2-KTMA 2026 WATER MAIN REPLACEMENT PROJECTS 6-22-2026 FINAL PENNBID.pdf

PDF 40 MB Posted

Attached to
2026 Water Main Replacement Projects 4148. 023
Solicitation number
Not on record
Issued by
Schuylkill County, Mcsherrystown Borough, Pennsylvania

About this file

Summary

This is a Project Manual and bidding document issued by Kline Township Municipal Authority for the 2026 Water Main Replacement Projects, prepared by Entech Engineering, Inc. The project encompasses three phases of water infrastructure replacement across Banks Township (Carbon County) and McAdoo Borough and Kline Township (Schuylkill County), Pennsylvania. Phase A involves replacement of approximately 4,300 linear feet of cast iron and asbestos cement lined pipe with new 4-12 inch ductile iron pipe, 118 service connections, and 7 fire hydrants along streets in Banks Township. Phase B includes approximately 3,000 linear feet of pipe replacement with new 4-8 inch ductile iron pipe, 52 services, and 4 hydrants in McAdoo Borough and Kline Township. Phase C covers approximately 4,400 linear feet of pipe replacement with new 4-8 inch ductile iron pipe, 50 services, and 10 fire hydrants in Kline Township. Bids will be received electronically via the PennBid Program until 10:00 a.m. on Tuesday, August 4, 2026. A mandatory pre-bid conference is scheduled for Wednesday, July 8, 2026, at 2:00 p.m. at the Kline Township Municipal Authority Office, with attendance required to submit a bid. All bidding documents are available at no cost through the PennBid Program.

Bidders must submit bids on a unit price basis with 10 percent bid security in the form of a bid bond. The project is subject to Davis Bacon Act federal wage rates, American Iron and Steel requirements, Build America Buy America compliance, Disadvantaged Business Enterprise (DBE) participation requirements with six good faith efforts documentation, and Public Works Employment Verification Act compliance. Successful bidders must provide performance and payment bonds, submit a Qualifications Statement demonstrating experience with similar projects, and comply with prevailing wage guidelines. The bid security of unsuccessful bidders with reasonable chance of award will be retained until the earlier of 7 days after the Effective Date of the Contract or 61 days after bid opening. All bids will remain subject to acceptance for 60 days after the bid opening, unless extended to 120 days if contract award is delayed by required government agency approval, bond sales, or grant awards. Owner reserves the right to reject any or all bids and will award the contract to the responsible bidder submitting the lowest responsive bid.

View the file

Other files

File Type Posted
1-2025-06-22 4148.024 KTMA Bidding Full Package.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

KLINE TOWNSHIP MUNICIPAL AUTHORITY

8 East Market Street

McAdoo, Pennsylvania 18237

2026 WATER MAIN REPLACEMENT PROJECTS

Banks Township, Carbon County and McAdoo Borough and Kline Township

Schuylkill County, Pennsylvania prepared by

Entech Engineering, Inc.

201 Penn Street

PO Box 32 Reading, Pennsylvania 19603

610-373-6667

Issued for Bidding:

June 22, 2026

Entech No. 4148.023

F O

HTLAEWNOM

M

O C

AI

NAVLYSNNE

P

KAREN C. POLLOCK

ENGINEER

No. 049133-E

PROFESSIONAL

REGISTERED

Entech Engineering, Inc. Entech No. 4148.023

TABLE OF CONTENTS 1

TABLE OF CONTENTS

BIDDING FORMS, CONTRACT FORMS, AND CONDITIONS OF THE CONTRACT

SECTION DESCRIPTION NO. PAGES

Cover Page Table of Contents

PROJECT INFORMATION

EJCDC C-111 Advertisement for Bids Document 00040 Project Information EJCDC C-200 Instructions to Bidders

BID FORM

EJCDC C-410 Bid Form Appendix A List of Subcontractors Appendix B List of Equipment and Materials Appendix C EJCDC C-451 – Qualifications Statement Appendix D Public Works Employment Verification Form Appendix E Schedule of Labor and Equipment Prices for Out of Scope Work Appendix F Worker Protection and Investment Certification Form Appendix G Prime Contractor DBE Compliance Statement Appendix H Asbestos Handling Qualification and Compliance Statement

REFERENCE DOCUMENTS

EJCDC C-430 Bid Bond EJCDC C-510 Notice of Award EJCDC C-520 Agreement Between Owner and Contractor for Construction Contract EJCDC C-550 Notice to Proceed EJCDC C-610 Performance Bond EJCDC C-615 Payment Bond EJCDC C-620 Contractor’s Application for Payment EJCDC C-625 Certificate of Substantial Completion EJCDC C-626 Notice of Acceptability of Work Document 00650 Construction Schedule EJCDC C-700 General Conditions of the Construction Contract EJCDC C-800 Supplementary Conditions Document 00830 Davis Bacon Rate Determination EJCDC C-940 Work Change Directive EJCDC C-941 Change Order EJCDC C-942 Field Order Document 00943 Contractor's Certification of Completion

TABLE OF CONTENTS 2

SECTION DESCRIPTION NO. PAGES

TECHNICAL SPECIFICATIONS

DIVISION 01 — GENERAL REQUIREMENTS

Section 010050 Administrative Provisions Section 010100 Summary of Work Section 010300 Locations of Existing Lines Section 010400 Allowances Section 010450 Coordination Section 010500 Field Engineering Section 011500 Measurements and Payments Section 012000 Project Meetings Section 013000 Submittals Section 013220 Photographic Documentation Section 014000 Quality Control Section 015000 Construction Facilities and Temporary Controls Section 015104 Working with Asbestos Cement Pipe (ACP) Section 015630 Soil Erosion and Sedimentation Control Section 015700 Traffic Regulation Section 016000 Materials and Equipment Section 017000 Mobilization and Project Closeout

DIVISION 31 – EARTHWORK

Section 311000 Site Clearing Section 311200 Finish Grading for Lawns Section 312319 Dewatering Section 312905 Topsoil and Seed Section 314000 Shoring Section 315000 Excavation Support Systems

DIVISION 32 – EXTERIOR IMPROVEMENTS

Section 324480 Restoration Section 325500 Paving and Surfacing

TABLE OF CONTENTS 3

DIVISION 33 – UTILITIES

Section 330130 Sewer Line Cleaning Section 330131 Television Inspection, Main Sewers Section 330132 Temporary Bypass Pumping Section 330133 Sewer Flow Control Section 330220 Rock Removal Section 330509 Pipeline Removal Abandonment Section 330510 Trenching Backfilling Compacting Section 332700 Fire Hydrant Section 332950 Below Grade Ductile Iron Cement Lined Pipe Section 332954 Service Connection and Line Piping Section 332966 Valve Boxes Section 332968 Buried Water Distribution Valves Section 332970 Tapping Sleeve and Valve and Line Stop Assemblies Section 332994 Thrust Blocks

ATTACHMENTS

Attachment A Submittal List Attachment B Steel Procurement Certification Attachment C American Iron & Steel (AIS) Act Attachment D AIS Sample Certification Letter Attachment E DBE Guidance Document Attachment F Environmental Due Diligence Phase A Tresckow Fire Loop Water Main

Replacement Attachment G Environmental Due Diligence Phase B Hancock Street Phase 2 Water Main

Replacement Attachment H Environmental Due Diligence Phase C Snyder Avenue Water Main

Replacement Attachment I Geotechnical Report Phase C Snyder Avenue Water Main Replacement Attachment J Highway Occupancy Permits Attachment K PADEP Clean Fill Information and Fact Sheet – Asbestos Program for Contractors Working in PA

TABLE OF CONTENTS 4

DRAWINGS

Phase A Tresckow Fire Loop Water Main Replacement Refer to Drawing No. G-001 for a complete list of drawings for Phase A

Phase B Hancock Street Phase 2 Water Main Replacement Refer to Drawings G-001 for a complete list of drawings for Phase B

Phase C Snyder Avenue Water Main Replacement Refer to Drawings G-001 for a complete list of drawings for Phase C

END OF TABLE OF CONTENTS

PROJECT INFORMATION

EJCDC® C-111, Advertisement for Bids for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ADVERTISEMENT FOR BIDS

KLINE TOWNSHIP MUNICIPAL AUTHORITY

2026 WATER MAIN REPLACEMENT PROJECTS

General Notice

Kline Township Municipal Authority (Owner) is requesting Bids for the construction of the following Project:

2026 Water Main Replacement Projects Entech No. 4148.023

Bids for the construction of the Project will be received electronically via the PennBid Program by the Kline Township Municipal Authority until 10:00 am local time Tuesday, August 4, 2026. After bid opening, a public notice will be issued via PennBid containing any available bid results. It should be noted that bid results are subject to further review and should not be construed as issuance of an award.

The Project includes the following Work:

Phase A Tresckow Fire Loop Water Main Replacement Project: Replacement of approximately 4,300 linear feet of cast iron and asbestos cement lined pipe with new 4-12 inch ductile iron pipe, 80 linear feet of 2-inch PE, 118 services, and 7 hydrants along Maple Street, Elm Street, Market Street (S.R.

4004), and Oak Street within Banks Township, Carbon County.

Phase B Hancock Street Phase 2 Water Main Replacement Project: Replacement of approximately 3,000 linear feet of cast iron and asbestos cement lined pipe with new 4-8 inch ductile iron pipe, 10 linear feet of 2-inch PE, 52 services, and 4 hydrants along Carl Street, Bayview Avenue, Kelayres Road (S.R. 1009), and Hancock Street within McAdoo Borough and Kline Township, Schuylkill County.

Phase C Snyder Avenue Water Main Replacement Project: Replacement of approximately 4,400 linear feet of cast iron pipe and asbestos cement pipe with new 4-8 inch ductile iron pipe, 50 services, and 10 fire hydrants along Carl Street, Snyder Avenue, Marcus Street, Bayview Terrace and Hillside Road within Kline Township, Schuylkill County.

Obtaining the Bidding Documents

All project documents are available at no cost via the PennBid Program (https://pennbid.bonfirehub.com).

Prime contractors are required to solicit and encourage Disadvantaged Business Enterprises (DBE) to participate with construction, supplies, equipment/materials.

Pre-bid Conference

A mandatory pre-bid conference for the Project will be held on Wednesday, July 8, 2026, at 2:00 p.m. at the Kline Township Municipal Authority Office located at 8 East Market Street, McAdoo, PA 18237.

Attendance at the pre-bid conference is required to bid.

Instructions to Bidders.

For all further requirements regarding bid submittal, 10% bid security, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.

https://pennbid.bonfirehub.com/

EJCDC® C-111, Advertisement for Bids for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Funding agency requirements that are applicable but not limited to this project include: Disadvantaged Business Enterprise (DBE) Solicitation Six Good Faith Efforts; Davis Bacon Act Federal Wage Rates, and American Iron and Steel requirements of P.L. 113-76, the Consolidation Appropriations Act of 2014.

Attention is called to the fact that Davis Bacon Act federal wage rates must be paid by the Contractors on this project and that employees and applicants for employment shall not be discriminated against because of their race, age, color, religion, sex, national origin, or handicap. Each Bidder is required to meet the requirements of Public Works Employment Verification Act, Act 127 of 2012.

Any and all steel products used or supplied in the performance of the contract or any subcontracts shall be from steel made in the United States. Any and all of the iron and steel, manufactured products and construction materials used in the project will be produced in the United States in a manner that complies with Build America, Buy America requirements.

The Kline Township Municipal Authority hereby reserves the right, which is understood and agreed to by all bidders, to refuse and reject any or all bids submitted, and also reserves the right to waive any informality in bids received.

Except as otherwise provided by law, no bidder may withdraw its bid for sixty (60) days after the Bid Due Date, unless the contract award is delayed by a required approval of another government agency, the sale of bonds, or the award of a grant or grants, in which case the Bids shall remain open to acceptance and shall be irrevocable for a period of one hundred twenty (120) days after the Bid Due Date.

This Advertisement is issued by:

Owner: Kline Township Municipal Authority By: Aaron DeBalko Title: Authority Chairman Date: June 22, 2026

+ + END OF ADVERTISEMENT FOR BIDS + +

PROJECT INFORMATION 00040 - 1

DOCUMENT 00040 – PROJECT INFORMATION

PART 1 – PROJECT IDENTIFICATION

1.1 PROJECT NAME

A. 2026 Water Main Replacement Projects

1. Phase A Tresckow Fire Loop Water Main Replacement Project

2. Phase B Hancock Street Phase 2 Water Main Replacement Project

3. Phase C Snyder Avenue Water Main Replacement Project

1.2 LOCATION

A. McAdoo Borough and Kline Township, Schuylkill County, Pennsylvania Banks Township, Carbon County

1.3 OWNER

A. Kline Township Municipal Authority 8 East Market Street McAdoo, Pennsylvania 18237

Contact: Aaron DeBalko Phone: 570-929-3177

1.4 ENGINEER

A. Entech Engineering, Inc.

201 Penn Street PO Box 32 Reading, PA 19603

Contact: Tyler Martz, Engineering Designer Phone: 570-628-5655

Email: tmartz@entecheng.com

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION 00040

mailto:tmartz@entecheng.com

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

TOC Page 1 of 1

INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1— Defined Terms

Article 2— Bidding Documents

Article 3— Qualifications of Bidders

Article 4— Pre-Bid Conference

Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

Article 6— Bidder’s Representations and Certifications

Article 7— Interpretations and Addenda

Article 8— Bid Security

Article 9— Contract Times

Article 10— Substitute and “Or Equal” Items

Article 11— Subcontractors, Suppliers, and Others

Article 12— Preparation of Bid

Article 13— Basis of Bid

Article 14— Submittal of Bid

Article 15— Modification and Withdrawal of Bid

Article 16— Opening of Bids

Article 17— Bids to Remain Subject to Acceptance

Article 18— Evaluation of Bids and Award of Contract

Article 19— Bonds and Insurance

Article 20— Signing of Agreement

Article 21— Sales and Use Taxes

Article 22— Steel Products Procurement Act

Article 23— Labor Requirements

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 1—DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office—The office from which the Bidding Documents are to be issued.

ARTICLE 2—BIDDING DOCUMENTS

2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.

2.03 Bidding Documents are available at no cost via the PennBid Program (https://pennbid.bonfirehub.com).

2.04 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.

1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader. It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.04.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 3—QUALIFICATIONS OF BIDDERS

3.01 Bidder is to submit the following information with its Bid to demonstrate Bidder’s qualifications to perform the Work:

A. All documents required under Article 2 of the Bid Form

B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.

C. Bidder’s state or other contractor license number, if applicable.

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

ARTICLE 4—PRE-BID CONFERENCE

4.01 A mandatory pre-bid conference will be held at the time and location indicated in the Advertisement or invitation to bid. Representatives of Owner and Engineer will be present to discuss the project. Bidders are required to attend this conference to submit a Bid.

4.02 Information presented at the pre-Bid conference does not alter the Contract Documents. Owner will issue Addenda to make any changes to the Contract Documents that result from discussions at the pre-Bid conference. Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.

ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

5.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

5.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

5.03 Other Site-related Documents

A. No other Site-related documents are available.

5.04 Site Visit and Testing by Bidders

A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.

B. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.

C. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

D. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

5.05 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

5.06 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Express Representations and Certifications in Bid Form, Agreement

A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

ARTICLE 7—INTERPRETATIONS AND ADDENDA

7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.

7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents via the “Messages/Vendor Discussions” feature in PennBid no later than seven (7) days prior to the date for receipt of bids.

7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda delivered to all registered plan holders. Questions received less than seven days prior to the date for opening of Bids may not be answered.

7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.

ARTICLE 8—BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 10 percent of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

ARTICLE 9—CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.

9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS

10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute or materials and equipment subsequently approved by Engineer prior to the submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received by Engineer within 10 days of the issuance of the Advertisement for Bids or invitation to Bidders. Each such request must comply with the requirements of Paragraphs 7.05 and 7.06 of the General Conditions, and the review of the request will be governed by the principles in those paragraphs. The burden of proof of the merit of the proposed item is upon Bidder. Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all registered Bidders.

Bidders cannot rely upon approvals made in any other manner.

10.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11.01 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work with the Bid submittal on the Bid Forms provided.

11.02 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute without an increase in Bid Price.

11.03 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.

Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.

ARTICLE 12—PREPARATION OF BID

12.01 The Bid Form is included with the Bidding Documents for Reference. Bidders shall complete the electronic bid form within PennBid (“Prepare Your Submission” tab), inclusive of all pricing items and required supporting documents as identified.

12.02 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.

12.03 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.

12.04 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

12.05 A Bid by an individual must show the Bidder’s name and official address.

12.06 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

12.07 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

12.08 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

12.09 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

12.10 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.

ARTICLE 13—BASIS OF BID

13.01 Unit Price

A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

13.02 Allowances

A. For cash allowances the Bid price must include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.

ARTICLE 14—SUBMITTAL OF BID

14.01 Bids shall be submitted online via the PennBid Program (https://pennbid.bonfirehub.com) by the date and time indicated in the Advertisement for Bids along with the Bid security and the other documents required to be submitted as identified herein.

ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID

15.01 Bids may be modified or withdrawn within PennBid at any time prior to the due date and time listed in the Advertisement for Bids.

15.02 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid in accordance with all Commonwealth of Pennsylvania laws and statutes (including but not limited to Pennsylvania Act of January 23, 1974 as may be amended), the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.

ARTICLE 16—OPENING OF BIDS

16.01 After bid opening, the time of which is listed in the Advertisement for Bids, a public notice will be issued via PennBid containing any available bid results. It should be noted that bid results are subject to further review and should not be construed as issuance of an award.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE

17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT

18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.

18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.

18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

18.05 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

B. In the comparison of Bids, owner may select any or all alternatives. The alternates may be applied in any order, not necessarily as they appear on the Bid Form.

18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents and whether the Owner’s prior direct experience with the Bidder, establishes that the Bidder does not possess the requisite integrity, reliability, operational capacity or past performance to successfully execute the Work.

18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 19—BONDS AND INSURANCE

19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.

ARTICLE 20—SIGNING OF AGREEMENT

20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.

ARTICLE 21—SALES AND USE TAXES

21.01 Owner is exempt from Pennsylvania state sales and use taxes on materials and equipment to be incorporated in the Work. Said taxes must not be included in the Bid. Refer to Paragraph SC-7.10 of the Supplementary Conditions for additional information.

ARTICLE 22—STEEL PRODUCTS PROCUREMENT ACT

22.01 The Contractor shall comply with Act No. 3 of 1978, known as the “Steel Products Procurement Act”. Except as provided in this Act, the Contractor shall only supply steel products to be used in the performance of the Contract, or any subcontract thereunder, which are produced in the United States. Certificates of compliance with regard to this Act shall be supplied by the Contractor to the Engineer.

ARTICLE 23—LABOR REQUIREMENTS

23.01 By submitting a Bid Proposal, the Bidder agrees to comply with the "Davis Bacon Wage Act").

23.02 During the performance of this Contract, the Contractor agrees as follows:

A. The Contractor will not discriminate against any employees or applicant for employment because of race, color, religion, sex, national origin, or handicap.

B. The Contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment, without regard to race, color, religion, sex, national origin, or handicap. Such action shall include, but not be limited to, the following:

employment, upgrading, demotion, or transfer; recruitment or recruitment advertising;

layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship.

C. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices which may be provided by the Authority setting forth the provisions of this nondiscrimination clause.

D. The Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, national origin, or handicap.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

E. The Contractor will send to each labor union or representative of workers with which the Contractor has a collective bargaining agreement or other contract or understanding, a notice, to be provided, advising the labor union or workers' representatives of the Contractor's commitments under this Section and shall post copies of the notice in conspicuous places available to employees and applicants for employment.

F. In the event of the Contractor's noncompliance with the nondiscrimination clauses of this Contract or with any of the said rules, regulations, or orders, this Contract may be canceled, terminated, or suspended in whole or in part and the Contractor may be declared ineligible for further Authority contracts.

G. The Contractor will include the provisions of these paragraphs in every subcontract or purchase order unless exempted.

23.03 No person who, at the time, is serving sentence in a penal or correctional institution shall be employed on the work covered by this Contract.

23.04 This project must be performed under prevailing wage guidelines. Prevailing wage documents are contained in the reference section of this Project Manual.

BID FORM

EJCDC® C-410, Bid Form for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

BID FORM FOR CONSTRUCTION CONTRACT

KLINE TOWNSHIP MUNICIPAL AUTHORITY

2026 WATER MAIN REPLACEMENT PROJECTS

The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 1—OWNER AND BIDDER

1.01 This Bid is submitted to: Electronic bids, inclusive of all requested supporting documents, shall be submitted via the PennBid Program (https://pennbid.bonfirehub.com).

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2—ATTACHMENTS TO THIS BID

2.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security;

B. Appendix A - List of Proposed Subcontractors;

C. Appendix B - List of Equipment and Materials;

D. Appendix C - Required Bidder Qualification Statement with supporting data;

E. Appendix D – Public Works Employment– Act 127;

F. Appendix E - Schedule of Labor and Equipment Prices for Out of Scope Work; and

G. Appendix F - Worker Protection and Investment Certification Form.

H. Appendix G - Prime Contractor Disadvantage Business Enterprise Compliance Statement and Procurement

I. Appendix H - Asbestos Handling Qualifications Statement

ARTICLE 3—BASIS OF BID—LUMP SUM BID AND UNIT PRICES

3.01 Unit Price Bids

A. Bidder will perform the following Work at the indicated unit prices:

Item Description Unit Est Qty Unit Price Total Price

Phase A Tresckow Fire Loop Water Main Replacement Project

Bonds and Insurance (Phase A, Phase B, and Phase C) LS 1 $ $

2 Mobilization LS 1 $ $

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Item Description Unit Est Qty Unit Price Total Price

Repair of Owner Mismarked Water Mains, Complete in Place – All Materials and Sizes EA 6 $ $

Repair of Owner Mismarked Water Services, Complete in Place – All Materials and Sizes EA 10 $ $

Traditional Excavation Test Pitting, Where Directed CY 100 $ $

Air Vacuum Test Pitting, Where Directed HR 30 $ $

Furnish and Install New 4-inch Ductile Iron Water Main with PennDOT 2A Coarse Aggregate Backfill to Connect to Existing Water Main, Complete in Place LF 100 $ $

Furnish and Install New 6-inch Ductile Iron Water Main with PennDOT 2A Coarse Aggregate Backfill to Connect to Existing Water Main, Complete in Place LF 30 $ $

Furnish and Install New 8-inch Ductile Iron Water Main with PennDOT 2A Coarse Aggregate Backfill, Complete in Place LF 4,120 $ $

Furnish and Install New 12-inch Ductile Iron Water Main with PennDOT 2A Coarse Aggregate Backfill, Complete in Place LF 30 $ $

Furnish and Install New 2-inch PE with Tracer Wire, Complete in Place LF 80 $ $

Furnish and Install New 8-inch Gate Valve and Valve Box, Complete in Place EA 18 $ $

Furnish and Install New 12-inch Gate Valve and Valve Box, Complete in Place EA 1 $ $

Furnish and Install 8”x8” Tapping Sleeve and Valve, Complete in Place. EA 2 $ $

Furnish and Install Fire Hydrant Assembly, including Hydrant, Hydrant Tee, Pipe, and Valve, Complete in Place. EA 7 $ $

Remove Existing Fire Hydrant, and Return to Owner, Where Directed, Complete in Place EA 2 $ $

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Item Description Unit Est Qty Unit Price Total Price

Furnish and Install New 3/4-inch PEX- A Service Line Tubing Open Cut, with PennDOT 2A Backfill, Complete in Place LF 2,600 $ $

Furnish and Install New 1-inch PEX-A Service Line Tubing Open Cut, with PennDOT 2A Backfill, Complete in Place LF 10 $ $

Furnish and Install New 3/4-inch Service Line Connections and Curb Stop and Box, Complete in Place EA 117 $ $

Furnish and Install New 1-inch Service Line Connections and Curb Stop and Box, Complete in Place EA 1 $ $

Replacement of Lead/Galvanized Service Line with 3/4-inch PEX-A Tubing with PennDOT 2A Backfill, Complete in Place LF 400 $ $

Core Existing Building for New Water Service, All Size, Complete in Place EA 20 $ $

Connection to Existing Plumbing, Complete in Place EA 20 $ $

Furnish and Install Pavement Restoration, Base Course, Depths as noted in Details, Complete in Place Ton 1,100 $ $

Furnish and Install Pavement Restoration Wearing Course, Depth as noted in Details, Complete in Place Ton 500 $ $

26 Roadway Milling, Where Directed SY 250 $ $

Furnish and Install temporary Pavement Restoration, Complete in Place LF 7,000 $ $

Furnish and Install Concrete Sidewalk Restoration, Complete in Place SF 1,200 $ $

Furnish and Install Concrete Curb Restoration, Complete in Place LF 550 $ $

Allowance to perform Compaction Testing of 2A Backfill or Asphalt with Nuclear Density Gauge, as Directed AL 1 $10,000.00 $ 10,000.00

Furnish and Install PennDOT 2A Coarse Aggregate Backfill (Where Directed), Complete in Place CY 40 $ $

Furnish and Install PennDOT Class A Concrete, Poured in Place, for CY 50 $ $

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Item Description Unit Est Qty Unit Price Total Price

Bedding or Encasement, Where Directed, Complete in Place

Unsuitable Earth Excavation (Where Directed) CY 40 $ $

34 Rock Removal CY 50 $ $

Allowance to perform pre and post construction CCTV of sewer main AL 1 $20,000.00 $20,000.00

Furnish Redline Record Drawings with each AFP and Surveyed Record Drawings LS 1 $ $

37 Demobilization and Closeout LS 1 $ $

Bid Price for Pay Items 1-37 SUBTOTAL

Phase A Tresckow Fire Loop Water Main Replacement Project

SUBTOTAL BID

PRICE $

Phase B Hancock Street Phase 2 Water Main Replacement Project

38 Mobilization LS 1 $ $

Repair of Owner Mismarked Water Mains, Complete in Place – All Materials and Sizes EA 5 $ $

Repair of Owner Mismarked Water Services, Complete in Place – All Materials and Sizes EA 6 $ $

Traditional Excavation Test Pitting, Where Directed CY 80 $ $

Air Vacuum Test Pitting, Where Directed CY 20 $ $

Furnish and Install New 4-inch Ductile Iron Water Main with PennDOT 2A Coarse Aggregate Backfill to Connect to Existing Water Main, Complete in Place LF 100 $ $

Furnish and Install New 6-inch Ductile Iron Water Main with PennDOT 2A Coarse Aggregate Backfill to Connect to Existing Water Main, Complete in Place LF 30 $ $

Furnish and Install New 8-inch Ductile Iron Water Main with PennDOT 2A Coarse Aggregate Backfill, Complete in Place LF 2,810 $ $

Furnish and Install New 2-inch PE with Tracer Wire, Complete in Place LF 10 $ $

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Item Description Unit Est Qty Unit Price Total Price

Furnish and Install New 8-inch Gate Valve and Valve Box, Complete in Place EA 22 $ $

Furnish and Install Fire Hydrant Assembly, including Hydrant, Hydrant Tee, Pipe, and Valve, Complete in Place. EA 4 $ $

Remove Existing Fire Hydrant, and Return to Owner, Where Directed, Complete in Place EA 3 $ $

Furnish and Install New 3/4-inch PEX- A Tubing Via Open Cut, with PennDOT 2A Backfill, Complete in Place LF 560 $ $

Furnish and Install New 3/4-inch PEX- A Tubing Via Trenchless, Complete in Place LF 390 $ $

Furnish and Install New 1-inch PEX-A Tubing Via Trenchless, Complete in Place LF 30 $ $

Furnish and Install New 3/4-inch Service Line Connections and Curb Stop and Box, Complete in Place EA 50 $ $

Furnish and Install New 1-inch Service Line Connections and Curb Stop and Box, Complete in Place EA 2 $ $

Replacement of Lead/Galvanized Service Line with 3/4-inch PEX-A Tubing with PennDOT 2A Backfill, Complete in Place LF 70 $ $

Core Existing Building for New Water Service, All Size, Complete in Place EA 5 $ $

Connection to Existing Plumbing, Complete in Place EA 5 $ $

Furnish and Install Pavement Restoration, Base Course, Depths as noted in Details, Complete in Place Ton 600 $ $

Furnish and Install Pavement Restoration Wearing Course, Depth as noted in Details, Complete in Place Ton 300 $ $

Furnish and Install temporary Pavement Restoration, Complete in Place LF 3,600 $ $

Furnish and Install Concrete Sidewalk Restoration, Complete in Place SF 700 $ $

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

Item Description Unit Est Qty Unit Price Total…

This is the start of the file's text. The full file is on GovTribe.