2_Noyes Levee Repairs_Specifications.pdf

PDF 2 MB Posted

Attached to
St. Vincent Township - Noyes Levee Repair
Solicitation number
W912ES25BA007
Issued by

About this file

This document is a comprehensive project specification for the Noyes Levee Repair project located in St. Vincent Township, Minnesota. The project involves repairing approximately 3,150 linear feet of levee damaged during spring flooding, with work consisting of stripping topsoil, removing debris and damaged soil, and recompacting levee fill from existing levee and borrow areas. Key technical requirements include excavating levee fill material from a designated borrow location, placing fill in 8-inch uncompacted layers, compacting to 95% Standard Proctor Density, and maintaining specific moisture content parameters between -1.0% to +3.0% of optimum.

The project also includes additional scope elements such as cleaning and televising two existing culverts, placing topsoil, seeding levee slopes with a native seed mix, installing erosion control blankets, and restoring the borrow pit area. The work will be performed under solicitation W912ES25BA007 by the U.S. Army Corps of Engineers St. Paul District, with specifications detailing precise technical requirements for earthwork, seeding, environmental protection, and quality control. The project specifications mandate strict adherence to testing protocols, environmental regulations, and specific construction methodologies to ensure proper levee restoration and long-term stability.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Noyes Levee Repair NOYES

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00.00 13 GENERAL

01 14 00.00 13 WORK RESTRICTIONS

01 22 00.00 10 MEASUREMENT AND PAYMENT

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 41 26.00 13 MINNESOTA NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 04.00 13 CONTRACTOR QUALITY CONTROL

01 50 02.00 13 TEMPORARY CONSTRUCTION FACILITIES

01 57 20.00 13 ENVIRONMENTAL PROTECTION

01 71 23.05 13 CONTRACTOR SURVEYS

01 78 02.00 10 CLOSEOUT SUBMITTALS

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION AND DECONSTRUCTION

DIVISION 31 - EARTHWORK

31 00 00.00 13 EARTHWORK

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 92 19.01 13 SEEDING

DIVISION 33 - UTILITIES

33 01 30.16 TV INSPECTION OF SEWER LINES

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00.00 13

GENERAL

PART 1 GENERAL

1.1 ORGANIZATION OF SPECIFICATIONS

1.2 USE OF REFERENCES

PART 2 PRODUCTS

2.1 RECYCLED/RECOVERED MATERIALS

PART 3 EXECUTION

3.1 DISPOSAL OF DEBRIS AND WASTE

3.1.1 Burning

3.1.2 Disposal offsite for useful purposes

3.1.3 Disposal in a locally operated sanitary landfill

3.1.4 Disposal of Solid Construction Debris and Waste

3.2 SCHEDULING

3.2.1 General

3.2.2 Notification

3.3 OTHER WORK

-- End of Section Table of Contents --

SECTION 01 00 00.00 13 Page 1 April 18, 2025

SECTION 01 00 00.00 13

GENERAL

PART 1 GENERAL

The Noyes Levee Repairs Project is located in St.Vincent Township Noyes, Minnesota. The purpose of this project is to repair approximately 3150 feet of levee that was damaged in spring flooding. Levee damage must be repaired by stripping topsoil, debris, and damaged soil from the levee and recompacting levee fill excavated from the existing levee and borrow area.

Work includes the placement of seed, erosion control matting, and borrow pit restoration. The two existing culverts through the levee are to be cleaned out and a televised inspection performed to confirm there are no deficiencies.

1.1 ORGANIZATION OF SPECIFICATIONS

The specifications which govern the materials and equipment to be furnished and the work to be performed under this Contract are listed in the Table of Contents. No attempt has been made in the specifications to segregate work to be performed by any trade, craft, or subcontractor. Any segregation between the trades or crafts must be solely a matter for agreement between the Contractor, Contractor's employees, and subcontractors.

1.2 USE OF REFERENCES

Reference to the standards, specifications, or codes of any technical society, organization, or association, or local, State, or Federal authority must mean the specific edition or revision listed.

Various publications are referenced in other sections of the specifications to establish requirements for the work. Any referenced publication is to be used solely for technical requirements. Measurement and payment and any other matters respecting the administration of this Contract must be governed by the terms of this Contract without considering any referenced publication. These references are identified in each section by document number, date and title. The addresses, phone numbers, and Internet addresses (if available) for references cited in these specifications are listed in the Unified Facilities Guide Specification: UFGS 01 42 00 SOURCES FOR REFERENCE PUBLICATIONS. The UFGS 01 42 00 is available on the TECHINFO page of the Corps of Engineers Huntsville District Internet site:

http://www.hnc.usace.army.mil/Missions/Engineering-Directorate/TECHINFO/.

PART 2 PRODUCTS

2.1 RECYCLED/RECOVERED MATERIALS

Government procurement policy is to acquire, in a cost effective manner, items containing the highest percentage of recycled and recovered materials practicable consistent with maintaining a satisfactory level of competition without adversely affecting performance requirements or exposing suppliers' employees to undue hazards from the recovered materials. The Environmental Protection Agency (EPA) has designated certain items which must contain a specified percent range of recovered or recycled materials. EPA designated products specified in this Contract comply with the stated policy and with the EPA guidelines. The Contractor must make all reasonable efforts to use recycled and recovered materials in providing the EPA designated products

SECTION 01 00 00.00 13 Page 2 April 18, 2025 and in otherwise utilizing recycled and recovered materials in the execution of the work.

