2-MPMA-Solids Handling-BIDDING 05-08-26.pdf
PDF 24 MB Posted
- Attached to
- Solids Handling Facility
- Solicitation number
- US.235665
- Issued by
- Monroe County, Pennsylvania
About this file
This document set consists of bidding drawings and contract specifications for the Mount Pocono Municipal Authority's Solids Handling Facility project, prepared by ARRO Consulting, Inc. The project involves construction of a solids handling building with sludge dewatering equipment at the Mount Pocono wastewater treatment plant in Coolbaugh Township, Monroe County, Pennsylvania. The scope includes the new building structure, site modifications, utility line relocations, yard piping installations, electrical connections, grading, stormwater management, erosion and sediment control, and site restoration. The drawings depict a 38-foot by 28-foot building housing a filter press system, supporting pump rooms, and equipment spaces across multiple floor elevations. Bids will be received through the PennBid program until 11:00 a.m. on Thursday, June 11, 2026. A pre-bid meeting and mandatory site visit are scheduled for 10:00 a.m. on Wednesday, May 27, 2026, at the Owner's address. Questions must be submitted through PennBid by 2:00 p.m. on Thursday, June 4, 2026.
The contract is subject to prevailing wage determination requirements established by the Commonwealth of Pennsylvania Department of Labor and Industry. The project drawings include 30 sheets detailing civil site plans, architectural and structural design, erosion and sediment control measures, process mechanical systems, HVAC, and plumbing installations. Structural elements include cast-in-place concrete foundations and slabs, concrete masonry unit walls with split-face finishes, wood roof trusses, structural steel beams and channels for equipment support, and various architectural features including exterior doors, windows, and louvers. The contractor is responsible for construction sequencing, temporary stabilization of disturbed areas, coordination with utility marking systems, proper waste disposal, and final site stabilization with permanent vegetation. The Mount Pocono Municipal Authority reserves the right to reject any or all bids and to waive any omissions, errors, or irregularities in bid submissions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-Solids Handling Press Building May 2026.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .