2-Project Manual.pdf

PDF 6 MB Posted

Attached to
North Lehigh Avenue Lighting Project
Solicitation number
Not on record
Issued by
Somerset County, Pennsylvania

About this file

Summary of North Lehigh Avenue Lighting Project Contract Documents

This project manual contains bidding and contract documents for the Borough of Frackville, Pennsylvania, in partnership with the Pennsylvania Department of Transportation (PennDOT) and Commonwealth Financing Authority, for the construction of the North Lehigh Avenue Lighting Project. The scope of work includes installation of decorative post-top street lighting assemblies with poles and foundations, underground electrical conduit, junction boxes, and power supply equipment, plus restoration of disturbed sidewalks, pavement, and curbing throughout Frackville Borough in Schuylkill County. Bids will be received electronically via PennBid until 2:00 p.m. on January 30, 2025, with a pre-bid virtual conference scheduled for January 6, 2026, at 10:00 a.m. The contract requires PENNDOT prequalification of all bidders and mandates adherence to prevailing minimum wage rates established by the Pennsylvania Department of Labor and Industry. The work must achieve substantial completion within 90 days and final completion within 120 days after the contract times commence, with liquidated damages assessed at $500 per day for delays beyond these timeframes.

The contract is awarded on a unit price basis with estimated quantities for individual line items covering bonds and insurance, mobilization, curb and sidewalk demolition, concrete sidewalk installation, concrete curb replacement, PennDOT inspection allowance ($20,000), miscellaneous basement work allowance ($10,000), pavement restoration, lighting assembly installation (12 units), conduit installation, directional boring, underground cable, utility test pits (17 units), junction boxes (2 units), and PP&L energy services allowance ($7,500). Contractor shall include in all unit prices appropriate overhead and profit, with the contract price subject to adjustment based on actual quantities determined by the engineer. The project is partially funded by a grant from the Commonwealth of Pennsylvania, Commonwealth Financing Authority. All materials, including steel products, must be produced in the United States in compliance with the Steel Products Procurement Act. Contractors must maintain comprehensive insurance coverage including workers' compensation, commercial general liability with minimum limits of $1,000,000 per occurrence and $2,000,000 aggregate, and automobile liability. Performance and payment bonds equal to the contract price are required, and prevailing wage documentation must be submitted with each application for payment in accordance with Public Works Employment Verification Act 127.

View the file

Other files

File Type Posted
1-2025-10-27 North Lehigh Ave Lighting Project HOP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

BOROUGH OF FRACKVILLE

42 South Center Street

Frackville, Pennsylvania 17931

NORTH LEHIGH AVENUE LIGHTING PROJECT

Frackville Borough

Schuylkill County, Pennsylvania

This Project was financed in part by a grant from Commonwealth of Pennsylvania, Commonwealth Financing Authority prepared by

Entech Engineering, Inc.

201 Penn Street, Suite 300

PO Box 32 Reading, Pennsylvania 19603

610-373-6667

Issued for Bidding:

December 19, 2025

Entech No. 4140.078

Entech Engineering, Inc. Entech #4140.078

TABLE OF CONTENTS 1

TABLE OF CONTENTS

BIDDING FORMS, CONTRACT FORMS, AND CONDITIONS OF THE CONTRACT

SECTION DESCRIPTION NO. PAGES

Cover Page Table of Contents

PROJECT INFORMATION

EJCDC C-111 Invitation to Bid Document 00040 Project Information EJCDC C-200 Instructions to Bidders

BID FORM

EJCDC C-410 Bid Form Appendix A List of Subcontractors Appendix B List of Equipment and Materials Appendix C Qualification Statement (EJCDC C-451) Appendix D Public Works Employment Verification Form – Act 127 Appendix E Non Discrimination/Sexual Harassment Certification Appendix F Schedule of Labor and Equipment Prices

REFERENCE DOCUMENTS

EJCDC C-430 Bid Bond EJCDC C-510 Notice of Award EJCDC C-520 Form of Agreement Between Owner and Contractor for Construction

Contract EJCDC C-550 Notice to Proceed EJCDC C-610 Performance Bond EJCDC C-615 Payment Bond Document 00616 Statement Accepting Provisions of the

PA Workmens' Compensation Act Document 00617 Waiver of Lien EJCDC C-620 Contractor’s Application for Payment EJCDC C-625 Certificate of Substantial Completion Document 00650 Construction Schedule EJCDC C-700 General Conditions of the Construction Contract EJCDC C-800 Supplementary Conditions to General Conditions Document 00830 Prevailing Minimum Wage Determination EJCDC-940 Work Change Directive EJCDC-941 Change Order

TABLE OF CONTENTS 2

SECTION DESCRIPTION NO. PAGES

EJCDC C-942 Field Order Document 00943 Contractor's Certification of Completion

TECHNICAL SPECIFICATIONS

DIVISION 01 — GENERAL REQUIREMENTS

Section 01005 Administrative Provisions Section 01010 Summary of Work Section 01040 Allowances Section 01045 Coordination Section 01047 Cutting and Patching Section 01050 Field Engineering Section 01150 Measurements and Payments Section 01200 Project Meetings Section 01300 Submittals Section 01322 Photographic Documentation Section 01400 Quality Control Section 01500 Construction Facilities and Temporary Controls Section 01570 Traffic Regulation Section 01600 Materials and Equipment Section 01700 Mobilization and Project Closeout

DIVISION 02 THRU DIVISION 16 (NOT USED)

TABLE OF CONTENTS 3

SECTION DESCRIPTION NO. PAGES

ATTACHMENTS

Attachment A Submittal List Attachment B Steel Products Procurement Act Certification Attachment C PENNDOT HOP & Supplement Attachment D Special Provisions

DRAWINGS

PENNDOT HOP Plans

END OF TABLE OF CONTENTS

PROJECT INFORMATION

EJCDC® C-111, Advertisement for Bids for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ADVERTISEMENT FOR BIDS

General Notice

Borough of Frackville (Owner) is requesting Bids for the construction of the following Project:

North Lehigh Avenue Lighting Project Project No. 4140.078

Bids for the construction of the Project will be received electronically via the PennBid program by the Borough of Frackville until 2:00 p.m. local time, January 30 , 2025. Abstract of Bids received will be posted on PennBid.

The Project includes the following Work:

The Contract consists of but is not limited to the installation of decorative post top street lighting assemblies, poles, and foundations; installation of underground electrical conduit, junction boxes, and power supply equipment; connection to electrical service; and restoration of all disturbed sidewalks, pavement, and curbing, all within Frackville Borough, Schuylkill County, Pennsylvania. The extent of the work is described in the contract documents.

Obtaining the Bidding Documents

All project documents and details are available at no cost at PennBid (https://pennbid.bonfirehub.com).

The project is subject to the Diverse Business Requirement and provisions of Section 303 of Title 74 of Purdon’s Statutes, 74 Pa. C.S. §303. Bidders must be PENNDOT qualified.

Pre-bid Conference

A virtual pre-bid conference for the Project will be held on January 6, 2026 at 10:00 AM. through registration and link provided on PennBID. Attendance at the pre-bid conference is encouraged but not required.

Instructions to Bidders.

For all further requirements regarding bid submittal, bid security, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.

Attention is called to the fact that prevailing minimum wage rates as determined by the Secretary of the Department of Labor and Industry must be paid by the Contractors on this project and that employees and applicants for employment shall not be discriminated against because of their race, age, color, religion, sex, national origin, or handicap. Each Bidder is required to meet the requirements of Public Works Employment Verification Act, Act 127 of 2012.

Any and all steel products used or supplied in the performance of the contract or any subcontracts shall be from steel made in the United States – Steel Procurement Act.

The Borough of Frackville hereby reserves the right, which is understood and agreed to by all bidders, to refuse and reject any or all bids submitted, and also reserves the right to waive any informality in bids received. This Project was financed in part by a grant from Commonwealth of Pennsylvania, Commonwealth Financing Authority.

EJCDC® C-111, Advertisement for Bids for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Except as otherwise provided by law, no bidder may withdraw its bid for sixty (60) days after the Bid Due Date, unless the contract award is delayed by a required approval of another government agency, the sale of bonds, or the award of a grant or grants, in which case the Bids shall remain open to acceptance and shall be irrevocable for a period of one hundred twenty (120) days after the Bid Due Date.

+ + END OF ADVERTISEMENT FOR BIDS +

PROJECT INFORMATION 00040 - 1

DOCUMENT 00040 – PROJECT INFORMATION

PART 1 – PROJECT IDENTIFICATION

1.1 PROJECT NAME

A. Borough of Frackville North Lehigh Avenue Lighting Project

1.2 LOCATION

A. Frackville Borough, Schuylkill County, Pennsylvania

1.3 OWNER

A. Borough of Frackville 42 South Center Street Frackville, Pennsylvania 17931

Contact: Ron Jordan, Borough President Phone: 570-874-3860

1.4 ENGINEER

A. Entech Engineering, Inc.

PO Box 32 201 Penn Street Reading, PA 19603

Contact: Karl Leitner Phone: 717-200-8272 email: KLeitner@entecheng.com

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION 00040

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TOC Page 1 of 1

INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1— Defined Terms

Article 2— Bidding Documents

Article 3— Qualifications of Bidders

Article 4— Pre-Bid Conference

Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

Article 6— Bidder’s Representations and Certifications

Article 7— Interpretations and Addenda

Article 8— Bid Security

Article 9— Contract Times

Article 10— Substitute and “Or Equal” Items

Article 11— Subcontractors, Suppliers, and Others

Article 12— Preparation of Bid

Article 13— Basis of Bid

Article 14— Submittal of Bid

Article 15— Modification and Withdrawal of Bid

Article 16— Opening of Bids

Article 17— Bids to Remain Subject to Acceptance

Article 18— Evaluation of Bids and Award of Contract

Article 19— Bonds and Insurance

Article 20— Signing of Agreement

Article 21— Sales and Use Taxes

Article 22— Steel products procurement act

Article 23— LABOR REQUIREMENTS

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 1—DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office—The office from which the Bidding Documents are to be issued.

ARTICLE 2—BIDDING DOCUMENTS

2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.

2.03 Complete sets of the Bidding Documents may be obtained at no cost on PennBid (https://pennbid.bonfirehub.com).

2.04 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.

1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader. It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.06.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 3—QUALIFICATIONS OF BIDDERS

3.01 A PENNDOT Prequalified Bidder is to submit the following information with its Bid to demonstrate Bidder’s qualifications to perform the Work:

A. Appendix A – List of Subcontractors

B. Appendix B – List of Equipment & Materials

C. Appendix C - EJCDC C-451 Statement of Qualifications

D. Appendix D – Public Works Employment Verification Form – Act 127

E. Appendix E – Non Discrimination/Sexual Harassment Certification

F. Appendix F – Schedule of Labor and Equipment Prices

G. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.

H. Bidder’s state or other contractor license number, if applicable.

I. Bidder must provide a copy of current PENNDOT prequalified certification with Bid.

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

ARTICLE 4—PRE-BID CONFERENCE

4.01 A non-mandatory virtual pre-bid conference will be held at the time and location indicated in the Advertisement or invitation to bid. Representatives of Owner and Engineer will be present to discuss the Project. PENNDOT prequalified Bidders are encouraged to attend and participate in the conference; however, attendance at this conference is not required to submit a Bid.

4.02 Information presented at the pre-Bid conference does not alter the Contract Documents. Owner will issue Addenda to make any changes to the Contract Documents that result from discussions at the pre-Bid conference. Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.

ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

5.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

5.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.

c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

5.03 Other Site-related Documents

A. No other Site-related documents are available.

5.04 Site Visit and Testing by Bidders

A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.

B. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

C. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

D. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

5.05 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.

5.06 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Express Representations and Certifications in Bid Form, Agreement

A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

C. Bidder must be PENNDOT prequalified.

ARTICLE 7—INTERPRETATIONS AND ADDENDA

7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.

7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents via the “Clarifications from Vendors” feature in PennBid.

7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered.

7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.

ARTICLE 8—BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 10 percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

ARTICLE 9—CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.

9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS

10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer within 10 days of the issuance of the Advertisement for Bids or invitation to Bidders. Each such request must comply with the requirements of Paragraphs 7.05 and 7.06 of the General Conditions, and the review of the request will be governed by the principles in those paragraphs. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

proposed item, such approval will be set forth in an Addendum issued to all registered Bidders.

Bidders cannot rely upon approvals made in any other manner.

10.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11.01 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work with the Bid submittal on the Bid Forms provided.

11.02 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute without an increase in Bid Price.

11.03 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.

Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.

ARTICLE 12—PREPARATION OF BID

12.01 The Bid Form is included with the Bidding Documents.

A. The Bid Form is available online via PennBid’s “Bid Form – Pricing” tab.

12.02 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.

12.03 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.

12.04 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

12.05 A Bid by an individual must show the Bidder’s name and official address.

12.06 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

12.07 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

12.08 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

12.09 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

12.10 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.

ARTICLE 13—BASIS OF BID

13.01 Unit Price

A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

13.02 Allowances

A. For cash allowances the Bid price must include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.

ARTICLE 14—SUBMITTAL OF BID

14.01 Bids shall be submitted online via the PennBid Program (https://pennbid.bonfirehub.com/) by the date and time indicated in the Advertisement for Bids along with the Bid security and the other documents required to be submitted under the terms of Article 2 of the Bid Form.

ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID

15.01 A Bid may be withdrawn or modified at any time within PennBid prior to the due date and time identified in the Advertisement for Bids.

