This statement of work describes HVAC installation requirements at three National Park Service locations in Yosemite National Park. The scope of work involves installing a new ducted split system using LPG at a 1,200 square foot residence, installing a new ductless multi-zone mini split system at the 1,415 square foot Wawona Community Center, and replacing an existing wall mount air conditioning unit with electric heat strip at the 960 square foot Hetch Hetchy Ranger Station. The contractor will provide all labor, equipment, materials and incidental costs to complete the installations in accordance with manufacturers' specifications and California building codes. The contractor must have at least one EPA universal technician certified employee on site, and work may only be performed from 8am to 5pm Monday through Friday.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 5_-_Limitations_On_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| 1_-_Contract_Price_Schedule.pdf | ||
| 4_-_Map_of_Locations_-_HVAC.pdf | ||
| 3_-_Wage_Determination_-_CA20230018_-_Mariposa_County_-_06-23-2023.pdf | ||
| Sol_140P8523Q0036.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
E X P E R I E N C E Y O U R A M E R I C A The National Park Service cares for special places saved by the American people so that all may experience our heritage.
Statement of Work
Objective
Yosemite National Park (YOSE or NPS) has a need for the installation of Heating, Ventilation, and Air Conditioning (HVAC) units at three locations. The installations required will be one ducted, split system (LPG), one ductless, multi-zone mini split system (electric), and one wall mount air conditioning system with heater (electric).
Background
Location #1 – WAQ 4195, 4619 North Hoover Way, Wawona, CA (see map attached) – this 1,200 square foot (SF) house was damaged during the Mono Wind Event in 2021 and needed extensive rebuilding.
There was no existing HVAC in the residence, so this is a completely new installation, including the gas furnace, condenser, ductwork and vent fans for the bathrooms and the kitchen.
Location #2 – Wawona Community Center, 7917 Chilnualna Falls Road, Wawona, CA (see map attached) – this building is utilized regularly for meetings, a community gathering space during emergency events, and a cooling center in the summer. The current HVAC system is inadequate for cooling during high heat events and the installation of a ductless, multi-zone mini split system is required.
Location #3 – MAB 2113 Hetch Hetchy Ranger Station, 9542 Hetch Hetchy Road, CA (see map attached)
– this building is located adjacent to the Hetchy Hetchy Campground and is utilized as the Ranger Office.
The current Bard wall-mounted air conditioning system is non-functioning. The purpose of the project is to remove and replace the existing HVAC system in kind or with an approved equal system.
Scope
The contractor shall provide all the necessary supervision, management, labor, transportation, equipment, materials, and any other direct incidental costs, overhead, and profit to replace the existing or install new HVAC systems at the three locations.
Location #1 – WAQ 4195. This is a 3-bedroom, 2 bathroom single family residence, approximately 1,200 SF of living space, located at roughly 4,000 feet elevation. The building is in the “rough in state” and is ready for mechanical installation. The gas supply is LPG. Electrical to be installed by the NPS electrician.
• The contractor shall supply and install one (1), Trane – 2.5 ton 14 SEER AC System with 80,000 BTU 96% Natural Gas Furnace Single Stage horizontal with 3 Ton blower (or approved equal)
• The contractor shall install the equipment in accordance with the manufacturer’s specifications and CA Building Codes
• The contractor shall supply and install a high elevation kit
• The contractor shall anchor the outdoor condenser to a preformed pad provided by the contractor, no ground disturbance is authorized for this project
• The furnace shall be 90% Annual Flue Utilization Efficiency (AFUE) and converted to LPG for use
• The contractor shall supply and install a PVC furnace flue through the roof or sidewall maintaining a waterproof seal and to manufacturer specifications
• The contractor shall supply and install gas piping from the existing system in the crawl space to the new furnace in the attic
Yosemite National Park
Carrie Toepper Facility Operations Specialist Buildings and Grounds Phone: 209-379-1089
National Park Service U.S. Department of the Interior
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
• The contractor shall supply and install the system in the attic in a horizontal position, it will be hung or placed on a framed platform with pump ups for support
• The contractor shall insulate the supply and return plenums
• The contractor shall insulate all ducting, including the trunkline and vent runs, metal ducting is preferable
• The contractor shall install the return air in a hallway location
• The contractor shall supply and install a drain pan, drain cut out, and drainage from the pan shall be piped to the exterior of the building
• The contractor shall supply and install all copper, insulated refrigerant lines
• The contractor shall supply and install a digital programmable thermostat in common hallway location and wire to manufacturer specifications
• The contractor shall supply and install all trim fixtures
• The contractor shall purge, evacuate, start, and test all equipment installed during this contract
Location #2 – Wawona Community Center. This is a 1,415 SF with a large meeting space, a small kitchen, and one unisex bathroom. The system will be primarily used for the cooling of the main meeting space. The building is located at roughly 4,000 feet elevation.
• The contractor shall supply and install one ductless multi-zone mini split system, including one (1) Westinghouse condenser 21 SEER Model #WHP36M4A21S and two (2) Westinghouse wall mount indoor head units, Model #WHP18WMA21S (or approved equal)
• The contractor shall supply and install copper refrigerant line sets and paintable refrigerant line set covers
• The contractor shall supply and install all electrical wiring from the indoor units to the outdoor unit
• The contractor shall supply and install all electrical wiring to the panel
• The contractor shall supply and install PVC condensate drain lines to the exterior of the building
• The contractor shall supply and install wall brackets for the installation of the condenser
• The contractor shall supply and install a programmable, wired wall mount controller
• The contractor shall purge, evacuate, start, and test all equipment installed during this contract
Location #3 – MAB 2113. This is an office, approximately 960 SF, is has an open plan. The existing BARD Air Conditioning system has failed and is in need of replacement. This building is located at roughly 3,8000 feet elevation.
• The contractor shall remove the existing BARD air conditioning unit and properly dispose of outside of YOSE and its refuse containers
• The contractor shall supply and install a single-phase, BARD W36AB-A15 – 3.0 ton air conditioner, 208-230 volts, 60 hz, heat strip 10KW or better (or approved equal)
• The contractor shall utilize existing ductwork
• The contractor shall perform start-up of all equipment
The contractor shall provide the following warranties in digital or hard copy format:
• 1 year workmanship and materials
• 10 years on parts by the manufacturer
• 10 years on compressors by manufacturer
The contractor shall not dispose of any waste using NPS dumpsters within Yosemite National Park or the surrounding communities.
The contractor shall keep the work area neat, orderly, and in a safe condition at all times. Store and use equipment, tool, and materials in a manner the does not present a hazard.
Prior to starting work, the contractor shall obtain hot work permits and required safety materials (fire blankets, extinguishers, per the direction of the NPS) from Yosemite fire officials. The COR will help coordinate obtaining permits. Hot work shall not be performed without permits.
The National Park Service cares for special places saved by the American people so that all may experience our heritage.
The contractor shall provide proof of universal technician type EPA certification 40 CFR 82.161 for at least one employee prior to award. This certified employee shall remain on site during work to ensure quality control.
It is the responsibility of the contractor to field verify any measurements provided in the scope of work.
Although not mandatory, it is highly recommended, contractors who would intend to bid on this project, participate in a one-day only site visit at a date to be determined. There will be no change orders or modifications to awarded contract for differing site conditions.
Additional Information
HAULING RESTRICTIONS: Vehicles over 45 feet are prohibited and 1-way controlled traffic for all other vehicles 20 miles East of Mariposa (Mariposa County) 24 hours per day, seven days per week due to rockslide repairs.
ON-SITE WORK HOURS: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated. Weekend and holiday work is not authorized.
BEAR/ ANIMAL SAFETY: Bears and other animals are active in Yosemite and surrounding areas. It is necessary for all visitors to practice bear and animal safety. Food items are not to be left in work trucks or anywhere else. The NPS provides bear boxes in campgrounds for food storage. Bear incidents are a ticketable offense in Yosemite.