose of checking for compliance with information given and the design concept expressed in Contract Documents.

C. Samples will be reviewed for aesthetic, color, or finish selection.

D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 017800 - Closeout Submittals.

3.12 SUBMITTALS FOR INFORMATION

A. When the following are specified in individual sections, submit them for information:

1. Design data.

2. Certificates.

3. Test reports.

4. Inspection reports.

5. Manufacturer's instructions.

6. Manufacturer's field reports.

7. Other types indicated.

B. Submit for Landscape Architect's knowledge as contract administrator or for Owner.

3.13 SUBMITTALS FOR PROJECT CLOSEOUT

A. Submit Correction Punch List for Substantial Completion.

B. Submit Final Correction Punch List for Substantial Completion.

C. When the following are specified in individual sections, submit them at project closeout in compliance with requirements of Section 017800 - Closeout Submittals:

1. Project record documents.

2. Operation and maintenance data.

3. Warranties.

4. Bonds.

5. Other types as indicated.

D. Submit for Owner's benefit during and after project completion.

3.14 NUMBER OF COPIES OF SUBMITTALS

A. Electronic Documents: Submit one electronic copy in PDF format; an electronically-marked up file will be returned. Create PDFs at native size and right-side up; illegible files will be rejected.

B. Samples: Submit the number specified in individual specification sections; one of which will be retained by Landscape Architect.

1. After review, produce duplicates.

2. Retained samples will not be returned to Contractor unless specifically so stated.

3.15 SUBMITTAL PROCEDURES

A. General Requirements:

1. Use a single transmittal for related items.

Plazas 013000 - 9 Administrative Requirements

2. Submit separate packages of submittals for review and submittals for information, when included in the same specification section.

3. Transmit using approved form.

a. Use Contractor's form, subject to prior approval by Landscape Architect.

4. Sequentially identify each item. For revised submittals use original number and a sequential numerical suffix.

5. Identify: Project; Contractor; subcontractor or supplier; pertinent drawing and detail number; and specification section number and article/paragraph, as appropriate on each copy.

6. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the work and Contract Documents.

a. Submittals from sources other than the Contractor, or without Contractor's stamp will not be acknowledged, reviewed, or returned.

7. Deliver each submittal on date noted in submittal schedule, unless an earlier date has been agreed to by all affected parties, and is of the benefit to the project.

a. Upload submittals in electronic form to Electronic Document Submittal Service website.

8. Schedule submittals to expedite the Project, and coordinate submission of related items.

a. For each submittal for review, allow 15 days excluding delivery time to and from the Contractor.

b. For sequential reviews involving Landscape Architect's consultants, Owner, or another affected party, allow an additional 7 days.

c. For sequential reviews involving approval from authorities having jurisdiction (AHJ), in addition to Landscape Architect's approval, allow an additional 30 days.

9. Identify variations from Contract Documents and product or system limitations that may be detrimental to successful performance of the completed work.

10. Provide space for Contractor and Landscape Architect review stamps.

11. When revised for resubmission, identify all changes made since previous submission.

12. Distribute reviewed submittals. Instruct parties to promptly report inability to comply with requirements.

13. Incomplete submittals will not be reviewed, unless they are partial submittals for distinct portion(s) of the work, and have received prior approval for their use.

14. Submittals not requested will not be recognized or processed.

B. Product Data Procedures:

1. Submit only information required by individual specification sections.

2. Collect required information into a single submittal.

3. Submit concurrently with related shop drawing submittal.

4. Do not submit (Material) Safety Data Sheets for materials or products.

C. Shop Drawing Procedures:

1. Prepare accurate, drawn-to-scale, original shop drawing documentation by interpreting

Contract Documents and coordinating related work.

2. Do not reproduce Contract Documents to create shop drawings.

3. Generic, non-project-specific information submitted as shop drawings do not meet the requirements for shop drawings.

D. Samples Procedures:

1. Transmit related items together as single package.

2. Identify each item to allow review for applicability in relation to shop drawings showing installation locations.

3.16 SUBMITTAL REVIEW

A. Submittals for Review: Landscape Architect will review each submittal, and approve, or take other appropriate action.

Plazas 013000 - 10 Administrative Requirements

B. Submittals for Information: Landscape Architect will acknowledge receipt and review. See below for actions to be taken.

C. Landscape Architect's actions will be reflected by marking each returned submittal using virtual stamp on electronic submittals.

1. Notations may be made directly on submitted items and/or listed on appended Submittal

Review cover sheet.