15.02 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid in accordance with all Commonwealth of Pennsylvania laws and statutes (including but not limited to Pennsylvania Act of January 23, 1974 as may be amended), the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.

ARTICLE 16—OPENING OF BIDS

16.01 Abstract of Bids received will be posted on PennBid.

ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE

17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT

18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.

18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.

18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

18.05 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

B. In the comparison of Bids, alternates will be applied in the same order of priority as listed in the Bid Form.

18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 19—BONDS AND INSURANCE

19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.

19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.

ARTICLE 20—SIGNING OF AGREEMENT

20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.

ARTICLE 21—SALES AND USE TAXES

21.01 Owner is exempt from Pennsylvania state sales and use taxes on materials and equipment to be incorporated in the Work. Said taxes must not be included in the Bid. Refer to Paragraph SC-7.10 of the Supplementary Conditions for additional information.

ARTICLE 22—STEEL PRODUCTS PROCUREMENT ACT

22.01 The Contractor shall comply with Act No. 3 of 1978, known as the “Steel Products Procurement Act”. Except as provided in this Act, the Contractor shall only supply steel products to be used in the performance of the Contract, or any subcontract thereunder, which are produced in the United States. Certificates of compliance with regard to this Act shall be supplied by the Contractor to the Engineer.

ARTICLE 23—LABOR REQUIREMENTS

23.01 By submitting a Bid Proposal, the Bidder agrees to comply with the "Pennsylvania Prevailing Wage Act" (Act of August 15, 1961, P.L. 987 as Amended).

23.02 During the performance of this Contract, the Contractor agrees as follows:

A. The Contractor will not discriminate against any employees or applicant for employment because of race, color, religion, sex, national origin, or handicap.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

B. The Contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment, without regard to race, color, religion, sex, national origin, or handicap. Such action shall include, but not be limited to, the following:

employment, upgrading, demotion, or transfer; recruitment or recruitment advertising;

layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship.

C. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices which may be provided by the Authority setting forth the provisions of this nondiscrimination clause.

D. The Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, national origin, or handicap.

E. The Contractor will send to each labor union or representative of workers with which the Contractor has a collective bargaining agreement or other contract or understanding, a notice, to be provided, advising the labor union or workers' representatives of the Contractor's commitments under this Section and shall post copies of the notice in conspicuous places available to employees and applicants for employment.

F. In the event of the Contractor's noncompliance with the nondiscrimination clauses of this Contract or with any of the said rules, regulations, or orders, this Contract may be canceled, terminated, or suspended in whole or in part and the Contractor may be declared ineligible for further Authority contracts.

G. The Contractor will include the provisions of these paragraphs in every subcontract or purchase order unless exempted.

23.03 No person who, at the time, is serving sentence in a penal or correctional institution shall be employed on the work covered by this Contract.

23.04 This project must be performed under Pennsylvania prevailing wage guidelines. Prevailing wage documents are contained in the reference section of this Project Manual.

BID FORM

EJCDC® C-410, Bid Form for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BID FORM FOR CONSTRUCTION CONTRACT

BOROUGH OF FRACKVILLE

NORTH LEHIGH AVENUE LIGHTING PROJECT

The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 1—OWNER AND BIDDER

1.01 This Bid is submitted to: Electronic bids, inclusive of all requested supporting documents, shall be submitted via the PennBid Program (https://pennbid.bonfirehub.com/).

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2—ATTACHMENTS TO THIS BID

2.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security;

B. List of Proposed Subcontractors;

C. List of Equipment and Materials;

D. Required Bidder Qualification Statement with supporting data; and

E. Public Works Employment Verification Form – Act 127

F. Non Discrimination/Sexual Harassment Certification

G. Schedule of Labor and Equipment Prices

H. Bidder’s current copy of PENNDOT prequalified certification

ARTICLE 3—BASIS OF BID—LUMP SUM BID AND UNIT PRICES

3.01 Unit Price Bids

A. Bidder will perform the following Work at the indicated unit prices

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Curbs, Sidewalks, and Pavement

Item No.

Description Unit Est Qty Unit Price Total Price

1 Bonds and Insurance LS 1

2 Mobilization LS 1

3 Curb and Sidewalk Demolition LS 1

4 Concrete Sidewalk Installation SY 150

5 Concrete Curb Replacement LF 120

6 PennDOT Inspection AL 1 $20,000.00 $20,000.00

7 Miscellaneous Basement under Sidewalk AL 1 $10,000.00 $10,000.00

8 Demobilization/Closeout LS 1

9 Misc. Unclassified Excavation CY 10

10 Misc. Cast In Place Concrete CY 10

11 Pavement Restoration SY 230

Curb and Sidewalk Subtotal

Pedestrian Lighting

12 Post Top Mount Decorative Street Light Assembly EA 12

13 2" Direct Burial Conduit LF 1428

14 3" Direct Burial Conduit LF 20

15 Trench and Backfill Type II, 24" Depth LF 1156

16 Directional Boring LF 80

17 AWG 8 Underground Cable, Copper, 1 Conductor LF 4100

18 Utility Test Pit EA 17

19 Asset Numbering System Update LS 1

20 Complete Power Supply System EA 1

21 Testing of Entire Lighting System LS 1

22 Junction Boxes EA 2

23 PP&L Energy Services for Highway Lighting AL 1 $7,500.00 $7,500.00

Pedestrian Lighting Subtotal

Total Base Bid

B. Bidder acknowledges that:

1. each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and

2. estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the Contract Documents.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 4—TIME OF COMPLETION

4.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

4.02 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 5—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF

ADDENDA

5.01 Bid Acceptance Period

A. This Bid will remain subject to acceptance for 60 days after the Bid opening, unless the contract award is delayed by a required approval of another government agency, the sale of bonds, or the award of a grant or grants, in which case this Bid shall remain open to acceptance and shall be irrevocable for a period of 120 days after the Bid opening.

5.02 Instructions to Bidders

A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.

5.03 Receipt of Addenda

A. Bidder hereby acknowledges receipt of the following Addenda:

Addendum Number Addendum Date

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Bidder’s Representations

A. In submitting this Bid, Bidder represents the following:

1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.

2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.

4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Supplementary Conditions, with respect to the Technical Data in such reports and drawings.

Bidder has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.

5. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and

(c) Bidder’s (Contractor’s) safety precautions and programs.

6. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.

7. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

8. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Bidder.

9. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

10. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

6.02 Bidder’s Certifications

A. The Bidder certifies the following:

1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.

2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.

3. Bidder has not solicited or induced any individual or entity to refrain from bidding.

4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 6.02.A:

a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.

c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.

d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BIDDER hereby submits this Bid as set forth above:

Bidder:

(typed or printed name of organization)

By:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

(typed or printed)

If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.

Attest:

(individual’s signature)

Name:

(typed or printed)

Title:

(typed or printed)

Date:

Address for giving notices:

Bidder’s Contact:

Name:

(typed or printed)

Title:

(typed or printed)

Phone:

Email:

Address:

Bidder’s Contractor License No.: (if applicable)

Entech Engineering, Inc. Entech No. 4140.078

LIST OF SUBCONTRACTORS A - 1

APPENDIX A - LIST OF SUBCONTRACTORS

The following is a list of Subcontractors submitted by:

(Bidder) dated which is an integral part of the Bid Form.

This list of Subcontractors is part of the Contract Documents. It is one of the items used to evaluate Bid Proposals. You are obligated by the Contract Documents to use Subcontractors that you list below. Only list one (1) subcontractor per Section of Work. If you intend to perform the work, indicate “None”.

SECTION OF WORK NAME

Street Lighting

Electrical

Paving

Electrical Testing

Traffic Control

LIST OF EQUIPMENT AND MATERIALS B - 1

APPENDIX B - LIST OF EQUIPMENT AND MATERIALS

The following is a list of Equipment and Materials submitted by:

dated which is an integral part of the Bid Form.

This list of Equipment and Materials is part of the Contract Documents. It is one of the items used to evaluate Bid Proposals. You are obligated by the Contract Documents to use Equipment and Materials that you list below. Only list one (1) Manufacturer per Component of Work.

COMPONENT OF WORK MANUFACTURER

All other equipment and material shall be as specified with no substitutions.

APPENDIX C

EJCDC C-451, Qualifications Statement.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

QUALIFICATIONS STATEMENT

ARTICLE 1—GENERAL INFORMATION

1.01 Provide contact information for the Business:

Legal Name of Business:

Corporate Office

Name: Phone number:

Title: Email address:

Business address of corporate office:

Local Office

Name: Phone number:

Title: Email address:

Business address of local office:

1.02 Provide information on the Business’s organizational structure:

Form of Business: ☐ Sole Proprietorship ☐ Partnership ☐ Corporation

☐ Limited Liability Company ☐ Joint Venture comprised of the following companies:

1.

2.

3.

Provide a separate Qualification Statement for each Joint Venturer.

Date Business was formed: State in which Business was formed:

Is this Business authorized to operate in the Project location? ☐ Yes ☐ No ☐ Pending

ARTICLE 2—LICENSING

2.01 Provide information regarding licensure for Business:

Name of License:

Licensing Agency:

License No: Expiration Date:

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .