2-Plant PS Bypass and Biotower Recycle Project Contract 1 Plan Drawings.pdf
PDF 9 MB Posted
- Solicitation number
- Not on record
- Issued by
- Washington County, Camp Hill Borough, Pennsylvania
About this file
This file consists of plan drawings for the Plant Pump Station (PS) Bypass and Biotower Recycle Ammonia Upgrades Project – Contract 1, prepared for the Canonsburg-Houston Joint Authority in Pennsylvania. The project involves the installation of bypass and recycle pipelines, vaults, and valves at two plant locations. Key work components include excavation to locate a 36-inch pipe from the Clarifier PS and installation of a new 24-inch recycle line to the Biotower PS, construction of a concrete vault containing a new flow meter and flow control valve, installation of a new 36-inch static mixer with associated concrete vault, provision of electrical power and control wiring and conduit, excavation to locate 18-inch and 24-inch force main lines, and installation of tees, bypass lines, and valves at the plant main pump station. Bids must be submitted electronically via PennBid no later than 2:00 p.m. prevailing time on July 1, 2026, with public bid opening at the Canonsburg Municipal Building, 68 East Pike Street, Suite 103, Canonsburg, PA 15317. A mandatory pre-bid meeting and site walkthrough is scheduled for June 12, 2026, at 10:00 a.m. at 315 Curry Hill Road, Canonsburg, PA 15317.
Proposal documents, bidding forms, plans, and specifications are available at no cost through PennBid at https://pennbid.bonfirehub.com. All bids must be submitted on forms furnished by the Canonsburg-Houston Joint Authority and must be accompanied by proposal security in the form of a certified check, bank cashier's check, treasurer's check, or bid bond equal to not less than ten percent (10%) of the total bid price. Proposal security shall be made payable to the Canonsburg-Houston Joint Authority. The contract requires payment of minimum salaries and wages as set forth in the Contract Documents. Bidders may withdraw, alter, or otherwise modify proposals within PennBid at any time prior to the submission deadline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-Plant PS Bypass and Biotower Recycle Project Contract 1 Bid Specifications.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. 230001.4 Sheet 1 of 13
BASE MAP TAKEN FROM CANONSBURG, PA
U.S.G.S. QUADRANGLE
SCALE: 1" = 1000'
CANONSBURG/HOUSTON JOINT AUTHORITY
WASHINGTON COUNTY, PENNSYLVANIA
GENERAL LOCATION MAP
CONTRACT 1
GENERAL AND ELECTRICAL
CONSTRUCTION
128 Tower Street Monongahela, PA 15063
MAY 2026
PREPARED BY :
PROJECT LOCATION
CALL BEFORE YOU DIG!
PENNSYLVANIA LAW REQUIRES
3 WORKING DAYS NOTICE FOR
CONSTRUCTION PHASE AND 10 WORKING
DAYS IN DESIGN STAGE-STOP CALL
Pennsylvania One Call System, Inc.
1-800-242-1776
POCS Serial Numbers- 20251922592
PLANT PUMP STATION BYPASS AND
BIOTOWER RECYCLE AMMONIA UPGRADES
EXISTING GAS MARKER
EXISTING GAS VALVE
EXISTING GAS SHUT-OFF
EXISTING WATER VALVE
EXISTING WATER SHUT-OFF
EXISTING FIRE HYDRANT
EXISTING UTILITY GUY ANCHOR
EXISTING LIGHT POLE
EXISTING UTILITY POLE
EXISTING STORM SEWER INLET
EXISTING SANITARY SEWER MANHOLE
EXISTING CITY MONUMENT
IRON PIN FOUND
LEGEND
DRILL HOLE
EXISTING VALVE PIT
PROPERTY/RIGHT-OF-WAY LINE (PER TAX MAPS)
EXISTING GAS LINE (APPROX.)
EXISTING UNDERGROUND TELEPHONE LINE
EXISTING POTABLE WATER LINE
EXISTING CONTOURS
EXISTING SANITARY SEWER PIPING
EXISTING SEWER LATERAL
EXISTING SANITARY SEWER MANHOLE
EXISTING SANITARY SEWER PIPING
EXISTING TELEPHONE MANHOLE
EXISTING STREET SIGN
MAIL BOX
EXISTING FENCE
EXISTING TREE STUMP
EXISTING GAS WELL
EXISTING TELEPHONE BOX
PROPOSED 12" COMPOST FILTER SOCK
PROPOSED INLET PROTECTION MAT
EXISTING NON-POTABLE WATER LINE
EXISTING YARD HYDRANT
PROPOSED 18" COMPOST FILTER SOCK
PROPOSED EROSION CONTROL BLANKET
File Name:
MILESTONES
CONSTRUCTION
AS-BUILT
AS-BID
PROJECT MANAGER:
PROJECT ENGINEER:
DRAFTSMAN:
DESIGNER:
APPROVED BY:
APPROVED BY:
SHEET NUMBER:
DRAWING NUMBER:
PROJECT NUMBER:
SCALE:
CAD File Plot Date :
DATE
PA ONE CALL
Phone: 724-263-4116
NOT PUBLISHED: ALL RIGHTS RESERVED
128 Tower Street Monongahela, PA 15063
C. GRIFFIN
A. LYNN
A. LYNN
D. ALTLAND
NO. REVISION DESCRIPTIONDATE
BID DOCUMENTSMAY 20260
CANONSBURG HOUSTON JOINT AUTHORITY
WWTP PLANT PUMP STATION BYPASS
AND BIOTOWER RECYCLE AMMONIA UPGRADE
WASHINGTON PENNSYLVANIA
DRAWING INDEX AND GENERAL NOTES
N/A
230001.4
1.2
2 of 13CHJA.PSBYPASS.dwg100.rev0(5.26.26).dwg5/26/26
TYPE
ASTM C-476 GROUT PROPORTIONS by VOLUME
PARTS BY VOLUME OF
PORTLAND CEMENT OR
BLENDED CEMENT
AGGREGATE, MEASURED IN DAMP, LOOSE CONDITION
FINE COARSE
FINE
GROUT 1
4 to 3 TIMES THE SUM OF
THE VOLUMES OF THE
CEMENTITIOUS MATERIALS
COARSE
GROUT 1
4 to 3 TIMES THE SUM OF
THE VOLUMES OF THE
CEMENTITIOUS MATERIALS
1 to 2 TIMES THE SUM OF
THE VOLUMES OF THE
CEMENTITIOUS MATERIALS
0 to 110
0 to 110
PARTS BY VOLUME OF
HYDRATED LIME OR
LIME PUTTY
Lands of:
Southpointe II Prop Owners Assn.
Parcel ID: 140-015-00-00-0011-00
Lan ds o f:
Can ons bur g H ous ton Join t Au tho rity
Par cel ID
: 14 0-0 -00 -00 -00 -14
Lands of:
Canonsburg Houston Joint Authority Parcel ID: 140-015-00-00-0011-02
Lands of:
CSX Transportation
Parcel ID: 520-013-11-00-0 002-00
Lands of:
Canonsburg Houston
Joint Authority
Parcel ID:
140-015-00-00-0011-52
Lan ds o f: N. S trab ane Exem pt P rop
Par cel ID
: 52 0-00
1-00 -00-0
-00
Lan ds o f:
Nor th S trab ane Tow nsh ip
Par cel ID
: 52 0-00
1-00 -00-0
-00
La nd s o f:
US
Po sta l S er vice Ex em pt Pr op er ty
Pa rc el I D:
0-0
-11 -00
-00
-01
Parcel ID: 520-013-11-00-0003-00
La nd s o f:
W as hin gt on Co un ty
Pa rc el I D:
0-0
-11
-00 -00
-01
Lands of:
Colleen E. Dunn & Judith A. Kramer Parcel ID: 520-013-11-00-0034-02
Lands of: Washington County Parcel ID: 520-013-00-00-0034-03
BORE HOLE 5-19
GND=931.70±
BORE HOLE 2-19
GND=929.35±
BORE HOLE 3-19
GND=930.13±
BORE HOLE 6-19
GND=928.93±
BORE HOLE 4-19
GND=927.28±
BORE HOLE 1-19
GND=927.16±
CLARIFIER
DIVISION
BOX
EFFLUENT
BOX
EFFLUENT
BOX
SCUM
BOX
SCUM
BOX
W.L.=936.00±
W.L.=936.00±
F.F.E.=930.67±
F.F.E.=930.00±
F.F.E.=93 4.5
0±
SCALE: 1"=50'
PROJECT SITE PLAN
50 1000
C h a r tie r s c r e e k
C h a r t ie r s c r e e k
C u r r y H il l
R o a d
File Name:
MILESTONES
CONSTRUCTION
AS-BUILT
AS-BID
PROJECT MANAGER:
PROJECT ENGINEER:
DRAFTSMAN:
DESIGNER:
APPROVED BY:
APPROVED BY:
SHEET NUMBER:
DRAWING NUMBER:
PROJECT NUMBER:
SCALE:
CAD File Plot Date :
DATE
PA ONE CALL
Phone: 724-263-4116
NOT PUBLISHED: ALL RIGHTS RESERVED
128 Tower Street Monongahela, PA 15063
C. GRIFFIN
A. LYNN
A. LYNN
D. ALTLAND
NO. REVISION DESCRIPTIONDATE
BID DOCUMENTSMAY 20260
CANONSBURG HOUSTON JOINT AUTHORITY
WWTP PLANT PUMP STATION BYPASS
AND BIOTOWER RECYCLE AMMONIA UPGRADE
WASHINGTON PENNSYLVANIA
PROJECT SITE PLAN
EROSION AND SEDIMENTATION CONTROL MEASURES
1" = 50'-0"
230001.4
1.3
3 of 13CHJA.PSBYPASS.dwg100.rev0(5.26.26).dwg5/26/26
PROPOSED 24" D.I. M.J.
MANUAL PLUG VALVE
W/VALVE BOX AT
SURFACE
PROPOSED 36"x36"x24"
D.I. M.J. WYE
INV. EL. APPROX. 920.5
(TB FIELD VERIFIED)
PROPOSED INFLUENT
CHAMBER BYPASS
VALVES
PROPOSED INLET
PROTECTION MATS
(REFER TO DRAWING 2.3)
(REFER TO DRAWING 3.3)
LEGEND NOTE:
REFER TO DRAWING 1.2 FOR SITE LEGEND
150 200
PROPOSED 9'x17'x10'-2"
PRE-CAST CONCRETE
FLOW METER VAULT
(REFER TO DRAWING 3.6)
PROPOSED 10'-6"x9'-5"x11'
PRE-CAST CONCRETE
STATIC MIXER VAULT
(REFER TO DRAWING 3.7)
(2) PROPOSED
24" D.I. M.J. 45°
ELBOWS
(2) PROPOSED
24" D.I. M.J.
22.5° ELBOWS
PROPOSED SOIL
STOCKPILE AREA
PROPOSED EROSION
CONTROL BLANKET
- 8' WIDE
PROPOSED SOIL
STOCKPILE AREA
PPROPOSED 24" M.J. D.I.
BIOTOWER RECYCLE
PIPE INTO EX. WET WELL
INV. EL.=924.60±
PROPOSED EROSION
CONTROL BLANKET
(IF REQUIRED)
FS12
FS12
30" D.I. OVERFLOW TO
EQUALIZATION TANK
INV. EL.=924.50± @WALL
PROPOSED 18" D.I. M.J.
MANUAL PLUG VALVE
W/VALVE BOX AT SURFACE
PROPOSED 24" D.I. M.J.
MANUAL PLUG VALVE
W/VALVE BOX AT
SURFACE
PROPOSED 24" D.I.
M.J. MANUAL PLUG
VALVE W/VALVE BOX
AT SURFACE
EXISTING 24" D.I. FORCE
MAIN FROM CANONSBURG
INV. EL.=927.10± @ WALL
EXISTING 18" D.I. FORCE
MAIN FROM CANONSBURG
INV. EL.=927.19± @ WALL
INFLUENT
CHAMBER
T/EL. 935.50
B/EL. 909.50
B/EL. 906.50
24" DIMJ CANONSBURG
FORCE MAIN
INV. EL.=927.10±
@ WALL
36" DIA. OPENING
IN MIDDLE WALL
CONC. FILLET
30" D.I. COMBINED SEWER
FROM NORTH STRABANE
SOUTHPOINTE &
WESTERN CENTER,
INV. EL.=926.00± @ WALL
INFLUENT
CHAMBER
WET WELL
WET WELL
30" DIA. OPENING
IN MIDDLE WALL
FOR OVERFLOW
B/EL.=924.50±
RSW-SG-02
INFLUENT
CHAMBER
EXISTING 24" D.I. FORCE
MAIN FROM CANONSBURG
INV. EL.=927.10± @ WALL
EXISTING 18" D.I. FORCE
MAIN FROM CANONSBURG
INV. EL.=927.19± @ WALL
T/EL. 935.50
WET
WELL
PROPOSED
24" D.I. M.J.
PLUG VALVE
PUMP ROOM
DRY WELL
T. MASONRY /EL. 946.00±
B/EL. 907.50
WET
WELL
PROPOSED 24" D.I. M.J.
MANUAL PLUG VALVE
W/VALVE BOX AT
SURFACE
PROPOSED 18" D.I. M.J.
MANUAL PLUG VALVE
W/VALVE BOX AT SURFACE
PROPOSED
24" D.I. M.J.
90° ELBOW
PROPOSED
18" D.I. M.J.
90° ELBOW
B/EL. 925.50
B/EL. 925.50
CORE HOLE INTO WET WELL
AND INSTALL NEW 24" D.I.
INFLUENT PIPE, USE LINK
SEAL OR APPROVED EQUAL
INV. EL.=927.74±
CORE HOLE INTO WET WELL
AND INSTALL NEW 18" D.I.
FORCE MAIN BYPASS, USE LINK
SEAL OR APPROVED EQUAL
CORE HOLE INTO WET WELL
AND INSTALL NEW 24" D.I.
FORCE MAIN BYPASS, USE LINK
SEAL OR APPROVED EQUAL
INV. EL.=927.74±
CORE HOLE INTO WET WELL
AND INSTALL NEW 18" D.I.
INFLUENT PIPE, USE LINK
SEAL OR APPROVED EQUAL
PROPOSED 18" D.I.
M.J. FORCE MAIN
BYPASS
INV. EL.=936.88±
PROPOSED 24" D.I.
M.J. FORCE MAIN
BYPASS
INV. EL.=927.74±
PROPOSED 24" D.I.
M.J. FORCE MAIN
BYPASS
INV. EL.=927.74±
PROPOSED 18" D.I. M.J.
MANUAL PLUG VALVE
W/VALVE BOX AT SURFACE
PROPOSED 18" D.I. M.J.
MANUAL PLUG VALVE
W/VALVE BOX AT SURFACE
PROPOSED 24" D.I.
M.J. MANUAL PLUG
VALVE W/VALVE BOX
AT SURFACE
PROPOSED 18"
D.I. M.J. TEE
PROPOSED 24"
D.I. M.J. TEE
PROPOSED 24"
D.I. M.J. TEE
PROPOSED 24"
D.I. M.J. TEE
PROPOSED 18"
D.I. M.J. TEE
GRADE EL. 933.25±
GRADE EL. 933.25±
PROPOSED
18" D.I. M.J.
90° ELBOWSEXISTING
ELECTRICAL
PANEL
EXISTING
ELECTRICAL
PANEL
EXISTING
ELECTRICAL
PANEL
PROPOSED 18" D.I.
M.J. 90° ELBOW
PROPOSED 18" D.I.
M.J. FORCE MAIN
BYPASS
INV. EL.=936.88±
PROPOSED
PIPE
SUPPORT PROPOSED 18" D.I.
M.J. 90° ELBOW
EL.=927.10± @ WALL
20" D.I. SUCTION
℄EL. 909.75
PROPOSED
18" D.I. M.J.
90° ELBOW
SOIL STOCKPILE
AREA
EROSION CONTROL
BLANKET - 8' WIDE
File Name:
MILESTONES
CONSTRUCTION
AS-BUILT
AS-BID
PROJECT MANAGER:
PROJECT ENGINEER:
DRAFTSMAN:
DESIGNER:
APPROVED BY:
APPROVED BY:
SHEET NUMBER:
DRAWING NUMBER:
PROJECT NUMBER:
SCALE:
CAD File Plot Date :
DATE
PA ONE CALL
Phone: 724-263-4116
NOT PUBLISHED: ALL RIGHTS RESERVED
128 Tower Street Monongahela, PA 15063
C. GRIFFIN
A. LYNN
A. LYNN
D. ALTLAND
NO. REVISION DESCRIPTIONDATE
BID DOCUMENTSMAY 20260
CANONSBURG HOUSTON JOINT AUTHORITY
WWTP PLANT PUMP STATION BYPASS
AND BIOTOWER RECYCLE AMMONIA UPGRADE
WASHINGTON PENNSYLVANIA
WWTP PLANT PUMP STATION
INFLUENT CHAMBER FORCE MAIN BYPASS
PLAN AND SECTIONS
1/4" = 1'-0"
230001.4
2.1
4 of 13CHJA.PSBYPASS.dwg100.rev0(5.26.26).dwg5/26/26
A2.3A2.3
INFLUENT CHAMBER FORCE MAIN BYPASS - PLAN VIEW
INFLUENT CHAMBER FORCE MAIN BYPASS - SECTION A-A
INFLUENT CHAMBER FORCE MAIN BYPASS - SECTION B-B
SCALE: 1/4" = 1'-0"
0 4' 8' 24' 32'16'
B2.3 B2.3
SCALE: 1/4" = 1'-0"
0 4' 8' 24' 32'16'
SCALE: 1/4" = 1'-0"
0 4' 8' 24' 32'16'
F.F.E.=930.67±
F.F.E.=930.00±
12'-9"
4'-8 1 2"
2'-0"
12'-1 3 4"
File Name:
MILESTONES
CONSTRUCTION
AS-BUILT
AS-BID
PROJECT MANAGER:
PROJECT ENGINEER:
DRAFTSMAN:
DESIGNER:
APPROVED BY:
APPROVED BY:
SHEET NUMBER:
DRAWING NUMBER:
PROJECT NUMBER:
SCALE:
CAD File Plot Date :
DATE
PA ONE CALL
Phone: 724-263-4116
NOT PUBLISHED: ALL RIGHTS RESERVED
128 Tower Street Monongahela, PA 15063
C. GRIFFIN
A. LYNN
A. LYNN
D. ALTLAND
NO. REVISION DESCRIPTIONDATE
BID DOCUMENTSMAY 20260
CANONSBURG HOUSTON JOINT AUTHORITY
WWTP PLANT PUMP STATION BYPASS
AND BIOTOWER RECYCLE AMMONIA UPGRADE
BIOTOWER RECYCLE LINE PLAN DETAIL
1" = 10'-0"
230001.4
3.1
5 of 13CHJA.PSBYPASS.dwg100.rev0(5.26.26).dwg5/26/26
PROPOSED 9'x17'x10'-2"
PRE-CAST CONCRETE
FLOW METER VAULT
(REFER TO DRAWING 3.6)
PROPOSED 24" D.I. M.J.
MANUAL PLUG VALVE
W/VALVE BOX AT
SURFACE
PROPOSED 36"x36"x24"
D.I. M.J. WYE
INV. EL. APPROX. 920.5
(TB FIELD VERIFIED)
PROPOSED 24" D.I. M.J.
BIOTOWER RECYCLE
PIPE INTO EX. WET WELL
INV. EL.=923.04±
PROPOSED
24" D.I. M.J.
22.5° ELBOW
(2) PROPOSED
24" D.I. M.J. 45°
ELBOWS
3.5
A3.4
A3.4
3.5 B
B
PROPOSED 4'-0" x 4'-0" ALUMINUM
WATER TIGHT DOUBLE DOOR ACCESS
HATCHES BY BILCO OR APPROVED EQUAL
SCALE: 1"=10'
BIOTOWER RECYCLE LINE PLAN DETAIL
10 200 30 40 50 60
LEGEND NOTE:
REFER TO DRAWING 1.2 FOR SITE LEGEND
PROPOSED
24" D.I. M.J.
22.5° ELBOW
PROPOSED 5'-0" x 5'-0"
ALUMINUM DOUBLE DOOR
ACCESS HATCHES BY
BILCO OR APPROVED EQUAL
PROPOSED 10'-6"x9'-5"x11'
PRE-CAST CONCRETE
STATIC MIXER VAULT
(REFER TO DRAWING 3.7)
PROPOSED 3" S.S. PIPE TO
CLARIFIER PUMP STATION
INV. EL.=924.25±
PROPOSED SOIL
STOCKPILE AREA
PROPOSED EROSION
CONTROL BLANKET
(IF REQUIRED)
PROPOSED INLET
PROTECTION MAT
PROPOSED INLET
PROTECTION MAT
WET WELL
42" DIA. INFLUENT PIPE
INV.=916.67±
W.L.=918.42±
STORAGE ROOM
F.F.E.=930.67±
36" D.I. EMERGENCY
OVERFLOW FROM
CLARIFIER PUMP
STATION WET WELL
INV.=919.00±
36" D.I. EMERGENCY OVERFLOW
TO EXISTING SECONDARY
EQUALIZATION BASIN
INV.=919.83±
OVERFLOW
T/FLARE=924.50±
T/GROUT=908.67±
BEAM "A"
BEAM
"B"
BEAM "A"
BEAM
"B"
BEAM "A"2" COVER, BOTTOM
(OVER WET WELL)
#4 BARS @ 12",
BOTTOM
#4 BARS @ 12", T&B
FROM 4" FLOOR DRAINS
INV.=926.75±
16" D.I. RECIRCULATION
LINE FROM BIO TOWERS
INV.=920.33±
24" FL. 90° FLARE ELBOW
(PUMP SUCTION, TYPCIAL)
2" SCHEDULE 80 PVC SUMP DISCHARGE
INTO WET WELL - INV.=926.00±
SUCTION CENTER
EL.=912.33±
8" S
C H
ED
U
LE
PV
C V
EN
T
PI
PE
SLAB=908.50±
3 4" 3 4"
3 4"
3 4"
PROPOSED 24" D.I.
M.J. RECYCLE LINE
INV. EL.=923.04±
Ex. 18" HDPE Stormwater Drain Pipe INV. EL.=925.55±
BIOTOWER PUMP STATION WET WELL - SECTION A-A
SCALE: 3/8" = 1'-0"
2' 4'0 6' 8' 10' 15' 20'
CORE HOLE INTO WET WELL
AND INSTALL NEW 24" D.I. M.J.
RECYCLE LINE, USE LINK
SEAL OR APPROVED EQUAL
INV. EL.=923.04±
SUPPORT REQUIRED DURING
INSTALATION OF RECYCLE LINE
(REFER TO DRAWING 3.3)
File Name:
MILESTONES
CONSTRUCTION
AS-BUILT
AS-BID
PROJECT MANAGER:
PROJECT ENGINEER:
DRAFTSMAN:
DESIGNER:
APPROVED BY:
APPROVED BY:
SHEET NUMBER:
DRAWING NUMBER:
PROJECT NUMBER:
SCALE:
CAD File Plot Date :
DATE
PA ONE CALL
Phone: 724-263-4116
NOT PUBLISHED: ALL RIGHTS RESERVED
128 Tower Street Monongahela, PA 15063
C. GRIFFIN
A. LYNN
A. LYNN
D. ALTLAND
NO. REVISION DESCRIPTIONDATE
BID DOCUMENTSMAY 20260
CANONSBURG HOUSTON JOINT AUTHORITY
WWTP PLANT PUMP STATION BYPASS
AND BIOTOWER RECYCLE AMMONIA UPGRADE
WASHINGTON COUNTY PENNSYLVANIA
WWTP BIOTOWER PUMP STATION
WET WELL - SECTION A-A
3/8" = 1'-0"
230001.4
3.2
6 of 13CHJA.PSBYPASS.dwg100.rev0(5.26.26).dwg5/26/26
W.L.=918.42±
ELECTRICAL/PUMP
HOIST ROOM
WET WELL
PUMP ROOM
SLAB.=908.50±
16" PLUG VALVE
" D
.I.
36" D.I. EFFLUENT PIPE
INV.=923.87±
C O
N C
R
ET
E
PI
PE
SU
PP
O
R T
8" S
C H
ED
U
LE
PV
C V
EN
T
PI
PE
RIDGE VENT
ALUMINUM GUTTER
& DOWNSPOUTS
STORAGE
ROOM
F.F.E.=930.67±
S.S. ACCESS LADDER
GAS UNIT
HEATER
16" D.I.
4" FLOOR DRAIN @ 2.0% SLOPE
W/ P-TRAP (TYPICAL)
ST
AI
R S
"T
IE
R
T/GROUT=910.00±
T/GROUT=908.67±
BEAM
"D"BEAM "A"
BEAM "B"
36" D.I. EMERGENCY OVERFLOW
FROM CLARIFIER PUMP
STATION WET WELL
INV.=919.00±
W16x57 MONORAIL
MAX. 3 TON CAPACITY
T/FLANGE EL.=942.67
(TYPICAL)
SHINGLES
FLUE EXHAUST & COMBUSTION
AIR DUCTS UP THROUGH ROOF
(TYPICAL)
SUCTION CENTER
EL.=912.33±
SUCTION
CENTER
EL.=912.67±
DISCHARGE CENTER
EL.=915.14±
S T
A
IR
W E
LL
SUMP DISCHARGE
INTO WET WELL
INV.=926.00±
4"
1"
3 4" 3 4"
4"
3 4"
4"
3 4"
MIN. R-38 INSULATION
BEAM
"C"
BEAM "F"
MIN. R-7.5 XPS RIGID
INSULATIONON EXTERIOR
OF CONCRETE WALL
AROUND PUMP ROOM
4"
3 4"
3 4"
GROUT SLOPE TO
PUMP SUCTION
T/SLAB=930.59±
3 4"
SUCTION
CENTER
@ ELBOW
EL.=912.75±
CONCRETE
PUMP
SUPPORT/PIER
PUMP #2
SCALE: 3/8" = 1'-0"
2' 4'0 6' 8' 10' 15' 20'
CORE HOLE INTO WET WELL
AND INSTALL NEW 24" D.I. M.J.
RECYCLE LINE, USE LINK
SEAL OR APPROVED EQUAL
INV. EL.=923.04±
BIOTOWER PUMP STATION WET WELL - SECTION B-B
(REFER TO DRAWING 3.3)
File Name:
MILESTONES
CONSTRUCTION
AS-BUILT
AS-BID
PROJECT MANAGER:
PROJECT ENGINEER:
DRAFTSMAN:
DESIGNER:
APPROVED BY:
APPROVED BY:
SHEET NUMBER:
DRAWING NUMBER:
PROJECT NUMBER:
SCALE:
CAD File Plot Date :
DATE
PA ONE CALL
Phone: 724-263-4116
NOT PUBLISHED: ALL RIGHTS RESERVED
128 Tower Street Monongahela, PA 15063
C. GRIFFIN
A. LYNN
A. LYNN
D. ALTLAND
NO. REVISION DESCRIPTIONDATE
BID DOCUMENTSMAY 20260
CANONSBURG HOUSTON JOINT AUTHORITY
WWTP PLANT PUMP STATION BYPASS
AND BIOTOWER RECYCLE AMMONIA UPGRADE
WASHINGTON COUNTY PENNSYLVANIA
WWTP BIOTOWER PUMP STATION
WET WELL - SECTION B-B
3/8" = 1'-0"
230001.4
3.3
7 of 13CHJA.PSBYPASS.dwg100.rev0(5.26.26).dwg5/26/26
GRADE
SECTION B-B
TOP VIEW
PLAN VIEW
PROPOSED CONCRETE SLAB
TOP RIM=931.17±
PRE-CAST CONCRETE VAULT
BY MACK INDUSTRIES OR
APPROVED EQUAL
PROPOSED CONCRETE SLAB
TOP RIM=931.17±
PROPOSED FLOW METER VAULT DETAIL
PROPOSED
24" D.I. M.J.
PIPE
INV.=923.04±
B 3.6
B 3.6
A 3.
A 3.
PROPOSED CONCRETE SLAB
TOP RIM=931.17±
STRUCTURAL FILL
STEEL REINFORCED POLYPROPYLENE
MANHOLE STEPS OR APPR'D. EQUAL
@ 12" SPACING
PROPOSED D.I.
M.J. PIPE
INV.=923.04±
PROPOSED 4'-0" x 4'-0" ALUMINUM WATER
TIGHT DOUBLE DOOR ACCESS HATCH BY
BILCO OR APPROVED EQUAL
PROPOSED 4'-0" x 4'-0" ALUMINUM
WATER TIGHT DOUBLE DOOR ACCESS
HATCH BY BILCO OR APPROVED EQUAL
(CENTERED IN SLAB TOP)
GRADE = 930.17±
PRE-CAST CONCRETE
VAULT BY MACK INDUSTRIES
OR APPROVED EQUAL
PROPOSED 24"
D.I. M.J. PIPE
INV.=924.60±
PROPOSED STEEL
REINFORCED
POLYPROPYLENE
MANHOLE STEPS @
12" SPACING
PROPOSED
24" D.I. M.J.
COUPLING
PROPOSED
24" D.I. M.J.
COUPLING
PROPOSED
24" D.I. M.J.
COUPLING
BOTTOM EL.=921.66
SECTION A-A
PROPOSED 24" D.I.
M.J. MODULATING
FLOW CONTROL
PLUG VALVE
PROPOSED 24" M.J.
MAGNETIC FLOW
METER (SEE SPECS)
PROPOSED 24" D.I.
M.J. MODULATING
FLOW CONTROL
PLUG VALVE
PROPOSED 24"
M.J. MAGNETIC
FLOW METER
PROPOSED 4'-0" x 4'-0" ALUMINUM
WATER TIGHT DOUBLE DOOR ACCESS
HATCHES BY BILCO OR APPROVED EQUAL
PROPOSED 24"
D.I. M.J. PIPE
INV.=923.04±
PROPOSED
24" D.I. M.J.
COUPLING
PROPOSED 24"
D.I. M.J. PIPE
INV.=923.04±
GRADE = 930.17± GRADE
PRE-CAST CONCRETE VAULT
BY MACK INDUSTRIES OR
APPROVED EQUAL
STRUCTURAL FILL
SCALE: 3/8" = 1'-0"
2' 4'0 6' 8' 10' 15' 20'
(REFER TO DRAWING 3.3)
PIPE SUPPORTS
(SEE D-1)PIPE SUPPORTS
(SEE D-1)
File Name:
MILESTONES
CONSTRUCTION
AS-BUILT
AS-BID
PROJECT MANAGER:
PROJECT ENGINEER:
DRAFTSMAN:
DESIGNER:
APPROVED BY:
APPROVED BY:
SHEET NUMBER:
DRAWING NUMBER:
PROJECT NUMBER:
SCALE:
CAD File Plot Date :
DATE
PA ONE CALL
Phone: 724-263-4116
NOT PUBLISHED: ALL RIGHTS RESERVED
128 Tower Street Monongahela, PA 15063
C. GRIFFIN
A. LYNN
A. LYNN
D. ALTLAND
NO. REVISION DESCRIPTIONDATE
BID DOCUMENTSMAY 20260
CANONSBURG HOUSTON JOINT AUTHORITY
WWTP PLANT PUMP STATION BYPASS
AND BIOTOWER RECYCLE AMMONIA UPGRADE
WASHINGTON PENNSYLVANIA
FLOW METER VAULT
PLAN AND SECTIONS
3/8" = 1'-0"
230001.4
4.1
8 of 13CHJA.PSBYPASS.dwg100.rev0(5.26.26).dwg5/26/26
GRADE
SECTION B-B
TOP VIEWPLAN VIEW
PROPOSED CONCRETE SLAB
TOP RIM=929.50±
PRE-CAST CONCRETE VAULT
BY MACK INDUSTRIES OR
APPROVED EQUAL
PROPOSED CONCRETE SLAB
TOP RIM=929.50±
PROPOSED STATIC MIXER VAULT DETAIL
B 3.7
B 3.7
A 3.
A 3.
PROPOSED CONCRETE SLAB
TOP RIM=929.50±
STRUCTURAL FILL
STEEL REINFORCED POLYPROPYLENE
MANHOLE STEPS OR APPR'D. EQUAL
@ 12" SPACING
PROPOSED 36"
D.I. M.J. PIPE
INV.=920.50±
GRADE = 928.50±
PRE-CAST CONCRETE
VAULT BY MACK INDUSTRIES
OR APPROVED EQUAL
PROPOSED 36"
D.I. M.J. PIPE
INV.=920.50±
PROPOSED STEEL
REINFORCED
POLYPROPYLENE
MANHOLE STEPS @
12" SPACING
BOTTOM EL.=919.16
SECTION A-A
PROPOSED 5'-0" x 5'-0"
ALUMINUM DOUBLE DOOR
ACCESS HATCHES BY
BILCO OR APPROVED EQUAL
PROPOSED 36"
D.I. M.J. PIPE
INV.=920.50±
PROPOSED
36" D.I. M.J.
COUPLING
GRADE = 928.50± GRADE
PRE-CAST CONCRETE VAULT
BY MACK INDUSTRIES OR
APPROVED EQUAL
STRUCTURAL FILL
SCALE: 3/8" = 1'-0"
2' 4'0 6' 8' 10' 15' 20'
(REFER TO DRAWING 3.3)
PROPOSED 5'-0" x 5'-0" ALUMINUM DOUBLE
DOOR ACCESS HATCHES BY BILCO OR
APPROVED EQUAL
PROPOSED 36"
D.I. M.J. PIPE
INV.=920.50±
PROPOSED 5'-0" x 5'-0"
ALUMINUM DOUBLE DOOR
ACCESS HATCHES BY
BILCO OR APPROVED EQUAL
PROPOSED
36" D.I. M.J.
COUPLING
PROPOSED 36"
D.I. M.J. PIPE
INV.=920.50±
PROPOSED
36" D.I. M.J.
COUPLING
PROPOSED
36" D.I. M.J.
COUPLING
PROPOSED 3" S.S. STRAIGHT PIPE
TO CLARIFIER PUMP STATION
INV. EL.=924.25±
PROPOSED RETRACTABLE
S.S. INJECTION QUILL
WITH MANUAL VALVE
AND HEAT TRACING 1/2" I.D. TUBING
WITH HEAT
TRACING
PROPOSED 3" S.S. PIPE
TO CLARIFIER PUMP STATION
INV. EL.=924.25±
PROPOSED RETRACTABLE
S.S. INJECTION QUILL
WITH MANUAL VALVE
AND HEAT TRACING
1/2" I.D. TUBING WITH
HEAT TRACING
PROPOSED
RETRACTABLE
S.S. INJECTION
QUILL WITH
MANUAL VALVE
AND HEAT
TRACING
PROPOSED 36" 316SS
STATIC MIXER WITH
316L MIXING ELEMENT
PROPOSED 36" 316SS
STATIC MIXER WITH
316L MIXING ELEMENT
File Name:
MILESTONES
CONSTRUCTION
AS-BUILT
AS-BID
PROJECT MANAGER:
PROJECT ENGINEER:
DRAFTSMAN:
DESIGNER:
APPROVED BY:
APPROVED BY:
SHEET NUMBER:
DRAWING NUMBER:
PROJECT NUMBER:
SCALE:
CAD File Plot Date :
DATE
PA ONE CALL
Phone: 724-263-4116
NOT PUBLISHED: ALL RIGHTS RESERVED
128 Tower Street Monongahela, PA 15063
C. GRIFFIN
A. LYNN
A. LYNN
D. ALTLAND
NO. REVISION DESCRIPTIONDATE
BID DOCUMENTSMAY 20260
CANONSBURG HOUSTON JOINT AUTHORITY
WWTP PLANT PUMP STATION BYPASS
AND BIOTOWER RECYCLE AMMONIA UPGRADE
WASHINGTON PENNSYLVANIA
STATIC MIXER VAULT
PLAN AND SECTIONS
3/8" = 1'-0"
230001.4
4.2
9 of 13CHJA.PSBYPASS.dwg100.rev0(5.26.26).dwg5/26/26
TRENCH BACKFILL
TIE RODS
TRENCH BACKFILL
PLAN VIEWS
CONCRETE ANCHOR BLOCKS
ELEVATION VIEW
TYPICAL THRUST
BLOCK FOR ALL
REQUIRED BENDS
NOT TO SCALE
THRUST BLOCK LOCATIONS
NOT TO SCALE
VERTICAL CHANGE ANCHOR
(TYPICAL FOR ALL PIPING EXCEPT 36" DIA.)
(TYPICAL FOR ALL FORCE MAIN PIPING)
NOTES:
1. ALL CONCRETE THRUST BLOCKS/CHANGE ANCHORS TO BE CLASS 'AA'.
2. THRUST BLOCK MUST EXTEND A MINIMUM OF 8" BELOW THE BOTTOM AND 8" MIN.
ABOVE THE TOP OF THE PIPE.
3. CHANGE ANCHOR MUST EXTEND A MINIMUM OF 8" EACH SIDE OF THE PIPE.
4. THRUST BLOCK/CHANGE ANCHOR MINIMUM LENGTH "L" MUST BE THE PIPE DIAMETER + 18".
5. THRUST BLOCK SHALL BE PLACED AGAINST UNDISTURBED OR COMPACTED TRENCH WALL.
6. CONCRETE SHALL BE KEPT BEHIND THE BELL OF ALL FITTINGS.
7. ALL FITTINGS TO USE "MEGALUG" MECHANICAL JOINT RESTRAINTS, OR APPROVED EQUAL
"L"
"L
"L
"L"
6-6/8"
11-13/16"
1-3/16"
7/8" DIA.
14"
15-5/16"
1- 1/
2"
3/
1- 1/
8" 9-
3/ 4"
1"
3/ 8"
3/8"
1-3/8" Copolymer Polypropylene Plastic
NO.3 DEFORMED STEEL ROD
TYPICAL VAULT STEPS
NOT TO SCALE
2' MIN.
D
PLAN VIEW
END THRUST BLOCK
2' MIN.
H
TRENCH
PROFILE VIEW
END THRUST BLOCK
HORIZONTAL TRUST BLOCK DETAILS
H
D
W
12"
12"
EPOXY COATED #5 REBARS
(ASTM A615 GRADE 60) (TYP.)
CONCRETE BLOCK SIZE
PER TABLE 1
CONCRETE BLOCK
SIZE PER TABLE 2
UNDISTURBED SOILW
2' M
IN
PLAN VIEW
PROFILE VIEW
VERTICAL THRUST BLOCK DETAILS
PIPE
SIZE DEAD END AND TEE
INCH DIA.
8 .5
2.5 3.5 5.5
2.5 3.5 4.5
.5
.5
6.5
.5 1.5 2.5
D H W CY D H W CY D H W CY
.5
.3 .75 1.5
4.5
HORIZONTAL
1/4 BEND
HORIZONTAL
1/8 BEND
PIPE
SIZE
HORIZONTAL
1/16 BEND
HORIZONTAL
1/32 BEND
INCH DIA.
8 .5
1.5 2.5 3.5
1.5 2.5 3.5
.25 .5
D H W CY
.5
1.5
2.5
1.5
2.5
.25 .4 .6
D H W CY
PIPE
SIZE
HORIZONTAL
1/16 BEND
HORIZONTAL
1/32 BEND
INCH DIA.
8 4.5
3.5
D H W CY
4.5
.5
2.25
D H W CY
TABLE 1
D IS THE DIMENSION INTO UNDISTURBED GROUND IN FEET
H IS HEIGHT OF THE THRUST BLOCK IN FEET
W IS WIDTH OF THRUST BLOCK IN FEET
ALL DIMENSIONS ARE MINIMUM.
THRUST BLOCKS IN LOOSE FILL OR SAND AREAS ARE NOT
INCLUDED IN THERE TABLES AND WILL REQUIRE ADDITIONAL
ANALYSIS.
TABLE 2
18 1 6.5 5 2.5 1 7.75 5.5 3 1 4.5 1.8755.25
18 1 4 4 1.25 1 2.75 2.75 .7
18 8 6 6.5 13 2 5.25 4.5 2.875
BEDDING MATERIAL
- AASHTO #67 OR
AASHTO #8
COARSE AGGREGATE
SPECIAL TRENCH BACKFILL
- PennDOT NO. 2A
COMPACT TO MIN. 95% MPD
MPD = MODIFED PROCTOR DENSITY
(ASTM D-1557)
OR
NATIVE TRENCH BACKFILL
(REFER TO RESTORATION DETAILS)
NOT TO SCALE
STANDARD TRENCH BEDDING DETAIL
12" 12"O.D.
6" 6"
PIPE DIA.
VARIES
TRENCH WIDTH
PROPOSED PIPE (SEE SITE PLANS FOR SIZE)
(FOR USE WITH ALL PIPING EXCEPT CONTINUOUSLY PERFORATED STORM PIPE,
USE INFILTRATION TRENCH BEDDING DETAIL BELOW)
SEE PLANS FOR
PIPE SIZE
6" 6"
VA
R
IE
S
6" 2A CRUSHED LIMESTONE
TRENCH DETAIL #1
MINIMUM CONSTRUCTION & RESTORATION DETAIL FOR
IN
DRIVEWAYS HAVING GRAVEL SURFACES
TRENCHING AND/OR SURFACE EXCAVATIONS
O.D.
AASHTO #8 STONE
PIPE BEDDING
SELECT BACKFILL
PaDOT 2A TYPE 'C'
PIPE TRENCH
+24" min.
(MAX. PAYMENT WIDTH=6')
MIN.
12"
MIN.
12"
NOT TO SCALE
EXISTING GRAVEL
SURFACE
NOT TO SCALE
ADJUSTABLE RISER
& VALVE BOX.
4" SHAFT SIZE
PROPOSED VALVE
GRADE
VA
R
IE
S
NOT TO SCALE
VALVE BOX DETAIL
"WATER" OR "SEWER" ON LID
SOLID CONC. BLOCK
12"x8"x4"
PROVIDE & INSTALL
STEM ROD (NUT)
EXTENSION AS NEEDED
FOR DEEP VALVES TO
WITHIN 3-ft OF GROUND
SURFACE
PROPOSED 34"x8"x8" STEEL
BASE PLATE
2" OF PROPOSED
NON-SHRINK GROUT
(8) PROPOSED 34" DIA. GALVANIZED
HEX NUTS AND WASHERS
5" 6"
C O
N
TR
AC
TO
R T
O
VE
R
IF
Y
H
EI
G H
T R
EQ
U
IR
ED
PROPOSED ADJUSTABLE CRADLE PIPE SUPPORT
(GRINNELL FIG. 264 OR APPROVED EQUAL)
PROPOSED 4" DIA. STD. WT.
STEEL SCH. 40 PIPE
DRILL EXISTING FLOOR SLAB AND
PLACE ALL THREAD IN EPOXY
ADHESIVE "SET" BY SIMPSON
STRONG-TIE OR EQUAL
EXISTING CONCRETE
FLOOR SLAB
SCALE: 1"=1'-0"
TYPE "1" PIPE SUPPORT DETAIL
(4) PROPOSED 34" DIA. x 11" LG.
GALVANIZED ANCHOR ROD OR
ALL THREAD
PROPOSED PIPE
WIDTH "W"
LE
N
G
TH
"L
CLASS "AA" CONCRETE
THRUST BLOCK
36" DIA. M.J. FITTING
24" & 36" DIA. THRUST BLOCK DETAIL
PIPE SIZE MAX. PIPE PRESSURE 90° ELBOW 45° ELBOW 22.5° ELBOW
MIN. BEARING AREA ("L" x "W" x "H") *
24" & 36" DIA. 50 psi 52 SQ.FT.
(11'-6" L x 4'-6" W x 4'-6" H)
* BASE ON 1500 PSF ALLOWABLE SOIL BEARING PRESSURE
28 SQ.FT.
(6'-3" L x 4'-6" W x 4'-6" H)
52 SQ.FT.
(3'-3" L x 4'-6" W x 4'-6" H)
PLAN VIEW
SECTION VIEW
CLASS "AA" CONCRETE
THRUST BLOCK
WIDTH "W"
H
EI
G H
T "H
1' -4
" M
IN
1' -4
" M
IN
36" DIA. M.J. FITTING
NOTES:
1. THRUST BLOCK SHALL BE PLACED AGAINST UNDISTURBED OR COMPACTED TRENCH WALL.
2. CONCRETE SHALL BE KEPT BEHIND THE BELL OF ALL FITTINGS.
3. ALL FITTINGS TO USE "MEGALUG" MECHANICAL JOINT RESTRAINTS, OR APPROVED EQUAL
NOT TO SCALE
File Name:
MILESTONES
CONSTRUCTION
AS-BUILT
AS-BID
PROJECT MANAGER:
PROJECT ENGINEER:
DRAFTSMAN:
DESIGNER:
APPROVED BY:
APPROVED BY:
SHEET NUMBER:
DRAWING NUMBER:
PROJECT NUMBER:
SCALE:
CAD File Plot Date :
DATE
PA ONE CALL
Phone: 724-263-4116
NOT PUBLISHED: ALL RIGHTS RESERVED
128 Tower Street Monongahela, PA 15063
C. GRIFFIN
A. LYNN
A. LYNN
D. ALTLAND
NO. REVISION DESCRIPTIONDATE
BID DOCUMENTSMAY 20260
CANONSBURG HOUSTON JOINT AUTHORITY
WWTP PLANT PUMP STATION BYPASS
AND BIOTOWER RECYCLE AMMONIA UPGRADE
WASHINGTON PENNSYLVANIA
SITE DETAILS
N/A
230001.4
D-1
10 of 13CHJA.PSBYPASS.dwg100.rev0(5.26.26).dwg5/26/26
F.F.E.=930.67±
F.F.E.=930.00±
12'-9"
4'-8 1 2"
2'-0"
12'-1 3 4"
File Name:
MILESTONES
CONSTRUCTION
AS-BUILT
AS-BID
PROJECT MANAGER:
PROJECT ENGINEER:
DRAFTSMAN:
DESIGNER:
APPROVED BY:
APPROVED BY:
SHEET NUMBER:
DRAWING NUMBER:
PROJECT NUMBER:
SCALE:
CAD File Plot Date :
DATE
PA ONE CALL
Phone: 724-263-4116
NOT PUBLISHED: ALL RIGHTS RESERVED
128 Tower Street Monongahela, PA 15063
C. GRIFFIN
A. LYNN
A. LYNN
D. ALTLAND
NO. REVISION DESCRIPTIONDATE
BID DOCUMENTSMAY 20260
CANONSBURG HOUSTON JOINT AUTHORITY
WWTP PLANT PUMP STATION BYPASS
AND BIOTOWER RECYCLE AMMONIA UPGRADE
BIOTOWER RECYCLE LINE ELECTRICAL DETAIL
1" = 10'-0"
230001.4
E-1
11 of 13CHJA.PSBYPASS.dwg100.rev0(5.26.26).dwg5/26/26
3.5
A3.4
30 40 50 60
A3.4
3.5 B
B
SCALE: 1"=10'
BIOTOWER RECYCLE LINE ELECTRICAL DETAIL
10 200
Existing MCC
2#12, 1#12G, IN 3/4"C FROM
EXISTING LP-BPB TO NEW
FLOWMETER TRANSMITTER
Existing
SCADA
Cabinet
NEW FLOWMETER
TRANSMITTER
1x FLOWMETER TRANSMITTER
CABLE IN 1" CONDUIT FROM
NEW FLOWMETER TRANSMITTER
TO FLOWMETER
Existing LP-BPB
208/120V 3PH
4W Panel
1x CAT6A SHIELDED
ETHERNET CABLE IN 1"
CONDUIT FROM EXISTING
SCADA CABINET TO
ACTUATOR IN FLOW
METER VAULT
3#10, 1#10G IN 1"C FROM
SPARE 30A BREAKER IN
EXISTING MCC TO
ACTUATOR DISCONNECT
Existing LP-CPB
208/120V 3PH
4W Panel
2#12, 1#12G IN 1" C
FROM EXISTING LP-CPB
TO NEW RECEPTACLE IN
STATIC MIXER VAULT
PROVIDE WEATHERPROOF WALL
MOUNTED RECEPTACLE IN STATIC
MIXER VAULT. 125V, 20A NEMA
5-20R, 2 POLE, 3 WIRE GROUNDED
TYPE GFCI
NOTES:
1. FOR ALL CONDUIT OUTSIDE, AT MINIMUM 1" CONDUIT
BE INSTALLED UNDERGROUND, 12" BELOW GRADE, 3"
CONCRETE ENCASED IF CROSSING THE ROADWAY.
ACTUATOR DISCONNECT:
3 POLE FUSED DISCONNECT
WITH FAST ACTING FUSES.
NEMA 4XSS. MANUFACTURER
SHALL SUPPLY APPROPRIATE
FUSE HOLDER AND FUSES FOR
INSTALLATION BY CONTRACTOR
NEW FLOW CONTROL
VALVE ACTUATOR
NEW FLOWMETER
3#10, 1#10G IN 1"C FROM
ACTUATOR DISCONNECT
TO ACTUATOR
1x 16/2 TSP WIRE IN
3/4"C FROM NEW
FLOWMETER
TRANSMITTER TO
EXISTING SCADA
CABINET
File Name:
MILESTONES
CONSTRUCTION
AS-BUILT
AS-BID
PROJECT MANAGER:
PROJECT ENGINEER:
DRAFTSMAN:
DESIGNER:
APPROVED BY:
APPROVED BY:
SHEET NUMBER:
DRAWING NUMBER:
PROJECT NUMBER:
SCALE:
CAD File Plot Date :
DATE
PA ONE CALL
Phone: 724-263-4116
NOT PUBLISHED: ALL RIGHTS RESERVED
128 Tower Street Monongahela, PA 15063
C. GRIFFIN
A. LYNN
A. LYNN
D. ALTLAND
NO. REVISION DESCRIPTIONDATE
BID DOCUMENTSMAY 20260
CANONSBURG HOUSTON JOINT AUTHORITY
WWTP PLANT PUMP STATION BYPASS
AND BIOTOWER RECYCLE AMMONIA UPGRADE
EROSION AND SEDIMENTATION DETAILS
NTS
230001.4
ES-1
12 of 13CHJA.PSBYPASS.dwg100.rev0(5.26.26).dwg5/26/26
STANDARD CONSTRUCTION DETAIL #4-1
Compost Filter Sock
SPECIFICATIONS: The Department recommends the use of the Penn State publication, "Erosion Control and Conservation Plantings on Noncropland," as the standard to use for the selection of species, seed specifications, mixtures, liming and fertilizing, time of seeding, and seeding methods. Specifications for these items may also be obtained from PennDOT's Publication # 408, Section 804 or by contacting the applicable county conservation district. Upon selection of a reference, that reference should be used to provide all specifications for seeding, mulching, and soil amendments. The following specification will be used for this project:
STANDARD E&S WORKSHEET #21: TEMPORARY AND PERMANENT
VEGETATIVE STABILIZATION SPECIFICATIONS
(TEMPORARY) SPECIES: Annual Ryegrass Formula "E"*
% PURE LIVE SEED: 98 %
APPLICATION RATE: 48 LB./ACRE
FERTILIZER TYPE: 10/20/20 (X-X-X)
FERTILIZER APPL. RATE: 678 LB./ACRE
LIMING RATE: 40 (see specification 02900) LBS/1000 SF MULCH TYPE: hydroseeding/cellulose wood fiber
MULCHING RATE: 0.75 T./ACRE
(PERMANENT) SPECIES: Annual Ryegrass Formula "B"**
% PURE LIVE SEED: 98 %
APPLICATION RATE 172 LB./ACRE
FERTILIZER TYPE: 10/20/20 (X-X-X)
FERTILIZER APPL. RATE: 678 LB./ACRE
LIMING RATE: 40 (see specification 02900) LBS/1000 SF MULCH TYPE: hydroseeding/cellulose wood fiber
MULCHING RATE: 0.75 T./ACRE
(PERMANENT - STEEP SLOPE) SPECIES: Crown Vetch Formula "C"**
PURE LIVE SEED: 99 %
APPLICATION RATE: 44 LB./ACRE
FERTILIZER TYPE: 10/20/20 (X-X-X)
FERTILIZER APPL. RATE: 678 LB./ACRE
LIMING RATE: 40 (see specification 02900) T./ACRE MULCH TYPE: Curlex I Erosion Control Blanket or equiv
MULCHING RATE: N/A T./ACRE
ANCHOR MATERIAL: PerDetail Drawing ANCHORING METHOD: PerDetail Drawing
RATE OF ANCHOR MATERIAL APPL.: LB./ACRE
(FORESTED AREAS) SPECIES: Annual Ryegrass Formula "D"**
PURE LIVE SEED: 98 %
APPLICATION RATE: 172 LB./ACRE
FERTILIZER TYPE: 10/20/20 (X-X-X)
FERTILIZER APPL. RATE: 678 LB./ACRE
LIMING RATE: 40 (see specification 02900) T./ACRE MULCH TYPE: hydroseeding/cellulose wood fiber
MULCHING RATE: 0.75 T./ACRE
30 98
0.15
0.15
0.15 0.10
0.15 0.15
0.15
0.15
** Seed Specifications Minimum % Max. % % by Mass Purity Germination Weed Seed Formula "E" Annual Ryegrass
Formula "B" Perennial Ryegrass Mix Creeping Red Fescue Or Chewings Fescue Kentucky Bluegrass Mix
Formula "C" Crown Vetch Annual Ryegrass
Formula "D" Tall Fescue Creeping Red Fescue Or Chewings Fescue
STANDARD CONSTRUCTION DETAIL #26
Pumped Water Filter Bag
PLAN VIEW
ELEVATION VIEW
STABILIZATION METHODS AND STANDARDS (Continued)
· SEEDING
Seed mixtures shall comply with Standard E&S Worksheet #21. Seeding rates are stated as pounds per acre (lb/A) of pure live seed (PLS). PLS is the product of the percentage of pure seed times the percentage of germination divided by 100 (e.g. [85% pure seed 72% germination] ÷ 100 = 61% PLS). Seed should not be used later than one year after the test date that appears on the label. Use of seed older than one year could result in less than satisfactory vegetative coverage and the need to re-seed the disturbed area. Actual seeding rates may be determined by dividing the PLS seeding rate by the %PLS shown on the seed tag, or calculated as shown above (e.g. for a PLS seeding rate of 12 lb/A from a seed lot with a PLS of 35%, the actual seeding rate is equal to 12 ÷ 0.35 = 34.3 lb/A). If more than one species is used, indicate the application rate for each species. A nurse crop may be necessary if the selected species do not rapidly germinate. If a nurse crop is used in conjunction with permanent seeding, the nurse crop should not hinder the establishment of the permanent vegetation. A nurse crop should not be applied at a rate exceeding 50% of its temporary seeding rate.
The Department recommends that soil testing be done prior to seeding and mulching to determine the proper soil amendments and application rates for the proposed seed mixture(s). In the absence of a soil test, soil amendments should be added at the rates specified by the selected seeding reference.
Fill slopes should be seeded and mulched at regular vertical increments -- 15 to 25 feet maximum -- as the fill is being constructed. This will allow the bottom of the fill to progress toward stabilization while work continues on the upper portion, making final stabilization easier to achieve and providing some vegetative buffering at the bottom of the slope.
Wherever seed and mulch is applied by hydroseeding methods, the seed and mulch should be applied in separate applications with the seed being applied first and the mulch sprayed on top of the seed. This is to ensure that the seed makes contact with the underlying soil. Soil preparation should be completed prior to adding seed to the hydroseeding equipment. Running seed through the pumping system can result in excessive abrasion of the seed and reduce the percentage of pure live seed in the application. Therefore all site preparation should be completed prior to the arrival of the hydroseeder.
In critical areas (e.g. adjacent to or within 50 feet of streams, ponds, or wetlands) a protective blanket should be provided for all seeded areas. Consideration should be given to use of mulch with netting or protective blankets for all seeded areas on slopes 3H:1V or steeper.
Vehicular traffic should be restricted from areas to be seeded to prevent soil compaction.
· TOPSOIL APPLICATION
Graded areas should be scarified or otherwise loosened to a depth of 3 to 5 inches to permit bonding of the topsoil to the surface areas and to provide a roughened surface to prevent topsoil from sliding down slope.
Topsoil should be uniformly distributed across the disturbed area to a depth of 4 to 8 inches minimum -- 2 inches on fill outslopes. Spreading should be done in such a manner that sodding or seeding can proceed with a minimum of additional preparation or tillage. Irregularities in the surface resulting from topsoil placement should be corrected in order to prevent formation of depressions unless such depressions are part of the PCSM plan.
Topsoil should not be placed while the topsoil or subsoil is in a frozen or muddy condition, when the subsoil is excessively wet, or in a condition that may otherwise be detrimental to proper grading and seedbed preparation.
Compacted soils should be scarified 6 to 12 inches along contour wherever possible prior to seeding.
· SPILL CONTROL
Spill control procedures are implemented anytime chemicals and/or hazardous substances are stored or used at the construction site. Substances include, but are not limited to fuel, lubricants, hydraulic fluids, coolants, paint, etc.
The spillage should be stopped as soon as it can be done safely, and the cleaned up immediately. Clean contaminated area, and properly dispose of contaminated materials properly. For all spills, notify the project foreman. Use the following spill prevention and controls when applicable:
· To the extent that it doesn't compromise clean-up activities, spills shall be covered and protected from stormwater run-on during rainfall,
· Spills shall not be buried or diluted with wash water,
· Used clean up materials, contaminated materials, and recovered spill material shall be stored and disposed of in accordance with federal, state and local regulations,
· Use absorbent materials on spills, rather than using water to hose down the spill,
· When water is used for cleaning and decontamination of a spill, the water shall not be allowed to enter stormwater conveyance or watercourses, and shall be collected and disposed of properly,
· All spill contaminated soil will be removed and disposed of properly,
· The condition of hydraulic equipment shall be visually assessed for potential leaks prior to use in the immediate vicinity approx. 25 feet of Swale.
· MULCHING
All seeded areas should be mulched or blanketed to minimize the potential for failure to establish an adequate vegetative cover. Mulching may also be used as a temporary stabilization of some disturbed areas in non-germinating seasons. Mulches should be applied at the rates shown in Table 11.6 (Appendix).
Straw and hay mulch should be anchored or tackified immediately after application to prevent being windblown. A tractor-drawn implement may be used to "crimp" the straw or hay into the soil -- about 3 inches. This method should be limited to slopes no steeper than 3H:1V. The machinery should be operated on the contour. Note: Crimping of hay or straw by running over it with tracked machinery is not recommended.
Polymeric and gum tackifiers mixed and applied according to manufacturer's recommendations may be used to tack mulch. Avoid application during rain and on windy days. A 24-hour curing period and a soil temperature higher than 45 F. are typically required. Application should generally be heaviest at edges of seeded areas and at crests of ridges and banks to prevent loss by wind. The remainder of the area should have binder applied uniformly. Binders may be applied after mulch is spread or sprayed into the mulch as it is being blown onto the soil. Applying straw and binder together is generally more effective. Synthetic binders, or chemical binders, may be used as recommended by the manufacturer to anchor mulch provided sufficient documentation is provided to show they are non-toxic to native plant and animal species.
Mulch on slopes of 8% or steeper should be held in place with netting. Lightweight plastic, fiber, or paper nets may be stapled over the mulch according to manufacturer's recommendations.
Shredded paper hydromulch should not be used on slopes steeper than 5%. Wood fiber hydromulch may be applied on steeper slopes provided a tackifier is used. The application rate for any hydromulch should be 2,000 lb/acre at a minimum.
E&SCP GENERAL NOTES (Continued)
· Immediately after earth disturbance activities cease in any area or subarea of the project, the operator shall stabilize all disturbed areas. During non-germinating months, mulch or protective blanketing shall be applied as described in the plan. Areas not at finished grade, which will be reactivated within 1 year, may be stabilized in accordance with the temporary stabilization specifications. Those areas which will not be reactivated within 1 year shall be stabilized in accordance with the permanent stabilization specifications.
· Permanent stabilization is defined as a minimum uniform, perennial 70% vegetative cover or other permanent non-vegetative cover with a density sufficient to resist accelerated erosion. Cut and fill slopes shall be capable of resisting failure due to slumping, sliding, or other movements.
· E&S BMPs shall remain functional as such until all areas tributary to them are permanently stabilized or until they are replaced by another BMP approved by the local conservation district or the Department.
· Upon completion of all earth disturbance activities and permanent stabilization of all disturbed areas, the owner and/or operator shall contact the local conservation district for an inspection prior to removal/conversion of the E&S BMPs.
· After final site stabilization has been achieved, temporary erosion and sediment BMPs must be removed or converted to permanent post construction stormwater management BMPs. Areas disturbed during removal or conversion of the BMPs shall be stabilized immediately. In order to ensure rapid revegetation of disturbed areas, such removal/conversions are to be done only during the germinating season.
· Upon completion of all earth disturbance activities and permanent stabilization of all disturbed areas, the owner and/or operator shall contact the local conservation district to schedule a final inspection.
· Failure to correctly install E&S BMPs, failure to prevent sediment-laden runoff from leaving the construction site, or failure to take immediate corrective action to resolve failure of E&S BMPs may result in administrative, civil, and/or criminal penalties being instituted by the Department as defined in Section 602 of the Pennsylvania Clean Streams Law. The Clean Streams Law provides for up to $10,000 per day in civil penalties, up to $10,000 in summary criminal penalties, and up to $25,000 in misdemeanor criminal penalties for each violation.
· Concrete wash water shall be handled in the manner described on the plan drawings. In no case shall it be allowed to enter any surface waters or groundwater systems.
· All channels shall be kept free of obstructions including but not limited to fill, rocks, leaves, woody debris, accumulated sediment, excess vegetation, and construction material/wastes.
· Underground utilities cutting through any active channel shall be immediately backfilled and the channel restored to its original cross-section and protective lining. Any base flow within the channel shall be conveyed past the work area in the manner described in this plan until such restoration is complete.
· Channels having riprap, Reno mattress, or gabion linings must be sufficiently over-excavated so that the design dimensions will be provided after placement of the protective lining.
· Erosion control blanketing shall be installed on all slopes 3H:1V or steeper within 50 feet of a surface water and on all other disturbed areas specified on the plan maps and/or detail sheets.
· Fill material for embankments shall be free of roots, or other woody vegetation, organic material, large stones, and other objectionable materials. The embankment shall be compacted in maximum 8" layered lifts at 95% maximum dry density.