D. Landscape Architect's and consultants' actions on items submitted for review: No Exceptions

Taken

1. Authorizing purchasing, fabrication, delivery, and installation:

a. "Approved", or language with same legal meaning.

b. "Approved as Noted, Resubmission not required", or language with same legal meaning.

1) At Contractor's option, submit corrected item, with review notations acknowledged and incorporated.

c. "Approved as Noted, Resubmit for Record", or language with same legal meaning.

1) Resubmit corrected item, with review notations acknowledged and incorporated.

Resubmit separately, or as part of project record documents.

2) Non-responsive resubmittals may be rejected.

2. Not Authorizing fabrication, delivery, and installation:

a. "Revise and Resubmit".

1) Resubmit revised item, with review notations acknowledged and incorporated.

2) Non-responsive resubmittals may be rejected.

b. "Rejected".

1) Submit item complying with requirements of Contract Documents.

E. Landscape Architect's and consultants' actions on items submitted for information:

1. Items for which no action was taken:

a. "Received" - to notify the Contractor that the submittal has been received for record only.

2. Items for which action was taken:

a. "Reviewed" - no further action is required from Contractor.

Plazas 013216 - 1 Construction Progress Schedule

SECTION 013216

CONSTRUCTION PROGRESS SCHEDULE

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Preliminary schedule.

B. Construction progress schedule, bar chart type.

1.02 RELATED REQUIREMENTS

A. Section 011000 - Summary: Work sequence.

1.03 REFERENCE STANDARDS

A. AGC (CPSM) - Construction Planning and Scheduling Manual; 2004.

B. M-H (CPM) - CPM in Construction Management - Project Management with CPM; 2016, with

Addendum (2021).

1.04 SUBMITTALS

A. Within 5 days after date of Agreement, submit preliminary schedule.

B. If preliminary schedule requires revision after review, submit revised schedule within 5 days.

C. Within 10 days after review of preliminary schedule, submit draft of proposed complete schedule for review.

1. Include written certification that major contractors have reviewed and accepted proposed schedule.

D. Within 5 days after joint review, submit complete schedule.

E. Submit updated schedule with each Application for Payment.

F. Submit in PDF format.

1.05 QUALITY ASSURANCE

A. Contractor's Administrative Personnel: 3 years minimum experience in using and monitoring

CPM schedules on comparable projects.

1.06 SCHEDULE FORMAT

A. Listings: In chronological order according to the start date for each activity. Identify each activity with the applicable specification section number.

B. Diagram Sheet Size: Maximum 22 x 17 inches or width required.

C. Sheet Size: Multiples of 11 X 17 inches.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION

3.01 PRELIMINARY SCHEDULE

A. Prepare preliminary schedule in the form of a horizontal bar chart.

3.02 CONTENT

A. Show complete sequence of construction by activity, with dates for beginning and completion of each element of construction.

B. Identify each item by specification section number.

C. Provide sub-schedules to define critical portions of the entire schedule.

D. Include conferences and meetings in schedule.

E. Show accumulated percentage of completion of each item, and total percentage of Work completed, as of the first day of each month.

Plazas 013216 - 2 Construction Progress Schedule

F. Provide separate schedule of submittal dates for shop drawings, product data, and samples, owner-furnished products, products identified under Allowances, and dates reviewed submittals will be required from Landscape Architect. Indicate decision dates for selection of finishes.

G. Indicate delivery dates for owner-furnished products.

H. Provide legend for symbols and abbreviations used.

3.03 BAR CHARTS

A. Include a separate bar for each major portion of Work or operation.

B. Identify the first work day of each week.

3.04 UPDATING SCHEDULE

A. Maintain schedules to record actual start and finish dates of completed activities.

B. Indicate progress of each activity to date of revision, with projected completion date of each activity.

C. Annotate diagrams to graphically depict current status of Work.

D. Identify activities modified since previous submittal, major changes in Work, and other identifiable changes.

E. Indicate changes required to maintain Date of Substantial Completion.

F. Submit reports required to support recommended changes.

3.05 DISTRIBUTION OF SCHEDULE

A. Distribute copies of updated schedules to Contractor's project site file, to subcontractors, suppliers, Landscape Architect, Owner, and other concerned parties.

B. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules.

Plazas 014000 - 1 Quality Requirements

SECTION 014000

QUALITY REQUIREMENTS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Submittals.

B. Quality assurance.

C. References and standards.

D. Testing and inspection agencies and services.

E. Contractor's construction-related professional design services.

F. Contractor's design-related professional design services.

G. Control of installation.

H. Tolerances.

I. Manufacturers' field services.

J. Defect Assessment.

1.02 RELATED REQUIREMENTS

A. Document…

This is the start of the file's text. The full file is on GovTribe.