PART 3 EXECUTION

3.1 DISPOSAL OF DEBRIS AND WASTE

The Contractor's attention is directed to Section 01 57 20.00 13 ENVIRONMENTAL PROTECTION and to the following CONTRACT CLAUSES: 52.236-7

PERMITS AND RESPONSIBILITIES; 52.236-9 PROTECTION OF EXISTING VEGETATION,

STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS; 52.236-10 OPERATIONS

AND STORAGE AREAS; and 52.236-12 CLEANING UP. Burning will not be permitted at the project site and debris or waste must not be left on the site.

Disposal of debris and waste must be by one of the following methods:

3.1.1 Burning

Burning will not be permitted at the project site.

3.1.2 Disposal offsite for useful purposes

In the interest of conservation, make a reasonable effort to dispose of the material offsite for some useful purpose. For example, cut timber into convenient lengths for saw logs, posts, cordwood, wood chips, paper making or other uses.

3.1.3 Disposal in a locally operated sanitary landfill

Select the disposal site with the approval of the Contracting Officer.

3.1.4 Disposal of Solid Construction Debris and Waste

Remove and dispose of solid construction debris and waste in compliance with Federal, State, and local requirements for solid waste disposal. Select the disposal site with the approval of the Contracting Officer.

3.2 SCHEDULING

3.2.1 General

Schedule and execute the work, incorporating the necessary requirements set forth in these specifications. Develop and submit a schedule in accordance with Section 01 32 01.00 13 PROJECT SCHEDULE and CONTRACT CLAUSE: 52.236-15

SCHEDULES FOR CONSTRUCTION CONTRACTS.

3.2.2 Notification

Inform the Government in writing, at the pre-construction conference, as to which hours of the day and days of the week for which work will be performed. Notify the Government at least 24 hours before work is to be conducted on overtime, in multiple shifts, on weekends, or on Federal Government holidays.

SECTION 01 00 00.00 13 Page 3 April 18, 2025

3.3 OTHER WORK

The Contractor must contact the other local units of government for work they may have going on in the area and coordinate work and schedules to prevent any delays in this Contract.

-- End of Section --

SECTION 01 00 00.00 13 Page 4 April 18, 2025

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 14 00.00 13

WORK RESTRICTIONS

PART 1 GENERAL

1.1 GROUNDS AND ROADWAYS

1.1.1 Parking

1.1.2 Snow Removal

1.2 BLASTING

1.3 INTERNATIONAL BORDER

1.4 SUBMITTALS

PART 2 EXECUTION

2.1 EXISTING UTILITIES

2.1.1 General

2.1.2 Buried Utilities

2.1.3 Interruption of Services

2.1.4 Minnesota One Call Excavation Notice System

2.2 PROTECTION OF TREES

2.2.1 Restoration of Damaged Trees

2.3 CONTRACTOR PROPOSED BORROW AND DISPOSAL AREAS

2.4 EXISTING FACILITIES

SECTION 01 14 00.00 13 Page 1 April 18, 2025

SECTION 01 14 00.00 13

WORK RESTRICTIONS

PART 1 GENERAL

1.1 GROUNDS AND ROADWAYS

1.1.1 Parking

Contractor parking must be coordinated with the Government.

1.1.2 Snow Removal

The Contractor is responsible for snow removal in the Contractor's access, work, and parking areas.

1.2 BLASTING

Blasting will not be permitted.

1.3 INTERNATIONAL BORDER

Contractor must carefully identify and mark the international border between the United States and Canada. All work and work activities must remain within the border of the United States. Do not conduct work activities in Canada without prior approval from the Contracting Officer and the United States Customs and Border Protection.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Interruption Of Services;G

PART 2 EXECUTION

2.1 EXISTING UTILITIES

2.1.1 General

Coordinate all utility relocation requirements. The Contractor is responsible for payment to the utility companies for all services, fees, and permits required to relocate and reestablish service. Protect all existing utilities.

2.1.2 Buried Utilities

Notify the Contracting Officer immediately if the Contractor damages any existing utility lines not intended to be removed. Repair of damaged

SECTION 01 14 00.00 13 Page 2 April 18, 2025 utilities must be in accordance with CLAUSE 52.236-9 PROTECTION OF EXISTING

VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS.

2.1.3 Interruption of Services

Utility services must not be interrupted except for brief periods to facilitate cut-ins. Provide temporary service and relocate existing utilities as required to construct the work shown and insure uninterrupted service. If interruption of services is unavoidable, request approval in writing at least15 calendar days prior to the proposed interruption. This submittal must fully describe all details of proposed interruption and the reasons why alternatives are not feasible. Information contained in the submittal must include, but not be limited to, utilities being affected, duration of outage, and any sketches required to support the submittal.

Coordinate with the owner of the utility and notify affected consumers at least 10 calendar days in advance of interruption of services. The Contracting Officer will not approve proposals which require interruption of services for more than 4 continuous hours.

2.1.4 Minnesota One Call Excavation Notice System

For contract work performed within the State of Minnesota, the Contractor must meet the requirements of Minnesota Statutes, Chapter 216D "Excavation Notice System." The Gopher State One Call notification center telephone numbers are:

Twin Cities Metro Area (651) 454-0002 Outstate (800) 252-1166

2.2 PROTECTION OF TREES

Trees outside of the clearing and grubbing limits or trees designated to remain must be protected as indicated below. The location of the tree protection fence must be staked by the Contractor and approved by the Contracting Officer.

The following measures must be implemented for tree protection and must be addressed in the Environmental Protection Plan required under Section

01 57 20.00 13 ENVIRONMENTAL PROTECTION:

a. The trees must be protected from wounds to the bark and foliage.

b. The critical root zone must be protected from compaction and grading.

c. Changes in temporary site drainage and ponding that affect the protected trees must be minimized to the extent possible.

The critical root zone of trees designated to be protected must be surrounded by a high visibility fence 4 feet in height, supplied and erected by the Contractor. The critical root zone is defined by an area extending 1.5 feet radius from each tree for each inch of Diameter at Breast Height (DBH). The fence must be securely erected and installed prior to any movement through the project site by construction vehicles or equipment, and remain in place until construction and clean-up are completed. The critical root zone must remain free of all construction activities including trenching, staging, stockpiling and storage of materials. Vehicles and equipment must not drive or park within the

SECTION 01 14 00.00 13 Page 3 April 18, 2025 critical root zone. Variation to the critical root zone size or configuration will only be permitted where it is absolutely necessary for construction of the project, and requires approval of the Contracting Officer. Short duration alterations of the critical root zone involving wood chips and limited equipment travel must be submitted in writing for approval.

Do not operate equipment in vegetated areas outside the work limits.

2.2.1 Restoration of Damaged Trees

Any existing tree designated to be protected that is damaged by the Contractor's operations must be replaced. Trees will be considered damaged if the critical root zone in cohesive soils is compacted, if there are significant wounds that could contribute to rot, or if distress (evident by reduced growth or other observations of distress documented by a forester) is observed prior to closing the contract. Trees must be replaced in kind on a caliper inch per caliper inch basis (DBH) (e.g. one 6-inch red oak must be replaced with two 3-inch red oaks, three 2-inch red oaks, or six 1-inch red oaks). Replacement tree size and location will be determined and staked by the Contracting Officer. Repair by pruning, aeration, soil conditioning, or other recommendation from a qualified forester will be considered by the Contracting Officer for substitution for replacement.

2.3 CONTRACTOR PROPOSED BORROW AND DISPOSAL AREAS

Any borrow and/or disposal areas proposed by the Contractor that are not already identified by the Government as approved for this project are subject to approval by the Contracting Officer. Evaluation requirements for suitability of Contractor proposed borrow materials are addressed in Section 31 00 00.00 13 EARTHWORK. Proposed borrow and/or disposal areas which involve the excavation or placement of material within cultural sites, wetlands, wooded areas, floodplain areas, or other environmentally sensitive sites may not be approved. The use of Contractor proposed borrow and/or disposal areas that are not preapproved may require the Government to prepare an environmental assessment. Preparation of an assessment would be completed by the Government at no cost to the Contractor. However, this may require additional review time and may result in additional requirements to offset environmental effects associated with the use of the proposed borrow and/or disposal areas. Unless the Contractor's proposed borrow and/or disposal areas are active commercial operations or are sites that have already been approved by the Government for this project, they must not be used for the project unless coordination with the State Historic Preservation Office (SHPO) regarding a previous or current Phase I cultural resources survey of the proposed borrow pit or disposal site is completed and documented. All costs associated with development of a new Phase I cultural resource survey to evaluate any Contractor selected borrow and/or disposal area as well as any costs associated with additional requirements for an environmental assessment must be borne by the Contractor. Also, there will be no schedule revisions based on the additional time required by the Government to evaluate the proposed borrow and/or disposal areas.

2.4 EXISTING FACILITIES

Contractor must protect existing gatewells structure and concrete pipes at station 38+47 and station 49+78 as shown on the as-built drawings. Prior to starting work, inspect and document the condition of the gatewells and

SECTION 01 14 00.00 13 Page 4 April 18, 2025 pipes in the presence of the government representative. After completion of the project the Contractor must reinspect the gatewells and pipes in the presence of the government. Any damage to the gatewells and or pipes due to the Contractor must be the responsibility of the Contractor to correct. If the Contractor's means and methods warrant concern about damaging the gatewell and the pipe the Contractor must employ special protective measures such as load distribution platforms to protect the existing infrastructure at no additional cost to the government.

Prior to starting work the contractor shall inspect and document the condition of the of the levee crown and side slopes, within the work areas, in the presence of the government. After completion of the project the Contractor must reinspect the levee crown and slopes in the presence of the Government. Exercise care to limit damage to the levee crown and side slopes. Any rutting or other damage done to the levee crown or slopes must be repaired by the Contractor at no additional cost to the government.

SECTION 01 14 00.00 13 Page 5 April 18, 2025

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 COMPENSATION

1.2 APPROVAL OF MATERIALS OR ALTERNATES

1.3 QUANTITY SURVEYS

1.4 MEASUREMENT UNITS

1.5 SUBMITTALS

1.6 JOB PAYMENT ITEMS

1.6.1 BONDS (Performance and Payment)

1.6.1.1 Payment

1.6.1.2 Unit of Measure

1.6.2 Culvert Cleaning

1.7.2.1 Payment

1.6.2.1 Unit of Measure

1.6.3 Culvert Inspection

1.6.3.1 Payment

1.6.3.2 Unit of Measure

1.6.4 Temporary Erosion and Sediment Control

1.6.4.1 Payment

1.6.4.2 Unit of Measure

1.6.5 Borrow Pit Restoration

1.6.5.1 Payment

1.6.5.2 Unit of Measure

1.6.6 Turf Maintenance

1.6.6.1 Payment

1.6.6.2 Unit of Measure

1.6.7 Grubbing

1.6.7.1 Payment

1.6.7.2 Unit of Measure

1.6.8 Temporary Access Ramp

1.6.8.1 Payment

1.6.8.2 Unit of Measure

1.7 UNIT PRICE PAYMENT ITEMS

1.7.1 Levee Fill

1.7.1.1 Payment

1.7.1.2 Measurement

1.7.1.3 Unit of Measure

1.7.2 Topsoil

1.7.2.1 Payment

1.7.2.2 Measurement

1.7.2.3 Unit of Measure

1.7.3 Seeding Levee Slopes

1.7.3.1 Payment

1.7.3.2 Measurement

1.7.3.3 Unit of Measure

1.7.4 Erosion Control Blanket

SECTION 01 22 00.00 10 Page 1 April 18, 2025

1.7.4.1 Payment

1.7.4.2 Measurement

1.7.4.3 Unit of Measure

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

SECTION 01 22 00.00 10 Page 2 April 18, 2025

SECTION 01 22 00.00 10

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 COMPENSATION

The payment provided for in the contract must constitute full compensation for furnishing all materials and for performing all work under the contract in a complete and acceptable manner. The contract work must include providing bonds (performance and payment), plant, equipment, tools, supplies, labor, supervision, incidental materials, quality control, environmental protection, meeting safety requirements, and performing all work required for which separate payment is not otherwise provided.

Compensation for all work shown, specified, or essential to completion of the project (whether or not the specific material or operation is indicated) must be included in the bid price. The payment provided for in the contract includes compensation for all risk, loss, damage, and expense arising out of the nature of the work or its prosecution, subject to conditions of the contract. Payment for each contract line item will constitute full compensation for furnishing the materials and constructing the work complete in place as specified.

All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, must be included in the item most closely associated with the work involved. It is the responsibility of the contractor to ensure that its pricing is not materially unbalanced and that the prices presented for each line item or subline item accurately reflect the work effort associated with those items, inclusive of overhead costs.

1.2 APPROVAL OF MATERIALS OR ALTERNATES

Requests for approval of materials and products, or substitutes thereof, will not be considered prior to award of the contract.

1.3 QUANTITY SURVEYS

Provide quantity surveys for bulk materials measured by volume or weight, unless an alternate method of measurement is specified. Quantity surveys are specified in Section 01 71 23.05 13 CONTRACTOR SURVEYS.

1.4 MEASUREMENT UNITS

When materials are measured in units other than the measurement units specified as the basis of payment, the measured quantities must be converted to the specified unit of measure. Factors for conversions from one basis or unit of measurement to another must be approved by the Contracting Officer.

SECTION 01 22 00.00 10 Page 3 April 18, 2025

1.5 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following must be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-03 Product Data

Delivery Ticket

Submit certified delivery tickets.

1.6 JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the Bid Schedule and described below. The job price and payment made for each item listed shall constitute full compensation for performing all work required for which separate payment is not otherwise provided.

1.6.1 BONDS (Performance and Payment)

1.6.1.1 Payment

Payment will be made for Performance and Payment Bonds required by this contract in accordance with FAR 52.232-5 paragraph (g).

1.6.1.2 Unit of Measure

Unit of measure: job.

1.6.2 Culvert Cleaning

1.7.2.1 Payment

Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for cleaning all existing culverts through the levee. Items of this work include, but are not limited to, cleaning and or heavy cleaning of all material found in the existing culverts.

1.6.2.1 Unit of Measure

Unit of measure: job.

1.6.3 Culvert Inspection

1.6.3.1 Payment

Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for inspecting all existing culverts through the levee. Items of this work include, but are not limited to, performing a televised inspection of each culvert, and recording any found deficiencies.

SECTION 01 22 00.00 10 Page 4 April 18, 2025

1.6.3.2 Unit of Measure

Unit of measure: job.

1.6.4 Temporary Erosion and Sediment Control

1.6.4.1 Payment

Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for maintaining erosion and sediment control features throughout the project. This item includes the preparation of the Stormwater Pollution Prevention plan per specification 01 41 26.00 13.

1.6.4.2 Unit of Measure

Unit of measure: job.

1.6.5 Borrow Pit Restoration

1.6.5.1 Payment

Payment will be made for furnishing all materials, equipment, and labor and performing all operations necessary for borrow pit restoration as specified. This includes but is not limited to final grading, spreading, and compaction of unused materials, surface preparation for seed, seeding, and mulching.

1.6.5.2 Unit of Measure

Unit of measure: Job.

1.6.6 Turf Maintenance

1.6.6.1 Payment

Payment will be made for furnishing all materials, equipment, and labor and performing all operations necessary for the maintenance of all seeded areas as specified. This includes but not limited to watering, reseeding, site visits, and reporting of activities until the turf is acceptable.

1.6.6.2 Unit of Measure

Unit of measure: job.

1.6.7 Grubbing

1.6.7.1 Payment

Payment will be made for furnishing all materials, equipment, and labor and performing all operations necessary for grubbing as indicated. Work

SECTION 01 22 00.00 10 Page 5 April 18, 2025 includes, but is not limited to, removal and disposal of woody vegetation stumps and roots.

1.6.7.2 Unit of Measure

Unit of measure: job.

1.6.8 Temporary Access Ramp

1.6.8.1 Payment

Payment will be made for furnishing all materials, equipment, and labor and performing all operations necessary for the construction, deconstruction, and maintenance of all temporary access ramps.

1.6.8.2 Unit of Measure

Unit of Measure: job.

1.7 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract for which contract unit price payments will be made are listed in the bid schedule and described below.

The unit price and payment made for each item listed shall constitute full compensation for performing all work required for each of the unit price items.

1.7.1 Levee Fill

1.7.1.1 Payment

Payment will be made for furnishing all materials, equipment, and labor and performing all operations necessary for the placement of levee fill as shown and specified. Work includes, but not limited to, stripping damaged area to competent material, excavation of levee fill from the borrow location, hauling, soil processing, placement, compaction, grading, and all required testing.

1.7.1.2 Measurement

Levee fill must be measured for payment by the cubic yard of acceptably placed material, after compaction and shaping to grade is complete. The quantity will be determined by the Quantity Surveys for Measurement and Payment specified in Section 01 71 23.05 13 CONTRACTOR SURVEYS. Fill outside the lines and grades shown will not be measured.

1.7.1.3 Unit of Measure

Unit of Measure: cubic yard.

SECTION 01 22 00.00 10 Page 6 April 18, 2025

1.7.2 Topsoil

1.7.2.1 Payment

Payment will be made for furnishing all materials, equipment, and labor and performing all operations necessary for the placement of topsoil. Work shall include stripping topsoil from the borrow source, stockpiling, hauling, and placement of topsoil to the lines and grades of the repair area as specified.

1.7.2.2 Measurement

Topsoil will be measured for payment by the cubic yard of placed material.

The quantity will be determined by the Quantity Surveys for Measurement and Payment specified in Section 01 71 23.05 13 CONTRACTOR SURVEYS. Topsoil placed outside of the lines and grades shown will not be measured.

1.7.2.3 Unit of Measure

Unit of measure: cubic yard.

1.7.3 Seeding Levee Slopes

1.7.3.1 Payment

Payment will be made for furnishing all materials, equipment, and labor and performing all operations necessary for seeding the levee slopes within the repair areas as specified. Work will include, but is not limited to, soil preparation, and placement of seed.

1.7.3.2 Measurement

Seeding will be measured for payment by the square yard. The area measured for payment will be limited to the areas designated for seeding the levee slopes as specified. The quantity will be determined by the Quantity Surveys for Measurement and Payment specified in Section 01 71 23.05 13

CONTRACTOR SURVEYS.

1.7.3.3 Unit of Measure

Unit of measure: square yard.

1.7.4 Erosion Control Blanket

1.7.4.1 Payment

Payment will be made for furnishing all materials, equipment, and labor and performing all operations necessary for the installation of the erosion control blanket as shown and specified.

SECTION 01 22 00.00 10 Page 7 April 18, 2025

1.7.4.2 Measurement

Erosion control blanket will be measured for payment by the square yard.

The area measured for payment will be limited to the areas designated for erosion control blanket as specified. The quantity will be determined by the Quantity Surveys for Measurement and Payment specified in Section

01 71 23.05 13 CONTRACTOR SURVEYS.

1.7.4.3 Unit of Measure

Unit of Measure: square yard.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

SECTION 01 22 00.00 10 Page 8 April 18, 2025

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01.00 10

PROJECT SCHEDULE

PART 1 GENERAL

1.1 SUBMITTALS

1.2 PROJECT SCHEDULER QUALIFICATIONS

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.2 BASIS FOR PAYMENT

3.3 SOFTWARE

3.3.1 Use of Critical Path Method

3.3.2 Level of Detail Required

3.3.3 Activity Durations

3.3.4 Procurement Activities

3.3.5 Critical Activities

3.3.6 Government Activities

3.3.7 Responsibility

3.3.8 Feature of Work

3.3.9 Scheduled Project Completion

3.3.10 Constraint of Last Activity

3.3.11 Early Project Completion

3.3.12 Interim Completion Dates

3.3.13 Default Progress Data Disallowed

3.3.14 Out-of-Sequence Progress

3.3.15 Extended Non-Work Periods

3.3.16 Negative Lags

3.4 PROJECT SCHEDULE SUBMISSIONS

3.4.1 Initial Project Schedule Submission

3.4.2 Project Schedule Updates

3.4.3 Standard Activity Coding Dictionary

3.5 SUBMISSION REQUIREMENTS

3.5.1 Earnings Reports

3.5.2 Network Diagram

3.6 PERIODIC PROGRESS MEETINGS

3.6.1 Meeting Attendance

3.6.2 Progress Meeting Contents

3.7 REQUESTS FOR TIME EXTENSIONS

3.7.1 Justification of Delay

3.7.2 Time Extension

3.8 RECOVERY SCHEDULE

3.9 OWNERSHIP OF FLOAT

3.10 TRANSFER OF SCHEDULE DATA INTO RESIDENT MANAGEMENT SYSTEM

SECTION 01 32 01.00 10 Page 1 April 18, 2025

SECTION 01 32 01.00 10 Page 2 April 18, 2025

SECTION 01 32 01.00 10

PROJECT SCHEDULE

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications; G

Initial Project Schedule; G

Periodic Schedule Update; G

1.2 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of Critical Path Method scheduling principles and application.

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Pursuant to the Contract Clause, SCHEDULES FOR CONSTRUCTION CONTRACTS (FAR 52.236-15), a project schedule as described below shall be prepared. The scheduling of construction must be the responsibility of the Contractor.

Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must contribute in developing and maintaining an accurate project schedule. The approved project schedule must be used to measure the progress of the work, to aid in evaluating time extensions, and to provide the basis of progress payments.

3.2 BASIS FOR PAYMENT

The project schedule must be the basis for measuring Contractor progress.

The Contracting Officer will use an approved project schedule to evaluate Contractor progress for payment purposes. In the case where project

SECTION 01 32 01.00 10 Page 3 April 18, 2025 schedule revisions have not been included in the project schedule, then the Contracting Officer may hold retaking up to the maximum allowed by contract, each payment period, until the project schedule updates have been accepted.

3.3 SOFTWARE

Use Computer software systems that are capable of providing all requirements of this specification.

3.3.1 Use of Critical Path Method

The project schedule must be clearly show the critical path. If a network analysis system is used, the Critical Path Method (CPM) of network calculation must be used to generate the project schedule, provided in either the Precedence Diagram Method (PMD) or the Arrow Diagram Method

(ADM).

3.3.2 Level of Detail Required

The project schedule shall include an appropriate level of detail. The Contracting Officer will use, but is not limited to, the following conditions to determine the appropriate level of detail to be used in the project schedule.

3.3.3 Activity Durations

Delineate job contract line items into subcategories, or activities. The number of activities shall be sufficient to allow the progress to be accurately determined between payment periods.

3.3.4 Procurement Activities

Tasks related to the procurement of long lead materials or equipment shall be included as separate activities in the project schedule. Long lead materials and equipment are those materials that have a procurement cycle of over 90 calendar days. Examples of procurement activities include, but are not limited to: submittals, approvals, procurement, fabrication, and delivery.

3.3.5 Critical Activities

The following activities must be listed as separate line activities on the Contractor's project schedule:

a. Prefinal inspection

b. Correction of punchlist from prefinal inspection.

c. Final inspection.

3.3.6 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, inspections, utility tie-in, Government furnished property, and notice to proceed for phasing requirements.

SECTION 01 32 01.00 10 Page 4 April 18, 2025

3.3.7 Responsibility

All activities shall be identified in the project schedule by the party (Prime Contractor, subcontractor, Government agency, etc.) responsible to perform the work. Activities shall not belong to more than one responsible party. The responsible party for each activity shall be identified by the Responsibility Code.

3.3.8 Feature of Work

All activities shall be identified in the project schedule according to the feature of work to which the activity belongs. Feature of work refers to, but is not limited to, a work breakdown structure for the project schedule. The feature of work for each activity shall be identified by the Feature of Work Code.

3.3.9 Scheduled Project Completion

The schedule interval shall extend from notice to proceed to the contract completion date. The notice to proceed date shall be taken as the date that notice to proceed was received.

3.3.10 Constraint of Last Activity

Completion of the last activity in the project schedule shall be constrained by the contract completion date. If the early finish of the last activity falls after the contract completion date, then the critical path shall show a negative float.

3.3.11 Early Project Completion

If the project schedule shows project completion prior to the contract completion date, the Contractor shall identify activities that have been accelerated and activities that are scheduled in parallel to support the "early" completion.

3.3.12 Interim Completion Dates

Contractually specified interim completion dates shall also be constrained to show negative float if the early finish date of the last activity in that phase falls after the interim completion date.

3.3.13 Default Progress Data Disallowed

Document the actual start and actual finish dates on the daily quality control report for every in-progress or completed activity and ensure that the data contained on the daily quality control reports is the sole basis for project schedule updating. Actual Start and Finish dates shall not be automatically updated by default mechanisms that may be included in CPM scheduling software systems. Actual start and finish dates on the CPM schedule shall match those dates provided from Contractor quality control reports.

3.3.14 Out-of-Sequence Progress

Notify the Contracting Officer prior to work on any activities that are out-of-sequence with the project schedule. The Contractor shall update the project schedule to correct any out-of-sequence work.

SECTION 01 32 01.00 10 Page 5 April 18, 2025

3.3.15 Extended Non-Work Periods

Identify Non-work periods of over 5 working days by addition of activities that represent the delays.

3.3.16 Negative Lags

Lag durations contained in the project schedule shall not have a negative value.

3.4 PROJECT SCHEDULE SUBMISSIONS

The Contractor shall provide the submissions as described below.

3.4.1 Initial Project Schedule Submission

The project schedule shall provide a reasonable sequence of activities which represent work through the entire contract period and shall be at a reasonable level of detail.

3.4.2 Project Schedule Updates

Based on the result of progress meetings, submit periodic project schedule updates not later than 4 working days after every monthly progress meeting.

The updated project schedule shall contain all approved progress, revisions and adjustments, based on the regular progress meeting.

The Contractor shall also furnish information and project schedule data, which in the judgment of the Contracting Officer, is necessary for verifying the Contractor's progress.

3.4.3 Standard Activity Coding Dictionary

The Contractor shall submit, with the initial project schedule, a coding scheme that shall be used throughout the project schedule for all activity codes contained in the project schedule. The coding scheme submitted shall list the values for each activity code category and translate those values into project specific designations. For example, a responsibility code value, "ELE", may be identified as "Electrical Subcontractor".

Activity code values shall represent the same information throughout the duration of the contract.

3.5 SUBMISSION REQUIREMENTS

The following items shall be submitted for each project schedule submission:

3.5.1 Earnings Reports

The Contractor shall submit a compilation of the Contractor's Total Earnings on the project through the most recent Monthly Progress Meeting. Activities shall be grouped by contract line item. The printed report shall contain, for each contract line item: activity number, activity description, line item amount, total quantity, quantity to date, SECTION 01 32 01.00 10 Page 6 April 18, 2025 percent complete (based on price), and earnings to date. A total project percent complete shall also be provided. If necessary to substantiate partial payment and requested by the Contracting Officer, the earnings report shall detail activities within a contract line item.

3.5.2 Network Diagram

A network diagram shall be required on the initial project schedule submission and on periodic submissions when requested by the Contracting Officer (not less than quarterly). The network diagram shall depict and display the order and interdependence of activities and the sequence in which the work is to be accomplished. The network diagram shall be constructed to meet the following conditions:

a. Continuous Flow. Diagrams shall show a continuous flow from left to right with no arrows from right to left. The activity or event number, description, duration, and estimated earned value shall be shown on the diagram.

b. Project Milestone Dates. Dates shall be shown on the diagram for start of project, any contract required interim completion dates, and contract completion dates.

c. Critical Path. The critical path shall be clearly shown.

d. Banding. Activities shall be grouped to assist in the understanding of the activity sequence. Typically, this flow will group activities by category of work, work area and/or responsibility.

e. S-Curves. Earnings curves showing projected early and late earnings and earnings to date.

3.6 PERIODIC PROGRESS MEETINGS

Progress meetings to discuss payment shall include a monthly onsite meeting or other regular intervals mutually agreed to at the preconstruction conference. During this meeting the Contractor shall describe, on an activity by activity basis, all proposed revisions and adjustments to the project schedule required to reflect the current status of the project.

3.6.1 Meeting Attendance

The Contractor's project manager and the Contractor's authorized representative responsible for preparation of the project schedule shall attend the regular progress meeting.

3.6.2 Progress Meeting Contents

Update information, including actual start dates, actual finish dates, remaining durations, and cost-to-date shall be subject to the approval of the Contracting Officer. The Contractor shall address the following minimum set of items, on an activity by activity basis, during each progress meeting.

SECTION 01 32 01.00 10 Page 7 April 18, 2025

a. Start and Finish Dates. The actual start and actual finish dates for each completed activity. The actual start and projected finish dates for each activity in-progress.

b. Completion. The earnings for each activity started. Payment will be based on earnings for each in-progress or completed activity.

Payment for individual activities will not be made for work that contains defects.

c. Project Schedule Changes. All changes pertaining to notice to proceed on change orders, change orders to be incorporated into the project schedule, Contractor proposed changes in work sequence, corrections to project schedule for out-of-sequence progress, lag durations, and other changes that have been made pursuant to contract provisions shall be specifically identified and discussed.

d. Other Changes. Other changes required due to delays in completion of any activity or group of activities include unusually severe weather, product procurement, or other delays or work stoppages which make re-planning the work necessary.

3.7 REQUESTS FOR TIME EXTENSIONS

Provide a justification of delay to the Contracting Officer in accordance with the contract clauses for approval within 10 days of a delay occurring. Also prepare a time impact analysis for each Government request for proposal (RFP) to justify time extensions.

3.7.1 Justification of Delay

Provide a description of the event(s) that caused the delay and/or impact to the work. As part of the description, identify all schedule activities impacted. Show that the event that caused the delay/impact was the responsibility of the Government. Provide a time impact analysis that demonstrates the effects of the delay or impact on the project completion date or interim completion date(s). Evaluate multiple impacts chronologically; each with its own justification of delay. With multiple impacts consider any concurrence of delay. A time extension becomes part of the project schedule and all future schedule updates upon approval by the Contracting Officer.

3.7.2 Time Extension

The Contracting Officer must approve the Justification of Delay including the time impact analysis before a time extension will be granted. No time extension will be granted unless the delay consumes all available Project Float and extends the projected finish date ("End Project" milestone) beyond the Contract Completion Date. The time extension will be in calendar days. Actual delays that are found to be caused by the Contractor's own actions, which result in a calculated schedule delay will not be a cause for an extension to the performance period, completion date, or any interim milestone date.

SECTION 01 32 01.00 10 Page 8 April 18, 2025

3.8 RECOVERY SCHEDULE

Should the Contracting Officer find it necessary, submit a recovery schedule pursuant to FAR 52.236-15 Schedules for Construction Contracts.

3.9 OWNERSHIP OF FLOAT

The project schedule shall include an appropriate level of detail. Float is available in the project schedule, at anytime, shall not be considered for the exclusive use of either the Government or the Contractor.

3.10 TRANSFER OF SCHEDULE DATA INTO RESIDENT MANAGEMENT SYSTEM

Ensure schedule data is uploaded to RMS. This data is additional supporting data in a form and detail required by the Contracting Officer pursuant to FAR 52.232-5 Payments under Fixed-Price Construction Contracts. The receipt of a proper payment request pursuant to FAR 52.232-27 Prompt Payment for Construction Contracts is contingent upon the Government receiving both acceptable and approvable hard copies and matching electronic versions of the application for progress payment.

SECTION 01 32 01.00 10 Page 9 April 18, 2025

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 1.1 SUBMITTAL IDENTIFICATION

1.2 1.2 SUBMITTAL CLASSIFICATION

1.2.1 1.2.1 Government Approved

1.2.2 1.2.2 Information Only

1.3 1.3 APPROVED SUBMITTALS

1.4 1.4 DISAPPROVED SUBMITTALS

1.5 1.5 WITHHOLDING OF PAYMENT

PART 2 PRODUCTS

PART 3 EXECUTION

3.1 3.1 GENERAL

3.2 3.2 SUBMITTAL REGISTER

3.3 3.3 TRANSMITTAL FORM (ENG FORM 4025)

3.4 3.4 GOVERNMENT REVIEW TIME

3.5 3.5 SCHEDULING

3.6 3.6 SUBMITTAL PROCEDURE

3.7 3.7 DEVIATIONS

3.8 3.8 CONTROL OF SUBMITTALS

3.9 3.9 GOVERNMENT APPROVED SUBMITTALS

3.10 3.10 INFORMATION ONLY SUBMITTALS

3.11 3.11 ATTACHMENTS

3.12 3.11 ATTACHMENTS

SECTION 01 33 00 Page 1 April 18, 2025

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 SUBMITTAL IDENTIFICATION

Submittals required are identified by SD numbers and titles as follows:

SD-01 Preconstruction Submittals

SD-03 Product Data

SD-06 Test Reports

SD-07 Certificates

SD-11 Closeout Submittals

1.2 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.2.1 Government Approved

Governmental approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.

Within the terms of FAR 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION - ALTERNATE I, Government approved submittals are considered to be "shop drawings."

1.2.2 Information Only

All submittals not requiring Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

1.3 APPROVED SUBMITTALS

The Contracting Officer's approval of submittals must not be construed as a complete check, but will indicate only that the general method of construction, materials, detailing and other information are satisfactory.

Approval will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this Contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work. After submittals have been approved by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

Government approval does not relieve the Contractor of their obligation to all requirements of the Contract.

SECTION 01 33 00 Page 2 April 18, 2025

1.4 DISAPPROVED SUBMITTALS

Make all corrections required by the Contracting Officer and promptly furnish a corrected submittal in the form specified for the initial submittal. If the Contractor considers any correction indicated on the submittals to constitute a change to the Contract, a notice in accordance with FAR 52.243-4 CHANGES must be given promptly to the Contracting Officer.

When resubmitting previously disapproved or partially approved submittals, provide a summary of the changes made in the submittal which includes the Government Comment and the changes made to the submittal in response to the Government Comment and the location of the change by page number and position on the page.

Within the submittal, the Contractor must call attention to the actual change on the page, either by highlighting or use of revision clouds.

1.5 WITHHOLDING OF PAYMENT

Payment for materials incorporated in the work will not be made if required approvals have not been obtained.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

3.1 GENERAL

Make submittals as required by the specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Units of weights and measures used on all submittals must be the same as those used in the Contract drawings. Each submittal must be complete and in sufficient detail to allow ready determination of compliance with Contract requirements. Prior to submittal, all items must be checked and approved by the Contractor's Quality Control (CQC) System Manager and each item must be signed and dated by the CQC System Manager indicating action taken. Proposed deviations from the Contract requirements must be clearly identified. Submittals must include items such as:

Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals. Submittals requiring Government approval must be scheduled and made prior to the acquisition of the material or equipment covered thereby. Samples remaining upon completion of the work shall be picked up and disposed in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.

3.2 SUBMITTAL REGISTER

At the end of this section is a sample Submittal Register, showing items of equipment and materials for which submittals are required by the specifications. This list may not be all inclusive and additional

SECTION 01 33 00 Page 3 April 18, 2025 submittals may be required. The Contractor must use RMS to produce the Submittal Register and to track and transmit all submittals. Maintain a submittal register for the project in accordance with Section 01 45 00.15 10

RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM).

3.3 TRANSMITTAL FORM (ENG FORM 4025)

A sample transmittal form (ENG Form 4025) is attached to this section, however the ENG Form 4025 must be produced using RMS and must be used for submitting both Government approved and information only submittals.

3.4 GOVERNMENT REVIEW TIME

Unless otherwise noted elsewhere, the Government is allowed 30 calendar days upon receipt to review a submittal. This applies to all submittals and resubmittals. Typically the actual review time is shorter.

3.5 SCHEDULING

Thirty days (exclusive of mailing time) must be allowed and shown on the register for review and approval. Additional time must be allowed for possible resubmittal. No delay damages or time extensions will be allowed for time lost in late submittals.

3.6 SUBMITTAL PROCEDURE

All submittals must be made prior to commencement of applicable work.

Submit one electronic copy in RMS of each submittal (both Government approved and for information only), unless otherwise indicated.

Each transmittal must address submittal items from only one specification section.

Transmittals returned for resubmission must be resubmitted in their entirety.

Coordinate and submit concurrently, submittals covering components of a system or interrelated items.

Submit certifications with the pertinent drawings.

Materials fabricated or delivered without Government approval of the shop drawing will be subject to rejection.

When approved by the Contracting Officer, routine test reports and delivery tickets may be submitted with daily quality control reports in place of following submittal procedures under this section.

3.7 DEVIATIONS

For submittals which include…