DISPOSAL OF CONSTRUCTION WASTES
All construction wastes associated with erosion and sedimentation control shall be disposed of in a landfill.
Specifically, all compost sock rings will be disposed of in a landfill once removed, after site final stabilization.
DOCUMENTATION
The contractor is responsible for keeping all reports on routine inspections up-to- date, including any records of product replacement or cleaning. Weekly inspections are required for:
1) Compost Filter Sock
2) Inlet Filter Bags
3) Erosion control mulch blanket 4)Riprap slope protection
5) Vegetation stabilization
A log showing dates that E&S BMPs were inspected, as well as any deficiencies found and the date they were corrected, shall be maintained on the site and be made available to regulatory agency officials at the time of inspection.
E&SCP GENERAL NOTES
· All earth disturbances, including clearing and grubbing as well as cuts and fills shall be done in accordance with the approved E&S plan. A copy of the approved drawings (stamped, signed and dated by the reviewing agency) must be available at the project site at all times. The reviewing agency shall be notified of any changes to the approved plan prior to implementation of those changes. The reviewing agency may require a written submittal of those changes for review and approval at its discretion.
· At least 7 days prior to starting any earth disturbance activities, including clearing and grubbing, the owner and/or operator shall invite all contractors, the landowner, appropriate municipal officials, the E&S plan preparer, the PCSM plan preparer, the licensed professional responsible for oversight of critical stages of implementation of the PCSM plan, and a representative from the local conservation district to an on-site preconstruction meeting.
· At least 3 days prior to starting any earth disturbance activities, or expanding into an area previously unmarked, the Pennsylvania One Call System Inc. shall be notified at 1-800-242-1776 for the location of existing underground utilities.
· All earth disturbance activities shall proceed in accordance with the sequence provided on the plan drawings. Deviation from that sequence must be approved in writing from the local conservation district or by the Department prior to implementation.
· Areas to be filled are to be cleared, grubbed, and stripped of topsoil to remove trees, vegetation, roots and other objectionable material.
· Clearing, grubbing, and topsoil stripping shall be limited to those areas described in each stage of the construction sequence. General site clearing, grubbing and topsoil stripping may not commence in any stage or phase of the project until the E&S BMPs specified by the BMP sequence for that stage or phase have been installed and are functioning as described in this E&S plan.
· At no time shall construction vehicles be allowed to enter areas outside the limit of disturbance boundaries shown on the plan maps. These areas must be clearly marked and fenced off before clearing and grubbing operations begin.
· Care should be taken when working along the perimeter of the site; in no event shall work extend beyond the limits shown on the plan.
· Topsoil required for the establishment of vegetation shall be stockpiled at the location(s) shown on the plan maps(s) in the amount necessary to complete the finish grading of all exposed areas that are to be stabilized by vegetation. Each stockpile shall be protected in the manner shown on the plan drawings. Stockpile heights shall not exceed 35 feet. Stockpile slopes shall be 2H:1V or flatter.
· Immediately upon discovering unforeseen circumstances posing the potential for accelerated erosion and/or sediment pollution, the operator shall implement appropriate best management practices to minimize the potential for erosion and sediment pollution and notify the local conservation district and/or the regional office of the Department.
· All building materials and wastes shall be removed from the site and recycled or disposed of in accordance with the Department's Solid Waste Management Regulations at 25 Pa. Code 260.1 et seq., 271.1, and 287.1 et. seq. No building materials or wastes or unused building materials shall be burned, buried, dumped, or discharged at the site.
· All off-site waste and borrow areas must have an E&S plan approved by the local conservation district or the Department fully implemented prior to being activated.
· The contractor is responsible for ensuring that any material brought on site is clean fill. Form FP-001 must be retained by the property owner for any fill material affected by a spill or release of a regulated substance but qualifying as clean fill due to analytical testing.
· All pumping of water from any work area shall be done according to the procedure described in this plan, over undisturbed vegetated areas.
· Until the site is stabilized, all erosion and sediment BMPs shall be maintained properly. Maintenance shall include inspections of all erosion and sediment BMPs after each runoff event and on a weekly basis. All preventative and remedial maintenance work, including clean out, repair, replacement, re-grading, re-seeding, re-mulching and re-netting must be performed immediately. If the E&S BMPs fail to perform as expected, replacement BMPs, or modifications of those installed will be required.
· Sediment tracked onto any public roadway or sidewalk shall be returned to the construction site by the end of each work day and disposed in the manner described in this plan. In no case shall the sediment be washed, shoveled, or swept into any roadside ditch, storm sewer, or surface water.
· All sediment removed from BMPs shall be disposed of in the manner described on the plan drawings.
· Areas which are to be topsoiled shall be scarified to a minimum depth of 3 to 5 inches -- 6 to 12 inches on compacted soils -- prior to placement of topsoil. Areas to be vegetated shall have a minimum 4 inches of topsoil in place prior to seeding and mulching. Fill outslopes shall have a minimum of 2 inches of topsoil.
· All fills shall be compacted as required to reduce erosion, slippage, settlement, subsidence or other related problems. Fill intended to support buildings, structures and conduits, etc. shall be compacted in accordance with local requirements or codes.
· All earthen fills shall be placed in compacted layers not to exceed 9 inches in thickness.
· Fill materials shall be free of frozen particles, brush, roots, sod, or other foreign or objectionable materials that would interfere with or prevent construction of satisfactory fills.
· Frozen materials or soft, mucky, or highly compressible materials shall not be incorporated into fills.
· Fill shall not be placed on saturated or frozen surfaces.
· Seeps or springs encountered during construction shall be handled in accordance with the standard and specification for subsurface drain or other approved method.
· All graded areas shall be permanently stabilized immediately upon reaching finished grade. Cut slopes in competent bedrock and rock fills need not be vegetated. Seeded areas within 50 feet of a surface water, or as otherwise shown on the plan drawings, shall be blanketed according to the standards of this plan.
INITIAL CONSTRUCTION
1. Install compost sock and inlet filter bags.
2. Construct wastewater facilities.
a. Clear and grub area as necessary for construction of tanks, buildings and installation of piping.
b. Separate topsoil from subsoil during excavation.
c. Install proposed piping, valves, vaults.
d. Any groundwater encountered during trench excavation shall be pumped into a pumped-water filter bag.
e. Install outfall structure with riprap.
f. Install erosion control blanket on all disturbed areas on side slope of Chartiers Creek.
g. Disturbed areas shall receive temporary seeding or compacted roadway subbase material within 4 days after disturbance ends.
4. Landscaping: Fine grade, place topsoil, amendments, seed and mulch all areas including staging areas.
a. Scarify graded areas to prevent topsoil from sliding on slopes.
b. Contractor is responsible to test soils prior to the application of amendments such as lime and fertilizer.
c. Do not place topsoil while the topsoil or subsoil is frozen or muddy or when the subsoil is excessively wet to allow proper grading and seedbed preparation.
d. Distribute topsoil across disturbed areas to a minimum depth of 4 inches, 2 inches minimum on fill outslopes. Correct surface irregularities to prevent formation of depressions.
e. Seed and mulch all disturbed areas following “Temporary and Permanent Vegetative Stabilization Specifications”.
6. Remove and properly dispose of temporary E&S controls after a uniform 70% vegetative perennial cover has been established.
EROSION AND SEDIMENT CONTROL INSPECTOR NOTE:
1. Note to Contractor: A written inspection report, on the Washington County Conservation District's Standard Form must be kept on a regular basis and must be available upon request.
STABILIZATION METHODS AND STANDARDS
· GENERAL
As soon as slopes, channels, ditches, and other disturbed areas reach final grade they must be stabilized. Upon completion or temporary cessation of the earth disturbance activity in a special protection watershed, that portion of the project site tributary to the special protection waters must be immediately stabilized. In all other watersheds, cessation of activity for at least 4 days requires temporary stabilization.
Keeping stabilization current with earthmoving is recommended for all projects, regardless of watershed classification. This chapter is intended to provide guidance and specifications for stabilization as well as information that is useful in achieving stabilization in the least amount of time.
· VEGETATIVE STABILIZATION
All disturbed areas that have not otherwise been stabilized and have significant potential for erosion should be stabilized with vegetation. This includes graded areas where it is anticipated that future earthmoving will take place within the coming year. Areas that will be subject to earthmoving within 12 months may be stabilized with temporary seed mixtures, predominantly annual grasses. All others should be stabilized with permanent seed mixtures -- predominantly perennial grasses. When final grade is achieved during non-germinating months, the area should be mulched until the beginning of the next planting season. However, the area will not be considered stabilized until a minimum uniform 70% vegetative cover of erosion resistant perennial species has been achieved. Critical areas --erodible soils, within 50 feet of a surface water, etc. -- should be blanketed.
Temporary erosion control BMPs that were installed for the earthmoving phase of the project must remain in place and be maintained in working order until permanent stabilization is achieved.
NOTE: Areas that do not receive sufficient sunlight to support vegetation (e.g.
under bridge decks) should be stabilized by some means other than vegetation.
As disturbed areas within a project approach final grade, preparations should be made for seeding and mulching to begin (i.e. anticipate the completion date and schedule the seeder).
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .