This document is a draft specification for dockside repairs to be performed on the USCGC KIMBALL (WMSL 418) for the U.S. Coast Guard in fiscal year 2024. The specification covers a wide range of work items, including renewing the slip-resistant deck covering, cleaning and inspecting potable water tanks, preserving the potable water tanks, providing tenting, grooming the air conditioning and refrigeration systems, and performing biennial maintenance on crane systems.
The key details include the specific work locations, required materials and services, quality assurance and control measures, operational testing, substrate preparation and repair, coating application, and restoration requirements. The document references various Coast Guard drawings, publications, and other standards that must be followed. The work is to be conducted under a federal contract opportunity with solicitation number 70Z08524QLREP0011, with the USCG as the procuring agency. The contractor is required to provide qualified technical representatives, including an NDE operator/Level 1 and a NACE-certified coating inspector, to oversee and inspect the preservation work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2 - KIMBALL (WMSL 418) DS FQ4 CLJ 24R2.pdf | ||
| 70Z08524QLREP00110002 Final.pdf | ||
| Clarification Request Updated.docx | DOCX document | |
| 70Z08524QLREP00110001 Final.pdf | ||
| 70Z08524QLREP0011 Solicitation.pdf | ||
| HSAM Appendix G Dockside.pdf | ||
| Non-Disclosure Form.pdf | ||
| 11 - Consolidated List of References.pdf | ||
| KIMBALL DS FQ4 FY24 SOS.xls | XLS spreadsheet | |
| Past Performance Information Form.docx | DOCX document | |
| 10 - Base Access Instructions.pdf | ||
| Clarification Request.docx | DOCX document | |
| S1.7r - JOTFOC Brand Name Osmosis Redacted.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC KIMBALL (WMSL 756)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2024
Developed By: Christian L Jaictin
(Rev-1, 18 April 2024)
USCGC KIMBALL (WMSL-418) DRYDOCK AVAILABILITY FY2024
ii (Rev-1)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. ix Consolidated List of Critical Inspection Items ............................................................................................. xi Principal Characteristics ............................................................................................................................. xii General Requirements WORK ITEM 1: Deck Covering (Slip-Resistant), Renew WORK ITEM 2: Tenting, Provide WORK ITEM 3: Tanks (Potable Water), Clean and Inspect WORK ITEM 4: Tanks (Potable Water), Preserve (Partial) WORK ITEM 5: Tanks (MP Fuel Service), Clean and Inspect WORK ITEM 6: Air Conditioning Plants, Groom WORK ITEM 7: Refrigeration Plant, System Groom WORK ITEM 8: Refrigeration Plant Flexible Hoses, Renew WORK ITEM 9: Reverse Osmosis, System Groom WORK ITEM 10: Potable Water Pneumatic Tanks, Clean and Inspect WORK ITEM 11: Folding Boom Cranes, Biennial Maintenance, Perform WORK ITEM 12: Dual Point Davit, Biennial Maintenance, Perform WORK ITEM 13: Incinerator, Inspect and Test WORK ITEM 14: HVAC Ducts, Modify WORK ITEM 15: Fire Prevention, Provide WORK ITEM 16: Temporary Services, Provide
WORK ITEM 17: <DE-SCOPED>
WORK ITEM 18: Air Conditioning Compressor, Renew WORK ITEM 19: Reduction Gear & Controllable Pitch Propeller Settling Tank, Clean and Inspect iii (Rev-1)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
18APR24 1 17 De-scoped Sea Trials Requirement
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-1)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 418A-WMSL 100-006, Rev A, Inboard and Outboard Profiles
Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements
Coast Guard Drawing 418A-WMSL-100-006, Rev A, Inboard and Outboard Profiles
Coast Guard Drawing 418A-WMSL-512-001, Rev D, HVAC System Diagram
Coast Guard Drawing 418A-WMSL-530-001, Rev C, Potable Water Systems Diagram
Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans
Coast Guard Drawing 750 WMSL 508-1, Rev C, Piping and Machinery Insulation Schedule and L/M
Coast Guard Drawing 750 WMSL 516-1, Rev E, A/C & Refrigeration Piping Diagram
Coast Guard Drawing 750 WMSL 520-001, Rev H, Seawater Cooling System Diagram
Coast Guard Drawing 750 WMSL 520-004, Rev E, Salt Water Cooling Unit 1320
Coast Guard Drawing 750 WMSL 520-005, Rev E, Salt Water Cooling System Unit 2110
Coast Guard Drawing 750 WMSL 520-008, Rev F, Salt Water Cooling Unit 2210
Coast Guard Drawing 750-WMSL 100-001, Rev B, General Arrangements
Coast Guard Drawing 750-WMSL_100_21, Rev F, Unit 2100 Structure – Inner Bottom – Fr 35 to Fr 44
(ASC100210)
Coast Guard Drawing 750-WMSL_100_22, Rev L, Unit 2110 Structure Inner Bottom to 1st Pltf Fr 35 –
44 (ASC100210)
Coast Guard Drawing 750-WMSL_520_1, Rev H, Seawater Cooling System
Coast Guard Drawing 750-WMSL-085-003, REV A, Compartment areas & volumes NSC 3 & Follow
(ASC308512)
Coast Guard Drawing 750-WMSL-085-025, Rev -, Compartment Areas & Volumes NSC 3 & Follow
(AS3085012)
Coast Guard Drawing 750-WMSL-100-33, Rev J, Unit 2320 – 1st Platform To 2nd Deck – Fr 52 To Fr
64 (ASC100232)
Coast Guard Drawing 750-WMSL-100-042, Rev J, Unit 3230 Structure - 2nd Dk to Main Deck - Fr 76 to
Fr 88 (ASC100323)
Coast Guard Drawing 750-WMSL-100-045, Rev K, 2nd Dk to Main Dk - Fr 82 to Aft (ASC100333)
Coast Guard Drawing 750-WMSL-100-049, Rev L, Unit 4220 Structure - 02 Lvl and Above - Fr 33 to Fr
44 (ASC100422)
Coast Guard Drawing 750-WMSL-100-083, Rev A, General Arrangements NSC 5 & Follow v (Rev-1)
Coast Guard Drawing 750-WMSL-100-084, Rev -, Topside Configuration for NSC 6 & Follow
Coast Guard Drawing 750-WMSL-100-37, Rev H, Unit 3120 Structure - 1st Platf to 2nd Dk - Fr 64 to Fr
76 (ASC100312)
Coast Guard Drawing 750-WMSL-167-001, Rev J, Manhole List Installation and Fabrication Details Ship
Wide (ASC167001)
Coast Guard Drawing 750-WMSL-300-024, Rev C, Unit 2240 - Main Dk Fr 44 to Fr 52 Arr of Elect Eqpt
(ASC300224)
Coast Guard Drawing 750-WMSL-320-579, Rev -, Electrical Installations Iwo New Aft Folding Cranes
Coast Guard Drawing 750-WMSL-485-001, Rev L, Sleeves-Pipe Structure Penetration (SP485000)
Coast Guard Drawing 750-WMSL-505-006, Rev D, List of Hoses
Coast Guard Drawing 750-WMSL-508-001, Rev C, Piping and Machinery Insulation Schedule and L/M
Coast Guard Drawing 750-WMSL-509-001, Rev A, HVAC Insulation Schedule and L/M (ASC509001)
Coast Guard Drawing 750-WMSL-512-004, Rev A, Vent and Air Conditioning Standard Instruction
(ASC512007)
Coast Guard Drawing 750-WMSL-512-015, Rev B, Label Plate List - HVAC (ASC512018)
Coast Guard Drawing 750-WMSL-512-036, Rev C, Vent & Air Cond Arr 1st Platf Unit 3120
(ASC512312)
Coast Guard Drawing 750-WMSL-512-037, Rev F, Vent & Air Cond Arr 2nd Dk Unit 3130
(ASC512313)Coast Guard Drawing 750-WMSL-512-045, Rev E, Vent & Air Conditioning 01
Level, Unit 4210 (ASC512421)
Coast Guard Drawing 750-WMSL-512-528, Rev B, HVAC Modifications to Protective Clothing
Storeroom
Coast Guard Drawing 750-WMSL-512-529, Rev B, HVAC Modifications to Cleaning Gear Locker
Coast Guard Drawing 750-WMSL-516-001, Rev E, A/C & Refrigeration Piping Diagram (ASC516001)
Coast Guard Drawing 750-WMSL-520-027, Rev B, Seawater Cooling System Diagram Selected Record
Drawing NSC 7
Coast Guard Drawing 750-WMSL-520-506, Rev F, Auxiliary Seawater Piping Mods FWD of FR 52
Coast Guard Drawing 750-WMSL-530-001, Rev G, Potable Water Systems Diagram
Coast Guard Drawing 750-WMSL-530-019, Rev E, Potable Water Unit 3120 (ASC530312-PW)
Coast Guard Drawing 750-WMSL-583-508, Rev -, Installations IWO Aft Folding Cranes
Coast Guard Drawing 750-WMSL-593-011, Rev B, Solid Waste System Schematic (ASC593026)
Coast Guard Drawing 750-WMSL-624-001, Rev E, Inter & Ext Joiner Dr, Lock & Passing Window List
& Dets (ASC624001)
Coast Guard Drawing 750-WMSL-635-502, Rev -, Insulation Arr & Details Thermal, Acoustic, & Fire
(WMSL 754 & Follow)
Coast Guard Drawing 750-WMSL-635-503, Rev B, Insulation Modifications To Baggage Room
Coast Guard Fleet Drawing FL-1702-11, Rev -, Inspection of Sheaves
NAVSEA Drawing 803-1385828, Rev P, Nozzles AFFF and Washdown Systems
NAVSEA Drawing 803-1385866, Rev E, Penetration, Bulkhead and Deck
NAVSEA Drawing 803-5184182, Rev B, Insulation, Passive Fire Protection- Installation Details
NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation for Compartments Installation
Details
NAVSEA Drawing 804-5773932, Rev A, Acoustic & Thermal Insulation for Ducts vi (Rev-1)
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series), Coatings and Color Manual
Coast Guard Technical Publication (TP) 7082, SWBS 533, Dec 2020, Potable and Chilled Water Tanks
Coast Guard Technical Publication (TP) 7107, SWBS 531, Jun 2007, Reverse Osmosis Water Purifier-
SW6994463CNG
Coast Guard Technical Publication (TP) 7168, January 2022, 3.2-ton Refrigeration Ships Store Plant
Coast Guard Technical Publication (TP) 7903, SWBS 583, Oct 2021, Aft Boat Handling System –Model
FB90-28
Coast Guard Technical Publication (TP) 7946, SWBS 593, May 2021, Incineration Plant - Installation, Operation, Maintenance & Spare Parts
Coast Guard Technical Publication (TP) 9900, SWBS 583, Nov 2020, Marine Crane – MODELS
DDP11000CTS & SP2200 – S/N 2382 DDP11000CTS & SP2200 (S/N: 2313) (HULL 756)
Coast Guard Technical Publication (TP) S9514-F1-MMA-010, SWBS 514, Jun 2020, Air Conditioning
Plant - 130-Ton Capacity, HFC-134A - Description, Operation & Maintenance - REV 2
Fire Prevention and Response
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 0850 (SFLC Std Spec 0850), 2022, General
Requirements for Drawing Preparation
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard
Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard
Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 3100 (SFLC Std Spec 3100), 2022, Inspect, Test and Recondition AC Synchronous Machines In-Place
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary
Machine Systems
Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2022, Clean
Shipboard Ventilation Systems
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire
Prevention and Response
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2022, Install Interior
Deck Covering Systems
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2022, Temporary
Services
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary
Hull Accesses
OTHER REFERENCES
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2019, Disinfection of Water-Storage Facilities vii (Rev-1)
American Society for Nondestructive Testing (ASNT), Recommended Practice No. SNT-TC-1A, 2020, Personnel Qualification and Certification in Nondestructive Testing
American Society for Nondestructive Testing (ASNT), Standard No. ANSI/ASNT CP-189-2020, 2020, ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel
ANSI/EASA Standard AR100-2015: Recommended Practice for the Repair of Rotating Electrical
Apparatus
ANSI/EASA Standard AR100-2020, Recommended Practice for the Repair of Rotating Electrical
Apparatus
ASTM International (ASTM) A653/A653M-20, 2020, Standard Specification for Steel Sheet, Zinc-
Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process
ASTM International (ASTM) D1330, 2022, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) F708-92(2022), 2022, Standard Practice for Design and Installation of
Rigid Pipe Hangers
ASTM International (ASTM), B209/B209M-21a, 2021, Standard Specification for Aluminum and
Aluminum-Alloy Sheet and Plate
ASTM Internationals (ASTM) G46, 2018, Standard Guide for Examination and Evaluation of Pitting
Corrosion
Code of Federal Regulations (CFR) Title 29, Part 1910, 2017, Occupational Safety and Health Standards
Code of Federal Regulations (CFR) Title 29, Part 1915, 2013, Occupational Safety and Health Standards for Shipyard Employment
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment
Code of Federal Regulations (CFR) Title 40, 2013, Protection of the Environment
Federal Specification (Fed Spec) HH-P-151, 1991, Rubber-Sheet, Cloth Insert
International Maritime Organization (IMO) International Convention for the Safety of Life At Sea
(SOLAS), 2009 as amended in 2010 and 2011
International Maritime Organization (IMO) International Life Saving Appliances Code (LSA), 2010 edition
MIL-C-24757, Nov 1990, Cloth, Fiberglass, Coated
MIL-D-16791, Jan 1993, Detergents, General Purpose (Liquid, Nonionic)
MIL-DTL-32585A, 2021, Insulation, Thermal and Acoustic, Fibrous Glass
MIL-PRF-24176C, 2020, Cement, Epoxy, Metal Repair and Hull Smoothing
MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric
MIL-PRF-24667C, May 2008, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application
MIL-PRF-24667D, 2021, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application
MIL-STD-1689A, 1990, Fabrication, Welding, and Inspection of Ships Structure
Naval Sea Systems Command (NAVSEA) 0640-LP-119-0175, 2019, NAVSEA OP 4 Rev 12, Ammunition and Explosives Safety Afloat
NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for
Fabrication, Welding, and Inspection of Submarine Structure
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2016, Bare Metal Power Tool Cleaning viii (Rev-1)
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2016, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2020, Bare Metal Power Tool Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 10 (WAB)/NACE WAB-2, 2015, Near-White Metal Wet Abrasive Blast
Cleaning ix (Rev-1)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
6 N Resilient mount type
6E2000 Mil Spec MIL-
M-17508, Barry
Controls 3114-4Â
NSN: 5342-00-58-8825 18 ea 460.00Â
7 N Tetrafluoroethane, Technical (R-134A)
NSN: 6830-01-370-6207 125 lbs $992.00
7 N -3/8” Henry Seal Cap
Valve (Main Valve
P/N: 2031) Bonnet, Stem & Seat Disc
Assembly
PN: 8-059-008 2 $184.16
7 N 1-5/8” Henry Seal Cap
Valve (Main Valve PN:
2032), Bonnet, Stem &
Seat Disc Assembly
PN: 8-059-010 3 $233.44
7 N 2-1/8” Henry Seal Cap
Valve (Main Valve PN:
2033), Bonnet, Stem &
Seat Disc Assembly
PN: 8-059-012 2 $440.57
7 N Henry “Y” Strainer
Assembly (Main
Assembly P/N: 896A-
5/8S)
PN: 5-010-003 (Screen) PN:
5-023-100 (Gasket) PN: 2-
023-080 (O-Ring)
7 N Sea Water Regulating
Valve (Condenser).
Metrex Valve Corp lead time is usually 6-8 weeks.
PN: M900P-125-LRFL2-3W 2 $2,552.00
7 N Sea Water Regulating
Valve (Oil Cooler).
Metrex Valve Corp lead time is usually 3-4 weeks
PN: DA-868T-75-SE-M 2 $1,740.00
7 N Disk, Rupturable NSN: 4820-01-366-7330 PN:
026-31284-000
6 $2,274.06
7 N Connector, Flexible, Liquid
NSN: 4730-01-561-7408 PN:
026-41967-000
2 $3,196.17
7 N Connector, Flexible, Vapor
NSN: 5935-01-561-7463 PN:
026-41968-000
2 $5,303.11
7 N Valve, Pressure Relief NSN:4820-01-561-6471
PN:022-11355-000
6 $352.12
10 N Bladder, Water NSN: 4510-01-601-2564 PN: 1 ea. 2,506.00 x (Rev-1)
660603996
11 Y *CB-OTH Mark IV
(Coast Guard Drawing
26B-CB-IV-801-001)
N/A 1 ea. N/A
11 Y *Long Range
Interceptor II (LRI-II)
Cutter Boat
N/A 1 ea. N/A
12 Y CB-OTH Mark IV
(Coast Guard Drawing
26B-CB-IV-801-001)
N/A 1 ea. N/A
12 Y Hook Model APR-356-CBH 2 ea. 5000.00
20 Y York Semi-hermetic screw compressor
PN: YCWS 1 ea 69,474.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xi (Rev-1)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5
(Inspection report particulars)):
Work
Item Title
1 Deck Covering (Slip-Resistant), Renew
3 Tanks (Potable Water), Clean and Inspect
7 Refrigeration Plant, System Groom
8 Refrigeration Plant Flexible Hoses, Renew
9 Reverse Osmosis, System Groom
11 Folding Boom Cranes, Biennial Maintenance, Perform
12 Dual Point Davit, Biennial Maintenance, Perform xii (Rev-1)
PRINCIPAL CHARACTERISTICS
418' WMSL
PHYSICAL
Length overall 418' 0"
Length between perpendiculars 390' 0"
Maximum beam 54' 0"
Beam @ 01 level 47' 9-1/8"
Depth (01 level @ side to baseline) 39' 2-3/4"
01 deck camber foredeck 1/4" in 1'-0"
Minimum berth depth 20' 0"
Height of highest projection Approximately 119'
Draft, design 14.40'
Design displacement 3925 long tons
MACHINERY
Two diesel engines MTU 20V, 20-cylinder 9,730 SHP each
One gas turbine General Electric LM2500; 29,500 SHP
Type of propulsion CODAG
Electrical system 24 Volt DC
Two controllable pitch propellers Rolls-Royce 5 blade, 14' 0" diameter; 229 RPM max
Two reduction gears RENK
One cross connect gear RENK
HULL
Hull material 5086 Aluminum
HSLA-80 Steel
ABS EH 36 Steel
ABS AH 36
Frame spacing
FWD of FR 9 2' 3"
FR 9 to FR 10 6' 9"
FR 10 to FR 98 4' 1"
FR 98 to FR 99 3'-8"
ELECTRICAL
Power Three 1360 kW, 450 V, 60 Hz, 3 Phase, 1800 RPM Caterpillar 3512B diesel engines with Baylor ship service generators
Shore tie cable Seven MIL-C-24368/2 (NATO) shore power receptacles, 400 A each
TANK CAPACITIES
Diesel oil 220,359 gal
Fresh water 12,454 gal
JP-5 Fuel 35,182 gal
1 (Rev-1)
00000_0623_FLT
REC_00000_FLT_Commercial Project @ CG Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for
Shipyard Employment
NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for
Fabrication, Welding, and Inspection of Submarine Structure
2 (Rev-1)
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire
Protection and Response work item, as applicable, during the performance of this availability.
3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety
Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.
3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan, as requested in the Fire Protection and Response work item, seven (7) days before the Arrival Conference.
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast
Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
3 (Rev-1)
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B-
Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY-
130.
3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with
NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.
3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B-
Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.
NOTE
NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in
NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding
Weldox 900 are considered the same as those for welding HY-130.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC
Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable
Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific
4 (Rev-1) portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is Small Quantity
Generator (H18690390036).
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an
NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’
Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous
Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental
Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For
Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor must be aware of the following:
5 (Rev-1)
3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the
Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast
Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.5.6.4 The Cutter will be surrounded by a Government-provided boom for the entirety of the availability.
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 None.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
6 (Rev-1)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK
ITEM #
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
7 (Rev-1)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER
COAT, BARRIER COAT, TOP
COAT, ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFAC
E
AMBIEN
T
ΔT
| DP -
SURFACE |
8 (Rev-1)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Place Surface Profile
Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /
TIME
9 (Rev-1)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area)
Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT
QA RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading
(mils)
10 (Rev-1)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
11 (Rev-1)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
12 (Rev-1)
4.2 Tank and Void Assessment form.
13 (Rev-1)
14 (Rev-1)
S22_018_634NN_ANS_0124_756
S22_025_634NN_ANS_0124_756
WORK ITEM 1: Deck Covering (Slip-Resistant), Renew
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to renew deck covering with slip-resistant deck covering system (MIL-PRF-24667 Type V Comp. G/D/L Non-skid) for areas as listed in
Table 1.
TABLE 1 SLIP-RESISTANT DECK COVERING
LOCATION COMPO
AREA
(SQFT)*
SYSTEM/APPENDIX
(SFLC STD 6310)
TOPCOAT COLOR
PRESERVE
LEVEL
NOTE
Star Deck incl. Platforms
Decks, Platforms
2,016 Weather Decks (Weather
Deck Non-Skid, MIL-
SPEC Coating for Steel)
Dark Gray 36076
Match existing adjacent surfaces
Renew MIL-PRF-24667D
Type V Comp. G/D/L
Non-skid
CIWS Deck incl. Launcher Dcks, Top of Fan Rooms
Decks, Tops
2,205 Weather Decks (Weather
Deck Non-Skid, MIL-
SPEC Coating for Steel)
Dark Gray 36076
Match existing adjacent surfaces
Renew MIL-PRF-24667D
Type V Comp. G/D/L
Non-skid *Approximated
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements
Coast Guard Drawing 418A-WMSL-100-006, Rev A, Inboard and Outboard Profiles
Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans
Coast Guard Drawing 750-WMSL-085-025, Rev -, Compartment Areas & Volumes NSC 3 &
Follow (AS3085012)
Coast Guard Drawing 750-WMSL-100-042, Rev J, Unit 3230 Structure - 2nd Dk to Main Deck -
Fr 76 to Fr 88 (ASC100323)
Coast Guard Drawing 750-WMSL-100-045, Rev K, 2nd Dk to Main Dk - Fr 82 to Aft
(ASC100333)
Coast Guard Drawing 750-WMSL-100-049, Rev L, Unit 4220 Structure - 02 Lvl and Above - Fr
33 to Fr 44 (ASC100422)
Coast Guard Drawing 750-WMSL-100-053, Rev K, Unit 4420 Structure - 01 Level and Abv - Fr
52 to Fr 67 (ASC100442)
15 (Rev-1)
Coast Guard Drawing 750-WMSL-100-084, Rev -, Topside Configuration for NSC 6 & Follow
NAVSEA Drawing 803-1385828, Rev P, Nozzles AFFF and Washdown Systems
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series), Coatings and Color
Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
American Society for Nondestructive Testing (ASNT), Recommended Practice No. SNT-TC-1A, 2020, Personnel Qualification and Certification in Nondestructive Testing
American Society for Nondestructive Testing (ASNT), Standard No. ANSI/ASNT CP-189-2020, 2020, ASNT Standard for Qualification and Certification of Nondestructive Testing
Personnel
ASTM Internationals (ASTM) G46, 2018, Standard Guide for Examination and Evaluation of
Pitting Corrosion
MIL-PRF-24176C, 2020, Cement, Epoxy, Metal Repair and Hull Smoothing
MIL-PRF-24667D, 2021, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering
Application
MIL-STD-1689A, 1990, Fabrication, Welding, and Inspection of Ships Structure
Naval Sea Systems Command (NAVSEA) 0640-LP-119-0175, 2019, NAVSEA OP 4 Rev 12, Ammunition and Explosives Safety Afloat
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP
11), 2020, Bare Metal Power Tool Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface
Preparation Standard SSPC-SP 10 (WAB)/NACE WAB-2, 2015, Near-White Metal Wet
Abrasive Blast Cleaning
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
• 3.3 Operational test – initial
• 3.4 Inspection
3.1.2 Tech Rep. The Contractor must provide the services of Tech Reps and personnel as follows:
• NDE Tech Rep: NDE Operator/Level 1
16 (Rev-1)
• Preservation Tech Rep: CIP Level 3 – Peer Review with Marine Specialty
3.1.2.1 NDE Tech Rep. The Contractor must provide the services of a qualified and certified NDE
Operator/Level 1 as follows:
• Perform NDE Operations.
3.1.2.1.1 Qualifications/certifications. NDE Operator/Level 1 certified and qualified in accordance with
ASNT No. SNT-TC-1A. Submit the Tech Rep’s qualifications/certifications to the COR at the Arrival
Conference.
3.1.2.1.2 Dates of services. Include the dates of services in which Tech Reps must be on site as per their subcontract documentation.
3.1.2.2 Preservation Tech Rep. The Contractor must provide the services of a Certified Coating Inspector having successfully completed the NACE International Coatings Inspector Program (CIP), Level 3 – Peer
Review with Marine Specialty to:
• Serve as an Independent Coating Tech Rep.
• Accomplish applicable requirements in SFLC Std Spec 0000, Paragraph 3.2.4.2.2 (Coating
Tech Rep).
• Oversee the Preservation Plan requirements in SFLC Std Spec 6310, Paragraph 3.2
(Preservation Plan).
• Review and sign daily reports summarizing work. See forms QA-1 thru QA-5 provided in the
General Requirements.
• Submit reports to the COR within 24 hours of each inspection.
3.1.2.2.1 Qualifications/certifications. Submit the Coating Tech Rep’s qualifications/certifications in accordance with SFLC Std Spec 0000, 3.2.4.2.2.3 and 3.2.4.2.4, include name, certificate number and documented completion of NACE Marine Coating Technology Course and Exam.
3.1.2.2.2 Submit the name and the certification of the Tech Rep to the COR at the Arrival Conference.
Include the dates of services the Qualified Tech Reps will be on site as per their subcontract documentation.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.3.1 Specific protections. Specific areas/equipment/components to be protected include, but are not limited to:
• Weapons, controls, and components (e.g. guns, CIWS, ESM systems, and controls)
• Machinery, equipment, and components (e.g. cranes, winches, capstans)
• C5ISC Equipment
• Antennas and controls
• Ventilation systems, and components (e.g. ventilation inlets/outlets, and trunks)
• Ordinance marks
• Ammo racks and foundations
• Ready service lockers
17 (Rev-1)
• Flag storage boxes.
• Wash down counter measure fittings
• Drains, covers, and plugs
3.1.3.2 Protection plan. Protection plan must be included in preservation plan. Mast equipment protection needs to be inspected by Coast Guard inspector prior to any preservation work commencing.
3.1.3.3 Inspection of integrity. Inspect the integrity of the protective covering at the beginning of each shift where surface preparation and/or painting will be accomplished. Ensure that equipment and machinery have not been infiltrated by contamination. Clean any contamination and repair any defects in the protective covering prior to continuing work.
3.1.3.4 Watertight closures. Close all weather tight closures in the vicinity of the work area or install double curtain baffles at the entrance of each access door where airborne contamination could occur during surface preparation and painting. Double curtain baffles are necessary at all closures that will be in use during the preservation process. Install a dirt collection mat on the deck directly inside each closure.
3.1.3.5 Deck drains. Plug or cover all deck drains, weather deck supply and discharge to prevent entry of blast grit or debris.
3.1.3.6 Counter Measure Wash Down (CMWD). Cover CMWD nozzles (i.e. NAVSEA Dwg 803-
1385828) to prevent entry of blast grit or debris using the following:
• Fender Washer (i.e. Carbon Steel, SAE J403H (1008-1020), UNS G10080-G10200, Zinc
Plated)
• Machine Screw (Stainless, Type 18-8, must comply with ANSI-B18.6.3 Slotted, Trusshead.
Full form threads are to extend to within 0.050 inch of the head bearing surface).
NOTE
The CMWD nozzle coverings are Parts 4 and 5 in
NAVSEA Drawing No 803-1385828.
3.1.3.7 C5ISC equipment. All C5ISC equipment and antennas not removed from the mast to accomplish this work item must be properly protected.
3.1.3.8 Cable protection. Ensure the cables are protected from abrasion, damage, and paint. Not bend any electrical cable to a radius less than 20 times their diameter. Not hoist a radar pedestal using its array.
CAUTION
Not bend any electrical cable to a radius less than 20 times their diameter.
Not hoist a radar pedestal using its array.
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, Paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
• Small boats
• Life rafts
• Weapons, controls, and components (e.g. guns, CIWS, ESM systems, and controls)
• Machinery, equipment, and components (e.g. cranes, winches, capstans)
18 (Rev-1)
• Ventilation systems, and components (e.g. ventilation inlets/outlets, and trunks)
• C5ISC Equipment
• Antennas and controls
• Ordinance marks
• Ammo racks and foundations
• Ready service lockers
• Flag storage boxes
• Wash down counter measure fittings
• Drains, covers, and plugs
• Closures (e.g. doors, hatches and scuttles)
• Rails and supports
• Ladders and supports
• Outfits, foundations, and fittings (e.g. chocks, cleats, cat paws)
• Switches, controls, and terminals
• Lights, alarms, cameras, speakers, sensors, switches, and supports
• Piping, hoses, and supports
• Cables, wires, and supports
NOTE
Coast Guard personnel will coordinate to remove all pyrotechnics from ready service lockers prior to commencement of the works.
3.1.5 Work locations. The concerned work areas are listed in Table 1. See the applicable drawings in section 2 for guidance, locations, and details.
3.1.6 Materials, tools, and services.